SlideShare a Scribd company logo
1 of 22
GMRInstituteofTechnology
A REPORT ON NAVARATNA TRADE HUB-
COMMERICIAL COMPLEX.
By
G. MOHAN SAI
(16341A0132)
Under the esteemed guidance of
MR. S VEERA BABU
PROJECT MANAGER,
NAVARATNA ESTATES LTD,
VISAKHAPATNAM.
1
GMRInstituteofTechnology
CONTENTS
• ACKNOWLEDGMENT
• ABSTRACT
• INTRODUCTION
• COMPANY’S PROFILE
• TASKS TAKEN UP
• PROBLEM DEFINITION
• METHODOLOGY
• LEARNINGS
• CONCLUSION
• REFERENCE
19-Aug-18
2
GMRInstituteofTechnology
ACKNOWLEDGMENT
I am very thankful to NAVARATNA ESTATES For having given me the
opportunity to undertake my summer training at their prestigious construction. It
was a very good learning experience for me to have worked at the site as this
project involved many unique construction practices and challenges . I would like
to convey my heartiest thanks to
Mr. M Y Subramanyam, Managing Director Navaratna Estates Visakhapatnam,
who heartily welcomed me for the internship. I would also like to give my Heart
felt thanks to Mr. S Veera Babu, Project Manager who guide and encouraged me
all through the summer training and imparted in-depth knowledge of the project.
Also I would like to thank Mr. A Satish, Project co-Ordinator, who assisted and
guide me whenever I need help, for giving their precious time and valuable
guidance during my internship programme.
Last but the least; I would like to thank all the staff for being so helpful during this
summer training.
19-Aug-18
3
GMRInstituteofTechnology
ABSTRACT
• Structural design is the primary aspect of civil engineering. The very basis of
construction of any building, residential house or dams, bridges, culverts, canals
etc. is designing. The foremost basic in structural engineering is the design of
simple basic components and members of a building viz., Slabs, Beams, Columns
and Footings. For their design, an architectural design is prepared using the Auto
CAD. In order to design them, it is important to first obtain the plan of the
particular building that is, positioning of the particular rooms such that they serve
their respective purpose and also suiting to the requirement and comfort of the
inhabitants. Thereby depending on the suitability; plan layout of beams and the
position of columns are fixed. Thereafter, the vertical loads are calculated namely
the dead load and live load from IS: 875.
• In this project, the design of G+5 floors commercial cum residential building is
done according to the Indian standards. IS456 has been used for the reinforcement
design. IS 875 has been used for the estimation of all the loads on the structure viz.
Dead Load, Live Load, and Wind Load. Once the loads are obtained, the slabs are
designed. Designing of slabs depends upon whether it is one-way or a two-way
slab, the end conditions and the loading. The analysis and designing of beams &
columns are done by the “STAAD PRO” software tool. The footings are designed
manually, after completion of designing the detailed estimation has to be carried
out.
19-Aug-18
4
GMRInstituteofTechnology
PROFILE OF THE COMPANY
• M/s Navaratna estates is a newly formed enterprise principally led by three
well known high net worth individuals of Visakhapatnam city having more
than two decades of experience in business and in real estates. The lead
people behind the enterprise are:
• Suresh Kumar Jain, M Y Subramanyam , Manchukonda Shyam
SANGHVI JEWELLERY MALL | SHYAM ZAVERI | MVS JEWEL PARK |
HIRA PANNA
It is a leading construction firm and has expertise infrastructure, capital and
maintenance projects through a range of procurement means for public and
private firms. They have worked in UAE. Navaratna estates established and
business core values. This was further accelerated by the requirements of
worldwide clients, partners and their dedicated team.
CORPARATE OFFICE
D.No. 10-1-27/4, Gold Plaza,4th floor, Sampath Vinayak Temple Road,
Asilmetta, Visakhapatnam 530003 Contact : 0891-6502222,6690956,
Email : navaratnaestates@gmail.com
UAE OFFICE
Maa Kuthari Global, 1005 & 1006,Dusseldorf Business Point,AL Barsha 1
Dubai,UAE, P.O.Box: 185719,Cell: +971 55 7876593
5
GMRInstituteofTechnology
THE PREVIOUS PROJECTS TAKEN UP BY THE FIRM
19-Aug-18
6
GMRInstituteofTechnology
INTRODUCTION
• Navaratna estates is a company registered under the provisions
of Companies Act 1956. The Company is engaged primarily in the
business of Real-estate and construction.
• To plan, develop, acquire, establish, construct, erect, lay, hire,
lease, buy, sell, operate, run, manage, maintain, enlarge, alter,
renovate, modernize, work in all its aspects including the customer
satisfaction. To create a better everyday life for many people. Our
business idea supports this vision by offering a wide range of well-
designed homes and buildings.
19-Aug-18
7
GMRInstituteofTechnology
TASKS TAKEN UP
 Site supervision at various site locations has bee carried out.
 The jungle clearance of the site was carried out.
 The shifting of bench marks and marking them on the certain location in
the site.
 The surveying of the site was done ,the reduced levels were taken using
total station device and transferred to AUTOCAD software .
 To check the levels by using auto level and to estimate the quantity of day’s
work.
 The reduced levels were taken and the excavation process was initiated.
 Learnt about the safety principles and policies of the project and go through
the various safety formats used in the site work.
19-Aug-18
8
GMRInstituteofTechnology
 Studying the layout setting plan and started establishing the elements of it,
i.e. labor campus toilets office cement go downs sheds.
Establishing the labour campus was initiated and the required materials were
incurred .
The toilets and offices were stared simultaneously the brick work, flooring
was started and the aluminum sheets were brought and made into the desired
shape.
The walls were constructed for the offices and labour campuses .
The finishing were done for the walls of the go downs and the flooring was
started the leveling was done and the gravel was poured and compaction the
subsurface is done till the settlement of the ground take place.
The plastering work for the walls was started before doing it the bricks was
watered to avoid the absorption of the water.
The curing was done the walls. The footing plan was studied.
The markings for the footing and the retaining wall was done.
19-Aug-18
Contd..
GMRInstituteofTechnology
Contd..
 Aluminium was carried out in the office room the door and the glass frame
were installed.
 The drilling process was done in excavation process when the hard rock
encountered, the holes were drilled and the cracking powder is poured into
it for the chemical reaction.
 The PCC work has started for the footing learned about the grade of
concrete used.
19-Aug-18
10
GMRInstituteofTechnology
Site location
19-Aug-18
11
Excavation regions of the site
Studying the Site footing plans
GMRInstituteofTechnology
19-Aug-18
12
Leveling of site using auto level
Drilling of hard rocks using cracking powder
GMRInstituteofTechnology
Site plans
19-Aug-18
13
GMRInstituteofTechnology
19-Aug-18
14
GMRInstituteofTechnology
Cont.
19-Aug-18
15
Surveying of the site using the total station Studying Column plan of site
building
Establishing the sheds and the aluminium work
GMRInstituteofTechnology
19-Aug-18
16
Brick masonry Electrical works
False ceiling of the offices
GMRInstituteofTechnology
PROBLEM DEFINTION
 While executing the excavation work at site the water is used to
preached.
 As the work site is with full of electrical and telephonic cables the
excavation work is done my manual methods which delays the
completion of the project.
 During the execution of excavation work, the rains causes so much
interruption in such a way that the work site is completely filled
with water.
 The work site is within the city limits the heavy traffic causes an
interruption for the progress of work.
 The availability of equipment and machinery during the work
progress is not up to the mark.
 Since the project location was in a heavy traffic area the
requirements(Materials, fuel) for the execution of work in site was
delayed.
19-Aug-18
17
GMRInstituteofTechnology
METHODOLOGY
 The technique used in the exaction were drilling and by using the breakers.
 The cracking powder was used to break the hard rocks encountered while
excavating .
 Profile leveling method was utilized in site for taking the reading of the
site.
 To overcome the parched water while excavating, the pump is used
transfer the water to surface into drain pipes.
 Additional support are used for effective execution of earth work.
 Proper Safety measures like Safety shoe, hand gloves, safety jackets are
provided while executing with electric cables.
 For the issues related to the sound pollution and the other environmental
factors necessary permission were taken from the respective departments.
 The structural designs and the footing, column plans were examined clearly
and if there are any changes , for the development of plan the intimation
was done to the expertise people.
19-Aug-18
18
GMRInstituteofTechnology
LEARNINGS
 Learned about ‘rebar’ its alignment and how to calculate the unit weight of
the steel using the formula and about the spacing between the bars.
 Learned about the brick work, about the joints and the spacing of it also
about the site preparation, hacking, marking, soaking of the bricks motor
mix.
 Learned about Damp proof coarse ,wall cladding e.g. In movie theatres
 Learned about the anchor bolts ,beam pockets- used for the installation of
the cooling tower and other amenities on the slab the anchor bolts are
placed in the absence of beam pockets. backfilling, cover block- in the
excavation or in the construction the footing, retaining wall.
 By dealing with auto level we learned quantity estimation of various works
involved in the site.
 Learnt to analyze the site work execution by observing corresponding
drawings.
 Based on the drawings, bar bending schedule and quantity of concrete are
estimated.
19-Aug-18
19
GMRInstituteofTechnology
CONCLUSION
It was a wonderful learning experience at Navaratna Estates site
of Trade hub commercial complex project for one month in
Visakhapatnam. It is advantageous in such a manner before
entering into the designated jobs we can come to know about
the practical approach for the existing site conditions. I gained
a lot of insight regarding almost every aspect of site. I was
given exposure in almost all the departments at the site. The
friendly welcome from all the employees is appreciating,
sharing their experience and giving their peace of wisdom
which they have gained in long journey of work. I am very
much thankful to the project manager. I hope this experience
will surely help me in my future and also in shaping my career.
19-Aug-18
20
GMRInstituteofTechnology
REFERENCE
• “Reinforcement placing”, and handling shall be as per IS-456
• IS 456 “Plain and Reinforced concrete Code”
• IS 6461(Part 5) “Glossary of terms relating to cement
concrete”
• Tender Specification
• Approved Drawings
• IS 10262 “Guidelines for Concrete mix design
proportionating”
• IS 3370 “Code for Practice concrete structure for storage of
liquids”
• IS 456 “Plain and Reinforced concrete”
• IS 383 “Specification for coarse and Fine Aggregate for
concrete”
• IS 800 2007 “Design Of steel Structures”
19-Aug-18
21
GMRInstituteofTechnology
ThankYou
19-Aug-18
22

More Related Content

What's hot

HC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyHC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyTeow Beng Hur
 
Sr[1].Mech. Eng. Ayad Anad CV 3
Sr[1].Mech. Eng. Ayad Anad CV 3Sr[1].Mech. Eng. Ayad Anad CV 3
Sr[1].Mech. Eng. Ayad Anad CV 3Eiad Anad
 
AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015Ahmed Yehia
 
SPUITGIETEN IN EEN NOTENDOP
SPUITGIETEN IN EEN NOTENDOPSPUITGIETEN IN EEN NOTENDOP
SPUITGIETEN IN EEN NOTENDOPTSGgroup
 
Kghm international, victoria project, past, present and what's next cim pre...
Kghm international, victoria project, past, present and what's next   cim pre...Kghm international, victoria project, past, present and what's next   cim pre...
Kghm international, victoria project, past, present and what's next cim pre...KGHM
 

What's hot (12)

Mohammad Ghayoor Khan CV oil
Mohammad Ghayoor Khan CV oilMohammad Ghayoor Khan CV oil
Mohammad Ghayoor Khan CV oil
 
HC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical PropertyHC PRECAST SYSTEM's Technical Property
HC PRECAST SYSTEM's Technical Property
 
Sr[1].Mech. Eng. Ayad Anad CV 3
Sr[1].Mech. Eng. Ayad Anad CV 3Sr[1].Mech. Eng. Ayad Anad CV 3
Sr[1].Mech. Eng. Ayad Anad CV 3
 
AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015AHMED YEHIA MARCH 2015
AHMED YEHIA MARCH 2015
 
Ugeshan Naidoo1
Ugeshan Naidoo1Ugeshan Naidoo1
Ugeshan Naidoo1
 
JAGMOC RESUME
JAGMOC RESUMEJAGMOC RESUME
JAGMOC RESUME
 
SPUITGIETEN IN EEN NOTENDOP
SPUITGIETEN IN EEN NOTENDOPSPUITGIETEN IN EEN NOTENDOP
SPUITGIETEN IN EEN NOTENDOP
 
mohammad fathi cv2017
mohammad fathi cv2017mohammad fathi cv2017
mohammad fathi cv2017
 
1. MAQ CV-
1. MAQ CV-1. MAQ CV-
1. MAQ CV-
 
cv1
cv1cv1
cv1
 
Muhammad Qasim Zaib C.V
Muhammad Qasim Zaib C.VMuhammad Qasim Zaib C.V
Muhammad Qasim Zaib C.V
 
Kghm international, victoria project, past, present and what's next cim pre...
Kghm international, victoria project, past, present and what's next   cim pre...Kghm international, victoria project, past, present and what's next   cim pre...
Kghm international, victoria project, past, present and what's next cim pre...
 

Similar to Intership report

internship report report
internship report reportinternship report report
internship report reportMohan Sai G
 
Industrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdIndustrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdSk Md Nayar
 
Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Abhimanyu Saraswat
 
Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installationguest470ea8
 
Analysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyAnalysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyIRJET Journal
 
summer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnasummer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnakishore1192
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)rahul jangid
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2Ravi Mehta
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CVAli Khidr
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Ram1239
 
CIVIL ENGINEERING PROJECT LIST FOR 2019-2020
CIVIL ENGINEERING PROJECT LIST FOR 2019-2020CIVIL ENGINEERING PROJECT LIST FOR 2019-2020
CIVIL ENGINEERING PROJECT LIST FOR 2019-2020IGEEKS TECHNOLOGIES
 

Similar to Intership report (20)

internship report report
internship report reportinternship report report
internship report report
 
Industrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdIndustrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures Ltd
 
Mahmoud CV 11-2015
Mahmoud CV 11-2015Mahmoud CV 11-2015
Mahmoud CV 11-2015
 
Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Summer Internship in Jaypee Group
Summer Internship in Jaypee Group
 
Pathak resume
Pathak resumePathak resume
Pathak resume
 
Resume -Amarnath
Resume -AmarnathResume -Amarnath
Resume -Amarnath
 
Resume -Amarnath
Resume -AmarnathResume -Amarnath
Resume -Amarnath
 
Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installation
 
MAMDOUH_CV
MAMDOUH_CVMAMDOUH_CV
MAMDOUH_CV
 
13.ICON Brochure
13.ICON Brochure13.ICON Brochure
13.ICON Brochure
 
Analysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case studyAnalysing the role of Cable Anchor in Hydroelectric project A case study
Analysing the role of Cable Anchor in Hydroelectric project A case study
 
summer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnasummer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patna
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering
 
RESUME
RESUMERESUME
RESUME
 
CIVIL ENGINEERING PROJECT LIST FOR 2019-2020
CIVIL ENGINEERING PROJECT LIST FOR 2019-2020CIVIL ENGINEERING PROJECT LIST FOR 2019-2020
CIVIL ENGINEERING PROJECT LIST FOR 2019-2020
 
JUNDEE MAR TEJEDO
JUNDEE MAR TEJEDOJUNDEE MAR TEJEDO
JUNDEE MAR TEJEDO
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

Intership report

  • 1. GMRInstituteofTechnology A REPORT ON NAVARATNA TRADE HUB- COMMERICIAL COMPLEX. By G. MOHAN SAI (16341A0132) Under the esteemed guidance of MR. S VEERA BABU PROJECT MANAGER, NAVARATNA ESTATES LTD, VISAKHAPATNAM. 1
  • 2. GMRInstituteofTechnology CONTENTS • ACKNOWLEDGMENT • ABSTRACT • INTRODUCTION • COMPANY’S PROFILE • TASKS TAKEN UP • PROBLEM DEFINITION • METHODOLOGY • LEARNINGS • CONCLUSION • REFERENCE 19-Aug-18 2
  • 3. GMRInstituteofTechnology ACKNOWLEDGMENT I am very thankful to NAVARATNA ESTATES For having given me the opportunity to undertake my summer training at their prestigious construction. It was a very good learning experience for me to have worked at the site as this project involved many unique construction practices and challenges . I would like to convey my heartiest thanks to Mr. M Y Subramanyam, Managing Director Navaratna Estates Visakhapatnam, who heartily welcomed me for the internship. I would also like to give my Heart felt thanks to Mr. S Veera Babu, Project Manager who guide and encouraged me all through the summer training and imparted in-depth knowledge of the project. Also I would like to thank Mr. A Satish, Project co-Ordinator, who assisted and guide me whenever I need help, for giving their precious time and valuable guidance during my internship programme. Last but the least; I would like to thank all the staff for being so helpful during this summer training. 19-Aug-18 3
  • 4. GMRInstituteofTechnology ABSTRACT • Structural design is the primary aspect of civil engineering. The very basis of construction of any building, residential house or dams, bridges, culverts, canals etc. is designing. The foremost basic in structural engineering is the design of simple basic components and members of a building viz., Slabs, Beams, Columns and Footings. For their design, an architectural design is prepared using the Auto CAD. In order to design them, it is important to first obtain the plan of the particular building that is, positioning of the particular rooms such that they serve their respective purpose and also suiting to the requirement and comfort of the inhabitants. Thereby depending on the suitability; plan layout of beams and the position of columns are fixed. Thereafter, the vertical loads are calculated namely the dead load and live load from IS: 875. • In this project, the design of G+5 floors commercial cum residential building is done according to the Indian standards. IS456 has been used for the reinforcement design. IS 875 has been used for the estimation of all the loads on the structure viz. Dead Load, Live Load, and Wind Load. Once the loads are obtained, the slabs are designed. Designing of slabs depends upon whether it is one-way or a two-way slab, the end conditions and the loading. The analysis and designing of beams & columns are done by the “STAAD PRO” software tool. The footings are designed manually, after completion of designing the detailed estimation has to be carried out. 19-Aug-18 4
  • 5. GMRInstituteofTechnology PROFILE OF THE COMPANY • M/s Navaratna estates is a newly formed enterprise principally led by three well known high net worth individuals of Visakhapatnam city having more than two decades of experience in business and in real estates. The lead people behind the enterprise are: • Suresh Kumar Jain, M Y Subramanyam , Manchukonda Shyam SANGHVI JEWELLERY MALL | SHYAM ZAVERI | MVS JEWEL PARK | HIRA PANNA It is a leading construction firm and has expertise infrastructure, capital and maintenance projects through a range of procurement means for public and private firms. They have worked in UAE. Navaratna estates established and business core values. This was further accelerated by the requirements of worldwide clients, partners and their dedicated team. CORPARATE OFFICE D.No. 10-1-27/4, Gold Plaza,4th floor, Sampath Vinayak Temple Road, Asilmetta, Visakhapatnam 530003 Contact : 0891-6502222,6690956, Email : navaratnaestates@gmail.com UAE OFFICE Maa Kuthari Global, 1005 & 1006,Dusseldorf Business Point,AL Barsha 1 Dubai,UAE, P.O.Box: 185719,Cell: +971 55 7876593 5
  • 6. GMRInstituteofTechnology THE PREVIOUS PROJECTS TAKEN UP BY THE FIRM 19-Aug-18 6
  • 7. GMRInstituteofTechnology INTRODUCTION • Navaratna estates is a company registered under the provisions of Companies Act 1956. The Company is engaged primarily in the business of Real-estate and construction. • To plan, develop, acquire, establish, construct, erect, lay, hire, lease, buy, sell, operate, run, manage, maintain, enlarge, alter, renovate, modernize, work in all its aspects including the customer satisfaction. To create a better everyday life for many people. Our business idea supports this vision by offering a wide range of well- designed homes and buildings. 19-Aug-18 7
  • 8. GMRInstituteofTechnology TASKS TAKEN UP  Site supervision at various site locations has bee carried out.  The jungle clearance of the site was carried out.  The shifting of bench marks and marking them on the certain location in the site.  The surveying of the site was done ,the reduced levels were taken using total station device and transferred to AUTOCAD software .  To check the levels by using auto level and to estimate the quantity of day’s work.  The reduced levels were taken and the excavation process was initiated.  Learnt about the safety principles and policies of the project and go through the various safety formats used in the site work. 19-Aug-18 8
  • 9. GMRInstituteofTechnology  Studying the layout setting plan and started establishing the elements of it, i.e. labor campus toilets office cement go downs sheds. Establishing the labour campus was initiated and the required materials were incurred . The toilets and offices were stared simultaneously the brick work, flooring was started and the aluminum sheets were brought and made into the desired shape. The walls were constructed for the offices and labour campuses . The finishing were done for the walls of the go downs and the flooring was started the leveling was done and the gravel was poured and compaction the subsurface is done till the settlement of the ground take place. The plastering work for the walls was started before doing it the bricks was watered to avoid the absorption of the water. The curing was done the walls. The footing plan was studied. The markings for the footing and the retaining wall was done. 19-Aug-18 Contd..
  • 10. GMRInstituteofTechnology Contd..  Aluminium was carried out in the office room the door and the glass frame were installed.  The drilling process was done in excavation process when the hard rock encountered, the holes were drilled and the cracking powder is poured into it for the chemical reaction.  The PCC work has started for the footing learned about the grade of concrete used. 19-Aug-18 10
  • 11. GMRInstituteofTechnology Site location 19-Aug-18 11 Excavation regions of the site Studying the Site footing plans
  • 12. GMRInstituteofTechnology 19-Aug-18 12 Leveling of site using auto level Drilling of hard rocks using cracking powder
  • 15. GMRInstituteofTechnology Cont. 19-Aug-18 15 Surveying of the site using the total station Studying Column plan of site building Establishing the sheds and the aluminium work
  • 17. GMRInstituteofTechnology PROBLEM DEFINTION  While executing the excavation work at site the water is used to preached.  As the work site is with full of electrical and telephonic cables the excavation work is done my manual methods which delays the completion of the project.  During the execution of excavation work, the rains causes so much interruption in such a way that the work site is completely filled with water.  The work site is within the city limits the heavy traffic causes an interruption for the progress of work.  The availability of equipment and machinery during the work progress is not up to the mark.  Since the project location was in a heavy traffic area the requirements(Materials, fuel) for the execution of work in site was delayed. 19-Aug-18 17
  • 18. GMRInstituteofTechnology METHODOLOGY  The technique used in the exaction were drilling and by using the breakers.  The cracking powder was used to break the hard rocks encountered while excavating .  Profile leveling method was utilized in site for taking the reading of the site.  To overcome the parched water while excavating, the pump is used transfer the water to surface into drain pipes.  Additional support are used for effective execution of earth work.  Proper Safety measures like Safety shoe, hand gloves, safety jackets are provided while executing with electric cables.  For the issues related to the sound pollution and the other environmental factors necessary permission were taken from the respective departments.  The structural designs and the footing, column plans were examined clearly and if there are any changes , for the development of plan the intimation was done to the expertise people. 19-Aug-18 18
  • 19. GMRInstituteofTechnology LEARNINGS  Learned about ‘rebar’ its alignment and how to calculate the unit weight of the steel using the formula and about the spacing between the bars.  Learned about the brick work, about the joints and the spacing of it also about the site preparation, hacking, marking, soaking of the bricks motor mix.  Learned about Damp proof coarse ,wall cladding e.g. In movie theatres  Learned about the anchor bolts ,beam pockets- used for the installation of the cooling tower and other amenities on the slab the anchor bolts are placed in the absence of beam pockets. backfilling, cover block- in the excavation or in the construction the footing, retaining wall.  By dealing with auto level we learned quantity estimation of various works involved in the site.  Learnt to analyze the site work execution by observing corresponding drawings.  Based on the drawings, bar bending schedule and quantity of concrete are estimated. 19-Aug-18 19
  • 20. GMRInstituteofTechnology CONCLUSION It was a wonderful learning experience at Navaratna Estates site of Trade hub commercial complex project for one month in Visakhapatnam. It is advantageous in such a manner before entering into the designated jobs we can come to know about the practical approach for the existing site conditions. I gained a lot of insight regarding almost every aspect of site. I was given exposure in almost all the departments at the site. The friendly welcome from all the employees is appreciating, sharing their experience and giving their peace of wisdom which they have gained in long journey of work. I am very much thankful to the project manager. I hope this experience will surely help me in my future and also in shaping my career. 19-Aug-18 20
  • 21. GMRInstituteofTechnology REFERENCE • “Reinforcement placing”, and handling shall be as per IS-456 • IS 456 “Plain and Reinforced concrete Code” • IS 6461(Part 5) “Glossary of terms relating to cement concrete” • Tender Specification • Approved Drawings • IS 10262 “Guidelines for Concrete mix design proportionating” • IS 3370 “Code for Practice concrete structure for storage of liquids” • IS 456 “Plain and Reinforced concrete” • IS 383 “Specification for coarse and Fine Aggregate for concrete” • IS 800 2007 “Design Of steel Structures” 19-Aug-18 21