SlideShare a Scribd company logo
1 of 29
Millau Viaduct
THE MILLAU VIADUCT PROJECT
AN ENGINEERING MARVEL
Presented By:
Shivam Sood: PP18085
Adarsh M.S : PP18086
Karan Dujari: PP18087
Shikhar Pandey: PP18088
Abhash Shrivastav: PP18089
Pushpak Pullawar: PP18090
Bhavya Agrawal: PP18091
Guided By:
Dr. T.K Ganguli
Question:
What are the challenges faced by the Project during the
life cycle and how it responded to those challenges and
opportunities?
Contents of the Presentation
1. Background
2. Project Timeline
3. Project Team and Stakeholders Involved
4. Intention behind Millau Viaduct Construction
5. Project Phases (Problems and Responses)
1. Pre-Construction and Planning Stage
2. Construction
3. Close-out
6. Conclusions and Keylearnings
1987-1992
1993-1996
1998-
2000
March
2001 May,2001
8th
Oct,2001
10th
October,2001
20th February, 2002
• Change of Governance
• Introduction of BFOT
• The first inter ministry
decree is amended in
order to conform the
concession conditions
and allow the toll system
Signature of the
concession contract
Beginning of Construction
phase
Construction
Project Design &
Conception EFFIAGE won the bid for
the delivery of the
Project
• The council of the
state approves the
project via ministry
decree
• Decision to build the
deck with steel
rather concrete
Procurement
Control of
Construction
Est. of the expert
committee of ACDC by
Jean Francois Coste
Feasibility
Studies/Research
14th December, 2004
Project Delivery
Inauguration of the
Millau Viaduct and
beginning of the
operation phases after
couple of days
Plan Completion12 Years
Project Timeline
Project Stakeholders
● Local Authorities
● The Conceding Authority
The State (Ministry of Infrastructure) is the conceding authority. The ministry
opened the concession of the Viaduct to competition and awarded it to
EFFiAGE group which is both structure’s builder and concessionary.
● Eiffage
Eiffage is the third largest group in France in the field of construction, civil
engineering and construction related services. It is currently in fifth position in
Europe. It has a staff of 41,000 in France and the rest of the world and in the
financial year 2000 had an ex-VAT turnover of 6.25 billion Euros.
● Eiffage Construction
In the case of the Millau viaduct, its subsidiary Eiffage TP, which is one of
the largest French civil engineering and earthworks companies, will be
responsible for all the concrete structures.
● The Arrondissement Interdépartemental des Ouvrages d’ Art
(AIOA)
Was given responsibility by the conceding authority to conduct monitoring.
the AIOA reports to the infrastructure directorate of Aveyron Department
which was also the construction manager for works on the A75 motorway
on both sides of the viaduct.
● The Compagnie du viaduc de Millau
This company was specially set up for the purpose and draws on the
experience of the Eiffage concessions department. This company is the project
owner, and has responsibility for the overall funding of the operation and its
subsequent management. It conducts negotiations with the other parties
involved with the viaduct (Central Government, local authorities, etc.). The
Compagnie du Viaduc de Millau has awarded the works to two large
subsidiaries of the Eiffage group: Eiffage construction will be responsible for
concrete construction and Eiffel for metal construction.
● Eiffel Construction
The members that will make up the deck and pylons of the viaduct are to be
manufactured at Lauterbourg and Fos-sur-Mer. Teams from Eiffel will then
assemble and install all the metal elements of the viaduct on site.
● SETEC
Was asked by Eiffage to manage the entire construction phase of the
viaduct. SETEC is particularly specialized in the management of large
infrastructure and building projects and it is responsible for monitoring,
consultancy and worksite coordination. SETEC will ensure that studies
and works are conducted to the highest standards. It will be assisted, for
monitoring the manufacture of the metal part of the structure, by the
engineering division of the SNCF (French national railways).
Intention behind Millau Viaduct Construction ?
● Millau Viaduct was the outcome of a government project,
commissioned in order to complete an important section of the A75
autoroute. Prior to construction of the viaduct, traffic travelling along
this route had to descend to the Tarn Valley and travel along the
Route National N9, passing through Millau (a city). This caused
particular problems (especially in terms of congestion) in the summer
holiday season due to the vast number of tourists travelling to
Southern France and Spain along this route.
● The government reacted to increasing traffic along this route in the
mid-1980s, quickly recognising the necessity for a method of
traversing the Tarn valley, and commissioning initial studies into four
available options in 1988.
● "The Eastern Option" - Requiring two major bridges. Shorter and better for
through traffic, but providing poor access to Millau.
● "The RN9 Option" - Following the original path of Route Nationale 9
providing good access to Millau but at the cost of technical difficulties and
intrusion on the town
● "The Western Option" - Requiring four major bridges, technically easier but
expensive and providing poor access to Millau.
● "The Median Option" – Traverse the middle of
the valley.
The fourth option was selected by ministerial decree on 28 June 1989. It
encompassed two possibilities.
● The High Solution:
Envisaging a 2,500-metre-long (8,200 ft) viaduct more than 200 meters
(660 ft.) above the river.
● The Low Solution:
Descending into the valley and crossing the river on a 200-metre-long
(660 ft.) bridge, then a viaduct of 2,300 meters (7,500 ft.).
Project Phases
● Pre-Construction and Planning
Stage
● Construction Stage
● Project Completion Stage/Close-out
Problems during Pre-Construction and Planning Stage
1. The problem was to decide the way to cross the Tarn Valley for
which choice between the high and low solutions was an vital
concern as no proper design was present.
2. Lack of construction skills.
3. Technical issues ( Material to be used for the deck, requirement
of temporary piers, high wind speeds and seismic activities at
such height.)
4. Manufacturing, logistics and inventory control.
5. Safety of the workers, employees and other team members.
6. Apart from indisputable proofs of the positive effects of viaduct
on local economic development some of them deplore
insufficient leadership from the state level.
7. There was lack of public funds available for the existing missing
link in A75 for which 2 millions francs was required,
management was in awe to get the funds as public funding was
not enough and expenses couldn’t be borne by them.
Responses to challenges and opportunities during Conceptualization
• After long construction studies by the Ministry of Public Works, the
low solution was abandoned because it would have intersected the
water table and had a negative impact on the town, cost more, and
lengthened the driving distance. High solution was decided by
ministerial decree. After the choice of the high viaduct, five teams
of architects and researchers worked on a technical solution. The
concept and design for the bridge was devised by
French designers and structural engineer Dr. Michel Virlogeux. He
worked with the Dutch engineering firm ARCADIS , responsible for the
structural engineering of the bridge.
• Effiage entered into the partnership with other companies to acquire
the construction skills it did not possess e.g.. Eiffel Construction
Metaliique for steel construction. Various structural components were
tested by CSTB in a wind tunnel.
● Effiage chose steel in order to shorten the construction period
and hence allowing them to collect the toll sooner, also use of
steel will make the deck slimmer and hence aesthetically more
appealing.
● Effiage planned and manufactured the components and logistics
well in advance. Steel components were prefabricated at Eiffel’s
2 factories at Lauterbourg and Fos-ur-mer on either sides of the
valley and 2 production units in middle of the valley to produce
HS-Concrete for piers and abutments.
• Appointed 2 safety officers and employees were provided with
PPEs and trainings well in advance before the work begun,
distribution of Index Cards (Giving details and order in which
tasks should be carried out, and risks involved and how to avoid
them).
• Due to the construction of Millau Viaduct, the localities will
benefit economically. This project is also going to improve the
relationships among the local communities, state authority took
active approach in improving the connectivity for travelling
public, constructed 9 kms road including a bridge to link the
valley from both the sides and another road for motorists to
travel around the construction site.
• The decision to procure the Millau Viaduct under a concession/BFOT
scheme was made. The decision relates to the lack of public funds
available to provide the A75 missing link, namely the Viaduct. Again, in the
initial planning stage, the link was conceived of as a free highway without
any toll. As the public budget could not accommodate such expense the
only way to avoid postponing the project delivery – and its economic
benefits – was to find a source of alternative funding. That is why the Millau
Viaduct came to rely exclusively on private finance. More precisely, the
initial investment relied on the corporate funds of the Compagnie Eiffage
which then re-negotiated a loan from the banks at a lower interest rate,
once the construction risks disappeared (Coste, 2006).
CHALLENGES
• To build the tallest piers in the
world
• To put 36000 ton freeway on top of
it.
SOLUTIONS
• Use of GPS satellite system, work
on all piers were independent,
invited experts in the field of form
works.
• Installed 7 extra temporary piers,
Decks were pre-constructed, Safety
and quality tests. Assembling of
pre-constructed decks started from
either sides, launch followed well
established procedure and
precautions, weather forecast, Used
hydraulic system, high pressure
traversers, guided by GPS system.
Problems faced during CONSTRUCTION PHASE
• Safety of travelling public
• HR management.
• Minimum environmental
impact.
• Material management.
• Constructed another 9km road
for people who are travelling.
• Aimed for Zero accidents, Most
of the staff worked for one
company and its subsidiaries
which attributed to quality HR
management.
• Engaged services of 2
environment specialists, employed
fewer machines and truck, used
steel instead of concrete,
Monitored air & noise levels, local
water resources.
•Secondary tracks to ferry
materials, manufactured material
according to requirements at site,
Recycled oils and lubricants.
• Extreme weather conditions like
high wind speed, rain.
• Complexity of formwork.
• Weather forecasting is done
effectively and activities are
planned accordingly.
• Invited experts in field of
formwork, designed self
climbing formwork, GPS
technology, Used formwork that
can withstand high speed
concreting and high wind
speed.
Problems faced during and even after Close-out
● Safety and Maintenance of the Viaduct
● Type of coating to be given.
● To monitor functioning quality of viaduct.
● Commissioning
● Risk of Suicidal Events
● Increased traffic than that to forecasted
● Local nuisance for media attraction for the issues of local
farmers.
● Maintenance frequency is increased with time and period of the
year keeping in mind the volume of passing vehicles.
● Coating was developed by Appia, a subsidiary of Eiffage after 2
years of research and test. Several activities like shot blasting,
applied bonding primer, heat sealed bituminous layer to surface
was done before application coating. (Type of Coating to be
used)
● Power, video, IT were installed for smooth functioning. Several
detectors were installed in order to detect minute movements
also to know wear & tear on structure. Measuring instruments
were installed to foundation slab for knowing different stress.
Cable stays were fitted with instruments that measured their
aging. (Safety & Monitoring)
Responses to Challenges and Opportunities during Close-out
● The outer most lanes are kept for emergency use only
(Ambulance/Media/Emergency) since this prohibits the
passengers and tourists to stop near the edge of the bridge.
(Safety and Monitoring)
● It was extensively tested for safety by fleet of 30 heavy trucks
weighing total of 1000 tons. The test was lasted for three and half
days, and analyzed 21 different type of load stresses. (Testing
and Commissioning)
Conclusion and Summary
● The main factors of success as decisions related to:
The technical choices, in
particular decision to
build the bridge in steel
The people who
contributed to the
different phases of
Viaduct
The Initial Planning and
Route Selection
The procurement
decisions and
Concession
Critical
Success
Factors
Key elements that lead to success of Millau Viaduct are as follows
● The initial design of viaduct by four experts P. Godin, M. Rat, M Panet
and M. Virlogeux was challenged by state (public), design
involvement of the international experts and the British Architect Sir
Norman Foster improved the process.
● The Millau Viaduct project provides an encouraging example of how
effective planning and project management can result in phenomenal
success, even in the largest and most complex of scenarios.
● Despite the immense technical challenge posed by such a bold
venture, Eiffage were able to demonstrate the competency and
attention to detail necessary to facilitate effective project
management. Precise co-ordination of numerous contractors and
other entities, as well as appropriate selection of cutting edge tools
and methodologies paved the way for a highly successful project.
● Extensive planning in the early stages of the project, as well as
consideration of the risks and uncertainties associated with such a
large-scale project all helped to ensure the management team were
able to easily respond to any difficulties or change in circumstances
over the course of the project. Of particular note, the communication
channels and "short command chain" both increased flexibility,
response times to changes in specification and general awareness
between the different entities involved in the project.
● The risk transfer methodology at that time proved profitable and
productive.
● The end result is an astonishing feat, both from a technical and a
managerial standpoint, and it is likely that the Millau Viaduct will stand
as one of our greatest technical achievements for quite some time
● https://www.wikiwand.com/en/Millau_Viaduct
● http://flax.nzdl.org/greenstone3/flax;jsessionid=5DE5EB50010ADF134AE474
87620992E1?a=d&c=BAWEPS&d=D1579&dt=simple&p.a=b&p.s=ClassifierB
rowse
● https://sites.google.com/site/themillauviaduct/challenges
● https://sites.google.com/site/projectmillauviaduct/
● http://www.omegacentre.bartlett.ucl.ac.uk/wp-
content/uploads/2014/12/FRANCE_MILLAU_PROFILE.pdf
References
Thank
You

More Related Content

What's hot

Depots presentation
Depots presentationDepots presentation
Depots presentationKumar M.
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge constructionKundan Sanap
 
Specialization of Civil Engineering
 Specialization of Civil Engineering Specialization of Civil Engineering
Specialization of Civil EngineeringRAMPRASAD KUMAWAT
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repairKartikSuryawanshi2
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever BridgeJeelkumar Patel
 
Curriculum Vitae Abdessamad YADINI
Curriculum Vitae Abdessamad YADINICurriculum Vitae Abdessamad YADINI
Curriculum Vitae Abdessamad YADINIAbdessamad Yadini
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railwayRAMPRASAD KUMAWAT
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of buildingKrishnagnr
 
PLANNING AND DESIGN OF SEWERS USING ADVANCED TECHNIQUES FOR PROPOSED SEWERA...
PLANNING AND DESIGN OF SEWERS  USING ADVANCED TECHNIQUES  FOR PROPOSED SEWERA...PLANNING AND DESIGN OF SEWERS  USING ADVANCED TECHNIQUES  FOR PROPOSED SEWERA...
PLANNING AND DESIGN OF SEWERS USING ADVANCED TECHNIQUES FOR PROPOSED SEWERA...Rajnish Bajaj
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume StudyAbontee
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridgesmukul srivastava
 
Measurement of Traffic Flow Characteristics at mid-block sections -Universal ...
Measurement of Traffic Flow Characteristics at mid-block sections -Universal ...Measurement of Traffic Flow Characteristics at mid-block sections -Universal ...
Measurement of Traffic Flow Characteristics at mid-block sections -Universal ...ShaikhAtif12
 

What's hot (20)

Depots presentation
Depots presentationDepots presentation
Depots presentation
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge construction
 
Specialization of Civil Engineering
 Specialization of Civil Engineering Specialization of Civil Engineering
Specialization of Civil Engineering
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
458
458458
458
 
Bridge
BridgeBridge
Bridge
 
Sydney harbour bridge
Sydney harbour bridgeSydney harbour bridge
Sydney harbour bridge
 
Bridge
BridgeBridge
Bridge
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repair
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
 
Curriculum Vitae Abdessamad YADINI
Curriculum Vitae Abdessamad YADINICurriculum Vitae Abdessamad YADINI
Curriculum Vitae Abdessamad YADINI
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
 
Design traffic For Highways
Design traffic For HighwaysDesign traffic For Highways
Design traffic For Highways
 
Segmental bridge constructin techniques
Segmental bridge constructin techniquesSegmental bridge constructin techniques
Segmental bridge constructin techniques
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
 
PLANNING AND DESIGN OF SEWERS USING ADVANCED TECHNIQUES FOR PROPOSED SEWERA...
PLANNING AND DESIGN OF SEWERS  USING ADVANCED TECHNIQUES  FOR PROPOSED SEWERA...PLANNING AND DESIGN OF SEWERS  USING ADVANCED TECHNIQUES  FOR PROPOSED SEWERA...
PLANNING AND DESIGN OF SEWERS USING ADVANCED TECHNIQUES FOR PROPOSED SEWERA...
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
 
Measurement of Traffic Flow Characteristics at mid-block sections -Universal ...
Measurement of Traffic Flow Characteristics at mid-block sections -Universal ...Measurement of Traffic Flow Characteristics at mid-block sections -Universal ...
Measurement of Traffic Flow Characteristics at mid-block sections -Universal ...
 

Similar to The Millau Viaduct Project - An Engineering Marvel

Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationPierre HUBERT
 
METRO RAIL ASIA 2010
METRO RAIL ASIA 2010METRO RAIL ASIA 2010
METRO RAIL ASIA 2010gifanta
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgradeRobert Lee - CEng, MICE, PMP
 
Status of roads in nairobi by ps mo r 2nd august 2012
Status of roads in nairobi  by ps mo r 2nd august 2012Status of roads in nairobi  by ps mo r 2nd august 2012
Status of roads in nairobi by ps mo r 2nd august 2012Functional Eco
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...peter747
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaductJayanta Sen
 
Cv c d'urbal-technical supervisor(°°)
Cv c d'urbal-technical supervisor(°°)Cv c d'urbal-technical supervisor(°°)
Cv c d'urbal-technical supervisor(°°)Durbal
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarAssociation for Project Management
 
Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Shobhit Shekhar
 
Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Atkins
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale BridgeZeynepUla2
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Crosstown TO
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Fairfax County
 
Torino Metro Experience
Torino Metro ExperienceTorino Metro Experience
Torino Metro Experiencegifanta
 

Similar to The Millau Viaduct Project - An Engineering Marvel (20)

Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate Presentation
 
METRO RAIL ASIA 2010
METRO RAIL ASIA 2010METRO RAIL ASIA 2010
METRO RAIL ASIA 2010
 
Firas Abbawy CV - Atkins
Firas Abbawy CV - AtkinsFiras Abbawy CV - Atkins
Firas Abbawy CV - Atkins
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
Status of roads in nairobi by ps mo r 2nd august 2012
Status of roads in nairobi  by ps mo r 2nd august 2012Status of roads in nairobi  by ps mo r 2nd august 2012
Status of roads in nairobi by ps mo r 2nd august 2012
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 
Cv c d'urbal-technical supervisor(°°)
Cv c d'urbal-technical supervisor(°°)Cv c d'urbal-technical supervisor(°°)
Cv c d'urbal-technical supervisor(°°)
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3
 
Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...Analyst presentation: Crossrail and our international tunnelling expertise - ...
Analyst presentation: Crossrail and our international tunnelling expertise - ...
 
M25 Media Pack
M25 Media PackM25 Media Pack
M25 Media Pack
 
Kari rouhonen
Kari rouhonenKari rouhonen
Kari rouhonen
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale Bridge
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020
 
Torino Metro Experience
Torino Metro ExperienceTorino Metro Experience
Torino Metro Experience
 

Recently uploaded

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 

Recently uploaded (20)

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 

The Millau Viaduct Project - An Engineering Marvel

  • 1. Millau Viaduct THE MILLAU VIADUCT PROJECT AN ENGINEERING MARVEL Presented By: Shivam Sood: PP18085 Adarsh M.S : PP18086 Karan Dujari: PP18087 Shikhar Pandey: PP18088 Abhash Shrivastav: PP18089 Pushpak Pullawar: PP18090 Bhavya Agrawal: PP18091 Guided By: Dr. T.K Ganguli
  • 2. Question: What are the challenges faced by the Project during the life cycle and how it responded to those challenges and opportunities?
  • 3. Contents of the Presentation 1. Background 2. Project Timeline 3. Project Team and Stakeholders Involved 4. Intention behind Millau Viaduct Construction 5. Project Phases (Problems and Responses) 1. Pre-Construction and Planning Stage 2. Construction 3. Close-out 6. Conclusions and Keylearnings
  • 4. 1987-1992 1993-1996 1998- 2000 March 2001 May,2001 8th Oct,2001 10th October,2001 20th February, 2002 • Change of Governance • Introduction of BFOT • The first inter ministry decree is amended in order to conform the concession conditions and allow the toll system Signature of the concession contract Beginning of Construction phase Construction Project Design & Conception EFFIAGE won the bid for the delivery of the Project • The council of the state approves the project via ministry decree • Decision to build the deck with steel rather concrete Procurement Control of Construction Est. of the expert committee of ACDC by Jean Francois Coste Feasibility Studies/Research 14th December, 2004 Project Delivery Inauguration of the Millau Viaduct and beginning of the operation phases after couple of days Plan Completion12 Years Project Timeline
  • 5. Project Stakeholders ● Local Authorities ● The Conceding Authority The State (Ministry of Infrastructure) is the conceding authority. The ministry opened the concession of the Viaduct to competition and awarded it to EFFiAGE group which is both structure’s builder and concessionary. ● Eiffage Eiffage is the third largest group in France in the field of construction, civil engineering and construction related services. It is currently in fifth position in Europe. It has a staff of 41,000 in France and the rest of the world and in the financial year 2000 had an ex-VAT turnover of 6.25 billion Euros.
  • 6. ● Eiffage Construction In the case of the Millau viaduct, its subsidiary Eiffage TP, which is one of the largest French civil engineering and earthworks companies, will be responsible for all the concrete structures. ● The Arrondissement Interdépartemental des Ouvrages d’ Art (AIOA) Was given responsibility by the conceding authority to conduct monitoring. the AIOA reports to the infrastructure directorate of Aveyron Department which was also the construction manager for works on the A75 motorway on both sides of the viaduct.
  • 7. ● The Compagnie du viaduc de Millau This company was specially set up for the purpose and draws on the experience of the Eiffage concessions department. This company is the project owner, and has responsibility for the overall funding of the operation and its subsequent management. It conducts negotiations with the other parties involved with the viaduct (Central Government, local authorities, etc.). The Compagnie du Viaduc de Millau has awarded the works to two large subsidiaries of the Eiffage group: Eiffage construction will be responsible for concrete construction and Eiffel for metal construction. ● Eiffel Construction The members that will make up the deck and pylons of the viaduct are to be manufactured at Lauterbourg and Fos-sur-Mer. Teams from Eiffel will then assemble and install all the metal elements of the viaduct on site.
  • 8. ● SETEC Was asked by Eiffage to manage the entire construction phase of the viaduct. SETEC is particularly specialized in the management of large infrastructure and building projects and it is responsible for monitoring, consultancy and worksite coordination. SETEC will ensure that studies and works are conducted to the highest standards. It will be assisted, for monitoring the manufacture of the metal part of the structure, by the engineering division of the SNCF (French national railways).
  • 9. Intention behind Millau Viaduct Construction ? ● Millau Viaduct was the outcome of a government project, commissioned in order to complete an important section of the A75 autoroute. Prior to construction of the viaduct, traffic travelling along this route had to descend to the Tarn Valley and travel along the Route National N9, passing through Millau (a city). This caused particular problems (especially in terms of congestion) in the summer holiday season due to the vast number of tourists travelling to Southern France and Spain along this route. ● The government reacted to increasing traffic along this route in the mid-1980s, quickly recognising the necessity for a method of traversing the Tarn valley, and commissioning initial studies into four available options in 1988.
  • 10. ● "The Eastern Option" - Requiring two major bridges. Shorter and better for through traffic, but providing poor access to Millau. ● "The RN9 Option" - Following the original path of Route Nationale 9 providing good access to Millau but at the cost of technical difficulties and intrusion on the town ● "The Western Option" - Requiring four major bridges, technically easier but expensive and providing poor access to Millau. ● "The Median Option" – Traverse the middle of the valley.
  • 11. The fourth option was selected by ministerial decree on 28 June 1989. It encompassed two possibilities. ● The High Solution: Envisaging a 2,500-metre-long (8,200 ft) viaduct more than 200 meters (660 ft.) above the river. ● The Low Solution: Descending into the valley and crossing the river on a 200-metre-long (660 ft.) bridge, then a viaduct of 2,300 meters (7,500 ft.).
  • 12. Project Phases ● Pre-Construction and Planning Stage ● Construction Stage ● Project Completion Stage/Close-out
  • 13. Problems during Pre-Construction and Planning Stage 1. The problem was to decide the way to cross the Tarn Valley for which choice between the high and low solutions was an vital concern as no proper design was present. 2. Lack of construction skills. 3. Technical issues ( Material to be used for the deck, requirement of temporary piers, high wind speeds and seismic activities at such height.) 4. Manufacturing, logistics and inventory control. 5. Safety of the workers, employees and other team members.
  • 14. 6. Apart from indisputable proofs of the positive effects of viaduct on local economic development some of them deplore insufficient leadership from the state level. 7. There was lack of public funds available for the existing missing link in A75 for which 2 millions francs was required, management was in awe to get the funds as public funding was not enough and expenses couldn’t be borne by them.
  • 15. Responses to challenges and opportunities during Conceptualization • After long construction studies by the Ministry of Public Works, the low solution was abandoned because it would have intersected the water table and had a negative impact on the town, cost more, and lengthened the driving distance. High solution was decided by ministerial decree. After the choice of the high viaduct, five teams of architects and researchers worked on a technical solution. The concept and design for the bridge was devised by French designers and structural engineer Dr. Michel Virlogeux. He worked with the Dutch engineering firm ARCADIS , responsible for the structural engineering of the bridge. • Effiage entered into the partnership with other companies to acquire the construction skills it did not possess e.g.. Eiffel Construction Metaliique for steel construction. Various structural components were tested by CSTB in a wind tunnel.
  • 16. ● Effiage chose steel in order to shorten the construction period and hence allowing them to collect the toll sooner, also use of steel will make the deck slimmer and hence aesthetically more appealing. ● Effiage planned and manufactured the components and logistics well in advance. Steel components were prefabricated at Eiffel’s 2 factories at Lauterbourg and Fos-ur-mer on either sides of the valley and 2 production units in middle of the valley to produce HS-Concrete for piers and abutments.
  • 17. • Appointed 2 safety officers and employees were provided with PPEs and trainings well in advance before the work begun, distribution of Index Cards (Giving details and order in which tasks should be carried out, and risks involved and how to avoid them). • Due to the construction of Millau Viaduct, the localities will benefit economically. This project is also going to improve the relationships among the local communities, state authority took active approach in improving the connectivity for travelling public, constructed 9 kms road including a bridge to link the valley from both the sides and another road for motorists to travel around the construction site.
  • 18. • The decision to procure the Millau Viaduct under a concession/BFOT scheme was made. The decision relates to the lack of public funds available to provide the A75 missing link, namely the Viaduct. Again, in the initial planning stage, the link was conceived of as a free highway without any toll. As the public budget could not accommodate such expense the only way to avoid postponing the project delivery – and its economic benefits – was to find a source of alternative funding. That is why the Millau Viaduct came to rely exclusively on private finance. More precisely, the initial investment relied on the corporate funds of the Compagnie Eiffage which then re-negotiated a loan from the banks at a lower interest rate, once the construction risks disappeared (Coste, 2006).
  • 19. CHALLENGES • To build the tallest piers in the world • To put 36000 ton freeway on top of it. SOLUTIONS • Use of GPS satellite system, work on all piers were independent, invited experts in the field of form works. • Installed 7 extra temporary piers, Decks were pre-constructed, Safety and quality tests. Assembling of pre-constructed decks started from either sides, launch followed well established procedure and precautions, weather forecast, Used hydraulic system, high pressure traversers, guided by GPS system. Problems faced during CONSTRUCTION PHASE
  • 20. • Safety of travelling public • HR management. • Minimum environmental impact. • Material management. • Constructed another 9km road for people who are travelling. • Aimed for Zero accidents, Most of the staff worked for one company and its subsidiaries which attributed to quality HR management. • Engaged services of 2 environment specialists, employed fewer machines and truck, used steel instead of concrete, Monitored air & noise levels, local water resources. •Secondary tracks to ferry materials, manufactured material according to requirements at site, Recycled oils and lubricants.
  • 21. • Extreme weather conditions like high wind speed, rain. • Complexity of formwork. • Weather forecasting is done effectively and activities are planned accordingly. • Invited experts in field of formwork, designed self climbing formwork, GPS technology, Used formwork that can withstand high speed concreting and high wind speed.
  • 22. Problems faced during and even after Close-out ● Safety and Maintenance of the Viaduct ● Type of coating to be given. ● To monitor functioning quality of viaduct. ● Commissioning ● Risk of Suicidal Events ● Increased traffic than that to forecasted ● Local nuisance for media attraction for the issues of local farmers.
  • 23. ● Maintenance frequency is increased with time and period of the year keeping in mind the volume of passing vehicles. ● Coating was developed by Appia, a subsidiary of Eiffage after 2 years of research and test. Several activities like shot blasting, applied bonding primer, heat sealed bituminous layer to surface was done before application coating. (Type of Coating to be used) ● Power, video, IT were installed for smooth functioning. Several detectors were installed in order to detect minute movements also to know wear & tear on structure. Measuring instruments were installed to foundation slab for knowing different stress. Cable stays were fitted with instruments that measured their aging. (Safety & Monitoring) Responses to Challenges and Opportunities during Close-out
  • 24. ● The outer most lanes are kept for emergency use only (Ambulance/Media/Emergency) since this prohibits the passengers and tourists to stop near the edge of the bridge. (Safety and Monitoring) ● It was extensively tested for safety by fleet of 30 heavy trucks weighing total of 1000 tons. The test was lasted for three and half days, and analyzed 21 different type of load stresses. (Testing and Commissioning)
  • 25. Conclusion and Summary ● The main factors of success as decisions related to: The technical choices, in particular decision to build the bridge in steel The people who contributed to the different phases of Viaduct The Initial Planning and Route Selection The procurement decisions and Concession Critical Success Factors
  • 26. Key elements that lead to success of Millau Viaduct are as follows ● The initial design of viaduct by four experts P. Godin, M. Rat, M Panet and M. Virlogeux was challenged by state (public), design involvement of the international experts and the British Architect Sir Norman Foster improved the process. ● The Millau Viaduct project provides an encouraging example of how effective planning and project management can result in phenomenal success, even in the largest and most complex of scenarios. ● Despite the immense technical challenge posed by such a bold venture, Eiffage were able to demonstrate the competency and attention to detail necessary to facilitate effective project management. Precise co-ordination of numerous contractors and other entities, as well as appropriate selection of cutting edge tools and methodologies paved the way for a highly successful project.
  • 27. ● Extensive planning in the early stages of the project, as well as consideration of the risks and uncertainties associated with such a large-scale project all helped to ensure the management team were able to easily respond to any difficulties or change in circumstances over the course of the project. Of particular note, the communication channels and "short command chain" both increased flexibility, response times to changes in specification and general awareness between the different entities involved in the project. ● The risk transfer methodology at that time proved profitable and productive. ● The end result is an astonishing feat, both from a technical and a managerial standpoint, and it is likely that the Millau Viaduct will stand as one of our greatest technical achievements for quite some time
  • 28. ● https://www.wikiwand.com/en/Millau_Viaduct ● http://flax.nzdl.org/greenstone3/flax;jsessionid=5DE5EB50010ADF134AE474 87620992E1?a=d&c=BAWEPS&d=D1579&dt=simple&p.a=b&p.s=ClassifierB rowse ● https://sites.google.com/site/themillauviaduct/challenges ● https://sites.google.com/site/projectmillauviaduct/ ● http://www.omegacentre.bartlett.ucl.ac.uk/wp- content/uploads/2014/12/FRANCE_MILLAU_PROFILE.pdf References