Metal-Clad SwitchgearMetal-Clad Switchgear
Installation & Precommissioning InspectionInstallation & Precommissioning Inspection
April 15, 2007
Abdullah M Al-Dushaishi
2
OUTLINEOUTLINE
EQUIPMENT INSTALLATION INSPECTION
BUSBAR INSTALLATION INSPECTION
CABLE CONNECTION INSPECTION
GROUNDING CONNECTION INSPECTION
SOME DESIGN CONCERNS
PRE-COMMISSIONING
REFERENCES
3
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Ensure that adequate protection is provided when installing
switchgear
Switchgear shall only be installed in an indoor, air-conditioned
environment
Switchgear shall have an unobstructed horizontal space of:
a) Not less than 2 meters in front
b) Not less than 1 meter in back and sides
Spacing requirement between equipment shall be based upon
the largest dimension for either
4
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Lifting/handling devices shall be provided within a room
containing switchgear to mechanically assist in removing to
floor level, any withdrawable component (e.g., circuit breaker,
contactor, potential transformer, etc.) weighing over 20 kg
Switchgear shall be free of any physical damage after
installation
Switchgear should be properly anchored to its foundation
5
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Switches, circuit breakers, and other operating mechanisms
shall be manually exercised to make sure that they are
properly aligned and operate freely
Grounding connections shall be made properly
Debris, scrap wires and surplus shall be removed from the
switchgear interior before closing the enclosure
6
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Covers, doors & enclosure parts shall
be properly tightened
The switchgear shall be vertically &
horizontally aligned before anchoring
Check components for proper
identification as per IFC drawings and
specifications
Nameplate on equipment shall conform
to single line diagrams and schematics
7
EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION
INSPECTIONINSPECTION
Concrete floor in front of switchgear shall be flush with the
roller level of lower breaker carriage rack and have a smooth
surface to facilitate removal and rolling of breaker
The bay spacing of transformers and the location of the
incoming circuit breakers on switchgear lineups shall be
positioned to minimize metal enclosed bus or cable bus length
and/or eliminate bends
Preferably, incomer circuit breakers shall be located at ends
of switchgear lineup
Unavoidable bends in cable bus or metal enclosed bus shall
be inside the substation building
8
BUSBAR INSTALLATIONBUSBAR INSTALLATION
INSPECTIONINSPECTION
Neutral buses shall not be used within
switchgear
Cable shall not be used to extend the
main bus of switchgear
9
BUSBAR INSTALLATIONBUSBAR INSTALLATION
INSPECTIONINSPECTION
Contact surfaces for the main bus
connections shall be clean
Tightness of bolted bus joints are correct
as per manufacturer's instruction for the
proper torque (foot-pound) levels
10
CABLECONNECTION INSPECTIONCABLECONNECTION INSPECTION
Cable phasing shall be in accordance
with connection diagram
Proper cable tags shall be provided
Cables termination shall be in accordance
with cable manufacturer's instruction
Cable connections are clean and securely
bolted.
Bolt torque values shall be as per
manufacturer's specifications
11
GROUNDING CONNECTIONGROUNDING CONNECTION
INSPECTIONINSPECTION
Sections of ground bus previously disconnected at shipping
sections shall be reconnected when units are installed
Secondary wirings are connected to switchgear ground bus as
indicated on IFC drawings
Ground bus shall be connected direct to grounding grid and
shall not run in metal conduit unless conduit is adequately
bonded to the circuit
12
SOMEDESIGN CONCERNSSOMEDESIGN CONCERNS
Switchgear shall not be used to control:
low voltage motors and
high voltage motors rated less than 5kV
In industrial facilities, 480V switchgear shall not be fed from
4160V systems
A separate 120 VAC branch circuit shall be provided for the
space heater
13
PRE-COMMISSIONINGPRE-COMMISSIONING
Check electrical relays, meters, or
instruments to determine connections
are made properly and devices function
properly
Check settings of the adjustable
current and voltage trip mechanisms to
confirm that they are at proper values.
Check control, power transformer and
PT fuses for size, type, and circuit
location
Check PT and CT ratios
14
PRE-COMMISSIONINGPRE-COMMISSIONING
Check wiring connections for
tightness at instrument transformers
and terminal blocks
Protective devices’ setting for
current, voltage, or other relays shall
be done on-site in accordance with
manufacturer’s recommendation
Ground-fault protection system shall
be tested in accordance with
manufacturer's instruction
15
PRE-COMMISSIONINGPRE-COMMISSIONING
Protective relays, overcurrent trip devices, and breakers shall
be tested for correct connections and operation at factory
Factory test results shall be referenced during
Precommissioning
16
PRE-COMMISSIONINGPRE-COMMISSIONING
Insulation resistance test shall be performed to make sure
switchgear is free from short circuits and grounds. This test shall
be done both phase to ground and phase to phase and with the
switches and breakers both opened and closed
Switchgear busbar shall be tested for insulation resistance with
a 1-minute test (phase to phase and phase to ground) with 1kV
megohmmeter
Instrument transformers shall be tested for insulation resistance
with a 1-minute test with 1 kV megohmmeter
17
PRE-COMMISSIONINGPRE-COMMISSIONING
Each circuit breaker protective relay device shall be calibrated
and tested with final settings in accordance with relay setting
summary or coordination study
With CT disconnected, CT secondary circuit shall be tested for
continuity and operation of applicable relays and meters by
applying current to the CT secondary winding
PT secondary circuit shall be tested by applying voltage to the
PT secondary, with PT disconnected, verifying operation of all
applicable relays and meters
18
PRE-COMMISSIONINGPRE-COMMISSIONING
Space heaters, switching and indicating devices shall be tested
for operation
Auxiliary devices interlocks shall be tested for operation
Local and remote control devices/circuits shall be tested
according to engineering specification
19
REFERENCESREFERENCES
NFPA 70 --National Electrical Code, 2005
NETA ATS -- Acceptance Testing Specification for Electrical
Power Distribution Equipment and Systems, 1999
SAES-P-116 -- Switchgear and Control Equipment, 28
February 2005
SAES-P-119 -- Onshore Substations, 30 march 2005

Switchgear Installation Precomissioning Inspection.PPT

  • 1.
    Metal-Clad SwitchgearMetal-Clad Switchgear Installation& Precommissioning InspectionInstallation & Precommissioning Inspection April 15, 2007 Abdullah M Al-Dushaishi
  • 2.
    2 OUTLINEOUTLINE EQUIPMENT INSTALLATION INSPECTION BUSBARINSTALLATION INSPECTION CABLE CONNECTION INSPECTION GROUNDING CONNECTION INSPECTION SOME DESIGN CONCERNS PRE-COMMISSIONING REFERENCES
  • 3.
    3 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Ensure that adequateprotection is provided when installing switchgear Switchgear shall only be installed in an indoor, air-conditioned environment Switchgear shall have an unobstructed horizontal space of: a) Not less than 2 meters in front b) Not less than 1 meter in back and sides Spacing requirement between equipment shall be based upon the largest dimension for either
  • 4.
    4 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Lifting/handling devices shallbe provided within a room containing switchgear to mechanically assist in removing to floor level, any withdrawable component (e.g., circuit breaker, contactor, potential transformer, etc.) weighing over 20 kg Switchgear shall be free of any physical damage after installation Switchgear should be properly anchored to its foundation
  • 5.
    5 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Switches, circuit breakers,and other operating mechanisms shall be manually exercised to make sure that they are properly aligned and operate freely Grounding connections shall be made properly Debris, scrap wires and surplus shall be removed from the switchgear interior before closing the enclosure
  • 6.
    6 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Covers, doors &enclosure parts shall be properly tightened The switchgear shall be vertically & horizontally aligned before anchoring Check components for proper identification as per IFC drawings and specifications Nameplate on equipment shall conform to single line diagrams and schematics
  • 7.
    7 EQUIPMENTINSTALLATIONEQUIPMENTINSTALLATION INSPECTIONINSPECTION Concrete floor infront of switchgear shall be flush with the roller level of lower breaker carriage rack and have a smooth surface to facilitate removal and rolling of breaker The bay spacing of transformers and the location of the incoming circuit breakers on switchgear lineups shall be positioned to minimize metal enclosed bus or cable bus length and/or eliminate bends Preferably, incomer circuit breakers shall be located at ends of switchgear lineup Unavoidable bends in cable bus or metal enclosed bus shall be inside the substation building
  • 8.
    8 BUSBAR INSTALLATIONBUSBAR INSTALLATION INSPECTIONINSPECTION Neutralbuses shall not be used within switchgear Cable shall not be used to extend the main bus of switchgear
  • 9.
    9 BUSBAR INSTALLATIONBUSBAR INSTALLATION INSPECTIONINSPECTION Contactsurfaces for the main bus connections shall be clean Tightness of bolted bus joints are correct as per manufacturer's instruction for the proper torque (foot-pound) levels
  • 10.
    10 CABLECONNECTION INSPECTIONCABLECONNECTION INSPECTION Cablephasing shall be in accordance with connection diagram Proper cable tags shall be provided Cables termination shall be in accordance with cable manufacturer's instruction Cable connections are clean and securely bolted. Bolt torque values shall be as per manufacturer's specifications
  • 11.
    11 GROUNDING CONNECTIONGROUNDING CONNECTION INSPECTIONINSPECTION Sectionsof ground bus previously disconnected at shipping sections shall be reconnected when units are installed Secondary wirings are connected to switchgear ground bus as indicated on IFC drawings Ground bus shall be connected direct to grounding grid and shall not run in metal conduit unless conduit is adequately bonded to the circuit
  • 12.
    12 SOMEDESIGN CONCERNSSOMEDESIGN CONCERNS Switchgearshall not be used to control: low voltage motors and high voltage motors rated less than 5kV In industrial facilities, 480V switchgear shall not be fed from 4160V systems A separate 120 VAC branch circuit shall be provided for the space heater
  • 13.
    13 PRE-COMMISSIONINGPRE-COMMISSIONING Check electrical relays,meters, or instruments to determine connections are made properly and devices function properly Check settings of the adjustable current and voltage trip mechanisms to confirm that they are at proper values. Check control, power transformer and PT fuses for size, type, and circuit location Check PT and CT ratios
  • 14.
    14 PRE-COMMISSIONINGPRE-COMMISSIONING Check wiring connectionsfor tightness at instrument transformers and terminal blocks Protective devices’ setting for current, voltage, or other relays shall be done on-site in accordance with manufacturer’s recommendation Ground-fault protection system shall be tested in accordance with manufacturer's instruction
  • 15.
    15 PRE-COMMISSIONINGPRE-COMMISSIONING Protective relays, overcurrenttrip devices, and breakers shall be tested for correct connections and operation at factory Factory test results shall be referenced during Precommissioning
  • 16.
    16 PRE-COMMISSIONINGPRE-COMMISSIONING Insulation resistance testshall be performed to make sure switchgear is free from short circuits and grounds. This test shall be done both phase to ground and phase to phase and with the switches and breakers both opened and closed Switchgear busbar shall be tested for insulation resistance with a 1-minute test (phase to phase and phase to ground) with 1kV megohmmeter Instrument transformers shall be tested for insulation resistance with a 1-minute test with 1 kV megohmmeter
  • 17.
    17 PRE-COMMISSIONINGPRE-COMMISSIONING Each circuit breakerprotective relay device shall be calibrated and tested with final settings in accordance with relay setting summary or coordination study With CT disconnected, CT secondary circuit shall be tested for continuity and operation of applicable relays and meters by applying current to the CT secondary winding PT secondary circuit shall be tested by applying voltage to the PT secondary, with PT disconnected, verifying operation of all applicable relays and meters
  • 18.
    18 PRE-COMMISSIONINGPRE-COMMISSIONING Space heaters, switchingand indicating devices shall be tested for operation Auxiliary devices interlocks shall be tested for operation Local and remote control devices/circuits shall be tested according to engineering specification
  • 19.
    19 REFERENCESREFERENCES NFPA 70 --NationalElectrical Code, 2005 NETA ATS -- Acceptance Testing Specification for Electrical Power Distribution Equipment and Systems, 1999 SAES-P-116 -- Switchgear and Control Equipment, 28 February 2005 SAES-P-119 -- Onshore Substations, 30 march 2005