SlideShare a Scribd company logo
PT. Escorindo Jasa Prima
METHOD OF WORKS FOR LIFTING
Stator Generator
By Stand Jack and Skid Roller
PLTU KALTIM TELUK BALIKPAPAN 2X110MW
Teluk Balikpapan Kalimantan Timur
Prepared by Review by Approved by Distribution
…
Rigging Engineer
…
…
…
SITE MANAGER
Master : Rigging
Origin : Client
Copies : CONST. DEPT
Rev. No. - BRIEF OF REVISION
Effective Date:
07 July 2015
√
√
√
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
2 of 22
REVISI:
-
TABLE OF CONTENT
TABLE OF CONTENT .......................................................................................................... 2
1. GENERAL...................................................................................................................... 3
2. PURPOSE ..................................................................................................................... 3
3. GENERAL NOTE........................................................................................................... 3
4. RESPONSIBILITY ......................................................................................................... 4
5. BASIC REQUIREMENT................................................................................................. 4
6. PREPARATION WORK ................................................................................................. 5
7. ORGANIZATION CHART .............................................................................................. 6
8. STATOR GENERATOR ERECTION SEQUENCE......................................................... 6
9. METHOD OF ERECTION OF STATOR GENERATOR.................................................. 7
10. FLOW CHART STATOR GENERATOR ON BASED.................................................. 8
11. PREPARATION WORKS: .......................................................................................... 9
12. LIFTING TOOLS ........................................................................................................ 9
13. RIGGING VIEW.......................................................................................................... 9
14. RIGGING EQUIPMENT............................................................................................ 19
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
3 of 22
REVISI:
-
1. GENERAL
This procedure provides information for the erection of Stator Generator PLTU
KALTIM TELUK BALIKPAPAN 2X110MW Teluk Balikpapan Kalimantan Timur
Project.
2. PURPOSE
This Procedure is to make sure that all people involve in the erection, assembly
and welding of Stator Generator activity understand and familiar to do the work
with quality control system for getting quality result as per client specification
and requirement, drawing, standard and code.
3. GENERAL NOTE
3.1.Inspection
As per the works required inspection, carry out inspection under attendance
of Superintendent / Engineer and as surreally record is result.
3.2.Safety
3.2.1. A safety officer presents all times Safety Briefing.
3.2.2. Job Safety Analysis (JSA) must be carried out for all crane lifts and all
other tasks that have potential risk to personnel of equipment.
3.2.3. Install scaffolding where necessary to install bolt in each beam and
member connection.
3.2.4. Pre lift study before any lifting activity.
3.2.5. Lift briefing and Safety briefing before any lift; assign responsibility to
all personnel involved. (Signalman, Rigger to crane driver, etc.)
3.2.6. Ensure all equipment required for installation is on hand and in
position before lift i.e. Chain blocks, Lever blocks, Podgy, Drifts,
Hammer, and Spanners. Etc.
3.2.7. Tag lines must be used to control lift.
3.2.8. Ground conditions must be ready before activities.
3.2.9. Set up safety rope around lifting area of Stator Generator area and
put notice board entered “KEEP OFF EXCEPT PERSONEL
CONCERNED”.
3.2.10. Lifting equipment should be in certification and tagged.
3.2.11. Crane and other machinery shall be inspected and certified.
3.3.Lifting
All conditions adapted to the Method of Works Install. Prior to
commencement of lifting works, assuredly carry out check of lifting
equipment.
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
4 of 22
REVISI:
-
3.4.Assembly and erection
Erection Stator Generator of accordance with the manuals and drawings.
4. RESPONSIBILITY
4.1.Chief Construction
Responsible for the overall planning, coordination and control of erection
work.
4.2.Field Engineer
Responsible for field erection work implementation and maintaining
acceptable quality standard.
4.3.Field Superintendent and Supervisor
Responsible for the actual performance of the erection crew and examine
the actual progress of work to ensure that it fit the drawing, specifications
and standards.
4.4.Quality Control Engineer
Responsible for monitor and inspect the erection activities to ensure it is
being done in compliance with procedure, ITP (Inspection and Test Plant),
drawing, Project specification and other reference standard document and
procedures.
4.5.Supporter Activities
These activities will support by Material Control, Quality Control, Welding
Section, and others section related with these activities.
5. BASIC REQUIREMENT
5.1.Schedule and Planning
Master schedule is usually provided by PT Adhi Karya. The detailed
schedule is prepared by Escorindo Jasa Prima according to his planning
which is based on PT Adhi Karya’s master schedule. The milestone and the
critical path can be identified which require proper planning. The sequence
of erection activities and the resources required is included in the planning.
5.2.Erection Drawing and Erection Manual
Erection drawing and manual usually provided by Vendor. The Field
Engineer and Superintendent shall check all drawings intended for Stator
Generator Erection. All the information required is completed and all
drawings shall be of latest revision.
5.3.Packing List
Packing List shall be provided by Vendor. This included all the listing of
materials, equipment and parts that are supplied.
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
5 of 22
REVISI:
-
The Packing List should indicate the quantity of the material and equipment
supplied and its specification as described in the erection drawing. This will
also indicate the size and the total weight of the component and the method
of storage. Also the packing number and material coding is very essential.
5.4.Storage Area and Warehouse
Upon a thorough check on the drawing and the packing list, the quantity of
materials and equipment is already known, including the method of storing,
the size of the storage area and the warehouse can be identifies.
5.5.Resources
Identification of resources is integral part of planning and scheduling is the
most essential part of the basic requirement in undertaking Structure Turbine
House in particular and in all jobs in general. Resources means, the
materials, labor and equipment needed to perform Structure Turbine House
Project.
6. PREPARATION WORK
6.1.Checking of Stator Generator Erection Drawings
This has to be done by the Chief Construction, Field Engineer,
Superintendent and Supervisor to determine the correct resources needed to
perform the job.
6.2.Checking of Client Supplied Material and Equipment
Checking and inspection of the materials and equipment including the spare
parts is to be done by the material control. He will make sure that all
materials, equipment and spare parts received from PT Adhi Karya, conform
to the quantity and the specifications started in the packing list or shipping.
6.3.Checking of Erection Materials, Equipment, Tools and Machinery
In the early stage of planning, these resources had been already identified.
The schedule of mobilization as on planned schedule made by the Chief
Construction and Engineer.
Checking of Labor
Labor requirement for every stage of erection job is prepared by the Chief
Engineer and his erection team, which is in accordance to their planning.
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
6 of 22
REVISI:
-
7. ORGANIZATION CHART
8. STATOR GENERATOR ERECTION SEQUENCE
It is assumed in this procedure that before starting the erection of the Stator
Generator, the supporting structure were already erected and checked by others
and clearance to proceed with the Stator Generator System erection had been
obtained.
The following sequences are for reference only. During actual field assembly,
refer to Method of Works Install and erection drawing (Rigging plan).
1. Install HaGun Gantry Crane, according to engineering drawing.
2. Install strand jack on position, according to engineering drawing.
3. Connects strand jack to stator generator by using recommended connector.
4. Lift by slowly stator generator until elevation 11000 mm top of level.
5. Moving horizontal HaGun Gantry Crane from start position to near of
foundation.
6. Replacing long foot to be short foot.
7. Move objet to foundation.
8. Degrading object until true position on the foundation.
9. Disconnect strand jack from stator generator.
10.Finishing works.
ORGANIZATION CHART
Stator Generator
By Stand Jack and Skidding Roller
PLTU KALTIM TELUK BALIKPAPAN 2X110MW
Teluk Balikpapan Kalimantan Timur
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
7 of 22
REVISI:
-
9. METHOD OF ERECTION OF STATOR GENERATOR
SRART
Control Position of Stator Generator
to be Lifted by Rigging Supervisor
Cleaning Stator Generator
Inspection Quality
by QC & Safety
NO
Connected all Sling for Lifting
YES
Lifting Stator Generator
by HaGun Gantry Crane
* From ELev. ±0.000
* To ELev. Target
Connected Stator Generator to Foundation
FINISH
METHOD OF
STATEMENT
PREPARINGACTIVITYINSITEERECTIONACTIVITY
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
8 of 22
REVISI:
-
10.FLOW CHART STATOR GENERATOR ON BASED
SRART
Control Position of Stator Generator
to be Lifted by Rigging Supervisor
Gantry Load Test, by using
Generator Lifting to elevation 250 mm up to ground floor
Inspection Quality
by QC & Safety
Repair
Lifting Stator Generator
by HaGun Gantry Crane
* From ELev. ±0.000
* To ELev. Target
Sliding Stator Generator
by HaGun Gantry Crane
to the proper position
Stator Generator Base on
Permanent Foundation
FINISH
Move Generator from Temporary
Laydown to Lifting area by Skidding
Stator Generator is Opening Cover
and Visual Check
Quality Inspection
by QC
Vendor Aproval
Connecting Sling to Stator Generator
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
9 of 22
REVISI:
-
11.PREPARATION WORKS:
Preparatory works such as strand guides and temporary scaffold access plat
form at top deck steel for jack operators and erectors and other levels access for
watchman at various elevations must be prepared in advance.
12.LIFTING TOOLS
1. Strand Jack capacities 200 ton : 4 unit
2. Skidding capacities 125 ton : 4 unit
3. Gantry capacities 200 ton : 1 unit
13.RIGGING VIEW
Figure 1
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
10 of 22
REVISI:
-
Figure 2
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
11 of 22
REVISI:
-
Figure 3
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
12 of 22
REVISI:
-
Figure 4
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
13 of 22
REVISI:
-
Figure 5
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
14 of 22
REVISI:
-
Figure 6
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
15 of 22
REVISI:
-
Figure 7
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
16 of 22
REVISI:
-
Figure 8
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
17 of 22
REVISI:
-
Figure 9
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
18 of 22
REVISI:
-
Figure 10
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
19 of 22
REVISI:
-
14.RIGGING EQUIPMENT
1. Strand Jack
Figure 11
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
20 of 22
REVISI:
-
Figure 12
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
21 of 22
REVISI:
-
Figure 13
PT. Escorindo Jasa Prima
Method of Works for Lifting
Stator Generator By Strand Jack
Document No:
Esco-RIG-HG-001
Date:
07 July 2015
PREPARED BY:
Rigging Department
APPROVED BY:
SITE MANAGER
Pages:
22 of 22
REVISI:
-
2. Skidding
Figure 14

More Related Content

What's hot

Rigging Engineering Basic
Rigging Engineering BasicRigging Engineering Basic
Rigging Engineering Basic
Badaruddin kendari
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
DusanJankovic8
 
Rigging & slinging
Rigging & slingingRigging & slinging
Rigging & slinging
Faizal Muhaini
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
Shaik Mohsin
 
Rigging
RiggingRigging
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
Surya Kant
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
List Supplier
 
Wrs rigging practice
Wrs rigging practiceWrs rigging practice
Wrs rigging practice
Luis Manuel Rodríguez
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
James McCann
 
Mobile crane inspector training student manual
Mobile crane inspector training   student manualMobile crane inspector training   student manual
Mobile crane inspector training student manual
Saul Ramirez
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
fcarlson
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
Paul Smith
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sites
Simon Faulkner-Duke
 
Lifting Operation.ppt
Lifting Operation.pptLifting Operation.ppt
Lifting Operation.ppt
ballabammoune1
 
Operating practices
Operating practicesOperating practices
Operating practices
ANA ISABEL R.R.
 
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANESB30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
ANA ISABEL R.R.
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
Rigger signalman handbook
Rigger  signalman handbookRigger  signalman handbook
Rigger signalman handbook
nhivan
 
Crane Hoist Operations
Crane Hoist OperationsCrane Hoist Operations
Crane Hoist Operations
KJP Consulting
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
hafiz abdul majid
 

What's hot (20)

Rigging Engineering Basic
Rigging Engineering BasicRigging Engineering Basic
Rigging Engineering Basic
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
 
Rigging & slinging
Rigging & slingingRigging & slinging
Rigging & slinging
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Rigging
RiggingRigging
Rigging
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
 
Wrs rigging practice
Wrs rigging practiceWrs rigging practice
Wrs rigging practice
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Mobile crane inspector training student manual
Mobile crane inspector training   student manualMobile crane inspector training   student manual
Mobile crane inspector training student manual
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sites
 
Lifting Operation.ppt
Lifting Operation.pptLifting Operation.ppt
Lifting Operation.ppt
 
Operating practices
Operating practicesOperating practices
Operating practices
 
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANESB30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
Rigger signalman handbook
Rigger  signalman handbookRigger  signalman handbook
Rigger signalman handbook
 
Crane Hoist Operations
Crane Hoist OperationsCrane Hoist Operations
Crane Hoist Operations
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 

Similar to Method of works install stator generator+strand jack + 07 july2015

Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
HaGun Gunawan
 
Erection method statement
Erection method statementErection method statement
Erection method statement
kanalbiru
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
mustafa hussain
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
Minh Bui Si
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
Katy A. Beitia G.
 
MS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfMS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdf
NajiRaheem2
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and fa
Al-Amin Ahmed Nabin
 
kolligars-I-1
kolligars-I-1kolligars-I-1
kolligars-I-1
kolligar situmorang
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)
Iqbal Mohammad
 
01.Nedumaran Instrument Engineer
01.Nedumaran Instrument Engineer01.Nedumaran Instrument Engineer
01.Nedumaran Instrument Engineer
T. Nedumaran
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
eSAT Publishing House
 
Kec training report
Kec training reportKec training report
Kec training report
Jasvinder Singh
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
Bruce Tharp
 
khaled-2
khaled-2khaled-2
Spe
SpeSpe
FUV CV
FUV CVFUV CV
Nes 362
Nes 362Nes 362
Nes 362
Prashant Naik
 
Technical Portfolio_2010 to 2017
Technical Portfolio_2010 to 2017Technical Portfolio_2010 to 2017
Technical Portfolio_2010 to 2017
Lukman Alhakim Wahid
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust
 
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Aestikani Mahani
 

Similar to Method of works install stator generator+strand jack + 07 july2015 (20)

Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
Erection method statement
Erection method statementErection method statement
Erection method statement
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
 
MS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfMS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdf
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and fa
 
kolligars-I-1
kolligars-I-1kolligars-I-1
kolligars-I-1
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)
 
01.Nedumaran Instrument Engineer
01.Nedumaran Instrument Engineer01.Nedumaran Instrument Engineer
01.Nedumaran Instrument Engineer
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
 
Kec training report
Kec training reportKec training report
Kec training report
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
 
khaled-2
khaled-2khaled-2
khaled-2
 
Spe
SpeSpe
Spe
 
FUV CV
FUV CVFUV CV
FUV CV
 
Nes 362
Nes 362Nes 362
Nes 362
 
Technical Portfolio_2010 to 2017
Technical Portfolio_2010 to 2017Technical Portfolio_2010 to 2017
Technical Portfolio_2010 to 2017
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
 

More from HaGun Gunawan

Grafik sondir 2007
Grafik sondir 2007Grafik sondir 2007
Grafik sondir 2007
HaGun Gunawan
 
Metode induksi HaGun institute
Metode induksi HaGun instituteMetode induksi HaGun institute
Metode induksi HaGun institute
HaGun Gunawan
 
X ref auto cad 2007+r4
X ref auto cad 2007+r4X ref auto cad 2007+r4
X ref auto cad 2007+r4
HaGun Gunawan
 
Ha gun treatment plant + pnup makassar+makalah
Ha gun treatment plant + pnup makassar+makalahHa gun treatment plant + pnup makassar+makalah
Ha gun treatment plant + pnup makassar+makalah
HaGun Gunawan
 
4jam menggambar rumah 3d
4jam menggambar rumah 3d4jam menggambar rumah 3d
4jam menggambar rumah 3d
HaGun Gunawan
 
Flow chart lifting plan+gantry+works
Flow chart lifting plan+gantry+worksFlow chart lifting plan+gantry+works
Flow chart lifting plan+gantry+works
HaGun Gunawan
 
Power Lift for Lifting Turbine+generator
Power Lift for Lifting Turbine+generatorPower Lift for Lifting Turbine+generator
Power Lift for Lifting Turbine+generator
HaGun Gunawan
 
13 detik membuat daftar isi di ms word 2007+r4.doc
13 detik membuat daftar isi di ms word 2007+r4.doc13 detik membuat daftar isi di ms word 2007+r4.doc
13 detik membuat daftar isi di ms word 2007+r4.doc
HaGun Gunawan
 
HaGun gantry crane
HaGun gantry craneHaGun gantry crane
HaGun gantry crane
HaGun Gunawan
 
Method of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanicsMethod of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanics
HaGun Gunawan
 
Steam drum lifting
Steam drum liftingSteam drum lifting
Steam drum lifting
HaGun Gunawan
 
HaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun treatment pl-ant-makalah-seminar di unjani bandungHaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun Gunawan
 
060 turbine+generator
060 turbine+generator060 turbine+generator
060 turbine+generator
HaGun Gunawan
 
062 generator+00 combine
062 generator+00 combine062 generator+00 combine
062 generator+00 combine
HaGun Gunawan
 
Catalyst coo ler north section 18march2014
Catalyst coo ler north section 18march2014Catalyst coo ler north section 18march2014
Catalyst coo ler north section 18march2014
HaGun Gunawan
 
Casing catalyst coo ler north section 18march2014
Casing catalyst coo ler north section 18march2014Casing catalyst coo ler north section 18march2014
Casing catalyst coo ler north section 18march2014
HaGun Gunawan
 
Sling and tailing+bundle
Sling and tailing+bundleSling and tailing+bundle
Sling and tailing+bundle
HaGun Gunawan
 

More from HaGun Gunawan (17)

Grafik sondir 2007
Grafik sondir 2007Grafik sondir 2007
Grafik sondir 2007
 
Metode induksi HaGun institute
Metode induksi HaGun instituteMetode induksi HaGun institute
Metode induksi HaGun institute
 
X ref auto cad 2007+r4
X ref auto cad 2007+r4X ref auto cad 2007+r4
X ref auto cad 2007+r4
 
Ha gun treatment plant + pnup makassar+makalah
Ha gun treatment plant + pnup makassar+makalahHa gun treatment plant + pnup makassar+makalah
Ha gun treatment plant + pnup makassar+makalah
 
4jam menggambar rumah 3d
4jam menggambar rumah 3d4jam menggambar rumah 3d
4jam menggambar rumah 3d
 
Flow chart lifting plan+gantry+works
Flow chart lifting plan+gantry+worksFlow chart lifting plan+gantry+works
Flow chart lifting plan+gantry+works
 
Power Lift for Lifting Turbine+generator
Power Lift for Lifting Turbine+generatorPower Lift for Lifting Turbine+generator
Power Lift for Lifting Turbine+generator
 
13 detik membuat daftar isi di ms word 2007+r4.doc
13 detik membuat daftar isi di ms word 2007+r4.doc13 detik membuat daftar isi di ms word 2007+r4.doc
13 detik membuat daftar isi di ms word 2007+r4.doc
 
HaGun gantry crane
HaGun gantry craneHaGun gantry crane
HaGun gantry crane
 
Method of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanicsMethod of induction in the process of mastering calculus in mechanics
Method of induction in the process of mastering calculus in mechanics
 
Steam drum lifting
Steam drum liftingSteam drum lifting
Steam drum lifting
 
HaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun treatment pl-ant-makalah-seminar di unjani bandungHaGun treatment pl-ant-makalah-seminar di unjani bandung
HaGun treatment pl-ant-makalah-seminar di unjani bandung
 
060 turbine+generator
060 turbine+generator060 turbine+generator
060 turbine+generator
 
062 generator+00 combine
062 generator+00 combine062 generator+00 combine
062 generator+00 combine
 
Catalyst coo ler north section 18march2014
Catalyst coo ler north section 18march2014Catalyst coo ler north section 18march2014
Catalyst coo ler north section 18march2014
 
Casing catalyst coo ler north section 18march2014
Casing catalyst coo ler north section 18march2014Casing catalyst coo ler north section 18march2014
Casing catalyst coo ler north section 18march2014
 
Sling and tailing+bundle
Sling and tailing+bundleSling and tailing+bundle
Sling and tailing+bundle
 

Recently uploaded

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 

Recently uploaded (20)

132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 

Method of works install stator generator+strand jack + 07 july2015

  • 1. PT. Escorindo Jasa Prima METHOD OF WORKS FOR LIFTING Stator Generator By Stand Jack and Skid Roller PLTU KALTIM TELUK BALIKPAPAN 2X110MW Teluk Balikpapan Kalimantan Timur Prepared by Review by Approved by Distribution … Rigging Engineer … … … SITE MANAGER Master : Rigging Origin : Client Copies : CONST. DEPT Rev. No. - BRIEF OF REVISION Effective Date: 07 July 2015 √ √ √
  • 2. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 2 of 22 REVISI: - TABLE OF CONTENT TABLE OF CONTENT .......................................................................................................... 2 1. GENERAL...................................................................................................................... 3 2. PURPOSE ..................................................................................................................... 3 3. GENERAL NOTE........................................................................................................... 3 4. RESPONSIBILITY ......................................................................................................... 4 5. BASIC REQUIREMENT................................................................................................. 4 6. PREPARATION WORK ................................................................................................. 5 7. ORGANIZATION CHART .............................................................................................. 6 8. STATOR GENERATOR ERECTION SEQUENCE......................................................... 6 9. METHOD OF ERECTION OF STATOR GENERATOR.................................................. 7 10. FLOW CHART STATOR GENERATOR ON BASED.................................................. 8 11. PREPARATION WORKS: .......................................................................................... 9 12. LIFTING TOOLS ........................................................................................................ 9 13. RIGGING VIEW.......................................................................................................... 9 14. RIGGING EQUIPMENT............................................................................................ 19
  • 3. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 3 of 22 REVISI: - 1. GENERAL This procedure provides information for the erection of Stator Generator PLTU KALTIM TELUK BALIKPAPAN 2X110MW Teluk Balikpapan Kalimantan Timur Project. 2. PURPOSE This Procedure is to make sure that all people involve in the erection, assembly and welding of Stator Generator activity understand and familiar to do the work with quality control system for getting quality result as per client specification and requirement, drawing, standard and code. 3. GENERAL NOTE 3.1.Inspection As per the works required inspection, carry out inspection under attendance of Superintendent / Engineer and as surreally record is result. 3.2.Safety 3.2.1. A safety officer presents all times Safety Briefing. 3.2.2. Job Safety Analysis (JSA) must be carried out for all crane lifts and all other tasks that have potential risk to personnel of equipment. 3.2.3. Install scaffolding where necessary to install bolt in each beam and member connection. 3.2.4. Pre lift study before any lifting activity. 3.2.5. Lift briefing and Safety briefing before any lift; assign responsibility to all personnel involved. (Signalman, Rigger to crane driver, etc.) 3.2.6. Ensure all equipment required for installation is on hand and in position before lift i.e. Chain blocks, Lever blocks, Podgy, Drifts, Hammer, and Spanners. Etc. 3.2.7. Tag lines must be used to control lift. 3.2.8. Ground conditions must be ready before activities. 3.2.9. Set up safety rope around lifting area of Stator Generator area and put notice board entered “KEEP OFF EXCEPT PERSONEL CONCERNED”. 3.2.10. Lifting equipment should be in certification and tagged. 3.2.11. Crane and other machinery shall be inspected and certified. 3.3.Lifting All conditions adapted to the Method of Works Install. Prior to commencement of lifting works, assuredly carry out check of lifting equipment.
  • 4. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 4 of 22 REVISI: - 3.4.Assembly and erection Erection Stator Generator of accordance with the manuals and drawings. 4. RESPONSIBILITY 4.1.Chief Construction Responsible for the overall planning, coordination and control of erection work. 4.2.Field Engineer Responsible for field erection work implementation and maintaining acceptable quality standard. 4.3.Field Superintendent and Supervisor Responsible for the actual performance of the erection crew and examine the actual progress of work to ensure that it fit the drawing, specifications and standards. 4.4.Quality Control Engineer Responsible for monitor and inspect the erection activities to ensure it is being done in compliance with procedure, ITP (Inspection and Test Plant), drawing, Project specification and other reference standard document and procedures. 4.5.Supporter Activities These activities will support by Material Control, Quality Control, Welding Section, and others section related with these activities. 5. BASIC REQUIREMENT 5.1.Schedule and Planning Master schedule is usually provided by PT Adhi Karya. The detailed schedule is prepared by Escorindo Jasa Prima according to his planning which is based on PT Adhi Karya’s master schedule. The milestone and the critical path can be identified which require proper planning. The sequence of erection activities and the resources required is included in the planning. 5.2.Erection Drawing and Erection Manual Erection drawing and manual usually provided by Vendor. The Field Engineer and Superintendent shall check all drawings intended for Stator Generator Erection. All the information required is completed and all drawings shall be of latest revision. 5.3.Packing List Packing List shall be provided by Vendor. This included all the listing of materials, equipment and parts that are supplied.
  • 5. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 5 of 22 REVISI: - The Packing List should indicate the quantity of the material and equipment supplied and its specification as described in the erection drawing. This will also indicate the size and the total weight of the component and the method of storage. Also the packing number and material coding is very essential. 5.4.Storage Area and Warehouse Upon a thorough check on the drawing and the packing list, the quantity of materials and equipment is already known, including the method of storing, the size of the storage area and the warehouse can be identifies. 5.5.Resources Identification of resources is integral part of planning and scheduling is the most essential part of the basic requirement in undertaking Structure Turbine House in particular and in all jobs in general. Resources means, the materials, labor and equipment needed to perform Structure Turbine House Project. 6. PREPARATION WORK 6.1.Checking of Stator Generator Erection Drawings This has to be done by the Chief Construction, Field Engineer, Superintendent and Supervisor to determine the correct resources needed to perform the job. 6.2.Checking of Client Supplied Material and Equipment Checking and inspection of the materials and equipment including the spare parts is to be done by the material control. He will make sure that all materials, equipment and spare parts received from PT Adhi Karya, conform to the quantity and the specifications started in the packing list or shipping. 6.3.Checking of Erection Materials, Equipment, Tools and Machinery In the early stage of planning, these resources had been already identified. The schedule of mobilization as on planned schedule made by the Chief Construction and Engineer. Checking of Labor Labor requirement for every stage of erection job is prepared by the Chief Engineer and his erection team, which is in accordance to their planning.
  • 6. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 6 of 22 REVISI: - 7. ORGANIZATION CHART 8. STATOR GENERATOR ERECTION SEQUENCE It is assumed in this procedure that before starting the erection of the Stator Generator, the supporting structure were already erected and checked by others and clearance to proceed with the Stator Generator System erection had been obtained. The following sequences are for reference only. During actual field assembly, refer to Method of Works Install and erection drawing (Rigging plan). 1. Install HaGun Gantry Crane, according to engineering drawing. 2. Install strand jack on position, according to engineering drawing. 3. Connects strand jack to stator generator by using recommended connector. 4. Lift by slowly stator generator until elevation 11000 mm top of level. 5. Moving horizontal HaGun Gantry Crane from start position to near of foundation. 6. Replacing long foot to be short foot. 7. Move objet to foundation. 8. Degrading object until true position on the foundation. 9. Disconnect strand jack from stator generator. 10.Finishing works. ORGANIZATION CHART Stator Generator By Stand Jack and Skidding Roller PLTU KALTIM TELUK BALIKPAPAN 2X110MW Teluk Balikpapan Kalimantan Timur
  • 7. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 7 of 22 REVISI: - 9. METHOD OF ERECTION OF STATOR GENERATOR SRART Control Position of Stator Generator to be Lifted by Rigging Supervisor Cleaning Stator Generator Inspection Quality by QC & Safety NO Connected all Sling for Lifting YES Lifting Stator Generator by HaGun Gantry Crane * From ELev. ±0.000 * To ELev. Target Connected Stator Generator to Foundation FINISH METHOD OF STATEMENT PREPARINGACTIVITYINSITEERECTIONACTIVITY
  • 8. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 8 of 22 REVISI: - 10.FLOW CHART STATOR GENERATOR ON BASED SRART Control Position of Stator Generator to be Lifted by Rigging Supervisor Gantry Load Test, by using Generator Lifting to elevation 250 mm up to ground floor Inspection Quality by QC & Safety Repair Lifting Stator Generator by HaGun Gantry Crane * From ELev. ±0.000 * To ELev. Target Sliding Stator Generator by HaGun Gantry Crane to the proper position Stator Generator Base on Permanent Foundation FINISH Move Generator from Temporary Laydown to Lifting area by Skidding Stator Generator is Opening Cover and Visual Check Quality Inspection by QC Vendor Aproval Connecting Sling to Stator Generator
  • 9. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 9 of 22 REVISI: - 11.PREPARATION WORKS: Preparatory works such as strand guides and temporary scaffold access plat form at top deck steel for jack operators and erectors and other levels access for watchman at various elevations must be prepared in advance. 12.LIFTING TOOLS 1. Strand Jack capacities 200 ton : 4 unit 2. Skidding capacities 125 ton : 4 unit 3. Gantry capacities 200 ton : 1 unit 13.RIGGING VIEW Figure 1
  • 10. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 10 of 22 REVISI: - Figure 2
  • 11. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 11 of 22 REVISI: - Figure 3
  • 12. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 12 of 22 REVISI: - Figure 4
  • 13. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 13 of 22 REVISI: - Figure 5
  • 14. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 14 of 22 REVISI: - Figure 6
  • 15. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 15 of 22 REVISI: - Figure 7
  • 16. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 16 of 22 REVISI: - Figure 8
  • 17. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 17 of 22 REVISI: - Figure 9
  • 18. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 18 of 22 REVISI: - Figure 10
  • 19. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 19 of 22 REVISI: - 14.RIGGING EQUIPMENT 1. Strand Jack Figure 11
  • 20. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 20 of 22 REVISI: - Figure 12
  • 21. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 21 of 22 REVISI: - Figure 13
  • 22. PT. Escorindo Jasa Prima Method of Works for Lifting Stator Generator By Strand Jack Document No: Esco-RIG-HG-001 Date: 07 July 2015 PREPARED BY: Rigging Department APPROVED BY: SITE MANAGER Pages: 22 of 22 REVISI: - 2. Skidding Figure 14