The document provides an execution plan for the KGA Mall project in Changanassery presented by Build Tech Associates. It includes an agenda, project brief detailing a 9 floor commercial and hospitality building, Build Tech's approach focusing on quality and safety, proposed construction methodology in 4 steps, site organization chart, deployment plans for equipment, shuttering materials, and manpower, milestone dates across a 12 month period, and pour joint plans for different floors.
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECTSAJJAD KHUDHUR ABBAS
The Project management plan presented here will describe the project manager’s approach and the general responsibilities of the project team. In addition to the project management plan, several other documents will be developed and used to ensure compliance with project requirements as well regulations and industry specific standards. The specific plans will include processes, flow diagrams, responsibility matrices, organizational charts, and other pertinent information to guide the project staff.
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECTSAJJAD KHUDHUR ABBAS
The Project management plan presented here will describe the project manager’s approach and the general responsibilities of the project team. In addition to the project management plan, several other documents will be developed and used to ensure compliance with project requirements as well regulations and industry specific standards. The specific plans will include processes, flow diagrams, responsibility matrices, organizational charts, and other pertinent information to guide the project staff.
The internship was divided into four parts
4 weeks: Site execution with emphasis on HSE and QA/QC.
2 weeks: Updating the status of Tower in Tracking Tool and creating a MSP program on the remaining activities left in the building.
1 week : Contract analysis
1 week : Marketing concepts used and preparation of case study on company.
Ques: 1.Why this system is called SLIPFORMING?
Ques: 3.Slipforming is mechanized way of constructing very high structures & involves Mechanical/Civil/Hydraulic Engineers. Explain?
Ques: 4.How the tapering structures are made by Slipforming? How do we reduce
diameter, wall thickness & do Lifting Simultaneously?
Ques: 5.Manpower saving in Slipforming (no carpenters required), Good for the
Country/Employment?
Ques: 6.Will mechanization in form work render our carpenters idle?
Ques: 7.Scaffolding is major capital investment in Construction Projects, no
scaffolding is required for Slipform Projects, and how Slipforming is cost effective?Please discuss.
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
The internship was divided into four parts
4 weeks: Site execution with emphasis on HSE and QA/QC.
2 weeks: Updating the status of Tower in Tracking Tool and creating a MSP program on the remaining activities left in the building.
1 week : Contract analysis
1 week : Marketing concepts used and preparation of case study on company.
Ques: 1.Why this system is called SLIPFORMING?
Ques: 3.Slipforming is mechanized way of constructing very high structures & involves Mechanical/Civil/Hydraulic Engineers. Explain?
Ques: 4.How the tapering structures are made by Slipforming? How do we reduce
diameter, wall thickness & do Lifting Simultaneously?
Ques: 5.Manpower saving in Slipforming (no carpenters required), Good for the
Country/Employment?
Ques: 6.Will mechanization in form work render our carpenters idle?
Ques: 7.Scaffolding is major capital investment in Construction Projects, no
scaffolding is required for Slipform Projects, and how Slipforming is cost effective?Please discuss.
Similar to 11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx (20)
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
Presented at NUS: Fuzzing and Software Security Summer School 2024
This keynote talks about the democratization of fuzzing at scale, highlighting the collaboration between open source communities, academia, and industry to advance the field of fuzzing. It delves into the history of fuzzing, the development of scalable fuzzing platforms, and the empowerment of community-driven research. The talk will further discuss recent advancements leveraging AI/ML and offer insights into the future evolution of the fuzzing landscape.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
Maintaining high-quality standards in the production of TMT bars is crucial for ensuring structural integrity in construction. Addressing common defects through careful monitoring, standardized processes, and advanced technology can significantly improve the quality of TMT bars. Continuous training and adherence to quality control measures will also play a pivotal role in minimizing these defects.
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfKamal Acharya
The College Bus Management system is completely developed by Visual Basic .NET Version. The application is connect with most secured database language MS SQL Server. The application is develop by using best combination of front-end and back-end languages. The application is totally design like flat user interface. This flat user interface is more attractive user interface in 2017. The application is gives more important to the system functionality. The application is to manage the student’s details, driver’s details, bus details, bus route details, bus fees details and more. The application has only one unit for admin. The admin can manage the entire application. The admin can login into the application by using username and password of the admin. The application is develop for big and small colleges. It is more user friendly for non-computer person. Even they can easily learn how to manage the application within hours. The application is more secure by the admin. The system will give an effective output for the VB.Net and SQL Server given as input to the system. The compiled java program given as input to the system, after scanning the program will generate different reports. The application generates the report for users. The admin can view and download the report of the data. The application deliver the excel format reports. Because, excel formatted reports is very easy to understand the income and expense of the college bus. This application is mainly develop for windows operating system users. In 2017, 73% of people enterprises are using windows operating system. So the application will easily install for all the windows operating system users. The application-developed size is very low. The application consumes very low space in disk. Therefore, the user can allocate very minimum local disk space for this application.
Automobile Management System Project Report.pdfKamal Acharya
The proposed project is developed to manage the automobile in the automobile dealer company. The main module in this project is login, automobile management, customer management, sales, complaints and reports. The first module is the login. The automobile showroom owner should login to the project for usage. The username and password are verified and if it is correct, next form opens. If the username and password are not correct, it shows the error message.
When a customer search for a automobile, if the automobile is available, they will be taken to a page that shows the details of the automobile including automobile name, automobile ID, quantity, price etc. “Automobile Management System” is useful for maintaining automobiles, customers effectively and hence helps for establishing good relation between customer and automobile organization. It contains various customized modules for effectively maintaining automobiles and stock information accurately and safely.
When the automobile is sold to the customer, stock will be reduced automatically. When a new purchase is made, stock will be increased automatically. While selecting automobiles for sale, the proposed software will automatically check for total number of available stock of that particular item, if the total stock of that particular item is less than 5, software will notify the user to purchase the particular item.
Also when the user tries to sale items which are not in stock, the system will prompt the user that the stock is not enough. Customers of this system can search for a automobile; can purchase a automobile easily by selecting fast. On the other hand the stock of automobiles can be maintained perfectly by the automobile shop manager overcoming the drawbacks of existing system.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Forklift Classes Overview by Intella PartsIntella Parts
Discover the different forklift classes and their specific applications. Learn how to choose the right forklift for your needs to ensure safety, efficiency, and compliance in your operations.
For more technical information, visit our website https://intellaparts.com
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
Immunizing Image Classifiers Against Localized Adversary Attacks
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
1. PROJECT EXECUTION PLAN
KGA MALL, CHANGANASSERY
Presented by:
M/s Build Tech Associates, Ernakulam
Date : 07.03.203
2. AGENDA
PROJECT BREIF
BUILD TECH’S APPROACH
CONSTRUCTION METHODOLOGY
SITE ORGANISATION CHART
PROPOESD DEPLOYMENT OF P&M
PROPOSED DEPLOYMENT OF SHUTTERING MATERIAL
MILESTONE DATES
PROPOSED MANPOWER DEPLOYMENT SCHEDULE
POUR JOINTS
3. PROJECT BRIEF
BUILDING : COMMERCIAL & HOSPITALITY
CLIENT : M/s KGA International Trades Pvt. Ltd.,
ARCHITECT : M/s Edifice Consultants Pvt. Ltd.,
CONTRACTOR : M/s BUILD TECH ASSOCIATES
NO: OF FLOORS : 09
PROJECT DURATION: 12 MONTHS
EXCAVATON : 49195 CUM
CONCRETE QTY : 28210 CUM
REINFORCEMENT : 4293 MT
BLOCK WORK : 7254 CUM
PLASTERING : 74990 SQM
4. BUILD TECH’S APPROACH
BUILD TECH is approaching this work not as an isolated project, rather as the start of
the long term association with respectable client. Similar to any other project of ours,
we are committed for the timely project completion with no compromise on the quality
of the product delivered as well as the safety of the human life involved during the
execution phase. In order to ensure the aforesaid deliverables we has our own “Safety
and Quality Policy”, its plans to execute in-line to the standards as laid out in the
contract document.
Our greatest strength in execution is we have our own In-house labours for all the civil
works and all the machineries we deployed at the project are our self-owned, with
reduces the uncertainty to a considerable extent.
Even for the specialized jobs such as Waterproofing, Painting etc., we are associated
with Best-In-Class and reputed teams for its execution.
We take this opportunity once again to thank you for your belief in us and for the
opportunity provided to be part of this prestigious project.
5. CONSTRUCTION METHODOLOGY
BUILD TECH’S project execution strategy is guided by four steps as below:
• Total Qty of Execution
• Scheduling
• Manpower Projection
• Material Projection
• P&M Projection
• Cashflow Projection
Planning
Step 1
Execute
Step 2
Monitoring
Step 3
Closing
Step 4
• Adhering Safety Plan
• Adhering Quality Plan
• Compiling with ITP
• Schedule Tracking
• Other record
upkeeping
• Handing over of
building, documents &
As-Build drawing
8. The activity starts Installation of Dewatering system followed with the mass
excavation above and then followed with three layers of the sheet pile 1.5m
apart for the maximum depth
EXCAVATION & SHEET PILING
9. EXCAVATION & SHEET PILING
• Two meter of excavation
is done after driving of
3m sheet pile.
• All sheet pile will be tied
horizontally at top using
ISMC/ISMB by welding
• Sheet piles are vertically
support with
ISMC/ISMB at 1m c/c.
12. DEWATERING
We propose to install “deep well dewatering system” around the building periphery
in required intervals. Dewatering will continue 24x7 until the completion of Lower
Ground Floor.
13. CONCRETE
Presently we have planned to source the concrete from the external batching plant
and 3 RMC plants are available within the distance of 15km, nearest being M/s
Ultratech RMC.
Parallelly we are in process of identifying land to install our own Batching Plant in a
view to avoid the dependency.
14. The Combination of MS sheet, Plywood, System shuttering is considered for different
structural elements.
System Formwork of BII is considered.
FORMWORK
Acierise Panel Formwork - Flexibility
23. MILESTONE DATES
Task Mode Task Name Duration Start Finish
Auto Scheduled Proposed KGA Mall 366 days 01-03-23 29-02-24
Auto Scheduled Mobilisation 32 days 01-03-23 01-04-23
Auto Scheduled Sub -Structure Work 183 days 03-03-23 01-09-23
Auto Scheduled Super -Structure Work 179 days 28-07-23 22-01-24
Auto Scheduled Civil Finishing - Internal 196 days 15-08-23 26-02-24
Auto Scheduled Civil Finishing - External 70 days 22-12-23 29-02-24