SlideShare a Scribd company logo
An Energy & Environment
Conscious, Sustainable &
Prosperous Organization
SESA STERLITE LTD
4X600 MW IPP
1
Power Business Overview
Location Capacity
Jharsuguda IPP 4X600 MW
Jharsuguda CPP 9X135 MW
TSPL 3X650 MW
4X600 MW IPP Jharsuguda (Supplied by SEPCO -III)
Boiler Make HBC China
TG DFPS China
2
Sesa Sterlite – Power Overview
Contributing to India’s Energy
Security
An Energy & Environment Conscious Sustainable Organization
PROJECT - BOILER MODIFICATION FOR RELIABILITY AND
STATION HEAT RATE IMPROVEMENT
3
4X600 MW INDEPENDENT POWER PLANT
 First 600 MW Power Plant of Odisha
 ESP – FF Hybrid precipitator maintaining SPM < 50 mg/Nm3
 Plant supplied by SEPCO-III China (Boiler- Harbin , Turbine- DFPS)
 Plant equipped with modern online performance and combustion
Optimisation softwares.
 IPP has got accreditation with EnMS 50001:2011 , EMS 14001:2004 ,
QMS 9001:2008 and OHSAS 18001:2007 to ensure sustainability .
 Opportunities identified and executed for efficiency and reliability
4
5
Milestone
Particulars U#1 U#2 U#3 U#4
1st Light up 20-Dec-10 12-Jun-10 20-May-11 19-Feb-12
Date of
Synchronization
27-Dec-10 10-Aug-10 9-Jul-11 29-Mar-12
Date of Achieving
Full Load
28-Dec-10 14-Oct-10 16-Aug-11 25-April-12
Date of COD 30-Mar-11 9-Nov-10 19-Aug-11 26-Apr-12
MILESTONES OF SSL , JHARSUGUDA
 Guaranteed Station Heat Rate achieved in all the Units
 Saving Potential in SHR identified in three parameters
 High Superheat Spray 150 TPH w.r.t 65 TPH (rated)
 High Reheat Spray 33 TPH w.r.t 0 TPH (rated)
 Less RH Steam Temperature 525 w.r.t 538 DegC
 High metal temperature excursion causing tube failures
 Difficult to Control Operating Parameter With Top Mill
Operation.
6
OPPORTUNITIES IN BOILER
BOILER DETAILS
Boiler Make The China Harbin Boilers co. Ltd
Boiler Type
Subcritical , Reheat, Single Furnace ,
Single Reheat , Forced Circulation ,
Balanced Draft , Dry bottom ,
Tangential corner fired pulverised Fuel
Fired
SH Outlet Steam pressure (MPa) 17.5
Design Temp (DegC) 541
Boiler Capacity (TPH) 2060
RH Steam Outlet Pressure (MPa) 3.8
RH Steam Temperature (DegC) 541
Fuel consumption (TPH) 433
7
 Losses identified at early stage
 Initiatives started to counter the problem
 Combustion Experts Dr. V T Satyanathan (Ex-BHEL) conducted study
 Combustion Experts of Squam Power Plant Technical Consultancy
engaged for optimisation
 STEAG Germany combustion optimisation software installed
 Online trials conducted and detailed study carried out
8
CORRECTIVE MEASURES
 Trials conducted since 2011 to Dec 2012 mainly focused on
 (i) SADC tuning
 (ii) Burner Tilts
 (iii) OFA damper regulations
 (iv) Soot Blowing Optimisation
 Trials Conducted but desired result could not be achieved with
above Trials.
 Conclusion: SSL insisted Sepco-III to study and provide solution.
9
ENGAGEMENT OF HBC- OEM
 Sepco-III depuetd Combustion expert from Harbin Boiler
 Trial Conducted by Harbin Experts from 4-18th December 2012
 Operation and combustion expert exercised all the possible
combinations
 CONCLUSION :
 Improvement in performance parameter not achieved
 Harbin suspected the variation in fuel was leading to deviations
 Harbin referred the problem to design institute for review and solution.
10
Review and Proposal
 Design institute recommended modification
 Harbin proposed modification in three zones of boiler
 Reduction of Surface area of LTSH from 12944 to 7696 m2
 Reduction of radiation side wall Re-Heater width from 8191 to6268
mm
 Increase of Economiser surface from 215000ft2 to 277000 ft2
 Boiler efficiency and SHR will remain unaffected.
 All the performance test will be carried out after modification.
11
Review and Approval of Project
 SSL & Ex-BHEL design expert Mr. Sivaraman Krishnamurthy
reviewed the proposed modification
 Proposal review meeting held at Harbin China in March 2013.
 Challenge of pressure part alteration in limited access reviewed
 Unit outage for longer time > 60 Days
 Directorate of Factories & Boiler reviewed and approved the
project
 SSL approved the project anticipating long term gain in
Conservation of natural resource and reduction in carbon
emission.
12
REMOVAL OF PRESSURE PART
 Material received within 3 months of project approval from China
 120 Nos. tube Reheat radiation wall removed from each side
 Water wall LTRH headers replaced with new headers
 Lower group of LTSH Removed
13
Cutting of LTRH
Tube and Header
Removal of LTRH
Header
Economiser Tube
cutting
ERECTION OF PRESSURE PART
 Erection methodology was prepared by Harbin & Sepco-III
 Job safety analysis carried out in detail
 Each lifting tools to be used in project tested before
commencement of project
14
Steam Cleaning of
Tubes
Erection of
Economiser Coil
Lifting of water wall panel
through bottom ash
hopper
Erection of Pressure Part
 Detailed Quality assurance plan to ensure quality work
 Radiography conducted in 100% joint in RH and LTSH area
 Radiography in 20% joint of Economiser.
15
Readiness for
position eco tube
Economiser coil in
position
PROJECT – Boiler Modification
 First modification started in Boiler of Unit#3 w.e.f 12th July 2013
 Modification carried out during scheduled annual overhaul of Unit-3
 Sepco-III executed the modification project
 Material was supplied from China in short duration of 3 months
16
Removal of LTRH
Header Fitment of new
LTRH Header
Erection of new
LTRH link pipe
PROJECT – Boiler Modification
 Manpower engaged 250
 No of Days for project completion - 60
 Cost of Project Rs 500 millions INR
 No of Welding Joints 3485
17
Lifting of Economiser Coil Addition of Economiser bank New Added Economiser bank
Re-Commissioning & Demonstration
 Detailed programme prepared for Boiler flushing
 Flushing continued for 3 Days to bring the parameters in limits
 Post-modification demonstration carried out for
 Boiler Efficiency test
 Boiler efficiency test at design and worst coal
 Demonstration for Zero Reheat spray and rated Super heater spray
 Demonstration for top mill and bottom mill operation
 Reliability test for design unit load ramp up and ramp down
 14 Days reliability run by OEM
All the tests were successfully completed
18
Boiler Parameters After Modification
19
S.No Parameter Description UOM Design
Before
Modificatio
n
After
Modificatio
n
1 Power Generation MW 600 599 601
2 Coal flow TPH 420 411 383
3 Main Steam Pressure Mpa 16.7 16.37 16.66
4 Main steam Temperature DegC 538 539 539
5 RH steam Temperature DegC 538 536 538
6 RH Steam Pressure MPa 3.8 3.61 3.49
7 SH Spray TPH 65 150 66
8 RH Spray TPH 0 25 0
 SH Spray Reduced from 150 TPH to 66 TPH
 RH Spray Reduced from 33 TPH to Zero
 Top Mills Service operation became normal operation
 Improvement in SHR of 14Kcal/KWH achieved
 SHR Improvement contributed to saving of 87000 MT of coal per
annum
 Reduction in CO2 emission by 2.3 lacs MT emission due to
improvement in SHR.
20
Result Summary
CALCULATION OF GAIN AFTER MODIFICATION
S.No.
IMPROVEMENT
AREA
UOM
Before
Modification
After
Modification
Improve
ment
Gain in
Heat
Rate
(Kcal/K
wh)
Net Saving
in Millions
(INR)Per
annum
Net
Saving
of Fuel
Per
Annum
(MT)
1 Av . Power Generation MW 600 600 0 0 0 0
2 Reheat Temperature DegC 525 538 13 6.7 24 10534
3 Reheat Spray % 2.4 0 2.4 7 26 11088
4 SH Spray % 8.6 3.5 5.1 0.12 0.44 190
Total Savings Per unit per Annum (@90% PLF , 3000 Kcal/Kg GCV) 50 21812
Total Saving Per Annum for 4X600 MW 201 87247
21
Thank You
22

More Related Content

What's hot

Methanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownMethanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut Down
Gerard B. Hawkins
 
METHANOL PRODUCTION USING VULCAN SYSTEMS COMBINED REFORMING TECHNOLOGY (ATR) ...
METHANOL PRODUCTION USING VULCAN SYSTEMS COMBINED REFORMING TECHNOLOGY (ATR) ...METHANOL PRODUCTION USING VULCAN SYSTEMS COMBINED REFORMING TECHNOLOGY (ATR) ...
METHANOL PRODUCTION USING VULCAN SYSTEMS COMBINED REFORMING TECHNOLOGY (ATR) ...
Gerard B. Hawkins
 
IATF PPT.pdf
IATF PPT.pdfIATF PPT.pdf
IATF PPT.pdf
puneetyadav159342
 
Revamps for Ageing Methanol Plants
Revamps for Ageing Methanol PlantsRevamps for Ageing Methanol Plants
Revamps for Ageing Methanol Plants
Gerard B. Hawkins
 
Plant maintenance
Plant maintenancePlant maintenance
Plant maintenance
Jainam Mehta
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
Mahendra K SHUKLA
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer Design
Gerard B. Hawkins
 
Flue Gas Desulphurization
Flue Gas DesulphurizationFlue Gas Desulphurization
Flue Gas Desulphurization
TusharRathore11
 
Turbine compressor introduction
Turbine compressor introductionTurbine compressor introduction
Turbine compressor introduction
Furqan Pakot
 
16 big losses for manufacturing and services
16 big losses for manufacturing and services16 big losses for manufacturing and services
16 big losses for manufacturing and services
Vishy Chandra
 
SYNGAS CONDITIONING UNIT FEASIBILITY CASE STUDY: COAL-TO-LIQUIDS
SYNGAS CONDITIONING UNIT FEASIBILITY CASE STUDY: COAL-TO-LIQUIDSSYNGAS CONDITIONING UNIT FEASIBILITY CASE STUDY: COAL-TO-LIQUIDS
SYNGAS CONDITIONING UNIT FEASIBILITY CASE STUDY: COAL-TO-LIQUIDS
Gerard B. Hawkins
 
Critical Success Factors for ERP
Critical Success Factors for ERPCritical Success Factors for ERP
Critical Success Factors for ERP
Glen Alleman
 
Feedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsFeedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen Plants
Gerard B. Hawkins
 
Scheduled Shutdown Maintenance
Scheduled Shutdown MaintenanceScheduled Shutdown Maintenance
Scheduled Shutdown Maintenancejdparfett
 
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu HozenAim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
avijit biswas
 
Pre-reformer Operations Technical Supplement
Pre-reformer Operations Technical SupplementPre-reformer Operations Technical Supplement
Pre-reformer Operations Technical Supplement
Gerard B. Hawkins
 
AMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdfAMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdf
PremBaboo4
 
Aiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumAiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumSatria Sakata
 

What's hot (20)

Methanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownMethanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut Down
 
METHANOL PRODUCTION USING VULCAN SYSTEMS COMBINED REFORMING TECHNOLOGY (ATR) ...
METHANOL PRODUCTION USING VULCAN SYSTEMS COMBINED REFORMING TECHNOLOGY (ATR) ...METHANOL PRODUCTION USING VULCAN SYSTEMS COMBINED REFORMING TECHNOLOGY (ATR) ...
METHANOL PRODUCTION USING VULCAN SYSTEMS COMBINED REFORMING TECHNOLOGY (ATR) ...
 
IATF PPT.pdf
IATF PPT.pdfIATF PPT.pdf
IATF PPT.pdf
 
Revamps for Ageing Methanol Plants
Revamps for Ageing Methanol PlantsRevamps for Ageing Methanol Plants
Revamps for Ageing Methanol Plants
 
Plant maintenance
Plant maintenancePlant maintenance
Plant maintenance
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer Design
 
Flue Gas Desulphurization
Flue Gas DesulphurizationFlue Gas Desulphurization
Flue Gas Desulphurization
 
Turbine compressor introduction
Turbine compressor introductionTurbine compressor introduction
Turbine compressor introduction
 
16 big losses for manufacturing and services
16 big losses for manufacturing and services16 big losses for manufacturing and services
16 big losses for manufacturing and services
 
SYNGAS CONDITIONING UNIT FEASIBILITY CASE STUDY: COAL-TO-LIQUIDS
SYNGAS CONDITIONING UNIT FEASIBILITY CASE STUDY: COAL-TO-LIQUIDSSYNGAS CONDITIONING UNIT FEASIBILITY CASE STUDY: COAL-TO-LIQUIDS
SYNGAS CONDITIONING UNIT FEASIBILITY CASE STUDY: COAL-TO-LIQUIDS
 
Critical Success Factors for ERP
Critical Success Factors for ERPCritical Success Factors for ERP
Critical Success Factors for ERP
 
Feedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsFeedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen Plants
 
Scheduled Shutdown Maintenance
Scheduled Shutdown MaintenanceScheduled Shutdown Maintenance
Scheduled Shutdown Maintenance
 
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu HozenAim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
 
Pre-reformer Operations Technical Supplement
Pre-reformer Operations Technical SupplementPre-reformer Operations Technical Supplement
Pre-reformer Operations Technical Supplement
 
AMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdfAMMONIA PLANT MATERIAL BALANCE.pdf
AMMONIA PLANT MATERIAL BALANCE.pdf
 
Aiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumAiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agrium
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
Book on Total Productive Maintenance
Book on Total Productive Maintenance Book on Total Productive Maintenance
Book on Total Productive Maintenance
 

Similar to Boiler Modification for SHR & Reliability Improvement SSL (IPP)

Paper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmizationPaper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmization
CANDHARE
 
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Global CCS Institute
 
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
Global CCS Institute
 
Jisc con optimisation, improved sustainability across the estate through us...
Jisc   con optimisation, improved sustainability across the estate through us...Jisc   con optimisation, improved sustainability across the estate through us...
Jisc con optimisation, improved sustainability across the estate through us...JISC's Green ICT Programme
 
Assement of-bag-filter-vs-esp-cpcb
Assement of-bag-filter-vs-esp-cpcbAssement of-bag-filter-vs-esp-cpcb
Assement of-bag-filter-vs-esp-cpcb
mkpq pasha
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
somnathmahapatra6
 
Another 30 years, thermal power plant R&M
Another 30 years, thermal power plant R&M  Another 30 years, thermal power plant R&M
Another 30 years, thermal power plant R&M Santosh Pardhi
 
India study i g c c
India study i g c cIndia study i g c c
India study i g c c
H Janardan Prabhu
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
UK Carbon Capture and Storage Research Centre
 
METHANOL PLANT ARC RETROFIT Case Study
METHANOL PLANT ARC RETROFIT Case StudyMETHANOL PLANT ARC RETROFIT Case Study
METHANOL PLANT ARC RETROFIT Case Study
Gerard B. Hawkins
 
Prajwal Patil
Prajwal PatilPrajwal Patil
Prajwal Patil
raman rangari
 
Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009
Shaun West
 
A practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reductionA practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reduction
EECO2
 
Partial List of Past SAVvy Engineering Projects
Partial List of Past SAVvy Engineering ProjectsPartial List of Past SAVvy Engineering Projects
Partial List of Past SAVvy Engineering ProjectsScott Vierstra
 
FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...
FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...
FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...
Umer Azeem
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
Aditya Narain
 
Steve Davidson Engineering Resume
Steve Davidson Engineering  ResumeSteve Davidson Engineering  Resume
Steve Davidson Engineering ResumeStephen Davidson
 
Adoption of supercritical technology (1)
Adoption of supercritical technology (1)Adoption of supercritical technology (1)
Adoption of supercritical technology (1)
HARSHIT GUPTA
 
Resume of operation specialist - Copy
Resume of operation specialist - CopyResume of operation specialist - Copy
Resume of operation specialist - CopyBirendra Barnwal
 

Similar to Boiler Modification for SHR & Reliability Improvement SSL (IPP) (20)

Paper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmizationPaper cid-furnace-feed-maxmization
Paper cid-furnace-feed-maxmization
 
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
 
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
 
Jisc con optimisation, improved sustainability across the estate through us...
Jisc   con optimisation, improved sustainability across the estate through us...Jisc   con optimisation, improved sustainability across the estate through us...
Jisc con optimisation, improved sustainability across the estate through us...
 
Assement of-bag-filter-vs-esp-cpcb
Assement of-bag-filter-vs-esp-cpcbAssement of-bag-filter-vs-esp-cpcb
Assement of-bag-filter-vs-esp-cpcb
 
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.pptAPP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
 
Resume yogesh
Resume yogeshResume yogesh
Resume yogesh
 
Another 30 years, thermal power plant R&M
Another 30 years, thermal power plant R&M  Another 30 years, thermal power plant R&M
Another 30 years, thermal power plant R&M
 
India study i g c c
India study i g c cIndia study i g c c
India study i g c c
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
METHANOL PLANT ARC RETROFIT Case Study
METHANOL PLANT ARC RETROFIT Case StudyMETHANOL PLANT ARC RETROFIT Case Study
METHANOL PLANT ARC RETROFIT Case Study
 
Prajwal Patil
Prajwal PatilPrajwal Patil
Prajwal Patil
 
Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009
 
A practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reductionA practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reduction
 
Partial List of Past SAVvy Engineering Projects
Partial List of Past SAVvy Engineering ProjectsPartial List of Past SAVvy Engineering Projects
Partial List of Past SAVvy Engineering Projects
 
FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...
FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...
FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
Steve Davidson Engineering Resume
Steve Davidson Engineering  ResumeSteve Davidson Engineering  Resume
Steve Davidson Engineering Resume
 
Adoption of supercritical technology (1)
Adoption of supercritical technology (1)Adoption of supercritical technology (1)
Adoption of supercritical technology (1)
 
Resume of operation specialist - Copy
Resume of operation specialist - CopyResume of operation specialist - Copy
Resume of operation specialist - Copy
 

Recently uploaded

Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Orkestra
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
IP ServerOne
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
Vladimir Samoylov
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
eCommerce Institute
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Sebastiano Panichella
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
Faculty of Medicine And Health Sciences
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
Howard Spence
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
Sebastiano Panichella
 
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
khadija278284
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
OECD Directorate for Financial and Enterprise Affairs
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Access Innovations, Inc.
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
faizulhassanfaiz1670
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Matjaž Lipuš
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Sebastiano Panichella
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
OWASP Beja
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
Access Innovations, Inc.
 

Recently uploaded (16)

Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
 
International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
 
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
 

Boiler Modification for SHR & Reliability Improvement SSL (IPP)

  • 1. An Energy & Environment Conscious, Sustainable & Prosperous Organization SESA STERLITE LTD 4X600 MW IPP 1
  • 2. Power Business Overview Location Capacity Jharsuguda IPP 4X600 MW Jharsuguda CPP 9X135 MW TSPL 3X650 MW 4X600 MW IPP Jharsuguda (Supplied by SEPCO -III) Boiler Make HBC China TG DFPS China 2 Sesa Sterlite – Power Overview Contributing to India’s Energy Security An Energy & Environment Conscious Sustainable Organization
  • 3. PROJECT - BOILER MODIFICATION FOR RELIABILITY AND STATION HEAT RATE IMPROVEMENT 3
  • 4. 4X600 MW INDEPENDENT POWER PLANT  First 600 MW Power Plant of Odisha  ESP – FF Hybrid precipitator maintaining SPM < 50 mg/Nm3  Plant supplied by SEPCO-III China (Boiler- Harbin , Turbine- DFPS)  Plant equipped with modern online performance and combustion Optimisation softwares.  IPP has got accreditation with EnMS 50001:2011 , EMS 14001:2004 , QMS 9001:2008 and OHSAS 18001:2007 to ensure sustainability .  Opportunities identified and executed for efficiency and reliability 4
  • 5. 5 Milestone Particulars U#1 U#2 U#3 U#4 1st Light up 20-Dec-10 12-Jun-10 20-May-11 19-Feb-12 Date of Synchronization 27-Dec-10 10-Aug-10 9-Jul-11 29-Mar-12 Date of Achieving Full Load 28-Dec-10 14-Oct-10 16-Aug-11 25-April-12 Date of COD 30-Mar-11 9-Nov-10 19-Aug-11 26-Apr-12 MILESTONES OF SSL , JHARSUGUDA
  • 6.  Guaranteed Station Heat Rate achieved in all the Units  Saving Potential in SHR identified in three parameters  High Superheat Spray 150 TPH w.r.t 65 TPH (rated)  High Reheat Spray 33 TPH w.r.t 0 TPH (rated)  Less RH Steam Temperature 525 w.r.t 538 DegC  High metal temperature excursion causing tube failures  Difficult to Control Operating Parameter With Top Mill Operation. 6 OPPORTUNITIES IN BOILER
  • 7. BOILER DETAILS Boiler Make The China Harbin Boilers co. Ltd Boiler Type Subcritical , Reheat, Single Furnace , Single Reheat , Forced Circulation , Balanced Draft , Dry bottom , Tangential corner fired pulverised Fuel Fired SH Outlet Steam pressure (MPa) 17.5 Design Temp (DegC) 541 Boiler Capacity (TPH) 2060 RH Steam Outlet Pressure (MPa) 3.8 RH Steam Temperature (DegC) 541 Fuel consumption (TPH) 433 7
  • 8.  Losses identified at early stage  Initiatives started to counter the problem  Combustion Experts Dr. V T Satyanathan (Ex-BHEL) conducted study  Combustion Experts of Squam Power Plant Technical Consultancy engaged for optimisation  STEAG Germany combustion optimisation software installed  Online trials conducted and detailed study carried out 8 CORRECTIVE MEASURES
  • 9.  Trials conducted since 2011 to Dec 2012 mainly focused on  (i) SADC tuning  (ii) Burner Tilts  (iii) OFA damper regulations  (iv) Soot Blowing Optimisation  Trials Conducted but desired result could not be achieved with above Trials.  Conclusion: SSL insisted Sepco-III to study and provide solution. 9
  • 10. ENGAGEMENT OF HBC- OEM  Sepco-III depuetd Combustion expert from Harbin Boiler  Trial Conducted by Harbin Experts from 4-18th December 2012  Operation and combustion expert exercised all the possible combinations  CONCLUSION :  Improvement in performance parameter not achieved  Harbin suspected the variation in fuel was leading to deviations  Harbin referred the problem to design institute for review and solution. 10
  • 11. Review and Proposal  Design institute recommended modification  Harbin proposed modification in three zones of boiler  Reduction of Surface area of LTSH from 12944 to 7696 m2  Reduction of radiation side wall Re-Heater width from 8191 to6268 mm  Increase of Economiser surface from 215000ft2 to 277000 ft2  Boiler efficiency and SHR will remain unaffected.  All the performance test will be carried out after modification. 11
  • 12. Review and Approval of Project  SSL & Ex-BHEL design expert Mr. Sivaraman Krishnamurthy reviewed the proposed modification  Proposal review meeting held at Harbin China in March 2013.  Challenge of pressure part alteration in limited access reviewed  Unit outage for longer time > 60 Days  Directorate of Factories & Boiler reviewed and approved the project  SSL approved the project anticipating long term gain in Conservation of natural resource and reduction in carbon emission. 12
  • 13. REMOVAL OF PRESSURE PART  Material received within 3 months of project approval from China  120 Nos. tube Reheat radiation wall removed from each side  Water wall LTRH headers replaced with new headers  Lower group of LTSH Removed 13 Cutting of LTRH Tube and Header Removal of LTRH Header Economiser Tube cutting
  • 14. ERECTION OF PRESSURE PART  Erection methodology was prepared by Harbin & Sepco-III  Job safety analysis carried out in detail  Each lifting tools to be used in project tested before commencement of project 14 Steam Cleaning of Tubes Erection of Economiser Coil Lifting of water wall panel through bottom ash hopper
  • 15. Erection of Pressure Part  Detailed Quality assurance plan to ensure quality work  Radiography conducted in 100% joint in RH and LTSH area  Radiography in 20% joint of Economiser. 15 Readiness for position eco tube Economiser coil in position
  • 16. PROJECT – Boiler Modification  First modification started in Boiler of Unit#3 w.e.f 12th July 2013  Modification carried out during scheduled annual overhaul of Unit-3  Sepco-III executed the modification project  Material was supplied from China in short duration of 3 months 16 Removal of LTRH Header Fitment of new LTRH Header Erection of new LTRH link pipe
  • 17. PROJECT – Boiler Modification  Manpower engaged 250  No of Days for project completion - 60  Cost of Project Rs 500 millions INR  No of Welding Joints 3485 17 Lifting of Economiser Coil Addition of Economiser bank New Added Economiser bank
  • 18. Re-Commissioning & Demonstration  Detailed programme prepared for Boiler flushing  Flushing continued for 3 Days to bring the parameters in limits  Post-modification demonstration carried out for  Boiler Efficiency test  Boiler efficiency test at design and worst coal  Demonstration for Zero Reheat spray and rated Super heater spray  Demonstration for top mill and bottom mill operation  Reliability test for design unit load ramp up and ramp down  14 Days reliability run by OEM All the tests were successfully completed 18
  • 19. Boiler Parameters After Modification 19 S.No Parameter Description UOM Design Before Modificatio n After Modificatio n 1 Power Generation MW 600 599 601 2 Coal flow TPH 420 411 383 3 Main Steam Pressure Mpa 16.7 16.37 16.66 4 Main steam Temperature DegC 538 539 539 5 RH steam Temperature DegC 538 536 538 6 RH Steam Pressure MPa 3.8 3.61 3.49 7 SH Spray TPH 65 150 66 8 RH Spray TPH 0 25 0
  • 20.  SH Spray Reduced from 150 TPH to 66 TPH  RH Spray Reduced from 33 TPH to Zero  Top Mills Service operation became normal operation  Improvement in SHR of 14Kcal/KWH achieved  SHR Improvement contributed to saving of 87000 MT of coal per annum  Reduction in CO2 emission by 2.3 lacs MT emission due to improvement in SHR. 20 Result Summary
  • 21. CALCULATION OF GAIN AFTER MODIFICATION S.No. IMPROVEMENT AREA UOM Before Modification After Modification Improve ment Gain in Heat Rate (Kcal/K wh) Net Saving in Millions (INR)Per annum Net Saving of Fuel Per Annum (MT) 1 Av . Power Generation MW 600 600 0 0 0 0 2 Reheat Temperature DegC 525 538 13 6.7 24 10534 3 Reheat Spray % 2.4 0 2.4 7 26 11088 4 SH Spray % 8.6 3.5 5.1 0.12 0.44 190 Total Savings Per unit per Annum (@90% PLF , 3000 Kcal/Kg GCV) 50 21812 Total Saving Per Annum for 4X600 MW 201 87247 21