SlideShare a Scribd company logo
2014
Prepared by
Md. Shaha Jalal
Mechanical Maintenance Technician
A large multinational power generation
company
Lifting Plan for Inlet Duct removal
Lifting Plan for Inlet duct
Tools & equipment to be used:
i. Manitowoc 4000 W Vicon Crawler Crane : 1 no.
Purpose : To lift the load.
Capacity : 150 ton
ii. P&H (70 ton capacity) Crane (trailing crane) : 1 no.
Purpose : To trail the load.
Capacity : 70 ton
iii. Trailer with Prime Mover. : 1 no.
Purpose : To shift the load.
Capacity : 50 ton
Length : 20 m (65 feet)
Width : 10 m (33 feet)
iv. Chain Blocks : 3 nos.
Purpose : To balance the load
Capacity : 15 ton
v. D-Shackles ,35 ton : 8 nos
vi. D-Shackles ,25 ton : 4 nos
vii. Wire Rope , 20 ton, length- 3 m (10 feet) : 16 nos
viii. Wire Rope , 20 ton, length- 4 m (13 feet) : 8 nos
ix. Wire Rope , 20 ton, length- 5 m(15 feet) : 16 nos
x. Wire Rope , 20 ton, length- 6 m(26 feet) : 8 nos
xi. Wire Rope , 20 ton, length- 9 m(30 feet) : 8 nos
xii. Spreader Beam : 2 no.
xiii. Hydraulic Jack, 100 ton : 4nos
xiv. Nylon Rope (Tag Line) – Diameter 1 inch : 2 rolls
xv. Warning Tape : 2 rolls
xvi. Walkie -Talkie System of same channel : 4 sets
Rigging Drawing for Lifting of Duct with 150 ton Crawler crane.
Specification of crane:
Load capacity (Max) : 150 ton
Boom Length : 130 feet
Counter Weight : 104.4 klb
Distance from mass center of the load : 11.5 m (38 ft)
Angle of boom : 73 degree.
Specifications of rigging accessories:
Spreader Beam:
Safe working load : 42 ton
Length : 8400 mm (27.552 ft)
Width : 219 mm (8.61 Inc.)
Required Quantity : 2 Nos
Chain Block:
Capacity : 15 ton
Required Quantity : 2 nos + 1 spare
Lifting lug:
As per Appendix: 01
Wire sling:
Capacity Length Qty
20 ton 3843 mm (13’) 02
20 ton 4500 mm(15’) 04
20 ton 8100 mm(26’) 02
Nylon Rope 1’’ --- 1 roll
Detail Arrangement:
All rigging accessories will be arranged as per drawing shown below.
Fig: Rigging arrangement for lifting DT#01
Lifting Procedure for DT#01:
a. Place the 150 ton crane at 38 feet radius from the center line of the load. (annex:04)
b. Hang the load with lifting accessories and lift up to 15 mm with the help of hydraulic jack at
jacking position.( Annex:01)
c. DT#01 will be lifted 42 ft from ground level.
Boom Length : 130 ft
Radius : 38 ft
Angle of boom = Cos-1
(38ft/130ft)
= 73 degree
Available lifting height = 38 tan 73°
= 124 ft
Available lifting height:
= 124 – Load height – Distance between touching
point to boom top.
= 124 – 35 – 47
= 42 ft
Lifting accessories length:
=37 ft
Load Capacity : 40 ton (from load chart: annex 02)
Load weight : 30 ton
Accessories : 2 ton
Total load weight : 32 ton
d. Slowly move the crane backward (north to south) until just before the load touches DT#02.
e. Swing the boom towards clockwise direction until just before the load touches steam pipe rack.
f. Repeat procedure: d and procedure: e until DT#01 is removed from the slot of inlet duct, so that
the crane can be mobilized (north to south) towards the trailer.
g. When the crane comes at a position in line with EDG (emergency diesel generator), annex#04
and boom will be swung 180 degree clockwise to lay down on trailer with the help of trailing
crane.
h. Place the trailing crane beside (east side of trailer) and in line (east to west) with trailer.
i. Hook up the trailing crane to lower lug with the help of wire sling as shown in the below
arrangement.
Fig: Rigging arrangement of trailer crane and main crane.
j. The load will be tilted down by lowering the main crane and lifting up the trailing crane as
shown in the below figure.
Figure: Load placement on trailer.
k. Trailer will be placed underneath the load and load will be put on the trailer bed.
l. Trailer will be moved to storage area.
m. In the storage area, DT#01 will be unloaded by two cranes (100 ton and 70 ton).
Lifting Procedure for DT#02:
a. Place the 150 ton crane from the center line of the load. (annex:04)
b. Hang the load with lifting accessories and lift up to 15 mm with the help of hydraulic jack at
jacking position.( Annex:01)
c. DT#02 will be lifted to 25 ft from ground level.
Figure: Lifting of DT#02
Boom Length : 130 ft
Radius : 38 ft
Angle of boom = Cos-1
(38ft/130ft)
= 73 degree
Available lifting height = 38 tan 73°
= 124 ft
Available lifting height:
= 124 – Load height – Distance
between touching point to
boom top.
= 124 – 49 – 50
= 25 ft
Load Capacity : 37 ton (from load chart:
annex 02)
Load weight : 28 ton
Accessories : 2 ton
Total load weight : 30 ton
Lifting accessories length= 37 ft
d. Swing the boom towards clockwise direction and will stop the crane just before when load will
touch the Gas turbine diffuser.
e. Slowly move the crane backward (north to south) just before the load touches DT#03.
f. Repeat procedure: d and procedure: e until DT#02 will be fully removed from the slot of inlet
duct, so that the crane can be mobilized (north to south) towards the trailer.
g. When the crane will come at a position in line with EDG ( emergency diesel generator), boom
will be swung 180 degree clockwise to lay down on trailer with the help of trailing crane.
h. Place the trailing crane beside (east side of trailer) and in line (east to west) with trailer as
shown for DT#01.
i. Hook up the trailing crane to lower lug with the help of wire sling.
j. The load will be tilted down by lowering the main crane and lifting up the trailing crane as
shown for DT#01.
k. Trailer will be placed underneath the load and load will be put on the trailer bed.
l. Trailer will be moved to storage area.
m. In the storage area, DT#02 will be unloaded by two cranes (100 ton and 70 ton).
Lifting Procedure for DT#03:
a. Place the 150 ton crane from the center line of the load. (annex:04)
Figure: Lifting of DT#03
b. Hang the load with lifting accessories and lift up to 15 mm with the help of hydraulic jack at
jacking position.( Annex:03)
c. DT#03 will be lifted 3.5 ft from ground level.
Boom Length : 130 ft
Radius : 38 ft
Angle of boom = Cos-1
(38ft/130ft)
= 73 degree
Available lifting height = 38 tan 73°
= 124 ft
d. Slowly swing the crane clockwise (west to east) and will stop the crane just before when load
will touch the Gas turbine diffuser.
e. Swing the boom towards clockwise direction until the load become in line with the road.
f. Slowly move the crane backward (north to south), so that the crane can be mobilized (north to
south) towards the trailer.
g. Load will be laid down on trailer with the help of trailing crane.
h. Place the trailing crane beside (east side of trailer) and in line (east to west) with trailer as
shown in the below arrangement same as DT#01.
i. Hook up the trailing crane to lower lug with the help of wire sling.
j. The load will be tilted down by lowering the main crane and lifting up the trailing crane as
shown for DT#01.
k. Trailer will be placed underneath the load and load will be put on the trailer bed.
l. Trailer will be moved to storage area.
m. In the storage area, DT#01 will be unloaded by two cranes (100 ton and 70 ton).
Available lifting height:
= 124 – Load height – Distance between
touching point to boom top.
= 124 – 68 – 52.5
=3.5ft
Lifting accessories length= 38.3 ft
Load Capacity : 40 ton (from load chart: annex 02)
Load weight : 35 ton
Accessories : 2 ton
Total load weight : 37 ton
Appendix-01:
Figure: Spreader beam with lifting lug.
Annex-01:
Table: list of lifting accessories for DT#01 & DT#02
Name Size Qty.
Wire Sling 20 ton x 13 ft 4pcs
Wire Sling 20 ton x 15 ft 4pcs
Wire Sling 20 ton x 26 ft 4pcs
Spreader beam 8400 mm x 219mm 1pc
Chain block 15 ton 2pcs
Shackle 35 ton 4pcs
Figure: Jacking Points of inlet Duct.
Annex-02:
Table-01: Load chart for 150 ton crane.
Table -02: Load chart of 70 ton crane.
Annex-03:
Name Size Qty.
Wire Sling 20 ton x 14 ft 4pcs
Wire Sling 20 ton x 15 ft 4pcs
Wire Sling 20 ton x 26 ft 4pcs
Spreader beam 8.100 m x 219mm 1pc
Chain block 15 ton 2pcs
Shackle 35 ton 6pcs
Table: lifting accessories for DT#03
Annex:04

More Related Content

What's hot

Below the hook
Below the hook Below the hook
Below the hook
BILL Bill Brown
 
Lifting Sling Safety
Lifting Sling SafetyLifting Sling Safety
Lifting Sling Safety
Hvacmach
 
Rigging Presentation
Rigging PresentationRigging Presentation
Rigging Presentation
Arkansas STEPS Network
 
Rigging and lifting
Rigging and liftingRigging and lifting
Rigging and lifting
Asghar Yaghouti
 
Lifting practices for engineers
Lifting practices for engineersLifting practices for engineers
Lifting practices for engineers
Salman Islam Shehzad
 
Lifting & Rigging by NEIS
Lifting & Rigging by NEISLifting & Rigging by NEIS
Lifting & Rigging by NEIS
Atlantic Training, LLC.
 
Rigging
RiggingRigging
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
HaGun Gunawan
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
shahriermahmud13
 
Steam drum lifting
Steam drum liftingSteam drum lifting
Steam drum lifting
HaGun Gunawan
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
James McCann
 
Lift Plan
Lift PlanLift Plan
Crane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttpCrane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttpMounir Bassaid
 
Lifting plan
Lifting planLifting plan
Lifting plan
tnsv22
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Riggingfcarlson
 
Gi 2016 industrial rigging safety
Gi 2016 industrial rigging safetyGi 2016 industrial rigging safety
Gi 2016 industrial rigging safety
John Newquist
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
List Supplier
 
presentation on mobile cranes
presentation on mobile cranespresentation on mobile cranes
presentation on mobile cranes
vipin balan
 

What's hot (20)

Below the hook
Below the hook Below the hook
Below the hook
 
Lifting Sling Safety
Lifting Sling SafetyLifting Sling Safety
Lifting Sling Safety
 
Rigging Presentation
Rigging PresentationRigging Presentation
Rigging Presentation
 
Rigging and lifting
Rigging and liftingRigging and lifting
Rigging and lifting
 
Basic Rigging
Basic RiggingBasic Rigging
Basic Rigging
 
Lifting practices for engineers
Lifting practices for engineersLifting practices for engineers
Lifting practices for engineers
 
Lifting & Rigging by NEIS
Lifting & Rigging by NEISLifting & Rigging by NEIS
Lifting & Rigging by NEIS
 
Rigging
RiggingRigging
Rigging
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
Steam drum lifting
Steam drum liftingSteam drum lifting
Steam drum lifting
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Lifting Safety
Lifting SafetyLifting Safety
Lifting Safety
 
Lift Plan
Lift PlanLift Plan
Lift Plan
 
Crane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttpCrane safety and_awareness_presentation_ttp
Crane safety and_awareness_presentation_ttp
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
 
Gi 2016 industrial rigging safety
Gi 2016 industrial rigging safetyGi 2016 industrial rigging safety
Gi 2016 industrial rigging safety
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
 
presentation on mobile cranes
presentation on mobile cranespresentation on mobile cranes
presentation on mobile cranes
 

Viewers also liked

Method of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanicsMethod of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanics
HaGun Gunawan
 
Lifting Plan for INSTALLATION XCR40 & XCR41 by using Crawler Crane CC2800-1 &...
Lifting Plan for INSTALLATION XCR40 & XCR41 by using Crawler Crane CC2800-1 &...Lifting Plan for INSTALLATION XCR40 & XCR41 by using Crawler Crane CC2800-1 &...
Lifting Plan for INSTALLATION XCR40 & XCR41 by using Crawler Crane CC2800-1 &...Abdul Karim
 
obras temporales
obras temporalesobras temporales
obras temporales
Luis Manuel Rodríguez
 
Mobile crane
Mobile craneMobile crane
Mobile crane
ANA ISABEL R.R.
 
Basic rigging training manual
Basic rigging training manualBasic rigging training manual
Basic rigging training manualSyam Tawakkal
 

Viewers also liked (7)

Method of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanicsMethod of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanics
 
Lifting Plan for INSTALLATION XCR40 & XCR41 by using Crawler Crane CC2800-1 &...
Lifting Plan for INSTALLATION XCR40 & XCR41 by using Crawler Crane CC2800-1 &...Lifting Plan for INSTALLATION XCR40 & XCR41 by using Crawler Crane CC2800-1 &...
Lifting Plan for INSTALLATION XCR40 & XCR41 by using Crawler Crane CC2800-1 &...
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
obras temporales
obras temporalesobras temporales
obras temporales
 
Mobile crane
Mobile craneMobile crane
Mobile crane
 
Wrs rigging practice
Wrs rigging practiceWrs rigging practice
Wrs rigging practice
 
Basic rigging training manual
Basic rigging training manualBasic rigging training manual
Basic rigging training manual
 

Similar to Lifting plan for inlet duct removal

Rigging Engineering Basic
Rigging Engineering BasicRigging Engineering Basic
Rigging Engineering Basic
Badaruddin kendari
 
Rig Operations & Equipment
Rig Operations & EquipmentRig Operations & Equipment
Rig Operations & Equipment
M.T.H Group
 
Crane 123
Crane 123Crane 123
Crane 123
Shivam patel
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
jdkskmdmdm
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
fijsekkdmdm2w
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
fskekkdmdmdm3e
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
zan2736ban
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
f8sejdkdmdijd
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
f8uesjdkdmdm
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
ufs89eodkdmdm
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
jdkskmmdmd1
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
pwg56547003
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
fujkskemdmdm4r
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
f7usuejkdkddm3
 
Caterpillar cat 325 d l excavator (prefix a3r) service repair manual (a3r0000...
Caterpillar cat 325 d l excavator (prefix a3r) service repair manual (a3r0000...Caterpillar cat 325 d l excavator (prefix a3r) service repair manual (a3r0000...
Caterpillar cat 325 d l excavator (prefix a3r) service repair manual (a3r0000...
hfjsejdkemmn
 
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
fujkskemdmdm4r
 
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
fijsekkdmdm2w
 
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
fskekkdmdmdm3e
 
Caterpillar cat 336 d l excavator (prefix ptb) service repair manual (ptb0000...
Caterpillar cat 336 d l excavator (prefix ptb) service repair manual (ptb0000...Caterpillar cat 336 d l excavator (prefix ptb) service repair manual (ptb0000...
Caterpillar cat 336 d l excavator (prefix ptb) service repair manual (ptb0000...
dueikdkmem
 

Similar to Lifting plan for inlet duct removal (20)

Rigging Engineering Basic
Rigging Engineering BasicRigging Engineering Basic
Rigging Engineering Basic
 
Rig Operations & Equipment
Rig Operations & EquipmentRig Operations & Equipment
Rig Operations & Equipment
 
US8231131
US8231131US8231131
US8231131
 
Crane 123
Crane 123Crane 123
Crane 123
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual Instant D...
 
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
Caterpillar Cat 325D L Excavator (Prefix A3R) Service Repair Manual (A3R00001...
 
Caterpillar cat 325 d l excavator (prefix a3r) service repair manual (a3r0000...
Caterpillar cat 325 d l excavator (prefix a3r) service repair manual (a3r0000...Caterpillar cat 325 d l excavator (prefix a3r) service repair manual (a3r0000...
Caterpillar cat 325 d l excavator (prefix a3r) service repair manual (a3r0000...
 
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
 
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
 
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
Caterpillar Cat 336D L Excavator (Prefix PTB) Service Repair Manual Instant D...
 
Caterpillar cat 336 d l excavator (prefix ptb) service repair manual (ptb0000...
Caterpillar cat 336 d l excavator (prefix ptb) service repair manual (ptb0000...Caterpillar cat 336 d l excavator (prefix ptb) service repair manual (ptb0000...
Caterpillar cat 336 d l excavator (prefix ptb) service repair manual (ptb0000...
 

Recently uploaded

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 

Recently uploaded (20)

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 

Lifting plan for inlet duct removal

  • 1. 2014 Prepared by Md. Shaha Jalal Mechanical Maintenance Technician A large multinational power generation company Lifting Plan for Inlet Duct removal
  • 2. Lifting Plan for Inlet duct Tools & equipment to be used: i. Manitowoc 4000 W Vicon Crawler Crane : 1 no. Purpose : To lift the load. Capacity : 150 ton ii. P&H (70 ton capacity) Crane (trailing crane) : 1 no. Purpose : To trail the load. Capacity : 70 ton iii. Trailer with Prime Mover. : 1 no. Purpose : To shift the load. Capacity : 50 ton Length : 20 m (65 feet) Width : 10 m (33 feet) iv. Chain Blocks : 3 nos. Purpose : To balance the load Capacity : 15 ton v. D-Shackles ,35 ton : 8 nos vi. D-Shackles ,25 ton : 4 nos vii. Wire Rope , 20 ton, length- 3 m (10 feet) : 16 nos viii. Wire Rope , 20 ton, length- 4 m (13 feet) : 8 nos ix. Wire Rope , 20 ton, length- 5 m(15 feet) : 16 nos x. Wire Rope , 20 ton, length- 6 m(26 feet) : 8 nos xi. Wire Rope , 20 ton, length- 9 m(30 feet) : 8 nos xii. Spreader Beam : 2 no. xiii. Hydraulic Jack, 100 ton : 4nos xiv. Nylon Rope (Tag Line) – Diameter 1 inch : 2 rolls xv. Warning Tape : 2 rolls xvi. Walkie -Talkie System of same channel : 4 sets
  • 3. Rigging Drawing for Lifting of Duct with 150 ton Crawler crane. Specification of crane: Load capacity (Max) : 150 ton Boom Length : 130 feet Counter Weight : 104.4 klb Distance from mass center of the load : 11.5 m (38 ft) Angle of boom : 73 degree. Specifications of rigging accessories: Spreader Beam: Safe working load : 42 ton Length : 8400 mm (27.552 ft) Width : 219 mm (8.61 Inc.) Required Quantity : 2 Nos Chain Block: Capacity : 15 ton Required Quantity : 2 nos + 1 spare Lifting lug: As per Appendix: 01 Wire sling: Capacity Length Qty 20 ton 3843 mm (13’) 02 20 ton 4500 mm(15’) 04 20 ton 8100 mm(26’) 02 Nylon Rope 1’’ --- 1 roll
  • 4. Detail Arrangement: All rigging accessories will be arranged as per drawing shown below. Fig: Rigging arrangement for lifting DT#01
  • 5. Lifting Procedure for DT#01: a. Place the 150 ton crane at 38 feet radius from the center line of the load. (annex:04) b. Hang the load with lifting accessories and lift up to 15 mm with the help of hydraulic jack at jacking position.( Annex:01) c. DT#01 will be lifted 42 ft from ground level. Boom Length : 130 ft Radius : 38 ft Angle of boom = Cos-1 (38ft/130ft) = 73 degree Available lifting height = 38 tan 73° = 124 ft Available lifting height: = 124 – Load height – Distance between touching point to boom top. = 124 – 35 – 47 = 42 ft Lifting accessories length: =37 ft Load Capacity : 40 ton (from load chart: annex 02) Load weight : 30 ton Accessories : 2 ton Total load weight : 32 ton
  • 6. d. Slowly move the crane backward (north to south) until just before the load touches DT#02. e. Swing the boom towards clockwise direction until just before the load touches steam pipe rack. f. Repeat procedure: d and procedure: e until DT#01 is removed from the slot of inlet duct, so that the crane can be mobilized (north to south) towards the trailer. g. When the crane comes at a position in line with EDG (emergency diesel generator), annex#04 and boom will be swung 180 degree clockwise to lay down on trailer with the help of trailing crane. h. Place the trailing crane beside (east side of trailer) and in line (east to west) with trailer. i. Hook up the trailing crane to lower lug with the help of wire sling as shown in the below arrangement. Fig: Rigging arrangement of trailer crane and main crane.
  • 7. j. The load will be tilted down by lowering the main crane and lifting up the trailing crane as shown in the below figure. Figure: Load placement on trailer. k. Trailer will be placed underneath the load and load will be put on the trailer bed. l. Trailer will be moved to storage area. m. In the storage area, DT#01 will be unloaded by two cranes (100 ton and 70 ton). Lifting Procedure for DT#02: a. Place the 150 ton crane from the center line of the load. (annex:04) b. Hang the load with lifting accessories and lift up to 15 mm with the help of hydraulic jack at jacking position.( Annex:01) c. DT#02 will be lifted to 25 ft from ground level.
  • 8. Figure: Lifting of DT#02 Boom Length : 130 ft Radius : 38 ft Angle of boom = Cos-1 (38ft/130ft) = 73 degree Available lifting height = 38 tan 73° = 124 ft Available lifting height: = 124 – Load height – Distance between touching point to boom top. = 124 – 49 – 50 = 25 ft Load Capacity : 37 ton (from load chart: annex 02) Load weight : 28 ton Accessories : 2 ton Total load weight : 30 ton Lifting accessories length= 37 ft
  • 9. d. Swing the boom towards clockwise direction and will stop the crane just before when load will touch the Gas turbine diffuser. e. Slowly move the crane backward (north to south) just before the load touches DT#03. f. Repeat procedure: d and procedure: e until DT#02 will be fully removed from the slot of inlet duct, so that the crane can be mobilized (north to south) towards the trailer. g. When the crane will come at a position in line with EDG ( emergency diesel generator), boom will be swung 180 degree clockwise to lay down on trailer with the help of trailing crane. h. Place the trailing crane beside (east side of trailer) and in line (east to west) with trailer as shown for DT#01. i. Hook up the trailing crane to lower lug with the help of wire sling. j. The load will be tilted down by lowering the main crane and lifting up the trailing crane as shown for DT#01. k. Trailer will be placed underneath the load and load will be put on the trailer bed. l. Trailer will be moved to storage area. m. In the storage area, DT#02 will be unloaded by two cranes (100 ton and 70 ton). Lifting Procedure for DT#03: a. Place the 150 ton crane from the center line of the load. (annex:04) Figure: Lifting of DT#03 b. Hang the load with lifting accessories and lift up to 15 mm with the help of hydraulic jack at jacking position.( Annex:03) c. DT#03 will be lifted 3.5 ft from ground level. Boom Length : 130 ft Radius : 38 ft Angle of boom = Cos-1 (38ft/130ft) = 73 degree Available lifting height = 38 tan 73° = 124 ft
  • 10. d. Slowly swing the crane clockwise (west to east) and will stop the crane just before when load will touch the Gas turbine diffuser. e. Swing the boom towards clockwise direction until the load become in line with the road. f. Slowly move the crane backward (north to south), so that the crane can be mobilized (north to south) towards the trailer. g. Load will be laid down on trailer with the help of trailing crane. h. Place the trailing crane beside (east side of trailer) and in line (east to west) with trailer as shown in the below arrangement same as DT#01. i. Hook up the trailing crane to lower lug with the help of wire sling. j. The load will be tilted down by lowering the main crane and lifting up the trailing crane as shown for DT#01. k. Trailer will be placed underneath the load and load will be put on the trailer bed. l. Trailer will be moved to storage area. m. In the storage area, DT#01 will be unloaded by two cranes (100 ton and 70 ton). Available lifting height: = 124 – Load height – Distance between touching point to boom top. = 124 – 68 – 52.5 =3.5ft Lifting accessories length= 38.3 ft Load Capacity : 40 ton (from load chart: annex 02) Load weight : 35 ton Accessories : 2 ton Total load weight : 37 ton
  • 11. Appendix-01: Figure: Spreader beam with lifting lug. Annex-01: Table: list of lifting accessories for DT#01 & DT#02 Name Size Qty. Wire Sling 20 ton x 13 ft 4pcs Wire Sling 20 ton x 15 ft 4pcs Wire Sling 20 ton x 26 ft 4pcs Spreader beam 8400 mm x 219mm 1pc Chain block 15 ton 2pcs Shackle 35 ton 4pcs
  • 12. Figure: Jacking Points of inlet Duct. Annex-02: Table-01: Load chart for 150 ton crane.
  • 13. Table -02: Load chart of 70 ton crane. Annex-03: Name Size Qty. Wire Sling 20 ton x 14 ft 4pcs Wire Sling 20 ton x 15 ft 4pcs Wire Sling 20 ton x 26 ft 4pcs Spreader beam 8.100 m x 219mm 1pc Chain block 15 ton 2pcs Shackle 35 ton 6pcs Table: lifting accessories for DT#03