SlideShare a Scribd company logo
1 of 12
Download to read offline
**5**
RIGGING ANALYSIS for
STEAM DRUM LIFTING by
WINCH
Refer to ASME B30.26-2004 Rigging Hardware and
Hoisting and Rigging Safety Manual (Book)
3/18/2013
BaLikPapan KaLtim
HaGun
BAB I. RIGGING ANALYSIS
A. Winch
Base-mounted winches, or tuggers, are a compact, versatile tool for many hoisting
and pulling operations. They are particularly useful in areas not accessible to mobile
cranes or where there is not enough headroom for a crane to operate. Figure 1
shows a tugger and snatch block arrangement for hoisting. Make sure that the rope
leaves the drum at a downward angle and that the loose end is securely anchored.
Figure 1
2
E-mail:gunawan_hagun@yahoo.co.id
B. Anchorage Points
Hoists, winches, tirfors, and other rigging devices require secure anchorage points.
Anchors may be overhead, in the floor, or at lateral points in walls or other structures.
The arrangement may involve columns, beams, beam clamps, welded lugs, slings, or
block and tackle. Whatever the method, riggers must be certain of the loads involved
and the anchorage required.
Lead Line Load Example A =
25 ton
1 line
= 25 ton
Lead Line Load Example B =
25 ton
6 line
= 4,167 ton ~ 5 ton
Load on structure A = 25 ton + 25 ton = 50 ton
Load on structure B = 25 ton + 5 ton = 30 ton
Load on structure = Load + Lead Line Load
Lead Line Load =
Load
Parts of Line at Load
3
E-mail:gunawan_hagun@yahoo.co.id
C. Angle effect to BLock Load
Analysis:
Load = 62 ton
Lead Line Load =
62 ton
8 line
= 7,75 ton ~ 8 ton
Load Block C = Load x Factor α deg angle (0o
)
Load Block C = 62 ton x 2 = 124 ton
.
Load Block D = Lead Line Load x Factor α deg angle (40o
)
Load Block D = 8 ton x 1.87 = 14.96 ton
.
Load Block E = Lead Line Load x Factor α deg angle (130o
)
Load Block E = 8 ton x 0.84 = 6.72 ton
.
Load Block F = Lead Line Load x Factor α deg angle (90o
)
Load Block F = 8 ton x 1.41 = 11.28 ton
4
E-mail:gunawan_hagun@yahoo.co.id
D. Rigging Blocks
The design factor for rigging blocks shall be a minimum of 4.
5
E-mail:gunawan_hagun@yahoo.co.id
E. Wire Rope Handling
Handling any kind of rope can be hazardous. Handling wire rope presents particular
hazards. Personnel should wear appropriate personal protective equipment such as
gloves and use caution to keep clothing or gloves from getting caught in sheaves or
drums during tugger/Winch operation.
6
E-mail:gunawan_hagun@yahoo.co.id
F. Hand Signals
Hand signals shall be in accordance with ASME B30.7-2006 and shall be posted
conspicuously.
7
E-mail:gunawan_hagun@yahoo.co.id
8
E-mail:gunawan_hagun@yahoo.co.id
G. LIFTING BY INCLINED AT AN ANGLE
9
E-mail:gunawan_hagun@yahoo.co.id
H. LOAD DISTRIBUTION OF INCLINED AT AN ANGLE
L Distence Lifting Lug L = 13000 mm
h Height of Lifting Lug h = 200 mm
∅
Diameter
∅
= 1800 mm
α Angle of Inclined α = 45 Deg
Y =
∅
/2 + h Y = 1100 mm
A = L Cos α A = 9192.388155 mm
B = Y Sin α B = 777.8174593 mm
C = (A/2) - B C = 3818.376618 mm
D = (A/2) + B D = 5374.011537 mm
W Weight Material W = 90 Ton
R1 = W (D/A) R1 = 52.61538462 Ton
R2 = W (C/A) R2 = 37.38461538 Ton
Control QW = 90 Ton
10
E-mail:gunawan_hagun@yahoo.co.id
L = 13000 mm
h = 200 mm
∅
= 1800 mm
W = 90 Ton
Uper Lower
R1 = R2 = QW =
α = 0 Deg 45.0000 Ton 45.0000 Ton 90 Ton
1 Deg 45.1329 Ton 44.8671 Ton 90 Ton
2 Deg 45.2659 Ton 44.7341 Ton 90 Ton
3 Deg 45.3991 Ton 44.6009 Ton 90 Ton
4 Deg 45.5325 Ton 44.4675 Ton 90 Ton
5 Deg 45.6663 Ton 44.3337 Ton 90 Ton
6 Deg 45.8004 Ton 44.1996 Ton 90 Ton
7 Deg 45.9351 Ton 44.0649 Ton 90 Ton
8 Deg 46.0703 Ton 43.9297 Ton 90 Ton
9 Deg 46.2062 Ton 43.7938 Ton 90 Ton
10 Deg 46.3428 Ton 43.6572 Ton 90 Ton
11 Deg 46.4803 Ton 43.5197 Ton 90 Ton
12 Deg 46.6187 Ton 43.3813 Ton 90 Ton
13 Deg 46.7582 Ton 43.2418 Ton 90 Ton
14 Deg 46.8987 Ton 43.1013 Ton 90 Ton
15 Deg 47.0405 Ton 42.9595 Ton 90 Ton
16 Deg 47.1837 Ton 42.8163 Ton 90 Ton
17 Deg 47.3283 Ton 42.6717 Ton 90 Ton
18 Deg 47.4744 Ton 42.5256 Ton 90 Ton
19 Deg 47.6222 Ton 42.3778 Ton 90 Ton
20 Deg 47.7718 Ton 42.2282 Ton 90 Ton
21 Deg 47.9233 Ton 42.0767 Ton 90 Ton
22 Deg 48.0768 Ton 41.9232 Ton 90 Ton
23 Deg 48.2325 Ton 41.7675 Ton 90 Ton
24 Deg 48.3906 Ton 41.6094 Ton 90 Ton
25 Deg 48.5511 Ton 41.4489 Ton 90 Ton
26 Deg 48.7143 Ton 41.2857 Ton 90 Ton
27 Deg 48.8802 Ton 41.1198 Ton 90 Ton
28 Deg 49.0492 Ton 40.9508 Ton 90 Ton
29 Deg 49.2213 Ton 40.7787 Ton 90 Ton
30 Deg 49.3967 Ton 40.6033 Ton 90 Ton
31 Deg 49.5758 Ton 40.4242 Ton 90 Ton
32 Deg 49.7586 Ton 40.2414 Ton 90 Ton
33 Deg 49.9455 Ton 40.0545 Ton 90 Ton
34 Deg 50.1366 Ton 39.8634 Ton 90 Ton
35 Deg 50.3323 Ton 39.6677 Ton 90 Ton
36 Deg 50.5329 Ton 39.4671 Ton 90 Ton
37 Deg 50.7386 Ton 39.2614 Ton 90 Ton
38 Deg 50.9498 Ton 39.0502 Ton 90 Ton
39 Deg 51.1668 Ton 38.8332 Ton 90 Ton
40 Deg 51.3901 Ton 38.6099 Ton 90 Ton
41 Deg 51.6200 Ton 38.3800 Ton 90 Ton
42 Deg 51.8569 Ton 38.1431 Ton 90 Ton
43 Deg 52.1015 Ton 37.8985 Ton 90 Ton
44 Deg 52.3541 Ton 37.6459 Ton 90 Ton
45 Deg 52.6154 Ton 37.3846 Ton 90 Ton
START
DATA MATERIAL
1. DIMENSION
2. WEIGHT
RIGGING DEPARTMENT
ANALYZE AND PLANED ACTIVITY FOR
LIFTING AND ERECTION WORK
REFERENCE
1. RIGGING BOOK
2. EQUIPMENT MANUAL
3. ASME B30.5-2004 Mobil & Locomotive cranes
4. ASME B30.6-2003 Derrick
5. ASME B30.10-1999 Hook
6. ASME B30.21-2005 manually lever operated hoist
7. ASME B30.24-2003 Safety standard for cranes,derrick, hoist, jacks, and Sling
8. ASME B30.26-2004 Rigging Hardware
9. BS EN 5973 Scaffolding
10. Australian Standard, AS 3569--1989, Wire ropes
11. Australian Standard, AS 2759--1985, Wire ropes
NEED DUO CRANE
Yes
No
MONO CRANE
TAILING DESIGN
JOB SAFETY ANALISYS
Safe
Risk
FINISH
Final Inspection by
HaGun Engineering
Prepare Final Report for ApprovaL
Handover
No
Yes
RIGGING PLAN
ACTION
CONTROL
RIGGING PLAN
LIFTING FOR
POWER CONTROL CENTERS
SLING13METER
01. OBJECTIVE
Rigging Study of Lifting Power Control Centers.
02. SCOPE OF APPLICATION
Rigging study is describe the guidelines and operating step of Lifting Power Control Centers.
03. REFERENCE
1. HaGun Engineering RIGGING DEPARTMENT REFERENCE
04. EQUIPMENT
No Equipment Qty Capacities Remark
01 Crawler Crane 1 unit 150 ton New
02 Boom Length 48 meter 1 unit New
03 Trailer 1 unit 80 ton New
05. RIGGING TOOLS
No Equipment Qty Capacities
01 Sling dia. 1.5" x 13 M 4 pcs 17 ton
02 Chain Block 2 pcs 10 ton
03 Shackle SWL 10 pcs 10 ton
04 Manila Rope 7/8"x10M 2 pcs
06. SAFETY REQUIREMENTS
No Equipment Qty
01 Safety Barricade Red White 77 mtr
02 Safety Cone 7 pcs
07. SAFETY FACTOR CALCULATION
No Equipment Qty
01 Weight of material 22.00 T
02 Crane Block 1.33 T
03 Wire Sling 0.15 T
04 Spreader Beam 0.60 T
05 Shackle 0.15 T
06 Total Weight 24.23 T
07 Crane Capacity 26.62 T
08 Safety Factor 1.1
SF = 26.62
24.23 = 1.1
Steel plates 1.5m x 6m x 20 mm thk for track
BOOM48METER
20000
R
20000
CRANE LAY OUT
MOVING OBJECT FROM A TO B
A
B

More Related Content

What's hot (20)

Operating practices
Operating practicesOperating practices
Operating practices
 
313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Rigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputRigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh Rajput
 
Wire rope
Wire ropeWire rope
Wire rope
 
Basic rigging training manual
Basic rigging training manualBasic rigging training manual
Basic rigging training manual
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
Liftingproedure
LiftingproedureLiftingproedure
Liftingproedure
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
 
Rigging Engineering Basic
Rigging Engineering BasicRigging Engineering Basic
Rigging Engineering Basic
 
Lifting practices for engineers
Lifting practices for engineersLifting practices for engineers
Lifting practices for engineers
 
Rigging Presentation by Pipeweldrig
Rigging Presentation by PipeweldrigRigging Presentation by Pipeweldrig
Rigging Presentation by Pipeweldrig
 
Wrs rigging practice
Wrs rigging practiceWrs rigging practice
Wrs rigging practice
 
Rigging Fundamentals Training by HTC
Rigging Fundamentals Training by HTCRigging Fundamentals Training by HTC
Rigging Fundamentals Training by HTC
 
Webbing Sling
Webbing SlingWebbing Sling
Webbing Sling
 
Mobile crane
Mobile craneMobile crane
Mobile crane
 
Safe Slinging Practices Training by PE
Safe Slinging Practices Training by PESafe Slinging Practices Training by PE
Safe Slinging Practices Training by PE
 
Rigging Safety Training by ATP
Rigging Safety Training by ATPRigging Safety Training by ATP
Rigging Safety Training by ATP
 
Rigging Presentation
Rigging PresentationRigging Presentation
Rigging Presentation
 

Viewers also liked

Method of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanicsMethod of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanicsHaGun Gunawan
 
2004 04 16_guide_prep_tap
2004 04 16_guide_prep_tap2004 04 16_guide_prep_tap
2004 04 16_guide_prep_tapSteph Cliche
 
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)Ashok Yadav
 
project report for vocational trainee
project report for vocational traineeproject report for vocational trainee
project report for vocational traineeSourav Jana
 
Heightworks IRATA Manual
Heightworks IRATA ManualHeightworks IRATA Manual
Heightworks IRATA ManualHeightworks Ltd
 
SFB5012 Project Paper May 16-G03178 Idzuari Azli
SFB5012 Project Paper May 16-G03178 Idzuari AzliSFB5012 Project Paper May 16-G03178 Idzuari Azli
SFB5012 Project Paper May 16-G03178 Idzuari AzliIdzuari Azli Bin Kamilan
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its InternalsAshrant Dass
 
Heightworks IRATA Training Manual Version 2 - Rope Access Training Manual
Heightworks IRATA Training Manual Version 2 - Rope Access Training ManualHeightworks IRATA Training Manual Version 2 - Rope Access Training Manual
Heightworks IRATA Training Manual Version 2 - Rope Access Training ManualHeightworks Ltd
 
Design a hostel complex to accommodate 1000 students
Design a hostel complex to accommodate 1000 studentsDesign a hostel complex to accommodate 1000 students
Design a hostel complex to accommodate 1000 studentsAshvini Kumar
 
Water and fire tube boilers
Water and fire tube boilersWater and fire tube boilers
Water and fire tube boilersTariq Jamshaid
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to BoilersSATYAKAM MOHAPATRA
 
Steam boilers
Steam boilersSteam boilers
Steam boilerssarat7
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsHrishikesh Devan
 
Cyclone separator
Cyclone separatorCyclone separator
Cyclone separatorWaqas Ahmed
 
3 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 20173 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 2017Drift
 

Viewers also liked (17)

Method of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanicsMethod of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanics
 
Rpc 4bypage
Rpc 4bypageRpc 4bypage
Rpc 4bypage
 
2004 04 16_guide_prep_tap
2004 04 16_guide_prep_tap2004 04 16_guide_prep_tap
2004 04 16_guide_prep_tap
 
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
 
project report for vocational trainee
project report for vocational traineeproject report for vocational trainee
project report for vocational trainee
 
Heightworks IRATA Manual
Heightworks IRATA ManualHeightworks IRATA Manual
Heightworks IRATA Manual
 
SFB5012 Project Paper May 16-G03178 Idzuari Azli
SFB5012 Project Paper May 16-G03178 Idzuari AzliSFB5012 Project Paper May 16-G03178 Idzuari Azli
SFB5012 Project Paper May 16-G03178 Idzuari Azli
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its Internals
 
Heightworks IRATA Training Manual Version 2 - Rope Access Training Manual
Heightworks IRATA Training Manual Version 2 - Rope Access Training ManualHeightworks IRATA Training Manual Version 2 - Rope Access Training Manual
Heightworks IRATA Training Manual Version 2 - Rope Access Training Manual
 
Design a hostel complex to accommodate 1000 students
Design a hostel complex to accommodate 1000 studentsDesign a hostel complex to accommodate 1000 students
Design a hostel complex to accommodate 1000 students
 
Steam generator part 1
Steam generator part 1Steam generator part 1
Steam generator part 1
 
Water and fire tube boilers
Water and fire tube boilersWater and fire tube boilers
Water and fire tube boilers
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to Boilers
 
Steam boilers
Steam boilersSteam boilers
Steam boilers
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam Generators
 
Cyclone separator
Cyclone separatorCyclone separator
Cyclone separator
 
3 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 20173 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 2017
 

Similar to Steam drum lifting

Design of bailong elevator case study
Design of bailong elevator   case studyDesign of bailong elevator   case study
Design of bailong elevator case studymechmitaoe
 
TAG WOOHOOPRESENTAION
TAG WOOHOOPRESENTAIONTAG WOOHOOPRESENTAION
TAG WOOHOOPRESENTAIONDwight Nava
 
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPTArie van Dijken
 
COMPACT_8W_10_12-UK-BD
COMPACT_8W_10_12-UK-BDCOMPACT_8W_10_12-UK-BD
COMPACT_8W_10_12-UK-BDeamon lim
 
Coates Hire Structural Propping & Support
Coates Hire Structural Propping & Support Coates Hire Structural Propping & Support
Coates Hire Structural Propping & Support Rafi Tchopourian
 
Plataforma Aéra Sob Trailler - 180 T "Dinolift"
Plataforma Aéra Sob Trailler - 180 T "Dinolift"Plataforma Aéra Sob Trailler - 180 T "Dinolift"
Plataforma Aéra Sob Trailler - 180 T "Dinolift"Riwal do Brasil
 
Preliminary Design of Containership
Preliminary Design of ContainershipPreliminary Design of Containership
Preliminary Design of ContainershipAhmed Atef
 
Igo50-Product-Guide.pdf
Igo50-Product-Guide.pdfIgo50-Product-Guide.pdf
Igo50-Product-Guide.pdfkredis1
 
Igo50 Self Erecting Tower Cranes Product-Guide.pdf
Igo50 Self Erecting Tower Cranes Product-Guide.pdfIgo50 Self Erecting Tower Cranes Product-Guide.pdf
Igo50 Self Erecting Tower Cranes Product-Guide.pdfCompass Equipment
 
Atlas Senior Deisgn Presentation
Atlas Senior Deisgn PresentationAtlas Senior Deisgn Presentation
Atlas Senior Deisgn PresentationSteven Polowy
 
Heavy Lifts PPVC Lifting Frame & Anchor.pdf
Heavy Lifts PPVC Lifting Frame & Anchor.pdfHeavy Lifts PPVC Lifting Frame & Anchor.pdf
Heavy Lifts PPVC Lifting Frame & Anchor.pdfVeeramuthuBalakrishn
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
Kimberly Access - Access Equipment Wall Chart 2013
Kimberly Access - Access Equipment Wall Chart 2013Kimberly Access - Access Equipment Wall Chart 2013
Kimberly Access - Access Equipment Wall Chart 2013KimberlyAccess
 
4B Forged Conveyor Chain Presentation
4B Forged Conveyor Chain Presentation4B Forged Conveyor Chain Presentation
4B Forged Conveyor Chain Presentation4B Braime Components
 
Design of Floating Bridge Cross Over
Design of Floating Bridge Cross OverDesign of Floating Bridge Cross Over
Design of Floating Bridge Cross OverIRJET Journal
 

Similar to Steam drum lifting (20)

Civil works mstart
Civil works mstartCivil works mstart
Civil works mstart
 
Design of bailong elevator case study
Design of bailong elevator   case studyDesign of bailong elevator   case study
Design of bailong elevator case study
 
Testtadano60ton
Testtadano60tonTesttadano60ton
Testtadano60ton
 
TAG WOOHOOPRESENTAION
TAG WOOHOOPRESENTAIONTAG WOOHOOPRESENTAION
TAG WOOHOOPRESENTAION
 
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
0264 GustoMSC_PowerPointTemplate_08_2010[1].PPT
 
COMPACT_8W_10_12-UK-BD
COMPACT_8W_10_12-UK-BDCOMPACT_8W_10_12-UK-BD
COMPACT_8W_10_12-UK-BD
 
screw jack 4.docx
screw jack 4.docxscrew jack 4.docx
screw jack 4.docx
 
Coates Hire Structural Propping & Support
Coates Hire Structural Propping & Support Coates Hire Structural Propping & Support
Coates Hire Structural Propping & Support
 
Plataforma Aéra Sob Trailler - 180 T "Dinolift"
Plataforma Aéra Sob Trailler - 180 T "Dinolift"Plataforma Aéra Sob Trailler - 180 T "Dinolift"
Plataforma Aéra Sob Trailler - 180 T "Dinolift"
 
Khung can-ban-ohaus-checkweigh-scales
Khung can-ban-ohaus-checkweigh-scalesKhung can-ban-ohaus-checkweigh-scales
Khung can-ban-ohaus-checkweigh-scales
 
Preliminary Design of Containership
Preliminary Design of ContainershipPreliminary Design of Containership
Preliminary Design of Containership
 
Igo50-Product-Guide.pdf
Igo50-Product-Guide.pdfIgo50-Product-Guide.pdf
Igo50-Product-Guide.pdf
 
Igo50 Self Erecting Tower Cranes Product-Guide.pdf
Igo50 Self Erecting Tower Cranes Product-Guide.pdfIgo50 Self Erecting Tower Cranes Product-Guide.pdf
Igo50 Self Erecting Tower Cranes Product-Guide.pdf
 
Atlas Senior Deisgn Presentation
Atlas Senior Deisgn PresentationAtlas Senior Deisgn Presentation
Atlas Senior Deisgn Presentation
 
Final pre.ppt
Final pre.pptFinal pre.ppt
Final pre.ppt
 
Heavy Lifts PPVC Lifting Frame & Anchor.pdf
Heavy Lifts PPVC Lifting Frame & Anchor.pdfHeavy Lifts PPVC Lifting Frame & Anchor.pdf
Heavy Lifts PPVC Lifting Frame & Anchor.pdf
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Kimberly Access - Access Equipment Wall Chart 2013
Kimberly Access - Access Equipment Wall Chart 2013Kimberly Access - Access Equipment Wall Chart 2013
Kimberly Access - Access Equipment Wall Chart 2013
 
4B Forged Conveyor Chain Presentation
4B Forged Conveyor Chain Presentation4B Forged Conveyor Chain Presentation
4B Forged Conveyor Chain Presentation
 
Design of Floating Bridge Cross Over
Design of Floating Bridge Cross OverDesign of Floating Bridge Cross Over
Design of Floating Bridge Cross Over
 

More from HaGun Gunawan

Metode induksi HaGun institute
Metode induksi HaGun instituteMetode induksi HaGun institute
Metode induksi HaGun instituteHaGun Gunawan
 
X ref auto cad 2007+r4
X ref auto cad 2007+r4X ref auto cad 2007+r4
X ref auto cad 2007+r4HaGun Gunawan
 
Ha gun treatment plant + pnup makassar+makalah
Ha gun treatment plant + pnup makassar+makalahHa gun treatment plant + pnup makassar+makalah
Ha gun treatment plant + pnup makassar+makalahHaGun Gunawan
 
4jam menggambar rumah 3d
4jam menggambar rumah 3d4jam menggambar rumah 3d
4jam menggambar rumah 3dHaGun Gunawan
 
Flow chart lifting plan+gantry+works
Flow chart lifting plan+gantry+worksFlow chart lifting plan+gantry+works
Flow chart lifting plan+gantry+worksHaGun Gunawan
 
Power Lift for Lifting Turbine+generator
Power Lift for Lifting Turbine+generatorPower Lift for Lifting Turbine+generator
Power Lift for Lifting Turbine+generatorHaGun Gunawan
 
13 detik membuat daftar isi di ms word 2007+r4.doc
13 detik membuat daftar isi di ms word 2007+r4.doc13 detik membuat daftar isi di ms word 2007+r4.doc
13 detik membuat daftar isi di ms word 2007+r4.docHaGun Gunawan
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015HaGun Gunawan
 
HaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun treatment pl-ant-makalah-seminar di unjani bandungHaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun treatment pl-ant-makalah-seminar di unjani bandungHaGun Gunawan
 
060 turbine+generator
060 turbine+generator060 turbine+generator
060 turbine+generatorHaGun Gunawan
 
062 generator+00 combine
062 generator+00 combine062 generator+00 combine
062 generator+00 combineHaGun Gunawan
 
Catalyst coo ler north section 18march2014
Catalyst coo ler north section 18march2014Catalyst coo ler north section 18march2014
Catalyst coo ler north section 18march2014HaGun Gunawan
 
Casing catalyst coo ler north section 18march2014
Casing catalyst coo ler north section 18march2014Casing catalyst coo ler north section 18march2014
Casing catalyst coo ler north section 18march2014HaGun Gunawan
 
Sling and tailing+bundle
Sling and tailing+bundleSling and tailing+bundle
Sling and tailing+bundleHaGun Gunawan
 

More from HaGun Gunawan (16)

Grafik sondir 2007
Grafik sondir 2007Grafik sondir 2007
Grafik sondir 2007
 
Metode induksi HaGun institute
Metode induksi HaGun instituteMetode induksi HaGun institute
Metode induksi HaGun institute
 
X ref auto cad 2007+r4
X ref auto cad 2007+r4X ref auto cad 2007+r4
X ref auto cad 2007+r4
 
Ha gun treatment plant + pnup makassar+makalah
Ha gun treatment plant + pnup makassar+makalahHa gun treatment plant + pnup makassar+makalah
Ha gun treatment plant + pnup makassar+makalah
 
4jam menggambar rumah 3d
4jam menggambar rumah 3d4jam menggambar rumah 3d
4jam menggambar rumah 3d
 
Flow chart lifting plan+gantry+works
Flow chart lifting plan+gantry+worksFlow chart lifting plan+gantry+works
Flow chart lifting plan+gantry+works
 
Power Lift for Lifting Turbine+generator
Power Lift for Lifting Turbine+generatorPower Lift for Lifting Turbine+generator
Power Lift for Lifting Turbine+generator
 
13 detik membuat daftar isi di ms word 2007+r4.doc
13 detik membuat daftar isi di ms word 2007+r4.doc13 detik membuat daftar isi di ms word 2007+r4.doc
13 detik membuat daftar isi di ms word 2007+r4.doc
 
HaGun gantry crane
HaGun gantry craneHaGun gantry crane
HaGun gantry crane
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
 
HaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun treatment pl-ant-makalah-seminar di unjani bandungHaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun treatment pl-ant-makalah-seminar di unjani bandung
 
060 turbine+generator
060 turbine+generator060 turbine+generator
060 turbine+generator
 
062 generator+00 combine
062 generator+00 combine062 generator+00 combine
062 generator+00 combine
 
Catalyst coo ler north section 18march2014
Catalyst coo ler north section 18march2014Catalyst coo ler north section 18march2014
Catalyst coo ler north section 18march2014
 
Casing catalyst coo ler north section 18march2014
Casing catalyst coo ler north section 18march2014Casing catalyst coo ler north section 18march2014
Casing catalyst coo ler north section 18march2014
 
Sling and tailing+bundle
Sling and tailing+bundleSling and tailing+bundle
Sling and tailing+bundle
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 

Steam drum lifting

  • 1. **5** RIGGING ANALYSIS for STEAM DRUM LIFTING by WINCH Refer to ASME B30.26-2004 Rigging Hardware and Hoisting and Rigging Safety Manual (Book) 3/18/2013 BaLikPapan KaLtim HaGun
  • 2. BAB I. RIGGING ANALYSIS A. Winch Base-mounted winches, or tuggers, are a compact, versatile tool for many hoisting and pulling operations. They are particularly useful in areas not accessible to mobile cranes or where there is not enough headroom for a crane to operate. Figure 1 shows a tugger and snatch block arrangement for hoisting. Make sure that the rope leaves the drum at a downward angle and that the loose end is securely anchored. Figure 1
  • 3. 2 E-mail:gunawan_hagun@yahoo.co.id B. Anchorage Points Hoists, winches, tirfors, and other rigging devices require secure anchorage points. Anchors may be overhead, in the floor, or at lateral points in walls or other structures. The arrangement may involve columns, beams, beam clamps, welded lugs, slings, or block and tackle. Whatever the method, riggers must be certain of the loads involved and the anchorage required. Lead Line Load Example A = 25 ton 1 line = 25 ton Lead Line Load Example B = 25 ton 6 line = 4,167 ton ~ 5 ton Load on structure A = 25 ton + 25 ton = 50 ton Load on structure B = 25 ton + 5 ton = 30 ton Load on structure = Load + Lead Line Load Lead Line Load = Load Parts of Line at Load
  • 4. 3 E-mail:gunawan_hagun@yahoo.co.id C. Angle effect to BLock Load Analysis: Load = 62 ton Lead Line Load = 62 ton 8 line = 7,75 ton ~ 8 ton Load Block C = Load x Factor α deg angle (0o ) Load Block C = 62 ton x 2 = 124 ton . Load Block D = Lead Line Load x Factor α deg angle (40o ) Load Block D = 8 ton x 1.87 = 14.96 ton . Load Block E = Lead Line Load x Factor α deg angle (130o ) Load Block E = 8 ton x 0.84 = 6.72 ton . Load Block F = Lead Line Load x Factor α deg angle (90o ) Load Block F = 8 ton x 1.41 = 11.28 ton
  • 5. 4 E-mail:gunawan_hagun@yahoo.co.id D. Rigging Blocks The design factor for rigging blocks shall be a minimum of 4.
  • 6. 5 E-mail:gunawan_hagun@yahoo.co.id E. Wire Rope Handling Handling any kind of rope can be hazardous. Handling wire rope presents particular hazards. Personnel should wear appropriate personal protective equipment such as gloves and use caution to keep clothing or gloves from getting caught in sheaves or drums during tugger/Winch operation.
  • 7. 6 E-mail:gunawan_hagun@yahoo.co.id F. Hand Signals Hand signals shall be in accordance with ASME B30.7-2006 and shall be posted conspicuously.
  • 10. 9 E-mail:gunawan_hagun@yahoo.co.id H. LOAD DISTRIBUTION OF INCLINED AT AN ANGLE L Distence Lifting Lug L = 13000 mm h Height of Lifting Lug h = 200 mm ∅ Diameter ∅ = 1800 mm α Angle of Inclined α = 45 Deg Y = ∅ /2 + h Y = 1100 mm A = L Cos α A = 9192.388155 mm B = Y Sin α B = 777.8174593 mm C = (A/2) - B C = 3818.376618 mm D = (A/2) + B D = 5374.011537 mm W Weight Material W = 90 Ton R1 = W (D/A) R1 = 52.61538462 Ton R2 = W (C/A) R2 = 37.38461538 Ton Control QW = 90 Ton
  • 11. 10 E-mail:gunawan_hagun@yahoo.co.id L = 13000 mm h = 200 mm ∅ = 1800 mm W = 90 Ton Uper Lower R1 = R2 = QW = α = 0 Deg 45.0000 Ton 45.0000 Ton 90 Ton 1 Deg 45.1329 Ton 44.8671 Ton 90 Ton 2 Deg 45.2659 Ton 44.7341 Ton 90 Ton 3 Deg 45.3991 Ton 44.6009 Ton 90 Ton 4 Deg 45.5325 Ton 44.4675 Ton 90 Ton 5 Deg 45.6663 Ton 44.3337 Ton 90 Ton 6 Deg 45.8004 Ton 44.1996 Ton 90 Ton 7 Deg 45.9351 Ton 44.0649 Ton 90 Ton 8 Deg 46.0703 Ton 43.9297 Ton 90 Ton 9 Deg 46.2062 Ton 43.7938 Ton 90 Ton 10 Deg 46.3428 Ton 43.6572 Ton 90 Ton 11 Deg 46.4803 Ton 43.5197 Ton 90 Ton 12 Deg 46.6187 Ton 43.3813 Ton 90 Ton 13 Deg 46.7582 Ton 43.2418 Ton 90 Ton 14 Deg 46.8987 Ton 43.1013 Ton 90 Ton 15 Deg 47.0405 Ton 42.9595 Ton 90 Ton 16 Deg 47.1837 Ton 42.8163 Ton 90 Ton 17 Deg 47.3283 Ton 42.6717 Ton 90 Ton 18 Deg 47.4744 Ton 42.5256 Ton 90 Ton 19 Deg 47.6222 Ton 42.3778 Ton 90 Ton 20 Deg 47.7718 Ton 42.2282 Ton 90 Ton 21 Deg 47.9233 Ton 42.0767 Ton 90 Ton 22 Deg 48.0768 Ton 41.9232 Ton 90 Ton 23 Deg 48.2325 Ton 41.7675 Ton 90 Ton 24 Deg 48.3906 Ton 41.6094 Ton 90 Ton 25 Deg 48.5511 Ton 41.4489 Ton 90 Ton 26 Deg 48.7143 Ton 41.2857 Ton 90 Ton 27 Deg 48.8802 Ton 41.1198 Ton 90 Ton 28 Deg 49.0492 Ton 40.9508 Ton 90 Ton 29 Deg 49.2213 Ton 40.7787 Ton 90 Ton 30 Deg 49.3967 Ton 40.6033 Ton 90 Ton 31 Deg 49.5758 Ton 40.4242 Ton 90 Ton 32 Deg 49.7586 Ton 40.2414 Ton 90 Ton 33 Deg 49.9455 Ton 40.0545 Ton 90 Ton 34 Deg 50.1366 Ton 39.8634 Ton 90 Ton 35 Deg 50.3323 Ton 39.6677 Ton 90 Ton 36 Deg 50.5329 Ton 39.4671 Ton 90 Ton 37 Deg 50.7386 Ton 39.2614 Ton 90 Ton 38 Deg 50.9498 Ton 39.0502 Ton 90 Ton 39 Deg 51.1668 Ton 38.8332 Ton 90 Ton 40 Deg 51.3901 Ton 38.6099 Ton 90 Ton 41 Deg 51.6200 Ton 38.3800 Ton 90 Ton 42 Deg 51.8569 Ton 38.1431 Ton 90 Ton 43 Deg 52.1015 Ton 37.8985 Ton 90 Ton 44 Deg 52.3541 Ton 37.6459 Ton 90 Ton 45 Deg 52.6154 Ton 37.3846 Ton 90 Ton
  • 12. START DATA MATERIAL 1. DIMENSION 2. WEIGHT RIGGING DEPARTMENT ANALYZE AND PLANED ACTIVITY FOR LIFTING AND ERECTION WORK REFERENCE 1. RIGGING BOOK 2. EQUIPMENT MANUAL 3. ASME B30.5-2004 Mobil & Locomotive cranes 4. ASME B30.6-2003 Derrick 5. ASME B30.10-1999 Hook 6. ASME B30.21-2005 manually lever operated hoist 7. ASME B30.24-2003 Safety standard for cranes,derrick, hoist, jacks, and Sling 8. ASME B30.26-2004 Rigging Hardware 9. BS EN 5973 Scaffolding 10. Australian Standard, AS 3569--1989, Wire ropes 11. Australian Standard, AS 2759--1985, Wire ropes NEED DUO CRANE Yes No MONO CRANE TAILING DESIGN JOB SAFETY ANALISYS Safe Risk FINISH Final Inspection by HaGun Engineering Prepare Final Report for ApprovaL Handover No Yes RIGGING PLAN ACTION CONTROL RIGGING PLAN LIFTING FOR POWER CONTROL CENTERS SLING13METER 01. OBJECTIVE Rigging Study of Lifting Power Control Centers. 02. SCOPE OF APPLICATION Rigging study is describe the guidelines and operating step of Lifting Power Control Centers. 03. REFERENCE 1. HaGun Engineering RIGGING DEPARTMENT REFERENCE 04. EQUIPMENT No Equipment Qty Capacities Remark 01 Crawler Crane 1 unit 150 ton New 02 Boom Length 48 meter 1 unit New 03 Trailer 1 unit 80 ton New 05. RIGGING TOOLS No Equipment Qty Capacities 01 Sling dia. 1.5" x 13 M 4 pcs 17 ton 02 Chain Block 2 pcs 10 ton 03 Shackle SWL 10 pcs 10 ton 04 Manila Rope 7/8"x10M 2 pcs 06. SAFETY REQUIREMENTS No Equipment Qty 01 Safety Barricade Red White 77 mtr 02 Safety Cone 7 pcs 07. SAFETY FACTOR CALCULATION No Equipment Qty 01 Weight of material 22.00 T 02 Crane Block 1.33 T 03 Wire Sling 0.15 T 04 Spreader Beam 0.60 T 05 Shackle 0.15 T 06 Total Weight 24.23 T 07 Crane Capacity 26.62 T 08 Safety Factor 1.1 SF = 26.62 24.23 = 1.1 Steel plates 1.5m x 6m x 20 mm thk for track BOOM48METER 20000 R 20000 CRANE LAY OUT MOVING OBJECT FROM A TO B A B