SlideShare a Scribd company logo
Erection of structural
components
Paramathmeka S
M.E structural engineering
P.S.G college of technology
1
Introduction
 Erection of the structural components in
prefabricated structures play the important part in
the construction of the building.
 The erection process includes the erection of
horizontal members, vertical members or complete
unit.
 To ensure effective and quality installation proper
planning and preparatory works are required before
the erection. It includes…
2
i. Method and sequence of assembly
and erection
ii. Method of providing temporary
supports
iii. Erection tolerance
iv. Handling and rigging requirements
3
Erection plan
 The erection plan, which is normally developed
by a registered professional engineer, is used
to establish the size and location of cranes, the
location of delivery trucks, and the sequence of
erection
4
Assembly plans
 Assembly plans are similar to erection
plans, except they are more detailed
and they include time components for
element installation and placements of
concretes or grouts.
 It is recommended that project
specifications require the submission
of an assembly plan.
5
Assembly plan
includes
 Drawings depicting the assembly
procedures. The plan should be
prepared by a registered Professional
engineer.
 A work area plan, depicting items
such as utilities overhead and below
the work area, drainage inlet
structures, and protective measures.
 Details of all equipment that will be
employed for the assembly of the
structure.
 Details of all equipment to be used to
lift elements, including cranes,
excavators, lifting slings, sling hooks,
and jacks. Include crane locations,
operation radii, and lifting calculations.
 Detailed sequence of construction
and a timeline for all operations.
Account for setting and cure time for
grouts, mechanical connections,
and concrete closure pours
 Calculations for all aspects of the
assembly plan including, erection
calculations, crane capacities,
rigging calculations, temporary false
work and framing, and element
handling stresses. The calculations
should be prepared by a registered
Professional engineer
 Methods of providing temporary
support of the elements. Include
methods of adjusting and securing
the element after placement.
6
 Procedures for controlling tolerance
limits—both horizontal and vertical.
Include details of any alignment jigs,
including templates for projecting
anchors and dowels.
 A detailed installation procedure for
connecting mechanical connectors,
including grouting procedures
 Include methods for curing grout and
closure pour concrete.
 Proposed methods for installing non-
shrink grout and the sequence and
equipment for the grouting operation.
 Methods for placement of fill
materials.
 Methods for forming and sealing
closure pour.
 Methods and equipment for installation
of post-tensioning systems, including
stressing and grouting procedures.
7
Preparatory work
 Check for site accessibility
 Check for delivery checklist
 Check for adequate crane capacity and
working clearance for hosting the
elements
 Conduct sample measurements
 Conduct visual inspection.
 Check for location and condition for
lifting
 Check for accessibility for unloading
point
 Check that the storage area condition.
8
As per IS 15916:2011
 In the erection of precast elements, all the following items of work shall be
included:
a) Slinging of the precast element;
b) Tying up of erection ropes connecting to the erection hooks;
c) Cleaning of the elements and the site of erection;
d) Cleaning of the steel inserts before incorporation in the joints, lifting up of the
elements, setting them down into the correct envisaged position;
e) Adjustment to get the stipulated level, line and plumb;
f) Welding of cleats;
g) Changing of the erection tackles;
h) Putting up and removing of the necessary scaffolding or supports
i) Welding of the inserts, laying of reinforcements in joints and grouting the
joints; and
j) Finishing the joints to bring the whole work to a workmanlike finished product.
9
Installation of vertical
precast components
Installation sequence includes
 Setting out
 Lifting and installation
 Grout work
 Joist casting and sealing
10
Setting out
o Setting
reference line
and offset line
o Provide level
pads
o Fitting of
compressible
form or backer
rod on the outer
perimeter of the
wall
11
Good practices for setting
out
 Check the accuracy of
offset line
 Check the shim plate
level and stability
 Check the position for
the starter bars
 Check the compressible
form and backer rod are
properly secured
12
Lifting and installation
 Lifting and rigging
the panels
 Adjust the panel to
the position
13
Good practices for lifting
and hoisting
 Check the hoisting condition
 Check the alignment and
verticality
 Check the stability of the
erected rod before releasing
the hoisting cable
14
Grouting
work
 Prepare and seal non-
shrink motor
 Prepare and pour non-
shrink grout for pipe works
 Keep the installed panel
undisturbed for 24hours
15
Good practices
for grouting
 Before grouting check the
joint width
 The grout used must be self
compactable and must have
a free flow
 Check whether all the
horizontal joints are
properly sealed
 Collect sample test cubes
for the grout used for
important components
16
Joint casting
and sealing
 Install the joint rebar as
required
 Set up form for casting
 Carry out concrete casting
 Removes form after
sufficient strength is
attained
 Place the connecting
plates between the panels
and weld
17
Good practices for joint
casting
 Joint rebars must be
accurately placed
 During casting the formwork
should be correctly secured
 For better water tightness
the joint gap should have
proper installation of grout
18
Installation of horizontal
precast components
Installation sequence
includes
 Setting out
 Lifting and installation
 Casting of joints
19
Setting out
 Set the reference line and
the offset line
Good practice
 Check the accuracy of the
offset line
 Check the level and stability
of shim plates
 Check the dimensions of the
protruding bars
20
Lifting and installation
 Put up temporary props
 Lift and rig the
elements in position
 Align and set the level
to suit before placing
the member
21
Good practices for lifting
 Beams should be
supported minimum
at two locations
 Balcony, slabs should
be supported in more
than two locations
 Levelness of the
precast elements to be
ensured before the
joisting action
22
Casting of
joints
 For cast in situ joints
place and lap the rebars
 Set up form work for
casting of joints
 Carry out concrete
casting
23
Good practice for joints
 The joints rebars should be
accurately placed
 The formwork should be
properly placed
 Supporting beams should
be a part of formwork
24
General
considerations
 Safety precautions in the work
are of utmost importance
 Only those skilled foremen,
trained workers and fitters who
have been properly instructed
about the safety precautions to
be taken should be employed on
the job.
 Transport of people, workers or
visitors, by using cranes and
hoists should be strictly
prohibited
 In the case of tower cranes running
on rails, the track shall not have a
slope more than 0.2 percent in the
longitudinal direction. In the
transverse direction the rails shall lie
in a horizontal plane.
 The track of the crane should be
checked daily to see that all fish
plates and bolts connecting them to
the sleepers are in place and in good
condition.
25
Reference
 IS15916:2011 -Building design and erection
using prefabricated concrete — code of
practice
 CONQUAS Quality Assessment Criteria
26
THANK YOU
27

More Related Content

What's hot

demolition of building
demolition of buildingdemolition of building
demolition of building
tushar garg
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
Rahul bhatnagar
 
Spun pile
Spun pileSpun pile
Spun pile
Wen Crystal
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
Wan Nee
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete Bridge
Shubham Das
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
Sagar Shah
 
Precast construction
Precast constructionPrecast construction
Precast construction
Divya Vishnoi
 
Pre-stressed Concrete
Pre-stressed ConcretePre-stressed Concrete
Pre-stressed Concrete
Katrina Mabini
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
Boopathi Raja
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
Being Deepak
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
gyan singh
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
Wilden How
 
Prefabrication types and Applications explained
Prefabrication types and Applications explainedPrefabrication types and Applications explained
Prefabrication types and Applications explained
Eyad Reda
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
Sourabh Jain
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
GAURAV. H .TANDON
 
Slipform
SlipformSlipform
Slipform
Rahul Razz
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
KHUSHBU SHAH
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ASHOK KUMAR TIWARY
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
Divya Vishnoi
 
Demolition of buildings
Demolition of buildingsDemolition of buildings
Demolition of buildings
Prince Srinivas
 

What's hot (20)

demolition of building
demolition of buildingdemolition of building
demolition of building
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Spun pile
Spun pileSpun pile
Spun pile
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete Bridge
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
Precast construction
Precast constructionPrecast construction
Precast construction
 
Pre-stressed Concrete
Pre-stressed ConcretePre-stressed Concrete
Pre-stressed Concrete
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Prefabrication types and Applications explained
Prefabrication types and Applications explainedPrefabrication types and Applications explained
Prefabrication types and Applications explained
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Slipform
SlipformSlipform
Slipform
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Demolition of buildings
Demolition of buildingsDemolition of buildings
Demolition of buildings
 

Similar to Erection of structural components in precast constructions

Precast elements
Precast elementsPrecast elements
Precast elements
Shrividhyah
 
Precast elements
Precast elementsPrecast elements
Precast elements
Shrividhyah
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
Minh Bui Si
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
hlksd
 
Erection Methodology (KG Marg) MLCP.pptx
Erection Methodology (KG Marg) MLCP.pptxErection Methodology (KG Marg) MLCP.pptx
Erection Methodology (KG Marg) MLCP.pptx
zrahman0161
 
Column & beam
Column & beamColumn & beam
Column & beam
Minh Bui Si
 
MFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdfMFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdf
ssuseref23d3
 
Safety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of ConstructionSafety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of Construction
Sandeep Jain
 
Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
Patsifit Construction Sdn.Bhd
 
iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdf
XiMdhk
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
ssuseref23d3
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
mahmoud909178
 
Amir QC
Amir QCAmir QC
Amir QC
aamir waheed
 
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of RotavatorIRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET Journal
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
Anees Khan
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
chongyih2
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
Katy A. Beitia G.
 
Lory Francis Navor - CV
Lory Francis Navor - CVLory Francis Navor - CV
Lory Francis Navor - CV
lory francis navor
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
Minh Bui Si
 
Setting out 12042018
Setting out 12042018Setting out 12042018
Setting out 12042018
Noorhazlinda Rahman
 

Similar to Erection of structural components in precast constructions (20)

Precast elements
Precast elementsPrecast elements
Precast elements
 
Precast elements
Precast elementsPrecast elements
Precast elements
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Erection Methodology (KG Marg) MLCP.pptx
Erection Methodology (KG Marg) MLCP.pptxErection Methodology (KG Marg) MLCP.pptx
Erection Methodology (KG Marg) MLCP.pptx
 
Column & beam
Column & beamColumn & beam
Column & beam
 
MFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdfMFRH Erection & Commissioning Method.pdf
MFRH Erection & Commissioning Method.pdf
 
Safety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of ConstructionSafety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of Construction
 
Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
 
iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdf
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
 
Amir QC
Amir QCAmir QC
Amir QC
 
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of RotavatorIRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
 
Lory Francis Navor - CV
Lory Francis Navor - CVLory Francis Navor - CV
Lory Francis Navor - CV
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Setting out 12042018
Setting out 12042018Setting out 12042018
Setting out 12042018
 

Recently uploaded

CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 

Recently uploaded (20)

CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 

Erection of structural components in precast constructions

  • 1. Erection of structural components Paramathmeka S M.E structural engineering P.S.G college of technology 1
  • 2. Introduction  Erection of the structural components in prefabricated structures play the important part in the construction of the building.  The erection process includes the erection of horizontal members, vertical members or complete unit.  To ensure effective and quality installation proper planning and preparatory works are required before the erection. It includes… 2
  • 3. i. Method and sequence of assembly and erection ii. Method of providing temporary supports iii. Erection tolerance iv. Handling and rigging requirements 3
  • 4. Erection plan  The erection plan, which is normally developed by a registered professional engineer, is used to establish the size and location of cranes, the location of delivery trucks, and the sequence of erection 4
  • 5. Assembly plans  Assembly plans are similar to erection plans, except they are more detailed and they include time components for element installation and placements of concretes or grouts.  It is recommended that project specifications require the submission of an assembly plan. 5
  • 6. Assembly plan includes  Drawings depicting the assembly procedures. The plan should be prepared by a registered Professional engineer.  A work area plan, depicting items such as utilities overhead and below the work area, drainage inlet structures, and protective measures.  Details of all equipment that will be employed for the assembly of the structure.  Details of all equipment to be used to lift elements, including cranes, excavators, lifting slings, sling hooks, and jacks. Include crane locations, operation radii, and lifting calculations.  Detailed sequence of construction and a timeline for all operations. Account for setting and cure time for grouts, mechanical connections, and concrete closure pours  Calculations for all aspects of the assembly plan including, erection calculations, crane capacities, rigging calculations, temporary false work and framing, and element handling stresses. The calculations should be prepared by a registered Professional engineer  Methods of providing temporary support of the elements. Include methods of adjusting and securing the element after placement. 6
  • 7.  Procedures for controlling tolerance limits—both horizontal and vertical. Include details of any alignment jigs, including templates for projecting anchors and dowels.  A detailed installation procedure for connecting mechanical connectors, including grouting procedures  Include methods for curing grout and closure pour concrete.  Proposed methods for installing non- shrink grout and the sequence and equipment for the grouting operation.  Methods for placement of fill materials.  Methods for forming and sealing closure pour.  Methods and equipment for installation of post-tensioning systems, including stressing and grouting procedures. 7
  • 8. Preparatory work  Check for site accessibility  Check for delivery checklist  Check for adequate crane capacity and working clearance for hosting the elements  Conduct sample measurements  Conduct visual inspection.  Check for location and condition for lifting  Check for accessibility for unloading point  Check that the storage area condition. 8
  • 9. As per IS 15916:2011  In the erection of precast elements, all the following items of work shall be included: a) Slinging of the precast element; b) Tying up of erection ropes connecting to the erection hooks; c) Cleaning of the elements and the site of erection; d) Cleaning of the steel inserts before incorporation in the joints, lifting up of the elements, setting them down into the correct envisaged position; e) Adjustment to get the stipulated level, line and plumb; f) Welding of cleats; g) Changing of the erection tackles; h) Putting up and removing of the necessary scaffolding or supports i) Welding of the inserts, laying of reinforcements in joints and grouting the joints; and j) Finishing the joints to bring the whole work to a workmanlike finished product. 9
  • 10. Installation of vertical precast components Installation sequence includes  Setting out  Lifting and installation  Grout work  Joist casting and sealing 10
  • 11. Setting out o Setting reference line and offset line o Provide level pads o Fitting of compressible form or backer rod on the outer perimeter of the wall 11
  • 12. Good practices for setting out  Check the accuracy of offset line  Check the shim plate level and stability  Check the position for the starter bars  Check the compressible form and backer rod are properly secured 12
  • 13. Lifting and installation  Lifting and rigging the panels  Adjust the panel to the position 13
  • 14. Good practices for lifting and hoisting  Check the hoisting condition  Check the alignment and verticality  Check the stability of the erected rod before releasing the hoisting cable 14
  • 15. Grouting work  Prepare and seal non- shrink motor  Prepare and pour non- shrink grout for pipe works  Keep the installed panel undisturbed for 24hours 15
  • 16. Good practices for grouting  Before grouting check the joint width  The grout used must be self compactable and must have a free flow  Check whether all the horizontal joints are properly sealed  Collect sample test cubes for the grout used for important components 16
  • 17. Joint casting and sealing  Install the joint rebar as required  Set up form for casting  Carry out concrete casting  Removes form after sufficient strength is attained  Place the connecting plates between the panels and weld 17
  • 18. Good practices for joint casting  Joint rebars must be accurately placed  During casting the formwork should be correctly secured  For better water tightness the joint gap should have proper installation of grout 18
  • 19. Installation of horizontal precast components Installation sequence includes  Setting out  Lifting and installation  Casting of joints 19
  • 20. Setting out  Set the reference line and the offset line Good practice  Check the accuracy of the offset line  Check the level and stability of shim plates  Check the dimensions of the protruding bars 20
  • 21. Lifting and installation  Put up temporary props  Lift and rig the elements in position  Align and set the level to suit before placing the member 21
  • 22. Good practices for lifting  Beams should be supported minimum at two locations  Balcony, slabs should be supported in more than two locations  Levelness of the precast elements to be ensured before the joisting action 22
  • 23. Casting of joints  For cast in situ joints place and lap the rebars  Set up form work for casting of joints  Carry out concrete casting 23
  • 24. Good practice for joints  The joints rebars should be accurately placed  The formwork should be properly placed  Supporting beams should be a part of formwork 24
  • 25. General considerations  Safety precautions in the work are of utmost importance  Only those skilled foremen, trained workers and fitters who have been properly instructed about the safety precautions to be taken should be employed on the job.  Transport of people, workers or visitors, by using cranes and hoists should be strictly prohibited  In the case of tower cranes running on rails, the track shall not have a slope more than 0.2 percent in the longitudinal direction. In the transverse direction the rails shall lie in a horizontal plane.  The track of the crane should be checked daily to see that all fish plates and bolts connecting them to the sleepers are in place and in good condition. 25
  • 26. Reference  IS15916:2011 -Building design and erection using prefabricated concrete — code of practice  CONQUAS Quality Assessment Criteria 26