SlideShare a Scribd company logo
1 
Kafr El Sheikh University 
Faculty of Engineering 
Civil Engineering Department 
Suez-Canal 
Cable-Stayed Bridge Project 
(The Graduation Project) 
Prepared By / 
Mohamed Ahmed Elfeky 
Mohammed Abdelkawy 
Ahmed Bahgat Zamil 
4th Year Civil
2 
The Cable-Stayed Bridge 
Basics 
The position of cable-stayed bridges within all bridge systems their spans range between continuous girders and arch bridges with shorter spans at one end, and suspension bridges with longer spans at the other. The economic main span range of cable-stayed bridges thus lies between 100m with one tower and 1100m with two towers. A typical cable stayed bridge is a deck with one or two pylons erected above the piers in the middle of the span. The cables are attached diagonally to the girder to provide additional supports. Large amounts of compression forces are transferred from the deck to the cables to the pylons and into the foundation. Cable stayed-bridges have a low center of gravity, which makes them efficient in resisting earthquakes. Cables are extremely well suited for axial tension, however are weak against compression and bending forces. As a result, long span cable stayed bridges, though strong under normal traffic loads, are vulnerable to the forces of winds. Special measures are taken to assure that the bridge does not vibrate or sway under heavy winds. Because the only part of the structure that extends above the road is the towers and cables, cable stayed bridges have a simple and elegant look.
3 
Advantages of cable-stayed bridges: First of all the bending moments are greatly reduced by the load transfer of the stay cables, By installing the stay cables with their predetermined precise lengths the support conditions for a beam rigidly supported at the cable anchor points can be achieved and thus the moments from permanent loads are minimized, Even for live loads the bending moments of the beam elastically supported by the stay cables remain small. 
Large compression forces in the beam are caused by the horizontal components of the inclined stay cables. The normal forces in the main and side span equal one another so that only uplift forces have to be anchored in the abutments which act as hold-down piers. A second important advantage of cable-stayed bridges is their ease of construction; - Arch bridges with large spans are not stable during erection until 
The arch is closed and the horizontal support forces are anchored. 
- Self-anchored suspension bridges, which may be required when 
Their horizontal cable component cannot economically be anchored 
Due to bad soil conditions, need temporary supports of their beams until the main cables are installed.
4 
- In cable-stayed bridges, however, the same flow of forces is 
Present during free-cantilever construction stages as after completion. 
This is true for free cantilevering to both sides of the tower 
As well as for free cantilevering the main span only. 
The Main Components OF Cable Stayed Bridge: 1-Deck: The deck or road bed is the roadway surface of a cable-stayed bridge. The deck can be made of different materials such as steel, concrete or composite steel-concrete. The choice of material for the bridge deck determines the overall cost of the construction of cable stayed bridges. The weight of the deck has significant impact on the required stay cables, pylons, and foundation.
5
6 
Pylon
7 
2-Pylon: Pylons of cable stayed bridges are aimed to support the weight and live load acting on the structure. There are several different shapes of pylons for cable stayed bridges such as Trapezoidal pylon, Twin pylon, A-frame pylon, and Single pylon. They are chosen based on the structure of the cable stayed bridge (for different cable arrangements), aesthetics, length, and other environmental parameters. The first cable-stayed bridges used steel towers. Since towers are mainly loaded by compression, concrete towers are more economical and, therefore, mainly used today. Only if extremely bad foundation conditions would require very long piles, are the lighter steel towers used today.
8 
3-Cables: 
Cables are one of the main parts of a cable-stayed bridge. They transfer the dead weight of the deck to the pylons. These cables are usually post- tensioned based on the weight of the deck. The cables post-tensioned forces are selected in a way to minimize both the vertical deflection of the deck and lateral deflection of the pylons. There are four major types of stay cables including, parallel-bar, parallel-wire, standard, and locked- coil cables. The choice of these cables depends mainly on the mechanical 
Properties, structural properties and economic criteria.
9 
1- Locked coil ropes: Traditionally used in Germany, completely shop fabricated, permit construction by geometry. Advantages: good corrosion protection, simple maintenance Disadvantages: reduced stiffness, subject to creep, reduced tensile strength and fatigue strength. Locked coil ropes consist of internal round wires with a diameter of 
5 mm and outer layers of Z-shaped wires with a depth of 6 – 7 mm, 
Fig. 3.2. Their modern corrosion protection comprises galvanizing of all wires, filling the interstices with a corrosion inhibitor and painting the outside in several layers. The different wire layers rotate in opposite directions in order to achieve twist-free ropes, Fig. 3.3.
10 
When stressing the cables, the Z-shaped outer wires are pressed against one another by lateral contraction and which ‘locks’ the rope surface against intrusion of water, hence the name ‘locked coil ropes’.
11 
2- Parallel wire cables: Developed by LAP in the 1960s from BBR post-tensioning system in order to overcome the disadvantages of 
Locked coil ropes, almost exclusively used in Germany since then, also completely shop-fabricated. Advantages: high stiffness, no creep, high tensile and fatigue strength with Hiam-anchorage Disadvantage: complex corrosion protection with several components Parallel wire cables comprise a bundle of straight wires with 7 mm or 1⁄4 inch diameter which are anchored with button heads in a retainer plate. In order to further improve the fatigue strength, the so-called ‘HiAm’ anchorage was developed and investigated in many tests. The basic design idea is to anchor the individual wires gradually by lateral pressure exerted by small steel balls into which the wires are broomed-out inside a conical anchor head.
12
13 
3- Parallel strand cables: Developed from strand tendons in order to exploit higher tensile strength and better availability of strands 
Advantages: cost-effective, fabrication on site from components, exchange of individual strands Disadvantage: slightly reduced stiffness.
14
15
16 
Main Types of Cable Stayed Bridges:
17
18 
Bridge Layout 
1) Bridge Structural Type: Concrete Box Girder Cable-Stayed Bridge 
2) Span Arrangement: 165+400+165=730m 
3) Stay Cable Arrangement: Semi Fan 
4) Stay Cable: Strand Cables 
5) Pylon Type: Reinforced Concrete H-Shaped Column 
6) Pylon Height: 150m 
7) Navigation Clearances: 70m Above H.H.W.L 
8) Bridge Width: 20m
19 
Bridge Components 
Cable-Stayed bridges have 3 main components:- 
1) Pylon 
2) Deck 
3) Cables 
3D Model
20 
The Pylon 
The Pylon is the main support of cable-stayed bridges. 
Cables link the deck to the pylon, so it can carry the deck safely. 
Our pylon is a Reinforced Concrete H-Shaped Column. 
The section of the pylon is a nonprismatic section 
Pylon Bottom Pylon Top
21 
The Deck 
The Deck View 
The Deck Properties:- 
The Deck Width = 20.00 meter 
(Consists of 4 lanes - 2 lanes in each direction , 2 sidewalks of width equals 2.0 m , and an island of width equals 2.0 meters) 
t1 = t2 = t3 = t4 = 0.30 m t5 = t6 = 0.25m 
L1 = L2 = 2.00 m 
The Depth = 3.00 m
22 
Material Properties for Pylon and Deck: concrete has a specified compressive strength equals 400 kg/cm^2, Considering Creep and Shrinkage.
23 
Cables 
In this bridge we have 16 cables in each side of the pylon 
The distance between cables in the deck plan equals to 10.00 meters In the Side Spans and Equal To 12 meters Between the Pylons 
The distance between them at its links to the pylon equals to 2.00 meters 
Material Properties: 
Fu = 17.7 T/Cm^2 Fy= .89* 17.7 = 15.7 T/Cm^2 
E = 1950 T/Cm^2 
Diameter = 15.7 mm
24 
Modeling Steps 
(Using CSI Bridge Program) 
1) Drawing the layout line of the bridge. 
The layout has 2 stations the 1st at 0.0 and the 2nd at 730.00. 
2) Defining the deck sec. which is box girder has 3 vents. 
3) Defining Lanes. 
4) Defining and drawing the pylon. 
5) Defining and drawing the rigid links to link the deck sec. to cables as one unit. 
6) Defining springs. 
7) Solving the model to get the deformation due to dead load. 
8) Defining the cables (Diameter & Pretension Force) which achieve deformation equals to zero. 
9) Defining the design vehicle and vehicle class. 
10) Defining All Cases Of Moving Load. 
11) Solving due to moving load and getting deformation.
25 
12) Defining the Earthquake loads Using Static Analysis (Seismic Coefficient Method) and Safety Was Checked by Dynamic Analysis (Time History Method). 
15) Solving the model due to earthquake forces. 
16) Defining the wind loads. 
17) Solving. 
18) Defining load combinations. 
19) Design the bridge. 
Philosophy of Analysis: 1-Find the value of cable tension that will give optimum deck profile for final model. 
2- Stage construction analysis to find cable force during erection. 3- Final checks with seismic, Wind and other effects
26 
The Program Outputs: 
Deformation due to Dead Load only (Without Cables) 
Joints Labels 
These joints are at the center of the deck.
27
28 
From the table: 
The max deflection is at p54 and p56 which are at the mid span, and equals to 54.41 m.
29 
We will use 3 groups of cables 
The 1st one consists of 5 cables (the nearest cables to the pylon) 
This group has cables of diameter equals to 7.00 cm, and a tension force of 340 ton of its end I which linked to the pylon. 
The Force in cables is put in a load pattern called Target. 
After Using Cables With Pretension Force:
30 
The 2nd group consists of the next 5 cables. 
This group has cables of diameter equals to 10.00 cm, and a tension force of 450 ton of its end I which linked to the pylon. 
The 3rd group consists of the next 6 cables. 
This group has cables of diameter equals to 12.00 cm, and a tension force of 618 ton of its end I which linked to the pylon.
31 
Deformed Shape: 
Almost no deformation … 
The output values are due to the combination between Target and Dead Load.
32
33 
The uplift at P34 equals to 3 cm, and the max Settlement equals to 1.5 cm at P71.
34 
The Pylon Sway due to Dead Load: 
The Max Sway from D.L. equals to17.6 cm. 
The Moment Diagram: 
Max Moment = 7272 t.m
35 
The Shear Force Diagram: 
Max Shear = 840 ton. 
The Normal Force Diagram: 
Max axil compression force in deck =12064 ton Reaction for pylon Column = 16574 ton
36 
Moving Loads: 
The Bridge consists of 4 lanes, 2 lanes in each direction, and 2 sidewalks of 2.00 m width in each one and central median 2m Width. 
The lane width equals to 3.50 meters.
37 
Moving Load Model (1): Consists Of concentrated and distributed load. Truck 60ton. Truck40ton.
38 
Truck 20ton. Uniform 0.25t/m^2 for The rest of road width 
Uniform 0.5t/m^2 for Pavements and Median
39
40 
The max deflection equals to 29 cm
41 
Bending Moment Diagram: 
Max Moment = 3956 t.m 
Shear Force Diagram: 
Max Shear = 243 ton
42 
Normal Force Diagram 
Max Torsion = 1882 t.m 
Moving Load Model (2): consists of uniform 0.5t/m^2 for bridge width
43 
the max deflection equals to 28.9 cm allowable Deflection (50-80) cm Safe
44 
Load Case for torsion (2 lanes occupy other 2lanes are empty) 
Max Torsion Moment = 2606 t.m
45 
Earthquake Analysis 
Dynamic Time History linear Analysis 
1) Define Mass Source:
46 
2) Define Time History Function: (time &acceleration) 
We Will Use (ELCENTRO) General EQ in X&Y Direction
47 
3) Define Time History Load Case: - Damping Ratio: Take (2%) 
- Response Modification Factor (R): Take = 3
48 
If we Want to increase the damping ratio we can use cable anchorage with Hydraulic Damper 
For great values up to 5%. This is reducing the response of the super structure.
49 
- Scale Factor: I*g/R= (1.3*9.81)/ (3) =4.25
50
51 
Max Lateral Displacement = 28.7 cm
52 
Normal Force Diagram
53 
Shear Force Diagram
54 
Bending Moment Diagram
55 
Seismic Analysis Using (Simplified Response Spectrum) >> (Seismic Coefficient Method) <<
56
57 
Max Lateral Displacement = 29.6 cm
58 
Bending Moment Diagram
59 
Shear Force Diagram
60 
Base Reactions
61 
Wind Loads 
Wind load which affect on the deck of the bridge and on the trucks can be calculated from the EGYPTIAN code of loads as following:
62 
Wind Load on Deck (With Live Load) 
Wind load (deck) = 0.15 * 6 = 0.9 ton /m. 
The wind applied in Y – Direction.
63
64 
Bending Moment Diagram
65 
Load Combinations 1) Characteristic Load Combinations 
According To Egyptian Code: 
1.35 Dead+1.35 Live (1) 
1.35 Dead+1.35 Live (2) 
1.35 Dead+1.35 Live (1) +0.9 Winds 
1 Dead+0.2 Live (1) +EQ 
1 Dead+0.2 Live (2) +EQ
66 
Final Design 
Design of cable: Subjected to Tension with Small Compression Values:
67 
Design of pylon: pylons designed as 
Columns subjected to Axial Force and Biaxial Moments. Max Straining Action: p m3 m2 23817.09 -3748 -5006.61 17244.32 -2914.12 -35635.8 17913.68 9806.453 -12637 17358.85 3167.38 31823.26
68 
Design by SCI COLUMN Program: 
Using 254 bar ᶲ 22 Total area Steel=966 Cm^2 Steel ratio = 0.4%
69 
Design of the Deck: Max Straining Action: 
Max Compression= 18171 ton 
Max positive Mx=9972.35 t.m Max negative Mx= -9605 t.m 
Max Positive My= 26560 t.m 
Max Negative My= 27280 t.m 
Max Torsion = 2845 t.m 
Max Shear = 1272 ton
70 
Flexure Design 
For Exterior Girder (right, left) 
Using upper and lower R.F.T = 50 ᶲ 25 (Upper & Lower) 
Achieve Moment of Resistance = 2512t.m
71 
For Exterior Girder (right, left) 
Using upper and lower R.F.T = 60 ᶲ 25 
Achieve Moment of Resistance = 3330t.m
72 
Design of Sec Using CSI COLUMN as Column:
73 
Comparison for Better Results: 
1- We can use prestressed concrete to achieve the tensile stresses and get Small effective cross section or using Steel deck. 2- We can do camber for Pylon and the deck to prevent high deflections for the deck And lateral Displacements For the pylon 3- high damping rubber bearings (HRB) were used as seismic isolators (supports) for the steel girder, 
With allowable movable length (seismic) = ± 450 mm. 
4- To limit the horizontal movements, lateral rubber bearings were installed between the bridge deck and the tower with a gap of 10 mm.
74

More Related Content

What's hot

Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Rajesh Prasad
 
Basic components and parts of bridge structures
Basic components and parts of bridge structuresBasic components and parts of bridge structures
Basic components and parts of bridge structures
Muhammad Qasim Jameel
 
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridges
Dheerendra Prasad
 
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABSANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ila vamsi krishna
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
Parikshit Hurukadli
 
Analysis of cable stayed bridges
Analysis of cable stayed bridgesAnalysis of cable stayed bridges
Analysis of cable stayed bridges
ParamaAthmeka
 
Modeling and Design of Bridge Super Structure and Sub Structure
Modeling and Design of Bridge Super Structure and Sub StructureModeling and Design of Bridge Super Structure and Sub Structure
Modeling and Design of Bridge Super Structure and Sub Structure
AIT Solutions
 
multistorey building design by sap and autocad
multistorey building design by sap and autocadmultistorey building design by sap and autocad
multistorey building design by sap and autocad
Razes Dhakal
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Pooja Lonare
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridge
Elamathy Murugan
 
project report on truss bridge
project report on truss bridgeproject report on truss bridge
project report on truss bridgerajdutt1111
 
Bridge foundation and its loading system
Bridge foundation and its loading systemBridge foundation and its loading system
Bridge foundation and its loading system
DEBASREE GHOSH
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
Animesh Verma
 
Suspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesSuspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed Bridges
Hussein Zidan
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
Jeelkumar Patel
 
suspension bridge
suspension bridgesuspension bridge
suspension bridge
Gaurav Rawat
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
Robin Nirwal
 

What's hot (20)

Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
Basic components and parts of bridge structures
Basic components and parts of bridge structuresBasic components and parts of bridge structures
Basic components and parts of bridge structures
 
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridges
 
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABSANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
 
Bridge
BridgeBridge
Bridge
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
 
Analysis of cable stayed bridges
Analysis of cable stayed bridgesAnalysis of cable stayed bridges
Analysis of cable stayed bridges
 
Modeling and Design of Bridge Super Structure and Sub Structure
Modeling and Design of Bridge Super Structure and Sub StructureModeling and Design of Bridge Super Structure and Sub Structure
Modeling and Design of Bridge Super Structure and Sub Structure
 
multistorey building design by sap and autocad
multistorey building design by sap and autocadmultistorey building design by sap and autocad
multistorey building design by sap and autocad
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridge
 
project report on truss bridge
project report on truss bridgeproject report on truss bridge
project report on truss bridge
 
Bridge foundation and its loading system
Bridge foundation and its loading systemBridge foundation and its loading system
Bridge foundation and its loading system
 
Reinforced slab
Reinforced slabReinforced slab
Reinforced slab
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Suspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesSuspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed Bridges
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
 
suspension bridge
suspension bridgesuspension bridge
suspension bridge
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 

Viewers also liked

Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
Sadek Abdelraheem
 
Cable stay bridge construction
Cable stay bridge constructionCable stay bridge construction
Cable stay bridge construction
Balkrishan Kushwah
 
Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acpJigar Shah
 
cable stayed bridge
cable stayed bridgecable stayed bridge
cable stayed bridge
Akruth Gowda
 
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UKCable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
David Collings
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Rajesh Prasad
 
Bridges construction
Bridges constructionBridges construction
Bridges construction
Shivam Mahajan
 
Reliability Assessment of Cable-Stayed Bridges
Reliability Assessment of Cable-Stayed BridgesReliability Assessment of Cable-Stayed Bridges
Reliability Assessment of Cable-Stayed Bridges
Franco Bontempi
 
Handbook cum coffee table book titled staying with cables a modern construct...
Handbook cum coffee table book titled staying with cables  a modern construct...Handbook cum coffee table book titled staying with cables  a modern construct...
Handbook cum coffee table book titled staying with cables a modern construct...
Rajesh Prasad
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Nnci roadway structure
Nnci roadway structureNnci roadway structure
Nnci roadway structure
Mohammed Abdelkawy
 
Unit 02 of my graduation project
Unit 02 of my graduation projectUnit 02 of my graduation project
Unit 02 of my graduation project
Mohammed Abdelkawy
 
Hotel Hilton AL Jubail
Hotel Hilton AL JubailHotel Hilton AL Jubail
Hotel Hilton AL Jubail
Mohammed Abdelkawy
 
road under bridge
road under bridgeroad under bridge
road under bridge
Pvrtechnologies Nellore
 
PDF Digital signatures
PDF Digital signaturesPDF Digital signatures
PDF Digital signatures
Bruno Lowagie
 
Pylon presentation2 T-Pylon
Pylon presentation2 T-PylonPylon presentation2 T-Pylon
Pylon presentation2 T-Pylon
Department of Energy and Climate Change
 
Parametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based programParametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based program
eSAT Journals
 
Al ESAYI Plaza Hotel - Jizan, KSA
Al ESAYI Plaza Hotel - Jizan, KSAAl ESAYI Plaza Hotel - Jizan, KSA
Al ESAYI Plaza Hotel - Jizan, KSA
Mohammed Abdelkawy
 
Sodic east town club house
Sodic east town club houseSodic east town club house
Sodic east town club house
Mohammed Abdelkawy
 
2013 icossar sa_sm_fb_upload
2013 icossar sa_sm_fb_upload2013 icossar sa_sm_fb_upload
2013 icossar sa_sm_fb_uploadStroNGER2012
 

Viewers also liked (20)

Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
Cable stay bridge construction
Cable stay bridge constructionCable stay bridge construction
Cable stay bridge construction
 
Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acp
 
cable stayed bridge
cable stayed bridgecable stayed bridge
cable stayed bridge
 
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UKCable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
Cable stay bridges, summary of a lecture delivered at Uni of Surrey, UK
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
 
Bridges construction
Bridges constructionBridges construction
Bridges construction
 
Reliability Assessment of Cable-Stayed Bridges
Reliability Assessment of Cable-Stayed BridgesReliability Assessment of Cable-Stayed Bridges
Reliability Assessment of Cable-Stayed Bridges
 
Handbook cum coffee table book titled staying with cables a modern construct...
Handbook cum coffee table book titled staying with cables  a modern construct...Handbook cum coffee table book titled staying with cables  a modern construct...
Handbook cum coffee table book titled staying with cables a modern construct...
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Nnci roadway structure
Nnci roadway structureNnci roadway structure
Nnci roadway structure
 
Unit 02 of my graduation project
Unit 02 of my graduation projectUnit 02 of my graduation project
Unit 02 of my graduation project
 
Hotel Hilton AL Jubail
Hotel Hilton AL JubailHotel Hilton AL Jubail
Hotel Hilton AL Jubail
 
road under bridge
road under bridgeroad under bridge
road under bridge
 
PDF Digital signatures
PDF Digital signaturesPDF Digital signatures
PDF Digital signatures
 
Pylon presentation2 T-Pylon
Pylon presentation2 T-PylonPylon presentation2 T-Pylon
Pylon presentation2 T-Pylon
 
Parametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based programParametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based program
 
Al ESAYI Plaza Hotel - Jizan, KSA
Al ESAYI Plaza Hotel - Jizan, KSAAl ESAYI Plaza Hotel - Jizan, KSA
Al ESAYI Plaza Hotel - Jizan, KSA
 
Sodic east town club house
Sodic east town club houseSodic east town club house
Sodic east town club house
 
2013 icossar sa_sm_fb_upload
2013 icossar sa_sm_fb_upload2013 icossar sa_sm_fb_upload
2013 icossar sa_sm_fb_upload
 

Similar to Calculation note suez canal cable stayed bridge

Acm Space Frames
Acm Space FramesAcm Space Frames
Acm Space Frames
Aaqib Iqbal
 
Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000
vivatechijri
 
Suspension bridge
Suspension bridge Suspension bridge
Suspension bridge
Sinu Santhosh
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Hossam Shafiq II
 
Cable strucutres(presentation)
Cable strucutres(presentation)Cable strucutres(presentation)
Cable strucutres(presentation)
Waseem Akbar
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
SauravShahane
 
Cable systems - form active structure system
Cable systems - form active structure systemCable systems - form active structure system
Cable systems - form active structure system
Archistudent Portal
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
KAVYA H
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission tower
naqeeb04
 
Cables in civil engineering
Cables in civil engineeringCables in civil engineering
Cables in civil engineering
AmmadMustafakamal
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
Hemant Srivastava
 
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
eSAT Journals
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
atchitect and design
 
Influence line diagram for model arch bridge
Influence line diagram for model arch bridgeInfluence line diagram for model arch bridge
Influence line diagram for model arch bridge
kunalsahu9883
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
Tek Narayan Bhattarai
 
analysis-and-design-of-four-leg-steel-tr-9e5db9cf.pdf
analysis-and-design-of-four-leg-steel-tr-9e5db9cf.pdfanalysis-and-design-of-four-leg-steel-tr-9e5db9cf.pdf
analysis-and-design-of-four-leg-steel-tr-9e5db9cf.pdf
Abdulwahedalsafany
 
Sub.ass.2
Sub.ass.2Sub.ass.2
Sub.ass.2
RajaVIGNESHPATHI
 
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS
IJMER
 
Uses of steel cables @akshay kumar
Uses of steel cables @akshay kumarUses of steel cables @akshay kumar
Uses of steel cables @akshay kumar
Akshay kumar
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12hlksd
 

Similar to Calculation note suez canal cable stayed bridge (20)

Acm Space Frames
Acm Space FramesAcm Space Frames
Acm Space Frames
 
Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000
 
Suspension bridge
Suspension bridge Suspension bridge
Suspension bridge
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
Cable strucutres(presentation)
Cable strucutres(presentation)Cable strucutres(presentation)
Cable strucutres(presentation)
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Cable systems - form active structure system
Cable systems - form active structure systemCable systems - form active structure system
Cable systems - form active structure system
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission tower
 
Cables in civil engineering
Cables in civil engineeringCables in civil engineering
Cables in civil engineering
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Influence line diagram for model arch bridge
Influence line diagram for model arch bridgeInfluence line diagram for model arch bridge
Influence line diagram for model arch bridge
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
analysis-and-design-of-four-leg-steel-tr-9e5db9cf.pdf
analysis-and-design-of-four-leg-steel-tr-9e5db9cf.pdfanalysis-and-design-of-four-leg-steel-tr-9e5db9cf.pdf
analysis-and-design-of-four-leg-steel-tr-9e5db9cf.pdf
 
Sub.ass.2
Sub.ass.2Sub.ass.2
Sub.ass.2
 
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS
 
Uses of steel cables @akshay kumar
Uses of steel cables @akshay kumarUses of steel cables @akshay kumar
Uses of steel cables @akshay kumar
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12
 

Recently uploaded

一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 

Recently uploaded (20)

一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 

Calculation note suez canal cable stayed bridge

  • 1. 1 Kafr El Sheikh University Faculty of Engineering Civil Engineering Department Suez-Canal Cable-Stayed Bridge Project (The Graduation Project) Prepared By / Mohamed Ahmed Elfeky Mohammed Abdelkawy Ahmed Bahgat Zamil 4th Year Civil
  • 2. 2 The Cable-Stayed Bridge Basics The position of cable-stayed bridges within all bridge systems their spans range between continuous girders and arch bridges with shorter spans at one end, and suspension bridges with longer spans at the other. The economic main span range of cable-stayed bridges thus lies between 100m with one tower and 1100m with two towers. A typical cable stayed bridge is a deck with one or two pylons erected above the piers in the middle of the span. The cables are attached diagonally to the girder to provide additional supports. Large amounts of compression forces are transferred from the deck to the cables to the pylons and into the foundation. Cable stayed-bridges have a low center of gravity, which makes them efficient in resisting earthquakes. Cables are extremely well suited for axial tension, however are weak against compression and bending forces. As a result, long span cable stayed bridges, though strong under normal traffic loads, are vulnerable to the forces of winds. Special measures are taken to assure that the bridge does not vibrate or sway under heavy winds. Because the only part of the structure that extends above the road is the towers and cables, cable stayed bridges have a simple and elegant look.
  • 3. 3 Advantages of cable-stayed bridges: First of all the bending moments are greatly reduced by the load transfer of the stay cables, By installing the stay cables with their predetermined precise lengths the support conditions for a beam rigidly supported at the cable anchor points can be achieved and thus the moments from permanent loads are minimized, Even for live loads the bending moments of the beam elastically supported by the stay cables remain small. Large compression forces in the beam are caused by the horizontal components of the inclined stay cables. The normal forces in the main and side span equal one another so that only uplift forces have to be anchored in the abutments which act as hold-down piers. A second important advantage of cable-stayed bridges is their ease of construction; - Arch bridges with large spans are not stable during erection until The arch is closed and the horizontal support forces are anchored. - Self-anchored suspension bridges, which may be required when Their horizontal cable component cannot economically be anchored Due to bad soil conditions, need temporary supports of their beams until the main cables are installed.
  • 4. 4 - In cable-stayed bridges, however, the same flow of forces is Present during free-cantilever construction stages as after completion. This is true for free cantilevering to both sides of the tower As well as for free cantilevering the main span only. The Main Components OF Cable Stayed Bridge: 1-Deck: The deck or road bed is the roadway surface of a cable-stayed bridge. The deck can be made of different materials such as steel, concrete or composite steel-concrete. The choice of material for the bridge deck determines the overall cost of the construction of cable stayed bridges. The weight of the deck has significant impact on the required stay cables, pylons, and foundation.
  • 5. 5
  • 7. 7 2-Pylon: Pylons of cable stayed bridges are aimed to support the weight and live load acting on the structure. There are several different shapes of pylons for cable stayed bridges such as Trapezoidal pylon, Twin pylon, A-frame pylon, and Single pylon. They are chosen based on the structure of the cable stayed bridge (for different cable arrangements), aesthetics, length, and other environmental parameters. The first cable-stayed bridges used steel towers. Since towers are mainly loaded by compression, concrete towers are more economical and, therefore, mainly used today. Only if extremely bad foundation conditions would require very long piles, are the lighter steel towers used today.
  • 8. 8 3-Cables: Cables are one of the main parts of a cable-stayed bridge. They transfer the dead weight of the deck to the pylons. These cables are usually post- tensioned based on the weight of the deck. The cables post-tensioned forces are selected in a way to minimize both the vertical deflection of the deck and lateral deflection of the pylons. There are four major types of stay cables including, parallel-bar, parallel-wire, standard, and locked- coil cables. The choice of these cables depends mainly on the mechanical Properties, structural properties and economic criteria.
  • 9. 9 1- Locked coil ropes: Traditionally used in Germany, completely shop fabricated, permit construction by geometry. Advantages: good corrosion protection, simple maintenance Disadvantages: reduced stiffness, subject to creep, reduced tensile strength and fatigue strength. Locked coil ropes consist of internal round wires with a diameter of 5 mm and outer layers of Z-shaped wires with a depth of 6 – 7 mm, Fig. 3.2. Their modern corrosion protection comprises galvanizing of all wires, filling the interstices with a corrosion inhibitor and painting the outside in several layers. The different wire layers rotate in opposite directions in order to achieve twist-free ropes, Fig. 3.3.
  • 10. 10 When stressing the cables, the Z-shaped outer wires are pressed against one another by lateral contraction and which ‘locks’ the rope surface against intrusion of water, hence the name ‘locked coil ropes’.
  • 11. 11 2- Parallel wire cables: Developed by LAP in the 1960s from BBR post-tensioning system in order to overcome the disadvantages of Locked coil ropes, almost exclusively used in Germany since then, also completely shop-fabricated. Advantages: high stiffness, no creep, high tensile and fatigue strength with Hiam-anchorage Disadvantage: complex corrosion protection with several components Parallel wire cables comprise a bundle of straight wires with 7 mm or 1⁄4 inch diameter which are anchored with button heads in a retainer plate. In order to further improve the fatigue strength, the so-called ‘HiAm’ anchorage was developed and investigated in many tests. The basic design idea is to anchor the individual wires gradually by lateral pressure exerted by small steel balls into which the wires are broomed-out inside a conical anchor head.
  • 12. 12
  • 13. 13 3- Parallel strand cables: Developed from strand tendons in order to exploit higher tensile strength and better availability of strands Advantages: cost-effective, fabrication on site from components, exchange of individual strands Disadvantage: slightly reduced stiffness.
  • 14. 14
  • 15. 15
  • 16. 16 Main Types of Cable Stayed Bridges:
  • 17. 17
  • 18. 18 Bridge Layout 1) Bridge Structural Type: Concrete Box Girder Cable-Stayed Bridge 2) Span Arrangement: 165+400+165=730m 3) Stay Cable Arrangement: Semi Fan 4) Stay Cable: Strand Cables 5) Pylon Type: Reinforced Concrete H-Shaped Column 6) Pylon Height: 150m 7) Navigation Clearances: 70m Above H.H.W.L 8) Bridge Width: 20m
  • 19. 19 Bridge Components Cable-Stayed bridges have 3 main components:- 1) Pylon 2) Deck 3) Cables 3D Model
  • 20. 20 The Pylon The Pylon is the main support of cable-stayed bridges. Cables link the deck to the pylon, so it can carry the deck safely. Our pylon is a Reinforced Concrete H-Shaped Column. The section of the pylon is a nonprismatic section Pylon Bottom Pylon Top
  • 21. 21 The Deck The Deck View The Deck Properties:- The Deck Width = 20.00 meter (Consists of 4 lanes - 2 lanes in each direction , 2 sidewalks of width equals 2.0 m , and an island of width equals 2.0 meters) t1 = t2 = t3 = t4 = 0.30 m t5 = t6 = 0.25m L1 = L2 = 2.00 m The Depth = 3.00 m
  • 22. 22 Material Properties for Pylon and Deck: concrete has a specified compressive strength equals 400 kg/cm^2, Considering Creep and Shrinkage.
  • 23. 23 Cables In this bridge we have 16 cables in each side of the pylon The distance between cables in the deck plan equals to 10.00 meters In the Side Spans and Equal To 12 meters Between the Pylons The distance between them at its links to the pylon equals to 2.00 meters Material Properties: Fu = 17.7 T/Cm^2 Fy= .89* 17.7 = 15.7 T/Cm^2 E = 1950 T/Cm^2 Diameter = 15.7 mm
  • 24. 24 Modeling Steps (Using CSI Bridge Program) 1) Drawing the layout line of the bridge. The layout has 2 stations the 1st at 0.0 and the 2nd at 730.00. 2) Defining the deck sec. which is box girder has 3 vents. 3) Defining Lanes. 4) Defining and drawing the pylon. 5) Defining and drawing the rigid links to link the deck sec. to cables as one unit. 6) Defining springs. 7) Solving the model to get the deformation due to dead load. 8) Defining the cables (Diameter & Pretension Force) which achieve deformation equals to zero. 9) Defining the design vehicle and vehicle class. 10) Defining All Cases Of Moving Load. 11) Solving due to moving load and getting deformation.
  • 25. 25 12) Defining the Earthquake loads Using Static Analysis (Seismic Coefficient Method) and Safety Was Checked by Dynamic Analysis (Time History Method). 15) Solving the model due to earthquake forces. 16) Defining the wind loads. 17) Solving. 18) Defining load combinations. 19) Design the bridge. Philosophy of Analysis: 1-Find the value of cable tension that will give optimum deck profile for final model. 2- Stage construction analysis to find cable force during erection. 3- Final checks with seismic, Wind and other effects
  • 26. 26 The Program Outputs: Deformation due to Dead Load only (Without Cables) Joints Labels These joints are at the center of the deck.
  • 27. 27
  • 28. 28 From the table: The max deflection is at p54 and p56 which are at the mid span, and equals to 54.41 m.
  • 29. 29 We will use 3 groups of cables The 1st one consists of 5 cables (the nearest cables to the pylon) This group has cables of diameter equals to 7.00 cm, and a tension force of 340 ton of its end I which linked to the pylon. The Force in cables is put in a load pattern called Target. After Using Cables With Pretension Force:
  • 30. 30 The 2nd group consists of the next 5 cables. This group has cables of diameter equals to 10.00 cm, and a tension force of 450 ton of its end I which linked to the pylon. The 3rd group consists of the next 6 cables. This group has cables of diameter equals to 12.00 cm, and a tension force of 618 ton of its end I which linked to the pylon.
  • 31. 31 Deformed Shape: Almost no deformation … The output values are due to the combination between Target and Dead Load.
  • 32. 32
  • 33. 33 The uplift at P34 equals to 3 cm, and the max Settlement equals to 1.5 cm at P71.
  • 34. 34 The Pylon Sway due to Dead Load: The Max Sway from D.L. equals to17.6 cm. The Moment Diagram: Max Moment = 7272 t.m
  • 35. 35 The Shear Force Diagram: Max Shear = 840 ton. The Normal Force Diagram: Max axil compression force in deck =12064 ton Reaction for pylon Column = 16574 ton
  • 36. 36 Moving Loads: The Bridge consists of 4 lanes, 2 lanes in each direction, and 2 sidewalks of 2.00 m width in each one and central median 2m Width. The lane width equals to 3.50 meters.
  • 37. 37 Moving Load Model (1): Consists Of concentrated and distributed load. Truck 60ton. Truck40ton.
  • 38. 38 Truck 20ton. Uniform 0.25t/m^2 for The rest of road width Uniform 0.5t/m^2 for Pavements and Median
  • 39. 39
  • 40. 40 The max deflection equals to 29 cm
  • 41. 41 Bending Moment Diagram: Max Moment = 3956 t.m Shear Force Diagram: Max Shear = 243 ton
  • 42. 42 Normal Force Diagram Max Torsion = 1882 t.m Moving Load Model (2): consists of uniform 0.5t/m^2 for bridge width
  • 43. 43 the max deflection equals to 28.9 cm allowable Deflection (50-80) cm Safe
  • 44. 44 Load Case for torsion (2 lanes occupy other 2lanes are empty) Max Torsion Moment = 2606 t.m
  • 45. 45 Earthquake Analysis Dynamic Time History linear Analysis 1) Define Mass Source:
  • 46. 46 2) Define Time History Function: (time &acceleration) We Will Use (ELCENTRO) General EQ in X&Y Direction
  • 47. 47 3) Define Time History Load Case: - Damping Ratio: Take (2%) - Response Modification Factor (R): Take = 3
  • 48. 48 If we Want to increase the damping ratio we can use cable anchorage with Hydraulic Damper For great values up to 5%. This is reducing the response of the super structure.
  • 49. 49 - Scale Factor: I*g/R= (1.3*9.81)/ (3) =4.25
  • 50. 50
  • 51. 51 Max Lateral Displacement = 28.7 cm
  • 52. 52 Normal Force Diagram
  • 53. 53 Shear Force Diagram
  • 54. 54 Bending Moment Diagram
  • 55. 55 Seismic Analysis Using (Simplified Response Spectrum) >> (Seismic Coefficient Method) <<
  • 56. 56
  • 57. 57 Max Lateral Displacement = 29.6 cm
  • 58. 58 Bending Moment Diagram
  • 59. 59 Shear Force Diagram
  • 61. 61 Wind Loads Wind load which affect on the deck of the bridge and on the trucks can be calculated from the EGYPTIAN code of loads as following:
  • 62. 62 Wind Load on Deck (With Live Load) Wind load (deck) = 0.15 * 6 = 0.9 ton /m. The wind applied in Y – Direction.
  • 63. 63
  • 64. 64 Bending Moment Diagram
  • 65. 65 Load Combinations 1) Characteristic Load Combinations According To Egyptian Code: 1.35 Dead+1.35 Live (1) 1.35 Dead+1.35 Live (2) 1.35 Dead+1.35 Live (1) +0.9 Winds 1 Dead+0.2 Live (1) +EQ 1 Dead+0.2 Live (2) +EQ
  • 66. 66 Final Design Design of cable: Subjected to Tension with Small Compression Values:
  • 67. 67 Design of pylon: pylons designed as Columns subjected to Axial Force and Biaxial Moments. Max Straining Action: p m3 m2 23817.09 -3748 -5006.61 17244.32 -2914.12 -35635.8 17913.68 9806.453 -12637 17358.85 3167.38 31823.26
  • 68. 68 Design by SCI COLUMN Program: Using 254 bar ᶲ 22 Total area Steel=966 Cm^2 Steel ratio = 0.4%
  • 69. 69 Design of the Deck: Max Straining Action: Max Compression= 18171 ton Max positive Mx=9972.35 t.m Max negative Mx= -9605 t.m Max Positive My= 26560 t.m Max Negative My= 27280 t.m Max Torsion = 2845 t.m Max Shear = 1272 ton
  • 70. 70 Flexure Design For Exterior Girder (right, left) Using upper and lower R.F.T = 50 ᶲ 25 (Upper & Lower) Achieve Moment of Resistance = 2512t.m
  • 71. 71 For Exterior Girder (right, left) Using upper and lower R.F.T = 60 ᶲ 25 Achieve Moment of Resistance = 3330t.m
  • 72. 72 Design of Sec Using CSI COLUMN as Column:
  • 73. 73 Comparison for Better Results: 1- We can use prestressed concrete to achieve the tensile stresses and get Small effective cross section or using Steel deck. 2- We can do camber for Pylon and the deck to prevent high deflections for the deck And lateral Displacements For the pylon 3- high damping rubber bearings (HRB) were used as seismic isolators (supports) for the steel girder, With allowable movable length (seismic) = ± 450 mm. 4- To limit the horizontal movements, lateral rubber bearings were installed between the bridge deck and the tower with a gap of 10 mm.
  • 74. 74