SlideShare a Scribd company logo
1 of 31
-Shailendra Yadav
EE-42(0705420096)
1
INTRODUCTION OF
SUBSTATION
It is situated at 26°34’2’’N & 80°32’57’’E coordinates
in Dahi Chowki 6.64 km far from Unnao railway station.
Constructed during 1994-98 by CGL.
The whole substation is divided in three parts:
132kv switchyard
400/220kv switchyard
765kv switchyard (Under construction)
2
INCOMING & OUTGOING LINE OF
SUBSTATION
•Unnao to Lucknow (400KV & 220KV both separate)
•Unnao to Bareily-1 (400KV)
•Unnao to Bareily-2 (400KV)
•Unnao to Agara (400KV)
•Unnao to Panki Kanpur(400KV & 220KV both separate)
•Unnao to Anpara (400KV)
•Unnao to PGCIL Lucknow-1 (400KV)
•Unnao to PGCIL Lucknow-2 (400KV)
•One bus bar for 400/220KV 315MVA ICT-1 & ICT-2 line.
3
OUTDOOR EQUIPMENT USED IN
SUBSTATION
 Two 100MVA 220/132KV transformer
 Two 315MVA 400/220KV transformer
 Shunt reactor
 Capacitor bank
 SF6 circuit breaker
 Isolators
 Lightning arresters
 Current transformer
 Capacitor voltage transformer
 Wave trap
 Isolators
4
Transformer H.V. side
bushing CT
COOLING SYSTEM
(ONAN)
ConservaterTank
L.V. side bushing
CTs
5
Oil pump
Oil pump is
used for
circulating oil
forcelly.
Radiator
plates are
used for
increasing
surface area
for natural air
cooling.
Radiator plates
Earthing
plate 6
 we use Cooling fans for
forced air cooling of
transformer . Total six fans
are used for each 100MVA
and eight fans are used for
each 315 MVA transformer.
But all fans never start at
same time . It start in pairs .
COOLING FANS
7
Tertiary
terminal
Tertiary terminal mostly
opened.
The output voltage of
tertiary terminal is 11KV in
100MVA transformer and
33KV in 315 MVA
transformer
Pressure
relief valve
box
8
OLTC
chamber
9
TERMINALS ON TANK COVER
In these photos we can see fogging near transformer due to
operation fire protection system.
10
BUCHHOLZ RELAY
Buchholz relay is a safety device mounted on some oil-filled power
transformers and reactors. It is used as a protective device sensitive to
the effects of dielectric failure inside the equipment.
11
OTI & WTI
OTI –oil temp. indicator
measure temp. of oil filled
in transformer. In OTI has
two mercury bulb.
WTI- winding temp.
indicator measure winding
temp of transformer. It has
four mercury bulb.
OTI panel
WTI panel
mercury
bulb
12
CURRENT TRANSFORMER
In electrical engineering, a current
transformer (CT) is used for
measurement of electric currents.
Current transformers, together
with voltage transformers (VT)
(potential transformers (PT)), are
known as instrument transformers.
When current in a circuit is too high
to directly apply to measuring
instruments, a current transformer
produces a reduced current accurately
proportional to the current in the
circuit, which can be conveniently
connected to measuring and
recording instruments.
13
14
PROTECTION DIAGRAM
A capacitor voltage transformer
(CVT) is a transformer used in
power systems to step-down extra
high voltage signals and provide
low voltage signals either for
measurement or to operate a
protective relay.
The device has at least four
terminals, a high-voltage terminal a
ground terminal and at least one set
of secondary terminals.
CVTs are typically single-phase
devices
CAPACITOR VOLTAGE TRANSFORMER
15
Cross sectional view of CVT
1 - Primary terminal
2 - Cast aluminum bellow housing
3 - Stainless steel expansion bellow
4 - Compression spring
5 - Insulated voltage connection
6 - Capacitor elements
7 - Insulator (porcelain or composite)
8 - Voltage divider tap connection
9 - Cast-epoxy bushing
10 - HF terminal connection
11 - Ferro-resonance suppression
device
12 - Secondary terminals
13 - Oil level sight-glass
14 - Aluminum terminal box
15 - Intermediate transformer
16 - Oil/air block
17 - Oil sampling device
18 - Compensating reactor
19 - Aluminum cover plate
16
1. High Voltage terminal
2. Compensation reactor
3. Intermediate voltage
transformer
4. Ground terminal
5. Ferro-resonance
suppression device
6. Damping resistor
7. Carrier (HF) terminal
(optional)
8. Overvoltage protective
device
9. Secondary terminals
10. Link, to be opened for
test purposes
PRINCIPLE CIRCUIT DIAGRAM OF
CVT
17
CIRCUIT BREAKER
A circuit breaker is an
automatically-operated
electrical switch
designed to protect an
electrical circuit from
damage caused by
overload or short circuit.
In this image we can
see a SF6 circuit breaker
with double break
system.
18
ISOLATORS
An isolators switch are
used to completely de-
energized an electrical
circuit. High-voltage
isolation switches are used
in electrical substations to
allow isolation of apparatus
such as circuit breakers and
transformers, and
transmission lines, for
maintenance.
Isolating rod
Earth link rod
19
PANTOGRAPH ISOLATORS
In open state In close state
20
Central rotating double
break isolator
21
Wave trap
 Wave trap are used in
power system for carrier
communication.
 It trap the higher
frequency above 50Hz.
 It is the effort to utilize
the same transmission line
between two substation for
the purpose of
communications
22
23
LIGHTNING ARRESTOR
The overvoltage protection
is obtained by the use of
lightning / surge arresters.
Lightning Arresters or
Surge Arresters are always
connected in Shunt to the
equipment to be protected,
they provide a low
impedance path for the
surge current to the ground.
Mostly in present days
zinc oxide (ZnO) gapless
arresters are in use.
24
INTERPOSING C.T.
The interposing CTs are used
for Power transformer
Differential Protection
circuit. In a delta/Star Power
transformer, the cts will be
connected star and delta
formation, for eliminating
Zero sequence current on star
side. There will be mismatch
of secondary current , to
maintain equilibrium,
interposing Cts will be
connected to Delta formed
CTs.
25
RELAYS
Differential
relay
O/F protection +FFR
Group A trip relay
CB trouble relay
Group B trip relay
DR earth switch
relay
O/C protection
relays
Breaker failure
relay
RES E/F +O/L
Protection relay
26
Relay testing box
A outer view of Relay
Relay conti….
27
SHUNT REACTOR
 Shunt Reactor is a thyristor controlled high impedance
transformer.
A stable bus
voltage can be
maintained by
providing
variable reactive
power based on
the bus voltage
deviations due
to the load
variations.
28
SHUNT CAPACITOR
BANK
Shunt capacitor banks
are used to improve the
quality of the electrical
supply.
provide capacitive
reactive compensation.
Power factor correction.
29
30
31

More Related Content

What's hot

180degree conduction mode of 3 phase inverter
180degree conduction mode of  3 phase inverter180degree conduction mode of  3 phase inverter
180degree conduction mode of 3 phase inverterdineshanand810
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 
Per unit calculation
Per unit calculationPer unit calculation
Per unit calculationobaidurbd
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptAshutosh Srivastava
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
Distribution systems
Distribution systemsDistribution systems
Distribution systemsSURAJ PRASAD
 
Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad ADARSH KUMAR
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devicesRahul Aman
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptxRahaf Waheep
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission lineDhananjay Jha
 
Presentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliancePresentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical applianceNishant Kumar
 
Differential Protection Relay
DifferentialProtection RelayDifferentialProtection Relay
Differential Protection Relaykishore kish
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guideSlides Hub
 
Applications of power electronics in HVDC
Applications of  power electronics in HVDCApplications of  power electronics in HVDC
Applications of power electronics in HVDCKabilesh K
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training ReportSWAPNILKUMARGUPTA
 
Switchgear and protection 2
Switchgear and protection 2Switchgear and protection 2
Switchgear and protection 2Md Irshad Ahmad
 
Alternator protection
Alternator protectionAlternator protection
Alternator protectionjawaharramaya
 

What's hot (20)

180degree conduction mode of 3 phase inverter
180degree conduction mode of  3 phase inverter180degree conduction mode of  3 phase inverter
180degree conduction mode of 3 phase inverter
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
Per unit calculation
Per unit calculationPer unit calculation
Per unit calculation
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
Distribution systems
Distribution systemsDistribution systems
Distribution systems
 
Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad Report on visiting 132/33 kv substation teliarganj allahabad
Report on visiting 132/33 kv substation teliarganj allahabad
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devices
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptx
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
 
Sag and tension
Sag and tensionSag and tension
Sag and tension
 
Presentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliancePresentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliance
 
Differential Protection Relay
DifferentialProtection RelayDifferentialProtection Relay
Differential Protection Relay
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guide
 
Applications of power electronics in HVDC
Applications of  power electronics in HVDCApplications of  power electronics in HVDC
Applications of power electronics in HVDC
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training Report
 
Switchgear and protection 2
Switchgear and protection 2Switchgear and protection 2
Switchgear and protection 2
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
 

Similar to Explore the Electrical Equipment at Unnao Substation

Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFjang041
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limitedVSRAGHU
 
Madan mohan malaviya
Madan mohan malaviyaMadan mohan malaviya
Madan mohan malaviyaAnuj Bansal
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptsrijan tripathi
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxsohaib268827
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOWSatya Prakash Chaurasia
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )AnandMohan271812
 
Load Distribution
Load DistributionLoad Distribution
Load DistributionArpit Gupta
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfDevesh54
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONRavi Phadtare
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfHariomgupta90
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaNandan Desai
 
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG  INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG Muneeb Amin Khan
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPURsahid raja khan
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptxAsif682330
 
Ppt on 400 kv gss raiser Bikaner- Yatendra Parashar
Ppt on 400 kv gss raiser Bikaner- Yatendra ParasharPpt on 400 kv gss raiser Bikaner- Yatendra Parashar
Ppt on 400 kv gss raiser Bikaner- Yatendra ParasharYatendra Parashar
 

Similar to Explore the Electrical Equipment at Unnao Substation (20)

Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
Madan mohan malaviya
Madan mohan malaviyaMadan mohan malaviya
Madan mohan malaviya
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) ppt
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
 
Load Distribution
Load DistributionLoad Distribution
Load Distribution
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdf
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, Hadala
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG  INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx
 
Ppt on 400 kv gss raiser Bikaner- Yatendra Parashar
Ppt on 400 kv gss raiser Bikaner- Yatendra ParasharPpt on 400 kv gss raiser Bikaner- Yatendra Parashar
Ppt on 400 kv gss raiser Bikaner- Yatendra Parashar
 

More from MarcWorld

CE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxCE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxMarcWorld
 
CE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxCE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxMarcWorld
 
Advanced Control System.ppt
Advanced Control System.pptAdvanced Control System.ppt
Advanced Control System.pptMarcWorld
 
SIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptSIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptMarcWorld
 
Super-Critical Boiler.ppt
Super-Critical Boiler.pptSuper-Critical Boiler.ppt
Super-Critical Boiler.pptMarcWorld
 
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdfMarcWorld
 
fall00_boone.ppt
fall00_boone.pptfall00_boone.ppt
fall00_boone.pptMarcWorld
 
FACTS-FlexibleACTransmissionSystem.ppt
FACTS-FlexibleACTransmissionSystem.pptFACTS-FlexibleACTransmissionSystem.ppt
FACTS-FlexibleACTransmissionSystem.pptMarcWorld
 
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.pptUnburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.pptMarcWorld
 
AKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
AKE2008H_08Luther_KWK-Subventionsloch_kurz.pptAKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
AKE2008H_08Luther_KWK-Subventionsloch_kurz.pptMarcWorld
 

More from MarcWorld (10)

CE 533 Chapter 21.pptx
CE 533 Chapter 21.pptxCE 533 Chapter 21.pptx
CE 533 Chapter 21.pptx
 
CE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxCE 533 Chapter 15.pptx
CE 533 Chapter 15.pptx
 
Advanced Control System.ppt
Advanced Control System.pptAdvanced Control System.ppt
Advanced Control System.ppt
 
SIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.pptSIPAT 660 MW Turbo- Governing & Protection System.ppt
SIPAT 660 MW Turbo- Governing & Protection System.ppt
 
Super-Critical Boiler.ppt
Super-Critical Boiler.pptSuper-Critical Boiler.ppt
Super-Critical Boiler.ppt
 
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
000-Forgings-PPT-Presentation-IMU_Basic_Knowledge_English_final_11-03-14.pdf
 
fall00_boone.ppt
fall00_boone.pptfall00_boone.ppt
fall00_boone.ppt
 
FACTS-FlexibleACTransmissionSystem.ppt
FACTS-FlexibleACTransmissionSystem.pptFACTS-FlexibleACTransmissionSystem.ppt
FACTS-FlexibleACTransmissionSystem.ppt
 
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.pptUnburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
Unburned Carbon versus CO2 Emission-PROMECON-BoilerOptimization.ppt
 
AKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
AKE2008H_08Luther_KWK-Subventionsloch_kurz.pptAKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
AKE2008H_08Luther_KWK-Subventionsloch_kurz.ppt
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

Explore the Electrical Equipment at Unnao Substation

  • 2. INTRODUCTION OF SUBSTATION It is situated at 26°34’2’’N & 80°32’57’’E coordinates in Dahi Chowki 6.64 km far from Unnao railway station. Constructed during 1994-98 by CGL. The whole substation is divided in three parts: 132kv switchyard 400/220kv switchyard 765kv switchyard (Under construction) 2
  • 3. INCOMING & OUTGOING LINE OF SUBSTATION •Unnao to Lucknow (400KV & 220KV both separate) •Unnao to Bareily-1 (400KV) •Unnao to Bareily-2 (400KV) •Unnao to Agara (400KV) •Unnao to Panki Kanpur(400KV & 220KV both separate) •Unnao to Anpara (400KV) •Unnao to PGCIL Lucknow-1 (400KV) •Unnao to PGCIL Lucknow-2 (400KV) •One bus bar for 400/220KV 315MVA ICT-1 & ICT-2 line. 3
  • 4. OUTDOOR EQUIPMENT USED IN SUBSTATION  Two 100MVA 220/132KV transformer  Two 315MVA 400/220KV transformer  Shunt reactor  Capacitor bank  SF6 circuit breaker  Isolators  Lightning arresters  Current transformer  Capacitor voltage transformer  Wave trap  Isolators 4
  • 5. Transformer H.V. side bushing CT COOLING SYSTEM (ONAN) ConservaterTank L.V. side bushing CTs 5
  • 6. Oil pump Oil pump is used for circulating oil forcelly. Radiator plates are used for increasing surface area for natural air cooling. Radiator plates Earthing plate 6
  • 7.  we use Cooling fans for forced air cooling of transformer . Total six fans are used for each 100MVA and eight fans are used for each 315 MVA transformer. But all fans never start at same time . It start in pairs . COOLING FANS 7
  • 8. Tertiary terminal Tertiary terminal mostly opened. The output voltage of tertiary terminal is 11KV in 100MVA transformer and 33KV in 315 MVA transformer Pressure relief valve box 8 OLTC chamber
  • 10. In these photos we can see fogging near transformer due to operation fire protection system. 10
  • 11. BUCHHOLZ RELAY Buchholz relay is a safety device mounted on some oil-filled power transformers and reactors. It is used as a protective device sensitive to the effects of dielectric failure inside the equipment. 11
  • 12. OTI & WTI OTI –oil temp. indicator measure temp. of oil filled in transformer. In OTI has two mercury bulb. WTI- winding temp. indicator measure winding temp of transformer. It has four mercury bulb. OTI panel WTI panel mercury bulb 12
  • 13. CURRENT TRANSFORMER In electrical engineering, a current transformer (CT) is used for measurement of electric currents. Current transformers, together with voltage transformers (VT) (potential transformers (PT)), are known as instrument transformers. When current in a circuit is too high to directly apply to measuring instruments, a current transformer produces a reduced current accurately proportional to the current in the circuit, which can be conveniently connected to measuring and recording instruments. 13
  • 15. A capacitor voltage transformer (CVT) is a transformer used in power systems to step-down extra high voltage signals and provide low voltage signals either for measurement or to operate a protective relay. The device has at least four terminals, a high-voltage terminal a ground terminal and at least one set of secondary terminals. CVTs are typically single-phase devices CAPACITOR VOLTAGE TRANSFORMER 15
  • 16. Cross sectional view of CVT 1 - Primary terminal 2 - Cast aluminum bellow housing 3 - Stainless steel expansion bellow 4 - Compression spring 5 - Insulated voltage connection 6 - Capacitor elements 7 - Insulator (porcelain or composite) 8 - Voltage divider tap connection 9 - Cast-epoxy bushing 10 - HF terminal connection 11 - Ferro-resonance suppression device 12 - Secondary terminals 13 - Oil level sight-glass 14 - Aluminum terminal box 15 - Intermediate transformer 16 - Oil/air block 17 - Oil sampling device 18 - Compensating reactor 19 - Aluminum cover plate 16
  • 17. 1. High Voltage terminal 2. Compensation reactor 3. Intermediate voltage transformer 4. Ground terminal 5. Ferro-resonance suppression device 6. Damping resistor 7. Carrier (HF) terminal (optional) 8. Overvoltage protective device 9. Secondary terminals 10. Link, to be opened for test purposes PRINCIPLE CIRCUIT DIAGRAM OF CVT 17
  • 18. CIRCUIT BREAKER A circuit breaker is an automatically-operated electrical switch designed to protect an electrical circuit from damage caused by overload or short circuit. In this image we can see a SF6 circuit breaker with double break system. 18
  • 19. ISOLATORS An isolators switch are used to completely de- energized an electrical circuit. High-voltage isolation switches are used in electrical substations to allow isolation of apparatus such as circuit breakers and transformers, and transmission lines, for maintenance. Isolating rod Earth link rod 19
  • 20. PANTOGRAPH ISOLATORS In open state In close state 20
  • 22. Wave trap  Wave trap are used in power system for carrier communication.  It trap the higher frequency above 50Hz.  It is the effort to utilize the same transmission line between two substation for the purpose of communications 22
  • 23. 23
  • 24. LIGHTNING ARRESTOR The overvoltage protection is obtained by the use of lightning / surge arresters. Lightning Arresters or Surge Arresters are always connected in Shunt to the equipment to be protected, they provide a low impedance path for the surge current to the ground. Mostly in present days zinc oxide (ZnO) gapless arresters are in use. 24
  • 25. INTERPOSING C.T. The interposing CTs are used for Power transformer Differential Protection circuit. In a delta/Star Power transformer, the cts will be connected star and delta formation, for eliminating Zero sequence current on star side. There will be mismatch of secondary current , to maintain equilibrium, interposing Cts will be connected to Delta formed CTs. 25
  • 26. RELAYS Differential relay O/F protection +FFR Group A trip relay CB trouble relay Group B trip relay DR earth switch relay O/C protection relays Breaker failure relay RES E/F +O/L Protection relay 26
  • 27. Relay testing box A outer view of Relay Relay conti…. 27
  • 28. SHUNT REACTOR  Shunt Reactor is a thyristor controlled high impedance transformer. A stable bus voltage can be maintained by providing variable reactive power based on the bus voltage deviations due to the load variations. 28
  • 29. SHUNT CAPACITOR BANK Shunt capacitor banks are used to improve the quality of the electrical supply. provide capacitive reactive compensation. Power factor correction. 29
  • 30. 30
  • 31. 31