Double Storey HC Precast System Drawing - 3D
Superstructure ( Frame & Wall ) :
- By HC Precast System
77 %
23 %
Sub- Structure By Other :
- Appointed By Client
INDUSTRIALISED BUILDING SYSTEM ( IBS )
is a system not a machine or component
IMPORTANT
ELEMENTS REQUIRED TO COMPLETE A BUILDING
SEQUENCE OF WORK : 5 Steps & No Variation Order
Step 1 Step 2 Step 3 Step 4 Step 5
Drawing Mould Production Delivery Installation
Conversion Fabrication Numbering
( 2D to 3D ) ( Decide by Client )
Speed, Quality & Environment
Step 1 : Drawing Conversion 2D To 3D - 1 Month
Original 2D To System 3D
Step 1 : Drawing Conversion 2D To 3D
Original 2D To System 3D
Original Drawing To System Shop Drawing - 1
Step 1a : M & E Conversion original to system shop drawing 1
Original Drawing To System Shop Drawing - 1
Step 1a : M & E Conversion original to system shop drawing 2
Step 2 : Mould Fabrication - 1 Month
1. Designed by You 2. Coping 1 Cast 3. Chequer Plate ( Tiling )
4. L shape Panel 5. Door Frame 1 Cast 6. Half Slab
Existing production 8 acres : 1,800 to 2,500 units
of single storey ( 1000 ft2 ) per year
Future development 13 acres : 2,500 to 3,500 units of
single storey ( 1000 ft2 ) per year
SPEED ( step 3 to 5 ) : Decide by Client : Production , Delivery & Installation
SPEED ( step 3 to 5 ) : Decide by Client : Production , Delivery & Installation
SPEED ( step 3 to 5 ) : Decide by Client : Production , Delivery & Installation
SPEED ( step 3 to 5 ) : Decide by Client : Production , Delivery & Installation
Every Truck Every 20m3 Casting & Leveling Mould Dismantling
Rebound Hammer Test Panel Lifting Vertical Curing 7days Proper Storage Yards
Step 3 : Production ( Decide by Client ) - 7 to 9 units / day
Step 4 : Delivery ( 4 Options ) - Decide by Client
1. Bay Yard to Block Yard 2. Bay Yard to Site yard (project) – Advance Casting
3. Storage Yard (factory) to Block Yard – Advance Casting 4. Storage Yard (factory) to Site Yard (project) – Advance Casting
Step 4a : Delivery ( 4 Options ) - Decide by Client
Step 5 : Installation - Decide By Client
Sequence Block by Block One Time Adjustment
Step 5a : Installation - Numbering
1. Panel Guide 2. Panel Installation 3. Wall Prop installation
4. Vertical Adjust 5. Expending Cement 6. Rebar Installation
Step 5b : Installation
7. Mould Installation 8. Wet joint Casting 9. Mould Dismantling
10. Half Slab installation 11. Rebar Install 12. RC Flat Roof Casting
Step 5c : Installation
Step 5d : Over View
Absolutely no Variation Order (V.O) due to :-
- No material wastage (minimal concreting at site)
- Accurate estimation by 3D drawing of building precast elements
-(wall, beam, staircase & partition ) compared to bricks,
-reinforcement work and concreting at site.
No Variation Order
1. If we talk about lowering house prices, what is the best way to do it? The
best way is to build houses faster and cheaper. One of the ways is by using
Industrial Building Systems ( IBS ).
2. Industrialised Building System is a system not a machine or component.
Responsibility of the building should not have many different mix system and
manufacture products.
3. System provider and manufacturer should provided installer of the building
precast element.
4. Same concept applies when we buy computer and hardware.
5. Q-Lassic or Conquas should be carried-out upon the completion of the
superstructure works (frame & wall) instead of upon of completion finishing
work.
IBS Superstructure In Malaysia 3 in 1
Single Storey Bungalow RM 125,000.00
3,891.31 ft2 / Wall High 4.0m / R.C Flat Roof
Completed In 10 Days With 6 Workers
Precast Element 86 % , Wet Work 14 %
Load Bearing Wall Modular Shear Keys Box System
Wet Joint
HC PRECAST SYSTEM
- The wall is designed to provide adequate fire resistance according to demand ( with minimum 2 hours as per BS8110 )
- The system is designed and approved by PE endorsed by independent checker
- Thickness of the wall can be customized according to requirement
- Our design and casting are following strictly to British Standard
Scopes Of Works For Superstructure : Frame & Wall
Included :
- Supply & install.
- Superstructure design calculation.
- Shop drawing for M&E location layout related to panel wall casting. (Subject to client / consultant confirmation)
- Setting out (panel) : TBM for each block & 4+2 Boundary point per unit must be provided.
- Mobile crane.
Excluded :
- Substructure design by others.
- Contractor All Risks Insurance.
- Security of our material & system works.
- Temporary water & electricity supply.
- Quarters for workers.
- Access road at project site.
- Storage yard at project site : 50mm thick crusher run base.
- Supply & install metal door & window frame.
- Supply & install M&E conduit.
- Skim coat.
Easy & Fast To Compare Our System Superstructure Price
Easy & Fast To Compare Our System Superstructure Price
Cost comparison of superstructure available online at our website
Cost comparison of superstructure available online at our website
Payment terms available online at our website
Installation Sequence by Numbering
System Drawing - 3 D
Finishing Views - 1
Finishing Views - 2
Finishing Views - 3
Finishing Views - 4
Finishing Views - 5
Finishing Views - 6
Finishing Views - 7
Finishing Views - 8
Finishing Views - 9
Finishing Views - 10
Finishing Views - 11
Finishing Views - 12
Finishing Views - 13
Finishing Views - 14
Finishing Views - 15
Finishing Views - 16
Finishing Views - 17
Finishing Views - 18
Finishing Views - 19
Finishing Views - 20
Finishing Views - 21
Finishing Views - 22
Finishing Views - 23
Finishing Views - 24
Thin layer of cement mortar (tiling works) due to evenness of the wall.
Vertical Views - 25
Vertical View - 26
SPEED & SEQUENCE : Decide by Client : Production , Delivery & Installation -1
SPEED & SEQUENCE : Decide by Client : Production , Delivery & Installation -2
SPEED & SEQUENCE : Decide by Client : Production , Delivery & Installation -3
THANK YOU
DESIGN BY YOU
PRODUCE BY HC

More Related Content

What's hot

IBS Factory Report Assignment
IBS Factory Report AssignmentIBS Factory Report Assignment
IBS Factory Report AssignmentHaziq1511
 
Prefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusPrefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusIEI GSC
 
PEB construction-Mukesh Bhavsar
PEB construction-Mukesh BhavsarPEB construction-Mukesh Bhavsar
PEB construction-Mukesh BhavsarMukesh Bhavsar
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Mega prefab company profile
Mega prefab company profileMega prefab company profile
Mega prefab company profilebassamnakfour
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibsUTHM
 
Modular Construction Advancements
Modular Construction AdvancementsModular Construction Advancements
Modular Construction AdvancementsAkhil Saxena
 
Prefabrication for improving Sustainability and Economics of Civil Engineerin...
Prefabrication for improving Sustainability and Economics of Civil Engineerin...Prefabrication for improving Sustainability and Economics of Civil Engineerin...
Prefabrication for improving Sustainability and Economics of Civil Engineerin...Ankit Singhai
 
Industrialised Building System report,
Industrialised Building System report, Industrialised Building System report,
Industrialised Building System report, Eraz
 
prefabrication structure report
prefabrication structure report prefabrication structure report
prefabrication structure report AbhishekM45
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...Haziq1511
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
#6a modular construction (1)
#6a    modular construction (1)#6a    modular construction (1)
#6a modular construction (1)Eveana Crystle
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building SolutionLee Wan Xuan
 
073 Modern Method of Construction https://www.blogger.com/profile/0220990482...
073 Modern Method of Construction  https://www.blogger.com/profile/0220990482...073 Modern Method of Construction  https://www.blogger.com/profile/0220990482...
073 Modern Method of Construction https://www.blogger.com/profile/0220990482...Dr Fereidoun Dejahang
 
CT3 1c aluminium formwork+
CT3 1c aluminium formwork+ CT3 1c aluminium formwork+
CT3 1c aluminium formwork+ Est
 

What's hot (20)

IBS Factory Report Assignment
IBS Factory Report AssignmentIBS Factory Report Assignment
IBS Factory Report Assignment
 
Prefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusPrefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed Impetus
 
PEB construction-Mukesh Bhavsar
PEB construction-Mukesh BhavsarPEB construction-Mukesh Bhavsar
PEB construction-Mukesh Bhavsar
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Mega prefab company profile
Mega prefab company profileMega prefab company profile
Mega prefab company profile
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibs
 
Modular Construction Advancements
Modular Construction AdvancementsModular Construction Advancements
Modular Construction Advancements
 
Prefabrication for improving Sustainability and Economics of Civil Engineerin...
Prefabrication for improving Sustainability and Economics of Civil Engineerin...Prefabrication for improving Sustainability and Economics of Civil Engineerin...
Prefabrication for improving Sustainability and Economics of Civil Engineerin...
 
Industrialised Building System report,
Industrialised Building System report, Industrialised Building System report,
Industrialised Building System report,
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES A PRESENTATION ON PREFABRICATED STRUCTURES
A PRESENTATION ON PREFABRICATED STRUCTURES
 
prefabrication structure report
prefabrication structure report prefabrication structure report
prefabrication structure report
 
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...IBS - Individual Assignment (Time comparison between IBS & traditional constr...
IBS - Individual Assignment (Time comparison between IBS & traditional constr...
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
MMC Revision Notes
MMC Revision NotesMMC Revision Notes
MMC Revision Notes
 
#6a modular construction (1)
#6a    modular construction (1)#6a    modular construction (1)
#6a modular construction (1)
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building Solution
 
073 Modern Method of Construction https://www.blogger.com/profile/0220990482...
073 Modern Method of Construction  https://www.blogger.com/profile/0220990482...073 Modern Method of Construction  https://www.blogger.com/profile/0220990482...
073 Modern Method of Construction https://www.blogger.com/profile/0220990482...
 
CT3 1c aluminium formwork+
CT3 1c aluminium formwork+ CT3 1c aluminium formwork+
CT3 1c aluminium formwork+
 
duplex villa ppt
duplex villa pptduplex villa ppt
duplex villa ppt
 

Similar to 1.6 _Important element required to complete a building

Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSTeow Beng Hur
 
Construction using Precast technology
Construction using Precast technologyConstruction using Precast technology
Construction using Precast technologyShubham Arora
 
Site%20 installation %20final_20070219
Site%20 installation %20final_20070219Site%20 installation %20final_20070219
Site%20 installation %20final_20070219Quang Nguyễn
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)Vijayakumar Kumar
 
Modern Construction Technologies
Modern Construction TechnologiesModern Construction Technologies
Modern Construction TechnologiesRahul Saraswat
 
telecommunication Towers
telecommunication Towerstelecommunication Towers
telecommunication TowersTowerpeople
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formworkMumtaz Alam
 
Roger Beck Resume
Roger Beck ResumeRoger Beck Resume
Roger Beck ResumeRoger Beck
 
Roger Beck resume
Roger Beck resumeRoger Beck resume
Roger Beck resumeRoger Beck
 
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |Venkateswaran S
 
Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet (Achievements from 2006 - 2013)Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet (Achievements from 2006 - 2013)Bikram Jeet
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniqueIEI GSC
 
Panel Built Information Packet
Panel Built Information PacketPanel Built Information Packet
Panel Built Information PacketPanel Built
 
20200923 inside metal am webinar_laborelec
20200923 inside metal am webinar_laborelec20200923 inside metal am webinar_laborelec
20200923 inside metal am webinar_laborelecSirris
 

Similar to 1.6 _Important element required to complete a building (20)

Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPS
 
Construction using Precast technology
Construction using Precast technologyConstruction using Precast technology
Construction using Precast technology
 
Site%20 installation %20final_20070219
Site%20 installation %20final_20070219Site%20 installation %20final_20070219
Site%20 installation %20final_20070219
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)
 
Modern Construction Technologies
Modern Construction TechnologiesModern Construction Technologies
Modern Construction Technologies
 
telecommunication Towers
telecommunication Towerstelecommunication Towers
telecommunication Towers
 
Mivan aluminium formwork
Mivan aluminium formworkMivan aluminium formwork
Mivan aluminium formwork
 
Roger Beck Resume
Roger Beck ResumeRoger Beck Resume
Roger Beck Resume
 
Roger Beck resume
Roger Beck resumeRoger Beck resume
Roger Beck resume
 
B.Agasthian July16
B.Agasthian July16B.Agasthian July16
B.Agasthian July16
 
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
 
Forehearth Design Automation
Forehearth Design AutomationForehearth Design Automation
Forehearth Design Automation
 
Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet (Achievements from 2006 - 2013)Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet (Achievements from 2006 - 2013)
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
Panel Built Information Packet
Panel Built Information PacketPanel Built Information Packet
Panel Built Information Packet
 
Plant Design IDI
Plant Design IDIPlant Design IDI
Plant Design IDI
 
Sure Controls
Sure ControlsSure Controls
Sure Controls
 
20200923 inside metal am webinar_laborelec
20200923 inside metal am webinar_laborelec20200923 inside metal am webinar_laborelec
20200923 inside metal am webinar_laborelec
 
Brochure
BrochureBrochure
Brochure
 
Vasco.ppt (1)
Vasco.ppt (1)Vasco.ppt (1)
Vasco.ppt (1)
 

1.6 _Important element required to complete a building

  • 1. Double Storey HC Precast System Drawing - 3D Superstructure ( Frame & Wall ) : - By HC Precast System 77 % 23 % Sub- Structure By Other : - Appointed By Client
  • 2. INDUSTRIALISED BUILDING SYSTEM ( IBS ) is a system not a machine or component IMPORTANT ELEMENTS REQUIRED TO COMPLETE A BUILDING SEQUENCE OF WORK : 5 Steps & No Variation Order Step 1 Step 2 Step 3 Step 4 Step 5 Drawing Mould Production Delivery Installation Conversion Fabrication Numbering ( 2D to 3D ) ( Decide by Client ) Speed, Quality & Environment
  • 3. Step 1 : Drawing Conversion 2D To 3D - 1 Month Original 2D To System 3D
  • 4. Step 1 : Drawing Conversion 2D To 3D Original 2D To System 3D
  • 5. Original Drawing To System Shop Drawing - 1 Step 1a : M & E Conversion original to system shop drawing 1
  • 6. Original Drawing To System Shop Drawing - 1 Step 1a : M & E Conversion original to system shop drawing 2
  • 7. Step 2 : Mould Fabrication - 1 Month 1. Designed by You 2. Coping 1 Cast 3. Chequer Plate ( Tiling ) 4. L shape Panel 5. Door Frame 1 Cast 6. Half Slab
  • 8. Existing production 8 acres : 1,800 to 2,500 units of single storey ( 1000 ft2 ) per year Future development 13 acres : 2,500 to 3,500 units of single storey ( 1000 ft2 ) per year SPEED ( step 3 to 5 ) : Decide by Client : Production , Delivery & Installation
  • 9. SPEED ( step 3 to 5 ) : Decide by Client : Production , Delivery & Installation
  • 10. SPEED ( step 3 to 5 ) : Decide by Client : Production , Delivery & Installation
  • 11. SPEED ( step 3 to 5 ) : Decide by Client : Production , Delivery & Installation
  • 12. Every Truck Every 20m3 Casting & Leveling Mould Dismantling Rebound Hammer Test Panel Lifting Vertical Curing 7days Proper Storage Yards Step 3 : Production ( Decide by Client ) - 7 to 9 units / day
  • 13. Step 4 : Delivery ( 4 Options ) - Decide by Client
  • 14. 1. Bay Yard to Block Yard 2. Bay Yard to Site yard (project) – Advance Casting 3. Storage Yard (factory) to Block Yard – Advance Casting 4. Storage Yard (factory) to Site Yard (project) – Advance Casting Step 4a : Delivery ( 4 Options ) - Decide by Client
  • 15. Step 5 : Installation - Decide By Client Sequence Block by Block One Time Adjustment
  • 16. Step 5a : Installation - Numbering
  • 17. 1. Panel Guide 2. Panel Installation 3. Wall Prop installation 4. Vertical Adjust 5. Expending Cement 6. Rebar Installation Step 5b : Installation
  • 18. 7. Mould Installation 8. Wet joint Casting 9. Mould Dismantling 10. Half Slab installation 11. Rebar Install 12. RC Flat Roof Casting Step 5c : Installation
  • 19. Step 5d : Over View
  • 20. Absolutely no Variation Order (V.O) due to :- - No material wastage (minimal concreting at site) - Accurate estimation by 3D drawing of building precast elements -(wall, beam, staircase & partition ) compared to bricks, -reinforcement work and concreting at site. No Variation Order
  • 21. 1. If we talk about lowering house prices, what is the best way to do it? The best way is to build houses faster and cheaper. One of the ways is by using Industrial Building Systems ( IBS ). 2. Industrialised Building System is a system not a machine or component. Responsibility of the building should not have many different mix system and manufacture products. 3. System provider and manufacturer should provided installer of the building precast element. 4. Same concept applies when we buy computer and hardware. 5. Q-Lassic or Conquas should be carried-out upon the completion of the superstructure works (frame & wall) instead of upon of completion finishing work.
  • 22. IBS Superstructure In Malaysia 3 in 1 Single Storey Bungalow RM 125,000.00 3,891.31 ft2 / Wall High 4.0m / R.C Flat Roof Completed In 10 Days With 6 Workers Precast Element 86 % , Wet Work 14 % Load Bearing Wall Modular Shear Keys Box System Wet Joint
  • 23. HC PRECAST SYSTEM - The wall is designed to provide adequate fire resistance according to demand ( with minimum 2 hours as per BS8110 ) - The system is designed and approved by PE endorsed by independent checker - Thickness of the wall can be customized according to requirement - Our design and casting are following strictly to British Standard Scopes Of Works For Superstructure : Frame & Wall Included : - Supply & install. - Superstructure design calculation. - Shop drawing for M&E location layout related to panel wall casting. (Subject to client / consultant confirmation) - Setting out (panel) : TBM for each block & 4+2 Boundary point per unit must be provided. - Mobile crane. Excluded : - Substructure design by others. - Contractor All Risks Insurance. - Security of our material & system works. - Temporary water & electricity supply. - Quarters for workers. - Access road at project site. - Storage yard at project site : 50mm thick crusher run base. - Supply & install metal door & window frame. - Supply & install M&E conduit. - Skim coat.
  • 24. Easy & Fast To Compare Our System Superstructure Price
  • 25. Easy & Fast To Compare Our System Superstructure Price
  • 26. Cost comparison of superstructure available online at our website
  • 27. Cost comparison of superstructure available online at our website
  • 28. Payment terms available online at our website
  • 55. Thin layer of cement mortar (tiling works) due to evenness of the wall.
  • 58. SPEED & SEQUENCE : Decide by Client : Production , Delivery & Installation -1
  • 59. SPEED & SEQUENCE : Decide by Client : Production , Delivery & Installation -2
  • 60. SPEED & SEQUENCE : Decide by Client : Production , Delivery & Installation -3
  • 61. THANK YOU DESIGN BY YOU PRODUCE BY HC