SlideShare a Scribd company logo
INDUSTRIALISED BUILDING SYSTEM (IBS)
It is a system which suit all architecturaldemands & not a machine or component
significantly difference from traditional cast in-situ construction
which relies heavily on customized site work
- The wall is designedto provide adequate fire resistance according to demand (withminimum 2hours as per BS8110)
- The system is designedand approved by PE and endorsed by independent checker
- Thickness of the wall can be customized according to requirement
- Our design and casting are following strictlyto British Standard
HC PRECAST SYSTEM
PATENTED UNITED STATE : US 6.819.870B2
PATENTED MALAYSIA : MY - 124213-AIN 2006
PATENTED MALAYSIA : MY - 139712-AIN 2009
MALAYSIAGREEN TECHNOLOGY
TRAINING UNIT
8 years expose precast wall, precast staircase,
half slab & precast beam with in-situ column.
- No touch-up - No water proofing
- No leaking - No crack
FACTORY CAPACITY : 21 ACRES
Existing production 8 acres : 1,800 to 2,500 units
of single storey (1000 ft2)per year
Future development 13 acres :2,500 to 3,500 units
of single storey (1000 ft2)per year
CONTENTS
1. BENEFITS INDUSTRIALISED BUILDING SYSTEM ( GREEN TECHNOLOGY )
2. PROPOSE FOR THE GOVERNMENT & PRIVATE
3. RM 90.00(m2)/RM 900(m3) : SUPERSTRUCTURE (FRAME & WALL)
4. INDUSTRIALISED BUILDING SYSTEM CONCEPT
5. CONSTRUCTION METHOD SEQUENCE
6. PRODUCTION & DELIVERY SEQUENCE
7. QUALITY CONTROL & ASSURANCE
8. COST COMPARISON/FAST & EASY (CONVENTIONAL vs HC PRECAST SYSTEM)
9. DESIGNED BY YOU PRODUCED BY HC PRECAST SYSTEM
10. SYSTEMATIC PRODUCTION, DELIVERY & WORK PROGRAM
11. PERCENTAGE ON SITE & OFF SITE WORK
12. FLEXIBILITYSUITARCHITECTURAL DEMANDS
13. PRECAST ELEMENT
14. FACTORY CAPACITY
15. COMPLETED PROJECTS
16. PATENTED
17. INTERNATIONAL PUBLICATIONS
18. COLLABORATION WITH AGENCY
19. INDEPENDENT CHECKER
1. BENEFITS INDUSTRIAL BUILDING SYSTEM : GREEN TECHNOLOGY
5
v) CONSULTANT :
- ARCHITECT
( Flexibility & Customized )
- C&S
( Construction Method Sequence )
- M&E
( Schematic Diagram of Shop Drawing )
- QS
( No Variation Order )
vi) SYSTEM PROVIDER :
- IBS/MANUFACTURE
- Payment Secure
vii) CONTRACTOR :
- Payment Secure
i) COUNTRY :
- 40% Labour Reduce
- Currency
- Social
ii) GOVERNMENT :
- Quality
- Speed
- Environment
- Green Technology
iii) PRIVATE DEVELOPER :
- Quality
- Speed
- Environment
- Green Technology
iv) END-USER :
- Quality
2. PROPOSE TO GOVERNMENT & PRIVATE DEVELOPER
Invite industrialized building systemprovider with manufacturing facility (flexibility to suit all architectural
demands) to participate to built the show unit with work below and superstructure without finishing for the
Government & Private Developer to identify the systemin terms of quality, speedand environment for
supply in its development.
----------------------------------------------------------------------------------------------------------------------------------------------------
1. Architect
• Appointed by the Government & Private Developer.
• Designof single storeybungalow of 1,000 ft2 (affordable home), up to superstructure without finishing.
• With M&E requirement.
• Wall finishing with plasteror skim coatonly.
• Doorand window frame included except doorleave.
• Ground floor without tiling.
2. Industrialized building system manufacturer have formed their BQ for superstructure
(in terms of wall area)and to submit work program with sequence ofwork for recordpurposes.
3. Properrecordby the Government & Private representative during construction, in terms of labour and
machinery involved per day up to completion (superstructure only).
4. Conquas or QLassic consultant( 2 ) engagedby the Government & Private Developer.
5. CostComparisonfor eachIndustrialized Building SystemManufacturerby the Government & Private
Developer(forsuperstructure only). Costwill be fixed for the selectedmanufacturerand supply to its
development.
3. RM 90.00(m2)/RM 900.00(m3)
SUPERSTRUCTURE(FRAME & WALLS) :
1. ISO : 9001 : 2008
2. Design Calculation
3. PE Endorsement
4. M&E Shop Drawing
5. Supply & Lay
6. FlexibilitySuitArchitectural Demands
7. Customized
8. Quality Control& Assurance
9. Speed as Required
10. No Leaking
3.1 RM 90.00(m2)/RM 900.00(m3)
Scope of Work for Superstructure :
Included :-
- Superstructure design calculation.
- Supply & Install.
- Setting out (panel)
- TBM for each block & 4 + 2 Boundary point per unit (must )be provided.
- Mobile crane.
- Shop drawing for M&E location layout related to panel wall casting.
(Subject to client / consultant confirmation)
Excluded :-
- Substructure design by others.
- Supply & install metal door & window frame.
- Supply & install M&E conduit.
- Skim coat.
- Storage yard at project site : 50mm thick crusher-run base.
- Access road at project site.
- Temporary water & electricity supply.
- Quarters for workers.
- Security at site for our material & system formworks.
- Contractor all Risks Insurance.
4. INDUSTRIALISED BUILDING SYSTEM CONCEPT
a) CONVENTIONALMETHOD :
i) ARCHITECT ( 2D layout plan & Elevation )
ii) C&S ( 2D layout plan & Structural detail )
iii) M&E ( 2D Superstructure drawing & schematic diagram )
iv) QS ( Bill OfQuantity )
b) GREEN TECHNOLOGY: 40% LABOUR REDUCE :
-Approval By Client, Confirmation & Endorsement By Consultant
c) SYSTEM PROVIDER : IBS/MANUFACTURE :
- Flexibility to suit Architectural , C&S demands
- While taking care ofwater leakage
- Comply building by law
- In proper connections
- Less joint improve aesthetic appearance
i) ARCHITECT : iii) M&E : Schematic diagram :
- 2D layout - Shop drawing
- 3D drawing
ii) C&S : Superstructure :- iv) QS :
- Frame & Wall ( 2D & 3D layout detail of - No variation order (vo)
precast element & off/on site work ) - 3D Superstructure drawing
4.a CONVENTIONALMETHOD : Single Storey
- i.1)ARCHITECT DRAWING : Layout Plan
4.a CONVENTIONALMETHOD : Single Storey
- i.2)ARCHITECT DRAWING : Elevation
4.a CONVENTIONALMETHOD : Single Storey
- ii.1) C&S DRAWING : Footing, Foundation, Gr. Flr & RoofLayout Plan
4.a CONVENTIONALMETHOD : Single Storey
- ii.2) C&S DRAWING : Gr. BeamStructural detail
4.a CONVENTIONALMETHOD : Single Storey
- iii.1) M&E DRAWING : Layout & Schematic Diagram
4.a CONVENTIONALMETHOD : Double storey
- i.1)ARCHITECT DRAWING : Gr.Flr Layout Plan
4.a CONVENTIONALMETHOD : Double storey
- i.2)ARCHITECT DRAWING : 1st
Flr Layout Plan
4.a CONVENTIONALMETHOD : Double Storey
- i.3)ARCHITECT DRAWING : RoofPlan
4.a CONVENTIONALMETHOD : Double Storey
- i.4)ARCHITECT DRAWING : Elevation
4.a CONVENTIONALMETHOD : Double Storey
- i.5)ARCHITECT DRAWING : SectionPlan
4.a CONVENTIONALMETHOD : Double Storey
- i.6)ARCHITECT DRAWING : SectionPlan
4.b GREEN TECHNOLOGY: 40% LABOUR REDUCE
- 1. Approval by Client, Confirmation & Endorsement by Consultant
86% PrecastElementat Factory
14% Wetwork on site (by System Formwork)
4.b GREEN TECHNOLOGY: 40% LABOUR REDUCE
- 2. Approval by Client, Confirmation & Endorsementby Consultant
4.b GREEN TECHNOLOGY: 40% LABOUR REDUCE
- 3. Approval by Client, Confirmation & Endorsementby Consultant
4.b GREEN TECHNOLOGY: 40% LABOUR REDUCE
- 4. Approval by Client, Confirmation & Endorsementby Consultant
4.c SYSTEM PROVIDER :Single Storey
- i.1)ARCHITECT : Layout Plan
4.c SYSTEM PROVIDER :Single Storey
- i.2)ARCHITECT : Layout , 3D Wall & Column
4.c SYSTEM PROVIDER :Single Storey
- ii.1) C&S : Layout Plan , 3D Wall & Column Schedule
4.c SYSTEM PROVIDER :Single Storey
- ii.2) C&S : Gr Flr Column, RoofBeam& Patty Wall Layout Plan
4.c SYSTEM PROVIDER :Single Storey
- ii.3) C&S : Raft Foundation, Column & Beam details
4.c SYSTEM PROVIDER :Single Storey
- ii.4) C&S : PanelList, Structural detail & Layout with numbering
4.c SYSTEM PROVIDER :Single Storey
- iii.1) M&E : Shop drawing confirmation & endorsementby Consultant
4.c SYSTEM PROVIDER :Single Storey
- iii.2) M&E : Shop drawing confirmation & endorsementby Consultant
4.c SYSTEM PROVIDER :Single Storey
- iii.3) M&E : Shop drawing confirmation & endorsementby Consultant
4.c SYSTEM PROVIDER :Single Storey
- iii.4) M&E : Schematic DiagramPanelList & Layout Plan
4.c SYSTEM PROVIDER :Double Storey
- i.1)ARCHITECT : 3D drawing
4.c SYSTEM PROVIDER :Double Storey
- i.2)ARCHITECT : Gr. Flr Layout, 3D drawing, Wall & Beam
4.c SYSTEM PROVIDER :Double Storey
- i.3)ARCHITECT : 1st
Flr Layout & 3D Slab Flr Plan
4.c SYSTEM PROVIDER :Double Storey
- i.4)ARCHITECT :1st
Flr Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.5)ARCHITECT : RoofPattyWall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER: Double Storey
- i.a1)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.a2)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.a3)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.a4)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.a5)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.a6)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.a7)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.a8)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
4.c SYSTEM PROVIDER :Double Storey
- i.6) C&S : PanelList, Structural detail & Layout with numbering
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Half Slab & System Formwork detail
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- In-situ Toilet & Up Stand Beamby System Formwork
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Half Slab Installation
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Half Slab
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Half Slab & Cantiliver Corridor Mould by System Formwork
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Half Slab & CantileverCorridor Mould by System Formwork
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Half Slab & External Mould by System Formwork
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Conduit Laying before BRC & Casting
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- BRC Laying
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- 1St
FloorSlab Casting & Level Checking
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Finishing Product 1St
FloorSlab
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Up Stand Beamby System Formwork
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Plumbing Ducting
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Plumbing installation
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Toiletin-situ by System Formwork
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Temporary plumbing ducting laying
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Conduit laying before casting
Manufacturer and system
supplier of the element is
the BEST and MOST
EXPERIENCED installer
of the providedbuilding
precast element.
The same concept applies
when we buy computer
and hardware
Eliminate improper
handling installation by
3rd party contractors
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- RecommendedInstallation
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- No Variation Order (VO) : 3D Superstructure drawing
Absolutely no Variation Order (V.O) due to :-
- No material wastage(minimal concreting at site)
- Accurate estimationby 3D drawing of building
precastelements (wall, beam, staircase & partition )
comparedto bricks, reinforcementwork and
concreting at site.
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Cork Joint for Split Level & Specification1
4.c SYSTEM PROVIDER :IBS/MANUFACTURER :
- Cork Joint for Split Level & Specification2
5. CONSTRUCTION METHOD SEQUENCE:
- i) Construction Method
5. CONSTRUCTION METHOD SEQUENCE:
- ii) Setting Out
5. CONSTRUCTION METHOD SEQUENCE:
- iii) Leveling Check list
5. CONSTRUCTION METHOD SEQUENCE:
- iv) Expanding Cement Motar
5. CONSTRUCTION METHOD SEQUENCE:
- v) In-Situ Column with PrecastBeamInstallation
6. PRODUCTION & DELIVERYSEQUENCE
6.1 -LogisticOption: Before Production
6.2 -Panel Casting
6.3 -Panel Lifting
6.4 -Bay Yard Storage
6.5 -Panel Storage Yard
6.6 -External Transport
6.7 -ProjectSite StorageYard
6.8 -Project Site Internal Transport
6.9 -Project Site Block Storage
6.1 LOGISTIC OPTION (BEFORE PRODUCTION)
i) Option1 :-
- Bay yard (factory) to block yard (project site)
ii) Option 2 :-
- Bay yard (factory) to site yard (project site)
iii)Option 3 :-
- Storage yard (factory)to block yard (project site)
iv) Option4 :-
- Storage yard (factory)to site yard (project site)
Notes :
a) Client/Consultant/MainContractorneed to choosewhich
optionto be used before production.
b) Rate for RM 900/m3 includes for option1 & 3.
c) An additionalof RM 30/m3 to be charged for option2 & 4.
d) Crusherrun base to be providedat site yard for option 1- 4.
6.1 OPTION 1 :
- BAY YARD (FACTORY)TO BLOCKYARD (PROJECTSITE)
6.1 OPTION 2 :
- BAY YARD (FACTORY)TO SITE YARD (PROJECTSITE)
6.1 OPTION 3 :
- STORAGE YARD (FACTORY)TO BLOCKYARD (PROJECTSITE)
6.1 OPTION 4 :
- STORAGE YARD (FACTORY)TO SITE YARD (PROJECTSITE)
6.2 PANELCASTING
6.3 PANELLIFITING
6.4 BAYYARD STORAGE
6.5 PANELSTORAGE YARD
6.6 EXTERNALTRANSPORT
6.7 PROJECT SITE STORAGE YARD
6.8 PROJECT INTERNAL TRANSPORT
ReboundHammer test carried out
daily & on selected Panel
7. QUALITYCONTROL & ASSURANCE
Ready Mixed Concrete : Concrete Grade to comply Engineer’s requirements.
- Slump Test carried out on every delivery.
- Cube Test taken for every 20m3.
7.1 QUALITY CONTROL & ASSURANCE
- Lifting Of Panelonly afterminimum 18 hours or as specified by Engineer.
- Panelstoredat stock yard for 7 days or as specifiedby Engineer curing before delivery to site.
- Panelstack individually as apposedto one on top anotherto prevent cracks
8. COST COMPARISON/FAST& EASY :
- CONVENTIONALvs HC PRECAST SYSTEM
8.1 COST COMPARISON/FAST& EASY :
- CONVENTIONALvs HC PRECASTSYSTEM
8.2 COST COMPARISON/FAST& EASY :
- CONVENTIONALVs HC PRECAST SYSTEM
8.3 COST COMPARISON/FAST& EASY :
- CONVENTIONALVs HC PRECAST SYSTEM
8.4 COST COMPARISON/FAST& EASY :
- CONVENTIONALVs HC PRECAST SYSTEM
Semi-D House : Single Storey (Superstructure/Frame & Wall)
Conventional : Original Design HC PrecastSystem
(Current Rate – July 2014) (Current Rate – July 2014)
RM 127.43/m2 Vs RM 90.00/m2
RATE CAN BE CHECKED & CHANGEBY YOU
8.5 COST COMPARISON/FAST& EASY :
- COMPARE OUR SYSTEM PRICE : Superstructure (frame & wall)
8.6 COST COMPARISON/FAST& EASY :
- COMPARE OUR SYSTEM PRICE : Superstructure (frame & wall)
9. DESIGNED BY YOU PRODUCED BY HC PRECAST SYSTEM
9.1 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.2 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.3 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.4 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.5 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.6 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.7 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.8 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.9 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
9.10 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
DESIGNED BY YOU
PRODUCED BY
HC PRECAST SYSTEM
THANK YOU
PART 1
10. SYSTEMATIC PRODUCTION,DELIVERY & WORKPROGRAM
300 UNITS SINGLE STOREY SEMI-D
PRODUCTION, DELIVERY, WORK PROGRAM
&
INSTALLATION SCHEDULE
11. PERCENTAGE ON SITE & OFF SITE WORK
11.1 PERCENTAGE ON SITE & OFF SITE WORK
11.2 PERCENTAGE ON SITE & OFF SITE WORK
11.3 PERCENTAGE ON SITE & OFF SITE WORK
11.4 PERCENTAGE ON SITE & OFF SITE WORK
12. FLEXIBILITY SUIT ARCHITECT DEMANDS
- MODULAR MOULD & SHEAR KEYS
12.1 FLEXIBILITY SUIT ARCHITECT DEMANDS
- MODULAR MOULD & SHEAR KEYS
12.2 FLEXIBILITY SUIT ARCHITECT DEMANDS
- MODULAR MOULD & SHEAR KEYS
13. PRECAST ELEMENT
13.1 WALLPANEL: CUSTOMIZED
13.2 COLUMN WET JOINTWITH SHEAR KEYS
13.2a PRECASTPANELWITH SHEAR KEYS
13.3 IN-SITU COLUMN/PRECASTBEAM WITH SHEAR KEYS
13.4 HALF SLAB
13.4a HALF SLAB CASTING
13.5 PRECASTSTAIRCASE 1
13.5a PRECASTSTAIRCASE 2
13.6 BAY WINDOW
13.6a PRECASTPANELWITH GROVE LINE
13.7 ARCH 1
13.7a ARCH2
13.7b ARCH 3
13.1 WALL PANEL : CUSTOMIZED
13.2 COLUMN WET JOINT WITH SHEAR KEYS
13.2a COLUMNWET JOINT WITH SHEAR KEYS
13.2a COLUMNWET JOINT WITH SHEAR KEYS
13.2b PRECAST PANELWITH SHEAR KEYS
13.3 IN-SITU COLUMN / PRECAST BEAM WITH SHEAR KEYS
13.4 HALF SLAB
13.4a HALF SLAB CASTING
13.5 STAIRCASE 1
13.5a STAIRCASE 2 ( in-situ landing slab support )
13.6 BAY WINDOW
13.6a PRECAST PANELWITH GROVE LINE
13.7 ARCH 1
13.7a ARCH 2
13.7b ARCH 3
14. FACTORY CAPACITY : 21 ACRES
Existing production 8 acres : 1,800 to 2,500 units
of single storey (1000 ft2)per year
Future development 13 acres :2,500 to 3,500 units of
single storey(1000 ft2) per year
15. COMPLETEDPROJECTS
15.1 - 42 units 3&5 Storey Shop Office at Andalas Klang
15.2 - 156 units Single Storey Terrace Houseat Kota Puteri
15.3 - 7 units Single Storey Shop Lots at Kota Puteri
15.4 - 10 units Exco Bungalows Selangorat Shah Alam
15.5 - 112 units Single Storey Terraceat Kota Puteri
15.6 - 119 units Double Storey TerraceHouse at Shah Alam
15.7 - 88 units Semi DetachedLow at Bukit Botak
15.8 - 119 units Single Storey Terraceat Bernam Jaya
15.9 - 34 units Semi DetachedHouse at Shah Alam
15.10 - 118 units Double Storey Terrace House at Kota Puteri
15.11 - Show Unit Single Storey Houseat Rasa Factory
15.12 - Training Unit Double Storey at Rasa Factory
15.1 - 42 units 3&5 Storey Shop Office at Andalas Klang
15.2 - 156 units Single Storey Terrace House at Kota Puteri
15.3 - 7 units Single Storey Shop Lots at Kota Puteri
15.4a - 10 units Exco Bungalows Selangor at Shah Alam
15.4b - 10 units Exco Bungalows Selangor at Shah Alam
15.4c - 10 units Exco Bungalows Selangor at Shah Alam
15.4d - 10 units Exco Bungalows Selangor at Shah Alam
15.5 - 112 units Single Storey Terrace at Kota Puteri
15.5a - 112 units Single Storey Terrace at Kota Puteri
15.6 - 119 units Double Storey Terrace House at Shah Alam
15.7 - 88 units Semi Detached Low at Bukit Botak
15.7a - 88 units Semi Detached Low at Bukit Botak
15.7b - 88 units Semi Detached Low at Bukit Botak
15.8 - 119 units Single Storey Terrace at Bernam Jaya
15.9 - 34 units Semi Detached House at Shah Alam
15.9a - 34 units Semi Detached House at Shah Alam
15.9b - 34 units Semi Detached House at Shah Alam
15.10 - 118 Units Double Storey Terrace House at Kota Puteri
15.10a - 118 Units Double Storey Terrace House at Kota Puteri
15.10b - 118 Units Double Storey Terrace House at Kota Puteri
15.11 - Show Unit Single Storey House at Rasa Factory
15.11a - Show Unit Single Storey House at Rasa Factory
15.11b - Show Unit Single Storey House at Rasa Factory
15.11c - Show Unit Single Storey House at Rasa Factory
15.12 - Training Unit Double Storey House at Rasa Factory
16. PATENTED UNITED STATE : US 6.819.870B2
16.1 PATENTEDMALAYSIA : MY - 124213-AIN 2006
MY - 139712-AIN 2009
17. INTERNATIONAL PUBLICATIONS
17.1 USA :-
- Jerome P. Lynch : 2013
17.2 PORTUGAL:-
- 15th World Conference : 2012
17.3 GERMANY :-
- CPI : 2011
17.4 MALAYSIA :-
- EARTHQUAKE
RESISTANCE TEST UTM : 2.011
“ Earthquakes and Structures “
(Impact Factor2012 = 1.381,
One of the highest among other
structural earthquake engineering journals,
indexed by
Journal Citations Reports®, ISI ThomsonReuters)
17.1 USA : Jerome P.Lynch - 2013
17.2 PORTUGAL : 15TH WORLD CONFERENCE - 2012
17.2a PORTUGAL: 15TH WORLD CONFERENCE - 2012
17.3 GERMANY : CPI - 2011
MalaysiaIBS CompanyArticleAppearIn CPI Worldwide Journal
In 8 DifferentLanguages (Based In GERMANY):
1. US
2. UK
3. Germany
4. French
5. Italian
6. Spanish
7. Portuguese
8. Indian
17.3a GERMANY: CPI - 2011
EARTHQUAKE RESISTANCE
TEST OF SCALED DOWN
DOUBLESTOREY BUILDINGBY
HC PRECASTSYSTEM IN
COLLABORATION WITH UTM,
JOHOR BASED ON 8 MAJOR
EARTHQUAKES, IN THE WORLD
17.4 BUILDING & INVESTMENT - 2011
17.4a BUILDING & INVESTMENT - 2011
18. COLLABORATION WITH AGENCY
18.1 - UTM
18.1a - UTM / CERTIFICATE
18.2 - UITM
18.3 - CREAM/CIDB
18.1 COLLABORATION WITH AGENCY
18.1a COLLABORATION WITH AGENCY
18.2 COLLABORATION WITH AGENCY
18.3 COLLABORATION WITH AGENCY
18.3a COLLABORATION WITH AGENCY
18.4b COLLABORATION WITH AGENCY
19. INDEPENDENT CHECKER – 1
19.1 INDEPENDENT CHECKER – 2&3
19.2 INDEPENDENT CHECKER – 4&5
DESIGNED BY YOU
PRODUCED BY
HC PRECAST SYSTEM
THANK YOU
PART 2

More Related Content

What's hot

industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
Aisyah Asyikin
 
Morocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case StudyMorocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case Study
CCL Concrete
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building Solution
Lee Wan Xuan
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]
JerotichMaswan
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
마 이환
 
Ct iii presentation
Ct iii presentationCt iii presentation
Ct iii presentation
Pui Chun Shian
 
Prefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusPrefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed Impetus
IEI GSC
 
duplex villa ppt
duplex villa pptduplex villa ppt
duplex villa ppt
Huzaifa Faisal
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
Nekumi Kida
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
Multi Storey Steel Structures
Multi Storey Steel StructuresMulti Storey Steel Structures
Multi Storey Steel Structures
Richa Industries Ltd
 
Construction of telecommunication towers
Construction of telecommunication towersConstruction of telecommunication towers
Construction of telecommunication towers
snookala
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1
zerospaces_
 
CSCM Ibs in malaysia
CSCM Ibs in malaysiaCSCM Ibs in malaysia
CSCM Ibs in malaysia
Est
 
Telecommunication infrastructure services
Telecommunication infrastructure servicesTelecommunication infrastructure services
Telecommunication infrastructure services
essafi
 
PEB construction-Mukesh Bhavsar
PEB construction-Mukesh BhavsarPEB construction-Mukesh Bhavsar
PEB construction-Mukesh Bhavsar
Mukesh Bhavsar
 
Building Technology PJT 1 Report
Building Technology PJT 1 Report Building Technology PJT 1 Report
Building Technology PJT 1 Report
ForestedTiger
 
MIVAN FRAMEWORK
MIVAN FRAMEWORKMIVAN FRAMEWORK
MIVAN FRAMEWORK
Qadir Raza
 
Introduction of Prefabricated structures
Introduction  of Prefabricated structuresIntroduction  of Prefabricated structures
Introduction of Prefabricated structures
Yogi Yogesh
 

What's hot (20)

industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
 
Morocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case StudyMorocco Mall Post Tensioned Concrete Case Study
Morocco Mall Post Tensioned Concrete Case Study
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building Solution
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Ct iii presentation
Ct iii presentationCt iii presentation
Ct iii presentation
 
Prefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed ImpetusPrefabricated construction systems in India- Precast Status and needed Impetus
Prefabricated construction systems in India- Precast Status and needed Impetus
 
duplex villa ppt
duplex villa pptduplex villa ppt
duplex villa ppt
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Multi Storey Steel Structures
Multi Storey Steel StructuresMulti Storey Steel Structures
Multi Storey Steel Structures
 
Construction of telecommunication towers
Construction of telecommunication towersConstruction of telecommunication towers
Construction of telecommunication towers
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1
 
CSCM Ibs in malaysia
CSCM Ibs in malaysiaCSCM Ibs in malaysia
CSCM Ibs in malaysia
 
Telecommunication infrastructure services
Telecommunication infrastructure servicesTelecommunication infrastructure services
Telecommunication infrastructure services
 
PEB construction-Mukesh Bhavsar
PEB construction-Mukesh BhavsarPEB construction-Mukesh Bhavsar
PEB construction-Mukesh Bhavsar
 
Building Technology PJT 1 Report
Building Technology PJT 1 Report Building Technology PJT 1 Report
Building Technology PJT 1 Report
 
MIVAN FRAMEWORK
MIVAN FRAMEWORKMIVAN FRAMEWORK
MIVAN FRAMEWORK
 
Introduction of Prefabricated structures
Introduction  of Prefabricated structuresIntroduction  of Prefabricated structures
Introduction of Prefabricated structures
 

Similar to Presentation 2016

Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPS
Teow Beng Hur
 
HAFIZ A WAHEED PORTFOLIO 2
HAFIZ A WAHEED PORTFOLIO 2HAFIZ A WAHEED PORTFOLIO 2
HAFIZ A WAHEED PORTFOLIO 2
Hafiz Waheed
 
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
IRJET Journal
 
designage - Profile-1
designage - Profile-1designage - Profile-1
designage - Profile-1
Tushar Patil
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructions
engineeringwatch
 
Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet (Achievements from 2006 - 2013)Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet
 
Ibrahim Naeem BIM Projects Portfolio
Ibrahim Naeem BIM Projects Portfolio Ibrahim Naeem BIM Projects Portfolio
Ibrahim Naeem BIM Projects Portfolio
Ibrahem Naeem
 
412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf
RenukaChalikwar2
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
Ali Meer
 
Prefabrication structures in construction
Prefabrication structures in constructionPrefabrication structures in construction
Prefabrication structures in construction
RajalekshmiSivaram
 
Training on Structural designing by CADD centre
Training on Structural designing by CADD centreTraining on Structural designing by CADD centre
Training on Structural designing by CADD centre
yashvant meena
 
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWAREREPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
RakeshDas161
 
My C.V -Updated Mrach 2015
My C.V -Updated Mrach 2015My C.V -Updated Mrach 2015
My C.V -Updated Mrach 2015
Mohamed Mostafa Abd Elrahiem
 
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
IRJET Journal
 
Analysis of G+2 building with seismic load using Etabs
Analysis of G+2 building with seismic load using EtabsAnalysis of G+2 building with seismic load using Etabs
Analysis of G+2 building with seismic load using Etabs
IRJET Journal
 
Hafiz A Waheed Portfolio
Hafiz A Waheed Portfolio Hafiz A Waheed Portfolio
Hafiz A Waheed Portfolio
Hafiz Waheed
 
4 YEARS EXP RESUME
4 YEARS EXP RESUME4 YEARS EXP RESUME
4 YEARS EXP RESUME
MS MOHAN KUMAR
 
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET Journal
 
Resume--Shishir
Resume--ShishirResume--Shishir
Resume--Shishir
Shishir Lokhande
 
IES Faculty - IESVE as a Design Application & Part L Clinic
IES Faculty - IESVE as a Design Application & Part L ClinicIES Faculty - IESVE as a Design Application & Part L Clinic
IES Faculty - IESVE as a Design Application & Part L Clinic
IES VE
 

Similar to Presentation 2016 (20)

Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPS
 
HAFIZ A WAHEED PORTFOLIO 2
HAFIZ A WAHEED PORTFOLIO 2HAFIZ A WAHEED PORTFOLIO 2
HAFIZ A WAHEED PORTFOLIO 2
 
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
 
designage - Profile-1
designage - Profile-1designage - Profile-1
designage - Profile-1
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructions
 
Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet (Achievements from 2006 - 2013)Bikram Jeet (Achievements from 2006 - 2013)
Bikram Jeet (Achievements from 2006 - 2013)
 
Ibrahim Naeem BIM Projects Portfolio
Ibrahim Naeem BIM Projects Portfolio Ibrahim Naeem BIM Projects Portfolio
Ibrahim Naeem BIM Projects Portfolio
 
412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf412346228-Pragati-Towers-Mumbai.pdf
412346228-Pragati-Towers-Mumbai.pdf
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
 
Prefabrication structures in construction
Prefabrication structures in constructionPrefabrication structures in construction
Prefabrication structures in construction
 
Training on Structural designing by CADD centre
Training on Structural designing by CADD centreTraining on Structural designing by CADD centre
Training on Structural designing by CADD centre
 
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWAREREPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
REPORT ON G+4 RCC HOSTEL BUILDING ANALYSIS AND DESIGN USING STAAD PRO SOFTWARE
 
My C.V -Updated Mrach 2015
My C.V -Updated Mrach 2015My C.V -Updated Mrach 2015
My C.V -Updated Mrach 2015
 
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
IRJET- Analysis and Design of G+3 Storey and G+25 Storey RC Frame Building St...
 
Analysis of G+2 building with seismic load using Etabs
Analysis of G+2 building with seismic load using EtabsAnalysis of G+2 building with seismic load using Etabs
Analysis of G+2 building with seismic load using Etabs
 
Hafiz A Waheed Portfolio
Hafiz A Waheed Portfolio Hafiz A Waheed Portfolio
Hafiz A Waheed Portfolio
 
4 YEARS EXP RESUME
4 YEARS EXP RESUME4 YEARS EXP RESUME
4 YEARS EXP RESUME
 
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
IRJET- Comparative Study of an Industrial Pre – Engineered Building with Conv...
 
Resume--Shishir
Resume--ShishirResume--Shishir
Resume--Shishir
 
IES Faculty - IESVE as a Design Application & Part L Clinic
IES Faculty - IESVE as a Design Application & Part L ClinicIES Faculty - IESVE as a Design Application & Part L Clinic
IES Faculty - IESVE as a Design Application & Part L Clinic
 

Recently uploaded

Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Speck&Tech
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
Uni Systems S.M.S.A.
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
DianaGray10
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
Neo4j
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Vladimir Iglovikov, Ph.D.
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
Zilliz
 
Large Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial ApplicationsLarge Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial Applications
Rohit Gautam
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
Neo4j
 
Building RAG with self-deployed Milvus vector database and Snowpark Container...
Building RAG with self-deployed Milvus vector database and Snowpark Container...Building RAG with self-deployed Milvus vector database and Snowpark Container...
Building RAG with self-deployed Milvus vector database and Snowpark Container...
Zilliz
 
Data structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdfData structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdf
TIPNGVN2
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
Neo4j
 
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Zilliz
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Paige Cruz
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website
Pixlogix Infotech
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
Edge AI and Vision Alliance
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
Matthew Sinclair
 

Recently uploaded (20)

Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
 
Large Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial ApplicationsLarge Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial Applications
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
 
Building RAG with self-deployed Milvus vector database and Snowpark Container...
Building RAG with self-deployed Milvus vector database and Snowpark Container...Building RAG with self-deployed Milvus vector database and Snowpark Container...
Building RAG with self-deployed Milvus vector database and Snowpark Container...
 
Data structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdfData structures and Algorithms in Python.pdf
Data structures and Algorithms in Python.pdf
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
 
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
Introducing Milvus Lite: Easy-to-Install, Easy-to-Use vector database for you...
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website20 Comprehensive Checklist of Designing and Developing a Website
20 Comprehensive Checklist of Designing and Developing a Website
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
 

Presentation 2016

  • 1. INDUSTRIALISED BUILDING SYSTEM (IBS) It is a system which suit all architecturaldemands & not a machine or component significantly difference from traditional cast in-situ construction which relies heavily on customized site work - The wall is designedto provide adequate fire resistance according to demand (withminimum 2hours as per BS8110) - The system is designedand approved by PE and endorsed by independent checker - Thickness of the wall can be customized according to requirement - Our design and casting are following strictlyto British Standard HC PRECAST SYSTEM PATENTED UNITED STATE : US 6.819.870B2 PATENTED MALAYSIA : MY - 124213-AIN 2006 PATENTED MALAYSIA : MY - 139712-AIN 2009 MALAYSIAGREEN TECHNOLOGY
  • 2. TRAINING UNIT 8 years expose precast wall, precast staircase, half slab & precast beam with in-situ column. - No touch-up - No water proofing - No leaking - No crack
  • 3. FACTORY CAPACITY : 21 ACRES Existing production 8 acres : 1,800 to 2,500 units of single storey (1000 ft2)per year Future development 13 acres :2,500 to 3,500 units of single storey (1000 ft2)per year
  • 4. CONTENTS 1. BENEFITS INDUSTRIALISED BUILDING SYSTEM ( GREEN TECHNOLOGY ) 2. PROPOSE FOR THE GOVERNMENT & PRIVATE 3. RM 90.00(m2)/RM 900(m3) : SUPERSTRUCTURE (FRAME & WALL) 4. INDUSTRIALISED BUILDING SYSTEM CONCEPT 5. CONSTRUCTION METHOD SEQUENCE 6. PRODUCTION & DELIVERY SEQUENCE 7. QUALITY CONTROL & ASSURANCE 8. COST COMPARISON/FAST & EASY (CONVENTIONAL vs HC PRECAST SYSTEM) 9. DESIGNED BY YOU PRODUCED BY HC PRECAST SYSTEM 10. SYSTEMATIC PRODUCTION, DELIVERY & WORK PROGRAM 11. PERCENTAGE ON SITE & OFF SITE WORK 12. FLEXIBILITYSUITARCHITECTURAL DEMANDS 13. PRECAST ELEMENT 14. FACTORY CAPACITY 15. COMPLETED PROJECTS 16. PATENTED 17. INTERNATIONAL PUBLICATIONS 18. COLLABORATION WITH AGENCY 19. INDEPENDENT CHECKER
  • 5. 1. BENEFITS INDUSTRIAL BUILDING SYSTEM : GREEN TECHNOLOGY 5 v) CONSULTANT : - ARCHITECT ( Flexibility & Customized ) - C&S ( Construction Method Sequence ) - M&E ( Schematic Diagram of Shop Drawing ) - QS ( No Variation Order ) vi) SYSTEM PROVIDER : - IBS/MANUFACTURE - Payment Secure vii) CONTRACTOR : - Payment Secure i) COUNTRY : - 40% Labour Reduce - Currency - Social ii) GOVERNMENT : - Quality - Speed - Environment - Green Technology iii) PRIVATE DEVELOPER : - Quality - Speed - Environment - Green Technology iv) END-USER : - Quality
  • 6. 2. PROPOSE TO GOVERNMENT & PRIVATE DEVELOPER Invite industrialized building systemprovider with manufacturing facility (flexibility to suit all architectural demands) to participate to built the show unit with work below and superstructure without finishing for the Government & Private Developer to identify the systemin terms of quality, speedand environment for supply in its development. ---------------------------------------------------------------------------------------------------------------------------------------------------- 1. Architect • Appointed by the Government & Private Developer. • Designof single storeybungalow of 1,000 ft2 (affordable home), up to superstructure without finishing. • With M&E requirement. • Wall finishing with plasteror skim coatonly. • Doorand window frame included except doorleave. • Ground floor without tiling. 2. Industrialized building system manufacturer have formed their BQ for superstructure (in terms of wall area)and to submit work program with sequence ofwork for recordpurposes. 3. Properrecordby the Government & Private representative during construction, in terms of labour and machinery involved per day up to completion (superstructure only). 4. Conquas or QLassic consultant( 2 ) engagedby the Government & Private Developer. 5. CostComparisonfor eachIndustrialized Building SystemManufacturerby the Government & Private Developer(forsuperstructure only). Costwill be fixed for the selectedmanufacturerand supply to its development.
  • 7. 3. RM 90.00(m2)/RM 900.00(m3) SUPERSTRUCTURE(FRAME & WALLS) : 1. ISO : 9001 : 2008 2. Design Calculation 3. PE Endorsement 4. M&E Shop Drawing 5. Supply & Lay 6. FlexibilitySuitArchitectural Demands 7. Customized 8. Quality Control& Assurance 9. Speed as Required 10. No Leaking
  • 8. 3.1 RM 90.00(m2)/RM 900.00(m3) Scope of Work for Superstructure : Included :- - Superstructure design calculation. - Supply & Install. - Setting out (panel) - TBM for each block & 4 + 2 Boundary point per unit (must )be provided. - Mobile crane. - Shop drawing for M&E location layout related to panel wall casting. (Subject to client / consultant confirmation) Excluded :- - Substructure design by others. - Supply & install metal door & window frame. - Supply & install M&E conduit. - Skim coat. - Storage yard at project site : 50mm thick crusher-run base. - Access road at project site. - Temporary water & electricity supply. - Quarters for workers. - Security at site for our material & system formworks. - Contractor all Risks Insurance.
  • 9. 4. INDUSTRIALISED BUILDING SYSTEM CONCEPT a) CONVENTIONALMETHOD : i) ARCHITECT ( 2D layout plan & Elevation ) ii) C&S ( 2D layout plan & Structural detail ) iii) M&E ( 2D Superstructure drawing & schematic diagram ) iv) QS ( Bill OfQuantity ) b) GREEN TECHNOLOGY: 40% LABOUR REDUCE : -Approval By Client, Confirmation & Endorsement By Consultant c) SYSTEM PROVIDER : IBS/MANUFACTURE : - Flexibility to suit Architectural , C&S demands - While taking care ofwater leakage - Comply building by law - In proper connections - Less joint improve aesthetic appearance i) ARCHITECT : iii) M&E : Schematic diagram : - 2D layout - Shop drawing - 3D drawing ii) C&S : Superstructure :- iv) QS : - Frame & Wall ( 2D & 3D layout detail of - No variation order (vo) precast element & off/on site work ) - 3D Superstructure drawing
  • 10. 4.a CONVENTIONALMETHOD : Single Storey - i.1)ARCHITECT DRAWING : Layout Plan
  • 11. 4.a CONVENTIONALMETHOD : Single Storey - i.2)ARCHITECT DRAWING : Elevation
  • 12. 4.a CONVENTIONALMETHOD : Single Storey - ii.1) C&S DRAWING : Footing, Foundation, Gr. Flr & RoofLayout Plan
  • 13. 4.a CONVENTIONALMETHOD : Single Storey - ii.2) C&S DRAWING : Gr. BeamStructural detail
  • 14. 4.a CONVENTIONALMETHOD : Single Storey - iii.1) M&E DRAWING : Layout & Schematic Diagram
  • 15. 4.a CONVENTIONALMETHOD : Double storey - i.1)ARCHITECT DRAWING : Gr.Flr Layout Plan
  • 16. 4.a CONVENTIONALMETHOD : Double storey - i.2)ARCHITECT DRAWING : 1st Flr Layout Plan
  • 17. 4.a CONVENTIONALMETHOD : Double Storey - i.3)ARCHITECT DRAWING : RoofPlan
  • 18. 4.a CONVENTIONALMETHOD : Double Storey - i.4)ARCHITECT DRAWING : Elevation
  • 19. 4.a CONVENTIONALMETHOD : Double Storey - i.5)ARCHITECT DRAWING : SectionPlan
  • 20. 4.a CONVENTIONALMETHOD : Double Storey - i.6)ARCHITECT DRAWING : SectionPlan
  • 21. 4.b GREEN TECHNOLOGY: 40% LABOUR REDUCE - 1. Approval by Client, Confirmation & Endorsement by Consultant 86% PrecastElementat Factory 14% Wetwork on site (by System Formwork)
  • 22. 4.b GREEN TECHNOLOGY: 40% LABOUR REDUCE - 2. Approval by Client, Confirmation & Endorsementby Consultant
  • 23. 4.b GREEN TECHNOLOGY: 40% LABOUR REDUCE - 3. Approval by Client, Confirmation & Endorsementby Consultant
  • 24. 4.b GREEN TECHNOLOGY: 40% LABOUR REDUCE - 4. Approval by Client, Confirmation & Endorsementby Consultant
  • 25. 4.c SYSTEM PROVIDER :Single Storey - i.1)ARCHITECT : Layout Plan
  • 26. 4.c SYSTEM PROVIDER :Single Storey - i.2)ARCHITECT : Layout , 3D Wall & Column
  • 27. 4.c SYSTEM PROVIDER :Single Storey - ii.1) C&S : Layout Plan , 3D Wall & Column Schedule
  • 28. 4.c SYSTEM PROVIDER :Single Storey - ii.2) C&S : Gr Flr Column, RoofBeam& Patty Wall Layout Plan
  • 29. 4.c SYSTEM PROVIDER :Single Storey - ii.3) C&S : Raft Foundation, Column & Beam details
  • 30. 4.c SYSTEM PROVIDER :Single Storey - ii.4) C&S : PanelList, Structural detail & Layout with numbering
  • 31. 4.c SYSTEM PROVIDER :Single Storey - iii.1) M&E : Shop drawing confirmation & endorsementby Consultant
  • 32. 4.c SYSTEM PROVIDER :Single Storey - iii.2) M&E : Shop drawing confirmation & endorsementby Consultant
  • 33. 4.c SYSTEM PROVIDER :Single Storey - iii.3) M&E : Shop drawing confirmation & endorsementby Consultant
  • 34. 4.c SYSTEM PROVIDER :Single Storey - iii.4) M&E : Schematic DiagramPanelList & Layout Plan
  • 35. 4.c SYSTEM PROVIDER :Double Storey - i.1)ARCHITECT : 3D drawing
  • 36. 4.c SYSTEM PROVIDER :Double Storey - i.2)ARCHITECT : Gr. Flr Layout, 3D drawing, Wall & Beam
  • 37. 4.c SYSTEM PROVIDER :Double Storey - i.3)ARCHITECT : 1st Flr Layout & 3D Slab Flr Plan
  • 38. 4.c SYSTEM PROVIDER :Double Storey - i.4)ARCHITECT :1st Flr Layout, 3D Wall & Column
  • 39. 4.c SYSTEM PROVIDER :Double Storey - i.5)ARCHITECT : RoofPattyWall Layout, 3D Wall & Column
  • 40. 4.c SYSTEM PROVIDER: Double Storey - i.a1)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
  • 41. 4.c SYSTEM PROVIDER :Double Storey - i.a2)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
  • 42. 4.c SYSTEM PROVIDER :Double Storey - i.a3)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
  • 43. 4.c SYSTEM PROVIDER :Double Storey - i.a4)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
  • 44. 4.c SYSTEM PROVIDER :Double Storey - i.a5)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
  • 45. 4.c SYSTEM PROVIDER :Double Storey - i.a6)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
  • 46. 4.c SYSTEM PROVIDER :Double Storey - i.a7)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
  • 47. 4.c SYSTEM PROVIDER :Double Storey - i.a8)ARCHITECT : RoofPatty Wall Layout, 3D Wall & Column
  • 48. 4.c SYSTEM PROVIDER :Double Storey - i.6) C&S : PanelList, Structural detail & Layout with numbering
  • 49. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Half Slab & System Formwork detail
  • 50. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - In-situ Toilet & Up Stand Beamby System Formwork
  • 51. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Half Slab Installation
  • 52. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Half Slab
  • 53. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Half Slab & Cantiliver Corridor Mould by System Formwork
  • 54. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Half Slab & CantileverCorridor Mould by System Formwork
  • 55. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Half Slab & External Mould by System Formwork
  • 56. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Conduit Laying before BRC & Casting
  • 57. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - BRC Laying
  • 58. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - 1St FloorSlab Casting & Level Checking
  • 59. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Finishing Product 1St FloorSlab
  • 60. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Up Stand Beamby System Formwork
  • 61. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Plumbing Ducting
  • 62. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Plumbing installation
  • 63. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Toiletin-situ by System Formwork
  • 64. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Temporary plumbing ducting laying
  • 65. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Conduit laying before casting
  • 66. Manufacturer and system supplier of the element is the BEST and MOST EXPERIENCED installer of the providedbuilding precast element. The same concept applies when we buy computer and hardware Eliminate improper handling installation by 3rd party contractors 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - RecommendedInstallation
  • 67. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - No Variation Order (VO) : 3D Superstructure drawing Absolutely no Variation Order (V.O) due to :- - No material wastage(minimal concreting at site) - Accurate estimationby 3D drawing of building precastelements (wall, beam, staircase & partition ) comparedto bricks, reinforcementwork and concreting at site.
  • 68. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Cork Joint for Split Level & Specification1
  • 69. 4.c SYSTEM PROVIDER :IBS/MANUFACTURER : - Cork Joint for Split Level & Specification2
  • 70. 5. CONSTRUCTION METHOD SEQUENCE: - i) Construction Method
  • 71. 5. CONSTRUCTION METHOD SEQUENCE: - ii) Setting Out
  • 72. 5. CONSTRUCTION METHOD SEQUENCE: - iii) Leveling Check list
  • 73. 5. CONSTRUCTION METHOD SEQUENCE: - iv) Expanding Cement Motar
  • 74. 5. CONSTRUCTION METHOD SEQUENCE: - v) In-Situ Column with PrecastBeamInstallation
  • 75. 6. PRODUCTION & DELIVERYSEQUENCE 6.1 -LogisticOption: Before Production 6.2 -Panel Casting 6.3 -Panel Lifting 6.4 -Bay Yard Storage 6.5 -Panel Storage Yard 6.6 -External Transport 6.7 -ProjectSite StorageYard 6.8 -Project Site Internal Transport 6.9 -Project Site Block Storage
  • 76. 6.1 LOGISTIC OPTION (BEFORE PRODUCTION) i) Option1 :- - Bay yard (factory) to block yard (project site) ii) Option 2 :- - Bay yard (factory) to site yard (project site) iii)Option 3 :- - Storage yard (factory)to block yard (project site) iv) Option4 :- - Storage yard (factory)to site yard (project site) Notes : a) Client/Consultant/MainContractorneed to choosewhich optionto be used before production. b) Rate for RM 900/m3 includes for option1 & 3. c) An additionalof RM 30/m3 to be charged for option2 & 4. d) Crusherrun base to be providedat site yard for option 1- 4.
  • 77. 6.1 OPTION 1 : - BAY YARD (FACTORY)TO BLOCKYARD (PROJECTSITE)
  • 78. 6.1 OPTION 2 : - BAY YARD (FACTORY)TO SITE YARD (PROJECTSITE)
  • 79. 6.1 OPTION 3 : - STORAGE YARD (FACTORY)TO BLOCKYARD (PROJECTSITE)
  • 80. 6.1 OPTION 4 : - STORAGE YARD (FACTORY)TO SITE YARD (PROJECTSITE)
  • 86. 6.7 PROJECT SITE STORAGE YARD
  • 87. 6.8 PROJECT INTERNAL TRANSPORT
  • 88. ReboundHammer test carried out daily & on selected Panel 7. QUALITYCONTROL & ASSURANCE Ready Mixed Concrete : Concrete Grade to comply Engineer’s requirements. - Slump Test carried out on every delivery. - Cube Test taken for every 20m3.
  • 89. 7.1 QUALITY CONTROL & ASSURANCE - Lifting Of Panelonly afterminimum 18 hours or as specified by Engineer. - Panelstoredat stock yard for 7 days or as specifiedby Engineer curing before delivery to site. - Panelstack individually as apposedto one on top anotherto prevent cracks
  • 90. 8. COST COMPARISON/FAST& EASY : - CONVENTIONALvs HC PRECAST SYSTEM
  • 91. 8.1 COST COMPARISON/FAST& EASY : - CONVENTIONALvs HC PRECASTSYSTEM
  • 92. 8.2 COST COMPARISON/FAST& EASY : - CONVENTIONALVs HC PRECAST SYSTEM
  • 93. 8.3 COST COMPARISON/FAST& EASY : - CONVENTIONALVs HC PRECAST SYSTEM
  • 94. 8.4 COST COMPARISON/FAST& EASY : - CONVENTIONALVs HC PRECAST SYSTEM Semi-D House : Single Storey (Superstructure/Frame & Wall) Conventional : Original Design HC PrecastSystem (Current Rate – July 2014) (Current Rate – July 2014) RM 127.43/m2 Vs RM 90.00/m2 RATE CAN BE CHECKED & CHANGEBY YOU
  • 95. 8.5 COST COMPARISON/FAST& EASY : - COMPARE OUR SYSTEM PRICE : Superstructure (frame & wall)
  • 96. 8.6 COST COMPARISON/FAST& EASY : - COMPARE OUR SYSTEM PRICE : Superstructure (frame & wall)
  • 97. 9. DESIGNED BY YOU PRODUCED BY HC PRECAST SYSTEM
  • 98. 9.1 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 99. 9.2 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 100. 9.3 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 101. 9.4 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 102. 9.5 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 103. 9.6 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 104. 9.7 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 105. 9.8 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 106. 9.9 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 107. 9.10 DESIGNED BYYOU PRODUCED BY HC PRECAST SYSTEM
  • 108. DESIGNED BY YOU PRODUCED BY HC PRECAST SYSTEM THANK YOU PART 1
  • 109. 10. SYSTEMATIC PRODUCTION,DELIVERY & WORKPROGRAM 300 UNITS SINGLE STOREY SEMI-D PRODUCTION, DELIVERY, WORK PROGRAM & INSTALLATION SCHEDULE
  • 110. 11. PERCENTAGE ON SITE & OFF SITE WORK
  • 111. 11.1 PERCENTAGE ON SITE & OFF SITE WORK
  • 112. 11.2 PERCENTAGE ON SITE & OFF SITE WORK
  • 113. 11.3 PERCENTAGE ON SITE & OFF SITE WORK
  • 114. 11.4 PERCENTAGE ON SITE & OFF SITE WORK
  • 115. 12. FLEXIBILITY SUIT ARCHITECT DEMANDS - MODULAR MOULD & SHEAR KEYS
  • 116. 12.1 FLEXIBILITY SUIT ARCHITECT DEMANDS - MODULAR MOULD & SHEAR KEYS
  • 117. 12.2 FLEXIBILITY SUIT ARCHITECT DEMANDS - MODULAR MOULD & SHEAR KEYS
  • 118. 13. PRECAST ELEMENT 13.1 WALLPANEL: CUSTOMIZED 13.2 COLUMN WET JOINTWITH SHEAR KEYS 13.2a PRECASTPANELWITH SHEAR KEYS 13.3 IN-SITU COLUMN/PRECASTBEAM WITH SHEAR KEYS 13.4 HALF SLAB 13.4a HALF SLAB CASTING 13.5 PRECASTSTAIRCASE 1 13.5a PRECASTSTAIRCASE 2 13.6 BAY WINDOW 13.6a PRECASTPANELWITH GROVE LINE 13.7 ARCH 1 13.7a ARCH2 13.7b ARCH 3
  • 119. 13.1 WALL PANEL : CUSTOMIZED
  • 120. 13.2 COLUMN WET JOINT WITH SHEAR KEYS
  • 121. 13.2a COLUMNWET JOINT WITH SHEAR KEYS
  • 122. 13.2a COLUMNWET JOINT WITH SHEAR KEYS
  • 123. 13.2b PRECAST PANELWITH SHEAR KEYS
  • 124. 13.3 IN-SITU COLUMN / PRECAST BEAM WITH SHEAR KEYS
  • 126. 13.4a HALF SLAB CASTING
  • 128. 13.5a STAIRCASE 2 ( in-situ landing slab support )
  • 130. 13.6a PRECAST PANELWITH GROVE LINE
  • 134. 14. FACTORY CAPACITY : 21 ACRES Existing production 8 acres : 1,800 to 2,500 units of single storey (1000 ft2)per year Future development 13 acres :2,500 to 3,500 units of single storey(1000 ft2) per year
  • 135. 15. COMPLETEDPROJECTS 15.1 - 42 units 3&5 Storey Shop Office at Andalas Klang 15.2 - 156 units Single Storey Terrace Houseat Kota Puteri 15.3 - 7 units Single Storey Shop Lots at Kota Puteri 15.4 - 10 units Exco Bungalows Selangorat Shah Alam 15.5 - 112 units Single Storey Terraceat Kota Puteri 15.6 - 119 units Double Storey TerraceHouse at Shah Alam 15.7 - 88 units Semi DetachedLow at Bukit Botak 15.8 - 119 units Single Storey Terraceat Bernam Jaya 15.9 - 34 units Semi DetachedHouse at Shah Alam 15.10 - 118 units Double Storey Terrace House at Kota Puteri 15.11 - Show Unit Single Storey Houseat Rasa Factory 15.12 - Training Unit Double Storey at Rasa Factory
  • 136. 15.1 - 42 units 3&5 Storey Shop Office at Andalas Klang
  • 137. 15.2 - 156 units Single Storey Terrace House at Kota Puteri
  • 138. 15.3 - 7 units Single Storey Shop Lots at Kota Puteri
  • 139. 15.4a - 10 units Exco Bungalows Selangor at Shah Alam
  • 140. 15.4b - 10 units Exco Bungalows Selangor at Shah Alam
  • 141. 15.4c - 10 units Exco Bungalows Selangor at Shah Alam
  • 142. 15.4d - 10 units Exco Bungalows Selangor at Shah Alam
  • 143. 15.5 - 112 units Single Storey Terrace at Kota Puteri
  • 144. 15.5a - 112 units Single Storey Terrace at Kota Puteri
  • 145. 15.6 - 119 units Double Storey Terrace House at Shah Alam
  • 146. 15.7 - 88 units Semi Detached Low at Bukit Botak
  • 147. 15.7a - 88 units Semi Detached Low at Bukit Botak
  • 148. 15.7b - 88 units Semi Detached Low at Bukit Botak
  • 149. 15.8 - 119 units Single Storey Terrace at Bernam Jaya
  • 150. 15.9 - 34 units Semi Detached House at Shah Alam
  • 151. 15.9a - 34 units Semi Detached House at Shah Alam
  • 152. 15.9b - 34 units Semi Detached House at Shah Alam
  • 153. 15.10 - 118 Units Double Storey Terrace House at Kota Puteri
  • 154. 15.10a - 118 Units Double Storey Terrace House at Kota Puteri
  • 155. 15.10b - 118 Units Double Storey Terrace House at Kota Puteri
  • 156. 15.11 - Show Unit Single Storey House at Rasa Factory
  • 157. 15.11a - Show Unit Single Storey House at Rasa Factory
  • 158. 15.11b - Show Unit Single Storey House at Rasa Factory
  • 159. 15.11c - Show Unit Single Storey House at Rasa Factory
  • 160. 15.12 - Training Unit Double Storey House at Rasa Factory
  • 161. 16. PATENTED UNITED STATE : US 6.819.870B2
  • 162. 16.1 PATENTEDMALAYSIA : MY - 124213-AIN 2006 MY - 139712-AIN 2009
  • 163. 17. INTERNATIONAL PUBLICATIONS 17.1 USA :- - Jerome P. Lynch : 2013 17.2 PORTUGAL:- - 15th World Conference : 2012 17.3 GERMANY :- - CPI : 2011 17.4 MALAYSIA :- - EARTHQUAKE RESISTANCE TEST UTM : 2.011
  • 164. “ Earthquakes and Structures “ (Impact Factor2012 = 1.381, One of the highest among other structural earthquake engineering journals, indexed by Journal Citations Reports®, ISI ThomsonReuters) 17.1 USA : Jerome P.Lynch - 2013
  • 165. 17.2 PORTUGAL : 15TH WORLD CONFERENCE - 2012
  • 166. 17.2a PORTUGAL: 15TH WORLD CONFERENCE - 2012
  • 167. 17.3 GERMANY : CPI - 2011 MalaysiaIBS CompanyArticleAppearIn CPI Worldwide Journal In 8 DifferentLanguages (Based In GERMANY): 1. US 2. UK 3. Germany 4. French 5. Italian 6. Spanish 7. Portuguese 8. Indian
  • 169. EARTHQUAKE RESISTANCE TEST OF SCALED DOWN DOUBLESTOREY BUILDINGBY HC PRECASTSYSTEM IN COLLABORATION WITH UTM, JOHOR BASED ON 8 MAJOR EARTHQUAKES, IN THE WORLD 17.4 BUILDING & INVESTMENT - 2011
  • 170. 17.4a BUILDING & INVESTMENT - 2011
  • 171. 18. COLLABORATION WITH AGENCY 18.1 - UTM 18.1a - UTM / CERTIFICATE 18.2 - UITM 18.3 - CREAM/CIDB
  • 181. DESIGNED BY YOU PRODUCED BY HC PRECAST SYSTEM THANK YOU PART 2