SlideShare a Scribd company logo
1 of 15
Download to read offline
2016
Kamilan, Idzuari Azli
MSc Asset Management & Maintenance
1/5/2016
Economic Analysis for Boiler
Acquisition in MLNG 1
Debottlenecking Project
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
1 | P a g e
Table of Contents
Abstract ................................................................................................................................................... 2
1.0 Introduction....................................................................................................................................... 3
1.1 Problem Statement ....................................................................................................................... 4
1.2 Objective........................................................................................................................................ 4
1.3 Scope ............................................................................................................................................. 4
2.0 Literature Review .............................................................................................................................. 5
2.1 Performing an Engineering Economy Study.................................................................................. 6
2.2 Definitions ..................................................................................................................................... 7
2.2.1 Cash Flows.............................................................................................................................. 7
2.2.2 Minimum Attractive Rate of Return (MARR) ......................................................................... 7
2.2.3 Present Worth (PW) ............................................................................................................... 7
2.2.4 Future Worth (FW)................................................................................................................. 7
2.2.5 Annual Worth (AW)................................................................................................................ 8
3.0 Methodology..................................................................................................................................... 9
4.0 Data Presentation............................................................................................................................ 10
5.0 Results and Discussion .................................................................................................................... 11
5.1 Analyzing Investment Alternatives by Using Equivalent Worth.................................................. 11
6.0 Conclusion ....................................................................................................................................... 13
7.0 References....................................................................................................................................... 14
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
2 | P a g e
Abstract
Malaysia Liquified Natural Gas Satu Sdn Bhd (MLNG 1) is producing super cooled natural gas at -160
degC by converting natural gas in gas form into liquid form (LNG). MLNG is owned and part of
Petronas group of business. This LNG is stored in LNG storage tank before transport into LNG cargo
for import to Japan, Korea, China, etc. Once the cargo reach imported country LNG receiving terminal,
the LNG will be transported to LNG Storage Tank before converting it back to Natural Gas in Gas form
for power generation usage.
Recently, MLNG 1 management instructed for MLNG 1 debottlenecking study to be carried out. The
objective of the study is to identify equipments/units in MLNG 1 process and utilities area which
debottleneck the whole LNG process from producing LNG as per its design 8.4 million tonnes of LNG
per annum (mpta). MLNG debottlencking study was successfully done with assistance from Petronas
GTS 2 months ago. 15 equipments/units was identified in the MLNG Satu debottlenecking report.
However, it is worth to note that insufficient steam from Boiler for steam generator contribute 50%
from total debottleneck. Based on this finding, MLNG 1 management decided that all 15
equipments/units shall be done with additional 2 Boilers was identified as top priority.
The aim of this project is to apply principles in engineering economics to assess the options in the
acquisition the 2 Boilers and give recommendation to MLNG 1 management for decision making in
choosing most economicall feasbile Boilers in MLNG 1 Debottlenecking project.
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
3 | P a g e
1.0 Introduction
A boiler is water containing vessel which transfers heat from a fuel source (oil, gas, coal) into steam
which is piped to a point where it can be used to run production equipment, to sterilize, provide heat,
to steam-clean, etc.
The energy given up by the steam is sufficient to convert it back into the form of water. When 100%
of the steam produced is returned to be reused, the system is called a closed system. Examples of
closed systems are closed steam heating, hot water heating, and "one-pipe" systems.
Since some processes can contaminate the steam, so it is not always desirable to feed the
condensate back into the boiler. A system that does not return the condensate is called an open
system.
The two main types of boilers are:
 Firetube - the fire or hot gases are directed through the inside of tubes within the boiler shell,
which are surrounded by water. The tubes are arranged in banks so that the gases can be
passed through the boiler up to 4 times before passing out the stack. This system exposes
the maximum heat transfer surface to the water. Firetube boilers are also known as shell
boilers and can produce up to approximately 750 hp or 25,000 lbs of steam per hour. 80% of
boilers in use are of this configuration.
 Watertube - the fire or hot gases are directed to and around the outside of tubes containing
water, arranged in a vertical position. Watertube boilers are usually rectangular in shape and
have two or more drums. The separation of steam and water takes place in the top drum,
while the bottom drum serves as a collection point for sludge. This system is usually used
when more than 750 hp or several hundred thousand lbs of steam per hour, are needed.
Malaysia Liquified Natural Gas Satu Sdn Bhd (MLNG 1) is producing super cooled natural gas at -160
degC by converting natural gas in gas form into liquid form (LNG). MLNG is owned and part of
Petronas group of business. This LNG is stored in LNG storage tank before transport into LNG cargo
for import to Japan, Korea, China, etc. Once the cargo reach imported country LNG receiving terminal,
the LNG will be transported to LNG Storage Tank before converting it back to Natural Gas in Gas form
for power generation usage.
Engineering economy involves the systematic evaluation of the economic merits of proposed
solutions to engineering problems. To be economically acceptable that is affordable, solutions to
engineering problems must demonstrate a positive balance of long-term benefits over long-term
costs, and they must also;
 promote the well-being and survival of an organization,
 embody creative and innovative technology and ideas,
 permit identification and scrutiny of their estimated outcomes, and
 translate profitability to the “bottom line” through a valid and acceptable measure of merit.
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
4 | P a g e
1.1 Problem Statement
MLNG 1 management acknowledge that MLNG 1 is not producing at 100% plant design capacity.
Recently, MLNG 1 management instructed for MLNG 1 debottlenecking study to be carried out. The
objective of the study is to identify equipments/units in MLNG 1 process and utilities area which
debottleneck the whole LNG process from producing LNG as per its design 8.4 million tonnes of LNG
per annum (mpta).
MLNG debottlencking study was successfully done with assistance from Petronas GTS 2 months ago.
15 equipments/units was identified in the MLNG Satu debottlenecking report. However, it is worth to
note that insufficient steam from Boiler for steam generator contribute 50% from total debottleneck.
Based on this finding, MLNG 1 management decided that all 15 equipments/units shall be done with
Boilers as top priority. Additional 2 boilers are required to be installed in 2 years time from MLNG 1
Debottlenecking report.
MLNG Debottlenecking Project Management team (PMT) was formed to undertake this
debottlenecking project. An engineering team study many Boiler alternatives available in the market
that the PMT can choose from. PMT should aware of each alternative machine has to offer
economically before acquire any of the alternatives.
1.2 Objective
The objective of this project paper is to apply principles in engineering economics to assess the
options in the acquisition the 2 Boilers and give recommendation to MLNG 1 management for
decision making in choosing most economically feasbile Boilers in MLNG 1 Debottlenecking project.
1.3 Scope
Since the objective of this project is to run an economic analysis, it is important to specify the scope
of the analysis. The scope will be comparing 3 alternatives with methods as follow;
 Analyzing investment alternatives by using equivalent worth method
 Analyzing cost-only alternatives by using equivalent worth method
 Rate-of-return method: Incremental analysis for investment alternatives
Three of basic methods for analyzing cash flows will be used in this project paper;
 Present worth (PW)
 Annual worth (AW)
 Future worth (FW)
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
5 | P a g e
2.0 Literature Review
Engineering economy involves formulating, estimating, and evaluating the expected economic
outcomes of alternatives designed to accomplish a defined purpose. Mathematical techniques
simplify the economic evaluation of alternatives.
The need for engineering economy is primarily motivated by the work that engineers do in
performing analyses, synthesizing, and coming to a conclusion as they work on projects of all sizes. In
other words, engineering economy is at the heart of making decisions. These decisions involve the
fundamental elements of cash flows of money, time, and interest rates.
Decisions are made routinely to choose one alternative over another by individuals in everyday life;
by engineers on the job; by managers who supervise the activities of others; by corporate presidents
who operate a business; and by government officials who work for the public good. Most decisions
involve money, called capital or capital funds, which is usually limited in amount. The decision of
where and how to invest this limited capital is motivated by a primary goal of adding value as future,
anticipated results of the selected alternative are realized. Engineers play a vital role in capital
investment decisions based upon their ability and experience to design, analyze, and synthesize.
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
6 | P a g e
2.1 Performing an Engineering Economy Study
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
7 | P a g e
2.2 Definitions
The equations and procedures of engineering economy utilize many terms and notations.
2.2.1 Cash Flows
Engineering economy bases its computations on the timing, size, and direction of cash flows. Cash
inflows are the receipts, revenues, incomes, and savings generated by project and business activity. A
plus sign indicates a cash inflow. Cash outflows are costs, disbursements, expenses, and taxes caused
by projects and business activity. A negative or minus sign indicates a cash outflow. When a project
involves only costs, the minus sign may be omitted for some techniques, such as benefit/cost analysis.
A cash flow diagram is a very important tool in an economic analysis, especially when the cash flow
series is complex. It is a graphical representation of cash flows drawn on the y axis with a time scale
on the x axis. The diagram includes what is known, what is estimated, and what is needed.
2.2.2 Minimum Attractive Rate of Return (MARR)
The Minimum Attractive Rate of Return (MARR) is a reasonable rate of return established for the
evaluation and selection of alternatives. A project is not economically viable unless it is expected to
return at least the MARR. MARR is also referred to as the hurdle rate, cutoff rate, benchmark rate,
and minimum acceptable rate of return.
2.2.3 Present Worth (PW)
The PW method is based on the concept of equivalent worth of all cash flows relative to some base
or beginning point in time called the present. All cash inflows and outflows are discounted to the
present point in time at an interest rate that is generally the MARR. A positive PW for an investment
project is an amount of profit over the inimum amount required by investors.
2.2.4 Future Worth (FW)
The FW is based on the equivalent worth of all cash inflows and outflows at the end of the study
period at an interest rate that is generally MARR. The economic information provided by the FW
method is very useful in capital investment decision situations.
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
8 | P a g e
2.2.5 Annual Worth (AW)
The AW of a project is an equal annual series of money amounts, for a stated study period, that is
equivalent to the cash inflows and outflows at an interest rate that is generally MARR.
AW = PW(A/P, i%, N) = FW(A/F, i%, N)
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
9 | P a g e
3.0 Methodology
DTSB has given these information for the purpose of this study;
MARR = 5% annually
Study period = 20 years
Therefore, the above reference values shall be used throughout the analysis. Assessing the
investment feasibility and profitability and recommending to management on making the best
decision, methods below will be carried out in this project paper;
1. Summary of information regarding each alternatives will be presented based on collected
data. Information such as capital investment, annual operating cost, annual labor cost and
annual power maintenance cost for each alternatives are important and will be presented in
a simple table.
2. Analyzing investment alternatives by using equivalent worth method will be conducted.
The respective values of PW, AW, FW will be computed.
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
10 | P a g e
4.0 Data Presentation
MLNG 1 Debottlenecking Project Team has gathered necessary data and made the following table for
the expected inflow and outflow on each water jet cutting equipment system.
The data were collected from many sources such as consultants, contractors, and original equipment
manufacturers.
MLNG 1 Debottlenecking Project Team provided the values of expected annual revenue for the study
period of 20 years for each alternative. All values are in Ringgit Malaysia (RM).
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
11 | P a g e
5.0 Results and Discussion
The most straightforward technique for comparing mutually exclusive alternatives when all useful
lives are equal to the study period is to determine the equivalent worth of each alternative based on
total investment at i = MARR. Then, for the investment alternatives, the one with the greatest
positive equivalent worth is selected. And, in the case of cost alternatives, the one with the least
negative equivalent worth is selected.
5.1 Analyzing Investment Alternatives by Using
Equivalent Worth
Present worth (PW) for each alternatives;
PW(5%)A = – 987,440 + (300,450 – 185,000)(P/A, 5%, 20)
= – 987,440 + 115,450(P/A, 5%, 20)
= – 987,440 + 115,450(12.4622)
= + RM 451,321.00
PW(5%)B = – 1,468,393+ (512,940– 290,000)(P/A, 5%, 20)
= – 1,468,393+ 222,940(P/A, 5%, 20)
= – 1,468,393+ 222,940(12.4622)
= + RM 1,309,930.00
PW(5%)C = – 2,109,039+ (647,380– 430,000) (P/A, 5%, 20)
= – 2,109,039+ 217,380 (P/A, 5%, 20)
= – 2,109,039+ 217,380 (12.4622)
= + RM 599,994.00
From the PW method, we can see that all of the alternatives are positive with B has the largest value
(+ RM 1,309,930.00)
Present worth (FW) for each alternatives;
FW(5%)A = PW(5%)A x (F/P, 5%, 20)
= RM 451,321.00 x 2.6533
= + RM 1,197,490.00
FW(5%)B = PW(5%)B x (F/P, 5%, 20)
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
12 | P a g e
= RM 1,309,930.00 x 2.6533
= + RM 3,475,637.27
FW(5%)C = FW(5%)C x (F/P, 5%, 20)
= RM 599,994.00 x 2.6533
= + RM 1,591,964.08
Based on the FW method, the choice is B because it has the largest value.
Annual worth (AW) for each alternatives;
FW(5%)A = PW(5%)A x (A/P, 5%, 20)
= RM 451,321.00 x 0.0802
= + RM 36,195.94
FW(5%)B = PW(5%)B x (A/P, 5%, 20)
= RM 1,309,930.00 x 0.0802
= + RM 105,056.39
FW(5%)C = FW(5%)C x (A/P, 5%, 20)
= RM 599,994.00 x 0.0802
= + RM 48,115.50
Alternative B again is chosen as it has the largest AW value compared to others.
PW, FW and FW for all Boiler A, B and C is summarised as above.
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
13 | P a g e
6.0 Conclusion
From the analysis, Boiler B is the most preferred alternative to be acquired by the company.
This recommendation is based on its PW, FW and AW.
Therefore, it is recommended that MLNG 1 management to choose Boiler B to be acquired for MLNG
1 Debottlenecking project.
Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016
14 | P a g e
7.0 References
Sullivan, Wicks, and Koelling. Engineering Economics, Fifteen Ed. Essex,
England: Pearson Education Limited, 2012
Blank, and Tarquin. Engineering Economy, Seventh Ed. 1221 Avenue of the
Americas, New York: McGraw-Hill, 2012

More Related Content

What's hot

SMID_016_AeroderivativeGTsforLNGPlants
SMID_016_AeroderivativeGTsforLNGPlantsSMID_016_AeroderivativeGTsforLNGPlants
SMID_016_AeroderivativeGTsforLNGPlants
Dexter Vaz
 
Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014
John Glenning
 
Studies of performance and emission characteristics of compressed natural gas...
Studies of performance and emission characteristics of compressed natural gas...Studies of performance and emission characteristics of compressed natural gas...
Studies of performance and emission characteristics of compressed natural gas...
IOSR Journals
 
M2G May 2015 GTI Presentation
M2G May 2015 GTI PresentationM2G May 2015 GTI Presentation
M2G May 2015 GTI Presentation
Charles Rice
 
Ig system & equipment oil tankers
Ig system &  equipment oil tankersIg system &  equipment oil tankers
Ig system & equipment oil tankers
jabbar2002pk200
 

What's hot (20)

Summer training report
Summer training reportSummer training report
Summer training report
 
Palmer international consulting_presentation_ertc_brussels_2014 (5)
Palmer international consulting_presentation_ertc_brussels_2014 (5)Palmer international consulting_presentation_ertc_brussels_2014 (5)
Palmer international consulting_presentation_ertc_brussels_2014 (5)
 
SMID_016_AeroderivativeGTsforLNGPlants
SMID_016_AeroderivativeGTsforLNGPlantsSMID_016_AeroderivativeGTsforLNGPlants
SMID_016_AeroderivativeGTsforLNGPlants
 
Winter 2015 pioga meeting all4
Winter 2015 pioga meeting   all4Winter 2015 pioga meeting   all4
Winter 2015 pioga meeting all4
 
Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014Velocys ppt140813_ENFL-ACS_2014
Velocys ppt140813_ENFL-ACS_2014
 
1 palmer international consulting_presentation_artc_singapore_2014 (10)
1 palmer international consulting_presentation_artc_singapore_2014 (10)1 palmer international consulting_presentation_artc_singapore_2014 (10)
1 palmer international consulting_presentation_artc_singapore_2014 (10)
 
Renovation
RenovationRenovation
Renovation
 
WORD FORMAT PROJECT REPORT ON VARIOUS MECHANICAL UNITS INVOLVED IN THE BOTTLI...
WORD FORMAT PROJECT REPORT ON VARIOUS MECHANICAL UNITS INVOLVED IN THE BOTTLI...WORD FORMAT PROJECT REPORT ON VARIOUS MECHANICAL UNITS INVOLVED IN THE BOTTLI...
WORD FORMAT PROJECT REPORT ON VARIOUS MECHANICAL UNITS INVOLVED IN THE BOTTLI...
 
Studies of performance and emission characteristics of compressed natural gas...
Studies of performance and emission characteristics of compressed natural gas...Studies of performance and emission characteristics of compressed natural gas...
Studies of performance and emission characteristics of compressed natural gas...
 
REFERENCE 2015
REFERENCE 2015REFERENCE 2015
REFERENCE 2015
 
Virtual pipelines 201: Industrial CNG Applications Beyond the Pipeline
Virtual pipelines 201: Industrial CNG Applications Beyond the PipelineVirtual pipelines 201: Industrial CNG Applications Beyond the Pipeline
Virtual pipelines 201: Industrial CNG Applications Beyond the Pipeline
 
New technology evaluation for SAGD facilities in oil sands
New technology evaluation for SAGD facilities in oil sandsNew technology evaluation for SAGD facilities in oil sands
New technology evaluation for SAGD facilities in oil sands
 
M2G May 2015 GTI Presentation
M2G May 2015 GTI PresentationM2G May 2015 GTI Presentation
M2G May 2015 GTI Presentation
 
Ig system & equipment oil tankers
Ig system &  equipment oil tankersIg system &  equipment oil tankers
Ig system & equipment oil tankers
 
Aircraft propulsion fuel injection
Aircraft propulsion   fuel injectionAircraft propulsion   fuel injection
Aircraft propulsion fuel injection
 
Project services offering (november 2016)
Project services offering (november 2016)Project services offering (november 2016)
Project services offering (november 2016)
 
Bioprocessing Presentation
Bioprocessing PresentationBioprocessing Presentation
Bioprocessing Presentation
 
March 2014 World Oil: Greener completions advance in the Marcellus
March 2014 World Oil: Greener completions advance in the MarcellusMarch 2014 World Oil: Greener completions advance in the Marcellus
March 2014 World Oil: Greener completions advance in the Marcellus
 
The Gas Recovery System Presentation
The Gas Recovery System PresentationThe Gas Recovery System Presentation
The Gas Recovery System Presentation
 
GAIL(India)Ltd.,PATA Petrochemical Complex
GAIL(India)Ltd.,PATA Petrochemical Complex GAIL(India)Ltd.,PATA Petrochemical Complex
GAIL(India)Ltd.,PATA Petrochemical Complex
 

Viewers also liked

kizomba A & B FWP engine overhaul project
kizomba A &  B FWP engine overhaul projectkizomba A &  B FWP engine overhaul project
kizomba A & B FWP engine overhaul project
Helio De Oliveira
 
Alpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAlpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan Sample
Agatha Maia Duarte de Assis
 
Sample project plan
Sample project planSample project plan
Sample project plan
mamoonnift
 

Viewers also liked (10)

Boiler Pressure Parts,SEAM INDUSTRIES LIMITED
Boiler Pressure Parts,SEAM INDUSTRIES LIMITEDBoiler Pressure Parts,SEAM INDUSTRIES LIMITED
Boiler Pressure Parts,SEAM INDUSTRIES LIMITED
 
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
Boiler Modification for SHR & Reliability Improvement  SSL (IPP)Boiler Modification for SHR & Reliability Improvement  SSL (IPP)
Boiler Modification for SHR & Reliability Improvement SSL (IPP)
 
Manufacturing Design Change
Manufacturing Design ChangeManufacturing Design Change
Manufacturing Design Change
 
kizomba A & B FWP engine overhaul project
kizomba A &  B FWP engine overhaul projectkizomba A &  B FWP engine overhaul project
kizomba A & B FWP engine overhaul project
 
project report for vocational trainee
project report for vocational traineeproject report for vocational trainee
project report for vocational trainee
 
Steam drum lifting
Steam drum liftingSteam drum lifting
Steam drum lifting
 
Alpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAlpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan Sample
 
Sample project plan
Sample project planSample project plan
Sample project plan
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to Boilers
 
Sample project plan
Sample project planSample project plan
Sample project plan
 

Similar to SFB5012 Project Paper May 16-G03178 Idzuari Azli

Methanol Reforming fuel cell
Methanol Reforming fuel cellMethanol Reforming fuel cell
Methanol Reforming fuel cell
Tao Ye
 
Lifting Solution For Compressor House
Lifting Solution For Compressor HouseLifting Solution For Compressor House
Lifting Solution For Compressor House
Samuel Farley
 
Project Report on Analysis of Boiler- Aditya
Project Report on Analysis of Boiler- AdityaProject Report on Analysis of Boiler- Aditya
Project Report on Analysis of Boiler- Aditya
Aditya Bhattacharjee
 
Improving steam boiler operating efficiency
Improving steam boiler operating efficiencyImproving steam boiler operating efficiency
Improving steam boiler operating efficiency
matsoh
 

Similar to SFB5012 Project Paper May 16-G03178 Idzuari Azli (20)

ntpc
ntpcntpc
ntpc
 
The resilience, inclusion or life cycle costing issues for a combined cycle p...
The resilience, inclusion or life cycle costing issues for a combined cycle p...The resilience, inclusion or life cycle costing issues for a combined cycle p...
The resilience, inclusion or life cycle costing issues for a combined cycle p...
 
Ong-Art CV 170208
Ong-Art CV 170208Ong-Art CV 170208
Ong-Art CV 170208
 
Internship saad
Internship saadInternship saad
Internship saad
 
Installation & Working of Coal Fired Thermal Power Plant
Installation & Working of Coal Fired Thermal Power PlantInstallation & Working of Coal Fired Thermal Power Plant
Installation & Working of Coal Fired Thermal Power Plant
 
Climate change due to fart and energy alternatives
Climate change due to fart and energy alternativesClimate change due to fart and energy alternatives
Climate change due to fart and energy alternatives
 
Methanol Reforming fuel cell
Methanol Reforming fuel cellMethanol Reforming fuel cell
Methanol Reforming fuel cell
 
Hydrogen refuelling dispensing station model
Hydrogen refuelling dispensing station model Hydrogen refuelling dispensing station model
Hydrogen refuelling dispensing station model
 
CV-cassidy
CV-cassidyCV-cassidy
CV-cassidy
 
FINAL REPORT (4)
FINAL REPORT (4)FINAL REPORT (4)
FINAL REPORT (4)
 
2009 ceftf tsinghua ccs clean coal report ccs guidelines for china and coal c...
2009 ceftf tsinghua ccs clean coal report ccs guidelines for china and coal c...2009 ceftf tsinghua ccs clean coal report ccs guidelines for china and coal c...
2009 ceftf tsinghua ccs clean coal report ccs guidelines for china and coal c...
 
Air pre heater
Air pre heaterAir pre heater
Air pre heater
 
Lifting Solution For Compressor House
Lifting Solution For Compressor HouseLifting Solution For Compressor House
Lifting Solution For Compressor House
 
Deck on consultancy, training and audits v0.1
Deck on consultancy, training and audits v0.1Deck on consultancy, training and audits v0.1
Deck on consultancy, training and audits v0.1
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Project Report on Analysis of Boiler- Aditya
Project Report on Analysis of Boiler- AdityaProject Report on Analysis of Boiler- Aditya
Project Report on Analysis of Boiler- Aditya
 
“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...“Towards net zero: extracting energy from flooded coal mines for heating and ...
“Towards net zero: extracting energy from flooded coal mines for heating and ...
 
Improving steam boiler operating efficiency
Improving steam boiler operating efficiencyImproving steam boiler operating efficiency
Improving steam boiler operating efficiency
 
Improving steam boiler operating efficiency
Improving steam boiler operating efficiencyImproving steam boiler operating efficiency
Improving steam boiler operating efficiency
 
Noncatalytic methane conversion technology in the microwave plasma torch by p...
Noncatalytic methane conversion technology in the microwave plasma torch by p...Noncatalytic methane conversion technology in the microwave plasma torch by p...
Noncatalytic methane conversion technology in the microwave plasma torch by p...
 

SFB5012 Project Paper May 16-G03178 Idzuari Azli

  • 1. 2016 Kamilan, Idzuari Azli MSc Asset Management & Maintenance 1/5/2016 Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project
  • 2. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 1 | P a g e Table of Contents Abstract ................................................................................................................................................... 2 1.0 Introduction....................................................................................................................................... 3 1.1 Problem Statement ....................................................................................................................... 4 1.2 Objective........................................................................................................................................ 4 1.3 Scope ............................................................................................................................................. 4 2.0 Literature Review .............................................................................................................................. 5 2.1 Performing an Engineering Economy Study.................................................................................. 6 2.2 Definitions ..................................................................................................................................... 7 2.2.1 Cash Flows.............................................................................................................................. 7 2.2.2 Minimum Attractive Rate of Return (MARR) ......................................................................... 7 2.2.3 Present Worth (PW) ............................................................................................................... 7 2.2.4 Future Worth (FW)................................................................................................................. 7 2.2.5 Annual Worth (AW)................................................................................................................ 8 3.0 Methodology..................................................................................................................................... 9 4.0 Data Presentation............................................................................................................................ 10 5.0 Results and Discussion .................................................................................................................... 11 5.1 Analyzing Investment Alternatives by Using Equivalent Worth.................................................. 11 6.0 Conclusion ....................................................................................................................................... 13 7.0 References....................................................................................................................................... 14
  • 3. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 2 | P a g e Abstract Malaysia Liquified Natural Gas Satu Sdn Bhd (MLNG 1) is producing super cooled natural gas at -160 degC by converting natural gas in gas form into liquid form (LNG). MLNG is owned and part of Petronas group of business. This LNG is stored in LNG storage tank before transport into LNG cargo for import to Japan, Korea, China, etc. Once the cargo reach imported country LNG receiving terminal, the LNG will be transported to LNG Storage Tank before converting it back to Natural Gas in Gas form for power generation usage. Recently, MLNG 1 management instructed for MLNG 1 debottlenecking study to be carried out. The objective of the study is to identify equipments/units in MLNG 1 process and utilities area which debottleneck the whole LNG process from producing LNG as per its design 8.4 million tonnes of LNG per annum (mpta). MLNG debottlencking study was successfully done with assistance from Petronas GTS 2 months ago. 15 equipments/units was identified in the MLNG Satu debottlenecking report. However, it is worth to note that insufficient steam from Boiler for steam generator contribute 50% from total debottleneck. Based on this finding, MLNG 1 management decided that all 15 equipments/units shall be done with additional 2 Boilers was identified as top priority. The aim of this project is to apply principles in engineering economics to assess the options in the acquisition the 2 Boilers and give recommendation to MLNG 1 management for decision making in choosing most economicall feasbile Boilers in MLNG 1 Debottlenecking project.
  • 4. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 3 | P a g e 1.0 Introduction A boiler is water containing vessel which transfers heat from a fuel source (oil, gas, coal) into steam which is piped to a point where it can be used to run production equipment, to sterilize, provide heat, to steam-clean, etc. The energy given up by the steam is sufficient to convert it back into the form of water. When 100% of the steam produced is returned to be reused, the system is called a closed system. Examples of closed systems are closed steam heating, hot water heating, and "one-pipe" systems. Since some processes can contaminate the steam, so it is not always desirable to feed the condensate back into the boiler. A system that does not return the condensate is called an open system. The two main types of boilers are:  Firetube - the fire or hot gases are directed through the inside of tubes within the boiler shell, which are surrounded by water. The tubes are arranged in banks so that the gases can be passed through the boiler up to 4 times before passing out the stack. This system exposes the maximum heat transfer surface to the water. Firetube boilers are also known as shell boilers and can produce up to approximately 750 hp or 25,000 lbs of steam per hour. 80% of boilers in use are of this configuration.  Watertube - the fire or hot gases are directed to and around the outside of tubes containing water, arranged in a vertical position. Watertube boilers are usually rectangular in shape and have two or more drums. The separation of steam and water takes place in the top drum, while the bottom drum serves as a collection point for sludge. This system is usually used when more than 750 hp or several hundred thousand lbs of steam per hour, are needed. Malaysia Liquified Natural Gas Satu Sdn Bhd (MLNG 1) is producing super cooled natural gas at -160 degC by converting natural gas in gas form into liquid form (LNG). MLNG is owned and part of Petronas group of business. This LNG is stored in LNG storage tank before transport into LNG cargo for import to Japan, Korea, China, etc. Once the cargo reach imported country LNG receiving terminal, the LNG will be transported to LNG Storage Tank before converting it back to Natural Gas in Gas form for power generation usage. Engineering economy involves the systematic evaluation of the economic merits of proposed solutions to engineering problems. To be economically acceptable that is affordable, solutions to engineering problems must demonstrate a positive balance of long-term benefits over long-term costs, and they must also;  promote the well-being and survival of an organization,  embody creative and innovative technology and ideas,  permit identification and scrutiny of their estimated outcomes, and  translate profitability to the “bottom line” through a valid and acceptable measure of merit.
  • 5. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 4 | P a g e 1.1 Problem Statement MLNG 1 management acknowledge that MLNG 1 is not producing at 100% plant design capacity. Recently, MLNG 1 management instructed for MLNG 1 debottlenecking study to be carried out. The objective of the study is to identify equipments/units in MLNG 1 process and utilities area which debottleneck the whole LNG process from producing LNG as per its design 8.4 million tonnes of LNG per annum (mpta). MLNG debottlencking study was successfully done with assistance from Petronas GTS 2 months ago. 15 equipments/units was identified in the MLNG Satu debottlenecking report. However, it is worth to note that insufficient steam from Boiler for steam generator contribute 50% from total debottleneck. Based on this finding, MLNG 1 management decided that all 15 equipments/units shall be done with Boilers as top priority. Additional 2 boilers are required to be installed in 2 years time from MLNG 1 Debottlenecking report. MLNG Debottlenecking Project Management team (PMT) was formed to undertake this debottlenecking project. An engineering team study many Boiler alternatives available in the market that the PMT can choose from. PMT should aware of each alternative machine has to offer economically before acquire any of the alternatives. 1.2 Objective The objective of this project paper is to apply principles in engineering economics to assess the options in the acquisition the 2 Boilers and give recommendation to MLNG 1 management for decision making in choosing most economically feasbile Boilers in MLNG 1 Debottlenecking project. 1.3 Scope Since the objective of this project is to run an economic analysis, it is important to specify the scope of the analysis. The scope will be comparing 3 alternatives with methods as follow;  Analyzing investment alternatives by using equivalent worth method  Analyzing cost-only alternatives by using equivalent worth method  Rate-of-return method: Incremental analysis for investment alternatives Three of basic methods for analyzing cash flows will be used in this project paper;  Present worth (PW)  Annual worth (AW)  Future worth (FW)
  • 6. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 5 | P a g e 2.0 Literature Review Engineering economy involves formulating, estimating, and evaluating the expected economic outcomes of alternatives designed to accomplish a defined purpose. Mathematical techniques simplify the economic evaluation of alternatives. The need for engineering economy is primarily motivated by the work that engineers do in performing analyses, synthesizing, and coming to a conclusion as they work on projects of all sizes. In other words, engineering economy is at the heart of making decisions. These decisions involve the fundamental elements of cash flows of money, time, and interest rates. Decisions are made routinely to choose one alternative over another by individuals in everyday life; by engineers on the job; by managers who supervise the activities of others; by corporate presidents who operate a business; and by government officials who work for the public good. Most decisions involve money, called capital or capital funds, which is usually limited in amount. The decision of where and how to invest this limited capital is motivated by a primary goal of adding value as future, anticipated results of the selected alternative are realized. Engineers play a vital role in capital investment decisions based upon their ability and experience to design, analyze, and synthesize.
  • 7. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 6 | P a g e 2.1 Performing an Engineering Economy Study
  • 8. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 7 | P a g e 2.2 Definitions The equations and procedures of engineering economy utilize many terms and notations. 2.2.1 Cash Flows Engineering economy bases its computations on the timing, size, and direction of cash flows. Cash inflows are the receipts, revenues, incomes, and savings generated by project and business activity. A plus sign indicates a cash inflow. Cash outflows are costs, disbursements, expenses, and taxes caused by projects and business activity. A negative or minus sign indicates a cash outflow. When a project involves only costs, the minus sign may be omitted for some techniques, such as benefit/cost analysis. A cash flow diagram is a very important tool in an economic analysis, especially when the cash flow series is complex. It is a graphical representation of cash flows drawn on the y axis with a time scale on the x axis. The diagram includes what is known, what is estimated, and what is needed. 2.2.2 Minimum Attractive Rate of Return (MARR) The Minimum Attractive Rate of Return (MARR) is a reasonable rate of return established for the evaluation and selection of alternatives. A project is not economically viable unless it is expected to return at least the MARR. MARR is also referred to as the hurdle rate, cutoff rate, benchmark rate, and minimum acceptable rate of return. 2.2.3 Present Worth (PW) The PW method is based on the concept of equivalent worth of all cash flows relative to some base or beginning point in time called the present. All cash inflows and outflows are discounted to the present point in time at an interest rate that is generally the MARR. A positive PW for an investment project is an amount of profit over the inimum amount required by investors. 2.2.4 Future Worth (FW) The FW is based on the equivalent worth of all cash inflows and outflows at the end of the study period at an interest rate that is generally MARR. The economic information provided by the FW method is very useful in capital investment decision situations.
  • 9. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 8 | P a g e 2.2.5 Annual Worth (AW) The AW of a project is an equal annual series of money amounts, for a stated study period, that is equivalent to the cash inflows and outflows at an interest rate that is generally MARR. AW = PW(A/P, i%, N) = FW(A/F, i%, N)
  • 10. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 9 | P a g e 3.0 Methodology DTSB has given these information for the purpose of this study; MARR = 5% annually Study period = 20 years Therefore, the above reference values shall be used throughout the analysis. Assessing the investment feasibility and profitability and recommending to management on making the best decision, methods below will be carried out in this project paper; 1. Summary of information regarding each alternatives will be presented based on collected data. Information such as capital investment, annual operating cost, annual labor cost and annual power maintenance cost for each alternatives are important and will be presented in a simple table. 2. Analyzing investment alternatives by using equivalent worth method will be conducted. The respective values of PW, AW, FW will be computed.
  • 11. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 10 | P a g e 4.0 Data Presentation MLNG 1 Debottlenecking Project Team has gathered necessary data and made the following table for the expected inflow and outflow on each water jet cutting equipment system. The data were collected from many sources such as consultants, contractors, and original equipment manufacturers. MLNG 1 Debottlenecking Project Team provided the values of expected annual revenue for the study period of 20 years for each alternative. All values are in Ringgit Malaysia (RM).
  • 12. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 11 | P a g e 5.0 Results and Discussion The most straightforward technique for comparing mutually exclusive alternatives when all useful lives are equal to the study period is to determine the equivalent worth of each alternative based on total investment at i = MARR. Then, for the investment alternatives, the one with the greatest positive equivalent worth is selected. And, in the case of cost alternatives, the one with the least negative equivalent worth is selected. 5.1 Analyzing Investment Alternatives by Using Equivalent Worth Present worth (PW) for each alternatives; PW(5%)A = – 987,440 + (300,450 – 185,000)(P/A, 5%, 20) = – 987,440 + 115,450(P/A, 5%, 20) = – 987,440 + 115,450(12.4622) = + RM 451,321.00 PW(5%)B = – 1,468,393+ (512,940– 290,000)(P/A, 5%, 20) = – 1,468,393+ 222,940(P/A, 5%, 20) = – 1,468,393+ 222,940(12.4622) = + RM 1,309,930.00 PW(5%)C = – 2,109,039+ (647,380– 430,000) (P/A, 5%, 20) = – 2,109,039+ 217,380 (P/A, 5%, 20) = – 2,109,039+ 217,380 (12.4622) = + RM 599,994.00 From the PW method, we can see that all of the alternatives are positive with B has the largest value (+ RM 1,309,930.00) Present worth (FW) for each alternatives; FW(5%)A = PW(5%)A x (F/P, 5%, 20) = RM 451,321.00 x 2.6533 = + RM 1,197,490.00 FW(5%)B = PW(5%)B x (F/P, 5%, 20)
  • 13. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 12 | P a g e = RM 1,309,930.00 x 2.6533 = + RM 3,475,637.27 FW(5%)C = FW(5%)C x (F/P, 5%, 20) = RM 599,994.00 x 2.6533 = + RM 1,591,964.08 Based on the FW method, the choice is B because it has the largest value. Annual worth (AW) for each alternatives; FW(5%)A = PW(5%)A x (A/P, 5%, 20) = RM 451,321.00 x 0.0802 = + RM 36,195.94 FW(5%)B = PW(5%)B x (A/P, 5%, 20) = RM 1,309,930.00 x 0.0802 = + RM 105,056.39 FW(5%)C = FW(5%)C x (A/P, 5%, 20) = RM 599,994.00 x 0.0802 = + RM 48,115.50 Alternative B again is chosen as it has the largest AW value compared to others. PW, FW and FW for all Boiler A, B and C is summarised as above.
  • 14. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 13 | P a g e 6.0 Conclusion From the analysis, Boiler B is the most preferred alternative to be acquired by the company. This recommendation is based on its PW, FW and AW. Therefore, it is recommended that MLNG 1 management to choose Boiler B to be acquired for MLNG 1 Debottlenecking project.
  • 15. Economic Analysis for Boiler Acquisition in MLNG 1 Debottlenecking Project 2016 14 | P a g e 7.0 References Sullivan, Wicks, and Koelling. Engineering Economics, Fifteen Ed. Essex, England: Pearson Education Limited, 2012 Blank, and Tarquin. Engineering Economy, Seventh Ed. 1221 Avenue of the Americas, New York: McGraw-Hill, 2012