The internship was divided into four parts
4 weeks: Site execution with emphasis on HSE and QA/QC.
2 weeks: Updating the status of Tower in Tracking Tool and creating a MSP program on the remaining activities left in the building.
1 week : Contract analysis
1 week : Marketing concepts used and preparation of case study on company.
Presentation. jkr lawatan IBS kilang HC Precast SystemTeow Beng Hur
IMPORTANT :
- Elements Required To Complete A Building
- Industrialised Building System ( IBS )
" is a system not a machine or component "
- Open System And Proprietary System Is A Technology
- Speed, Quality & Environment
- SEQUENCE OF WORK : 5 Steps & No Variation Order
- Step 1 : Drawing Conversion ( 2D to 3D )
- Step 2 : Mould Fabrication
- Step 3 : Production ( Decide by Client )
- Step 4 : Delivery ( Decide by Client )
- Step 5 : Installation Numbering ( Decide by Client )
Prefabricated construction systems in India- Precast Status and needed ImpetusIEI GSC
Presentation on Prefabricated construction systems in India- Precast Status and needed Impetus by Prof S. K. Singh,Sr. Principal Scientist & Professor, AcSIR, CSIR-Central Building Research Institute, Roorkee at #33NCCE 33rd National Convention of Civil Engineers at #IEIGSC
ONE OF THE WAY TO IMPROVE THE OUTFLOW OF CURRENCY IS THE UTILIZATION OF INDUSTRIAL BUILDING SYSTEM ( IBS ) :
- IBS is a system which suits all architectural demands. It is neither a machine nor component,
- IBS Superstructure In Malaysia 3in1 : HC PRECAST SYSTEM
- Load Bearing + Modular Shear Keys Wet Joint + Box System
Presentation. jkr lawatan IBS kilang HC Precast SystemTeow Beng Hur
IMPORTANT :
- Elements Required To Complete A Building
- Industrialised Building System ( IBS )
" is a system not a machine or component "
- Open System And Proprietary System Is A Technology
- Speed, Quality & Environment
- SEQUENCE OF WORK : 5 Steps & No Variation Order
- Step 1 : Drawing Conversion ( 2D to 3D )
- Step 2 : Mould Fabrication
- Step 3 : Production ( Decide by Client )
- Step 4 : Delivery ( Decide by Client )
- Step 5 : Installation Numbering ( Decide by Client )
Prefabricated construction systems in India- Precast Status and needed ImpetusIEI GSC
Presentation on Prefabricated construction systems in India- Precast Status and needed Impetus by Prof S. K. Singh,Sr. Principal Scientist & Professor, AcSIR, CSIR-Central Building Research Institute, Roorkee at #33NCCE 33rd National Convention of Civil Engineers at #IEIGSC
ONE OF THE WAY TO IMPROVE THE OUTFLOW OF CURRENCY IS THE UTILIZATION OF INDUSTRIAL BUILDING SYSTEM ( IBS ) :
- IBS is a system which suits all architectural demands. It is neither a machine nor component,
- IBS Superstructure In Malaysia 3in1 : HC PRECAST SYSTEM
- Load Bearing + Modular Shear Keys Wet Joint + Box System
ONE OF THE WAY TO IMPROVE THE OUTFLOW OF CURRENCY IS THE UTILIZATION OF INDUSTRIAL BUILDING SYSTEM ( IBS ) :
- IBS is a system which suits all architectural demands. It is neither a machine nor component,
- IBS Superstructure In Malaysia 3in1 : HC PRECAST SYSTEM
- Load Bearing + Modular Shear Keys Wet Joint + Box System
Prefabrication is the practice of assembling components of a structure in a factory or other manufacturing site and transporting to the construction site where the structure is to be located.
It is combination of good design with modern high performance components and quality controlled manufacturing procedures.
Here we discuss about prefabricated structures, its advantages and disadvantages. Prefabricated structures manufacturers will provide efficient design as per their functionality.
Prefabrication is the practice of assembling components of a structure in a factory or other manufacturing site, and transporting them to the construction site where the structure is to be located.
ONE OF THE WAY TO IMPROVE THE OUTFLOW OF CURRENCY IS THE UTILIZATION OF INDUSTRIAL BUILDING SYSTEM ( IBS ) :
- IBS is a system which suits all architectural demands. It is neither a machine nor component,
- IBS Superstructure In Malaysia 3in1 : HC PRECAST SYSTEM
- Load Bearing + Modular Shear Keys Wet Joint + Box System
Prefabrication is the practice of assembling components of a structure in a factory or other manufacturing site and transporting to the construction site where the structure is to be located.
It is combination of good design with modern high performance components and quality controlled manufacturing procedures.
Here we discuss about prefabricated structures, its advantages and disadvantages. Prefabricated structures manufacturers will provide efficient design as per their functionality.
Prefabrication is the practice of assembling components of a structure in a factory or other manufacturing site, and transporting them to the construction site where the structure is to be located.
The internship was divided into four parts
4 weeks: Site execution with emphasis on HSE and QA/QC.
2 weeks: Updating the status of Tower in Tracking Tool and creating a MSP program on the remaining activities left in the building.
1 week : Contract analysis
1 week : Marketing concepts used and preparation of case study on company.
It mentions my work during my intern at HBCH & RC, Mohali, in 3 departments- Billing, Execution & Quality. It helped me to learn a lot of construction activities on Site.
This session will guide you through all the essential elements of preparing an engineered lift plan. From the reason a plan is needed to the engineering required along with drawings and calculations, learn how to prepare and present the submission to the client.
Speaker: Jamison Fox, P.E., International Industrial Contracting Corporation
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Systems, Inc.
GSE presentation given at CONTE 2019. The presentation was a recap of the project to build new simulators for Southern Nuclear and was given by GSE's Michael Battaglia.
Ques: 1.Why this system is called SLIPFORMING?
Ques: 3.Slipforming is mechanized way of constructing very high structures & involves Mechanical/Civil/Hydraulic Engineers. Explain?
Ques: 4.How the tapering structures are made by Slipforming? How do we reduce
diameter, wall thickness & do Lifting Simultaneously?
Ques: 5.Manpower saving in Slipforming (no carpenters required), Good for the
Country/Employment?
Ques: 6.Will mechanization in form work render our carpenters idle?
Ques: 7.Scaffolding is major capital investment in Construction Projects, no
scaffolding is required for Slipform Projects, and how Slipforming is cost effective?Please discuss.
My Contributions in Health and Safety, QA/QC and Basic of Site Execution in J...Abhimanyu Saraswat
The internship was divided into four parts
4 weeks: Site execution with emphasis on HSE and QA/QC.
2 weeks: Updating the status of Tower in Tracking Tool and creating a MSP program on the remaining activities left in the building.
1 week : Contract analysis
1 week : Marketing concepts used and preparation of case study on company.
Investigation of behaviour of concrete on adding crumbAbhimanyu Saraswat
Concrete is the basic ingredient for all types of construction. The current scenario of rapid urbanization and modernization, has resulted in escalated demand for aggregates, sand, water and cement. This demand has been met by causing extra burden on the environment. This thesis was an noble attempt to reduce that burden by replacing sand by "Crumb Rubber".
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
2. Introduction
The Jaypee group is a Rs.20,000 crore well diversified infrastructural
industrial conglomerate in india.
• JAYPEE GROUP OF COMPANIES
– Jaiprakash Power Ventures Ltd.
– Jaypee Infratech Ltd.
– Jaypee Power Grid Ltd.
– Jaypee Cement
– Jaypee Greens
– Jaypee Sports International Ltd.
– Jaypee Hotels
– Jaypee Information Technology Ltd.
– Jaypee Institute of Information and Technology
3. Project Details
• Name : Jaypee Greens – Wish town
• Location: Noida, U.P.
• Date of commencement: November – 2009
• Project cost : 2000 cr.
• Client : Jaypee Greens
• Architect : Arcop Associates Pvt.Ltd.
• St.Consultant : Vintech consultants
• Area : 500 ha.
• No. of towers : 320
• No. of units : 8000
4.
5. 1. Planning
• At Jaypee the scheduling and planning is done on the basis of
trigger amount (amount demand from the customer based on
construction status slab wise).
• The amount to be raised each month will be decided in the
review meeting and monthly schedule is prepared according to
that.
• Status is updated on weekly basis to keep track of the work
done to meet the demand schedule to be collected from the
customer.
6.
7.
8.
9. 1.1 Facility Management Group(FMG)
The FMG department at the Jaypee ensures the
delivery or handover of the flats by
checking all the facilities in the tower.
• Checking of all the activities installed in flat
or in tower
• Ensuring the quality of the work done as per
specification
• Deals with outside authority for building
completion certificate.
• Flat can be handover by getting the clearance
from the FMG group.
• Check whether it meet the requirements of its
occupants.
• Final decisions are being made by FMG
regarding the completion of the tower
10. • We were asked to make the scheduled for the finishing
activities for one of project KALYPSO COURT in the MSP
(Microsoft Project).
• The finishing activities of every tower are breakdown into
different parts and according to that work is carried out.
• The WBS of such activities are first created on MSP and then
the activities are entered based on the work to be carried out.
• The WBS various activities created in msp are shown in figure
below.
11.
12.
13. • The duration is decided and predecessor are assigned to each activities
based on the time and resources available.
• The total no. of duration achieved after assigning the no. of days is 818
days for the finishing work of one tower (G+25) having 3 units at each
floor.
14. 2. Site Execution
The planning done for the structural work of a building is basically
based on the slab cycle, here in this project the average slab cycle
period was 20-25 days.
15. Column Reinforcement:
– Extension of Bars
– Providing Stirrups
– Binding of stirrups to the vertical bars.
• All column reinforcement shall be
embedded minimum Ld from the floor
level.
• Lap length shall be calculated on the
basis of diameters of smaller bar.
• Fe 500 should be used conforming to
IS-1786
• The stirrups dia vary from 8mm to
12mm conforming to specification
mentioned in the drawing.
• Also the spacing between the stirrups
should also be as per the drawing.
• In lap portion the spacing of stirrups
shall be 150mm C/C.
16. Shuttering/Formwork of Column & slab
• For placing the shuttering properly as per
the drawing to avoid any deviations either
T point are used or marking are on the
starter in (X,Y) direction.
• The shuttering used in this project was
from pranav.
• Stripping time of forms of slabs (spanning
upto 4.5mt.)
– For OPC Cement : 5days
– For PPC or OPC + Fly Ash : 7days
• Beams soffits (Props left under)(spanning
upto 6.0mt.)
– For OPC Cement : 7days
– For PPC or OPC + Fly Ash : 9days
• Stripping time of forms for columns:
– For OPC Cement : 24 Hours
– For PPC or OPC + Fly Ash : 36 Hours
17. Beam & Slab Reinforcement
• All reinforcement used in this work shall conform to IS:1786 with
Fe415 or 500 and shall be in the form of deformed bars.
• The slab reinforcement shall be provided both in X and Y direction.
• The main should be placed along the shorter span and the
distribution bar should be placed along the longer span.
18. Concreting of Column & Slab
• All structural concrete shall be design mix concrete (controlled
concrete) of minimum grade M20 for column.
• The column has a concrete cover of 40 mm on all the sides.
• The concrete cover for slab is 20mm.
• The concrete cover for beam is 25mm.
• The concreting should be done upto the bottom of the beam of
the next floor. And the height can be calculated by measuring
from the sofit of slab to the bottom of the beam.
19. • Checking of bars for Beam, Slab and Column from the
drawings provided from the site office.
• Preparing the BBS (Bar Bending Schedule) for the same.
• To calculate the no. of bars = (L/spacing)+1 for the slabs.
20. 3. Procurement
• The management based procurement strategy is used in Jaypee for
the procurement of materials with the help of tool developed by
SAP.
21.
22.
23. 4. Safety
• Jaypee Group believes it to be the responsibility of all.
• Tool box talk -2 times/week
• A safety supervisor to be always present at site ,to monitor all the
safety checklists
• PPE were worn by workers
• Safety signboards were installed at entrance
• Helmets are compulsory
24. •No helmet while working at heights
•No safety belts
•SOPs were not defined to the workers
•Not proper maintenance of equipments.
25. 4.1Case
• This accident took place at garden isles project in Jaypee Wish Town.
• Health and Safety department at Jaypee prepared an investigating report
which only contained name of person, cause of fatality and
compensation to be paid with an attached copy of the F.I.R.
26. • Reason : As per safety guidelines, while removing the safety net another net
should be installed at a place just below where the previous net existed and
another net 6 floors below that for extra protection but none of this safety
measures were taken, resulting in this fatality.
• After this incident, the construction activity was stopped for 2days,
resulting in huge loss in the productivity.
• We also pointed out that, only on this site alone there have been 6
fatalities due to unavailability of PPE’s and improper supervision from
the In-Charge
27.
28. • Shortfall in safety :
– Only few workers at site wore safety shoes other all workers worked
in slippers and were allowed to do so.
– Some laborers were not wearing safety belt
– There were many duct openings were no rail or covering object was
kept.
– In basement area workers worked continuously for hours without any
PPE’s and were exposed to dust particles which are potential
occupational health hazards.
• Reason:
– The mindset of the workers towards safety was awful. They didn’t
imply to basic requirements of working at heights like wearing
helmet, safety boots and wearing a safety harness while working on
the edges.
– The reason given by them for not wearing PPE’s was that, it hindered
their productivity and movement
– The amount of these PPE’s per worker ratio was also very less.
30. 5. Contracts:
We were given three contracts documents:
• Concession agreement between TEA and Jaypee Group :
studied
• Fabrication and installation of Façade in JSPI : Summarized
document prepared which was between Jaypee Group and SJ
Fabricators.
• Comparative study between CPWD conditions and contract
condition was done for : Agreement between Jaypee Group
and ARCOP
• Contract Assigment - By Daksh and Abhimanyu.xlsx
31. 6. Quality
• sieve analysis of coarse aggregate
(is 2386-1983)
• flakiness index of coarse aggregate
(is 2386-part 1)
• specific gravity of aggregates by
pycnometer (is 2386- part 3)
• Impact and Crushing strength of
Aggregates. (IS 2386- Part 4)
• Silt Content of Sand. (IS 2386- Part
2)
• Note: Cement was not tested as
Jaypee Cement was used in
construction.
32.
33. Thesis Work
• Thesis Topic: Implementation of
ERP in Small & Medium scale
Construction companies in india.
• ERP (Enterprise Resource Planning) is
used in this organization as a tool for
Procurement of materials, budgeting,
Project schedule, Billing etc.
• The ERP software in this organization
was developed by SAP as per
requirement asked by the employees.
• The different modules used in ERP are:
– Material Module
– Project Schedule Module
– Cost & Budget Module
– CRF Module
– Accounts Module
34. The difficulties occurred in successful implementation of ERP
by the employees in the organization are as follows:
– Not proper day to day update.
– Not proper interdisciplinary communication.
– Awareness regarding the software.
– Huge initial installation charges
– Not accessible by all the departments.