SlideShare a Scribd company logo
Royal University of Bhutan
Jigme Namgyel Engineering College
Department of Civil Engineering & Surveying
Tutor : Phurba Tamang
Designation: Associate lecturer
Department of Civil Engineering and Surveying
SETTING OUT WORKS
MODULE: SURVEYING
Spring Semester 2020
MID-TERM REVIEW, 2017
Setting Out Works
Introduction
Setting out is a survey undertaken in order to transfer onto the site, the plans prepared as a result
of some previous survey. Here, instead of using data from the site to prepare plans, the plans and
designs prepared by the designer are transferred accurately onto the actual site. It may be
described as the fixing of well defined points in the filed showing the horizontal and vertical
positions required by the plans.
To build according to the plan, a contractor must have reference lines and points established in
the field. This involves placing of pegs or marks to define the lines and levels of work where after,
the construction proceeds according to these marks. Some factors to be considered during setting
out works are:
1. The reference lines and points should be well defined, not easily perishable, close to the work
yet out of way or actual construction operations.
2. A very high degree of accuracy should be maintained and only extremely low tolerances
should be allowed. In order to achieve this, frequent and independent checking should be
done.
3. The instrument used should be checked frequently and discrepancies if any should be
removed.
MID-TERM REVIEW, 2017
Setting Out of Buildings
Setting out of a building involves the transfer of the architect’s plan form paper onto the actual
site. The objective of setting out a building is to provide the builder with clearly defined outlines for
excavation. Two methods are generally used for setting out a building.
A. By Using a Circumscribing Rectangle
MID-TERM REVIEW, 2017
Setting Out of Buildings
A. By Using a Circumscribing Rectangle
Since stakes cannot be set at the exact corner points of a building ( if set so, these will be lost
during excavation , these are fixed at the corner of a bigger rectangle circumscribing the actual
building. Any suitable distance of the outer rectangle from the building can be chosen, but a
distance of usually 2 to 4 m is considered to be ideal. The actual procedure consist of the following
steps.
a. Preparation of the foundation trench plan showing the width of the foundation for various
walls.
b. Temporary pegs are driven at the actual corner points of the buildings.
c. Then using these pegs as reference a parallel line say AB of required length is set out at an
arbitrarily selected distance ( say 2 m ) from the actual center line.
d. A chord is stretched between the pegs A and B. At A, a line is set out perpendicular to AB
( with a tape using 3, 4. 5 method ). On this line, the position D is marked by setting a peg.
e. Set (d) is repeated at point B so as to obtain point C.
f. Having now set out the reference rectangle ABCD, the actual corners can be marked using the
sides of the reference rectangle ABCD.
g. Once all the points are staked, a chord is passed around the periphery of the rectangle and the
actual excavation lines are marked using lime.
MID-TERM REVIEW, 2017
Setting Out of Buildings
B. By Centerline Method
MID-TERM REVIEW, 2017
Setting Out of Buildings
B. By Centerline Method ( Commonly Preferred )
Procedure
a. From the plan, the centre lines of the walls are calculated. Then the centre lines of the rooms
are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points are A, B, C,
D, E, F and G which are marked by pegs with nails on top.
b. The setting of the corner points is checked according to diagonals AC, BD, CF and EG.
c. During excavation, the centre points A, B, C,…. may be removed. Therefore, the centre lines are
extended and the centre points marked about 2 m away from the outer edge of excavation.
Thus, the points A1, A2, B1, B2 . . . . . are marked outside the trench. The centre lines are shown
clearly by stretching thread or rope.
d. From the plan, the width of excavation is found out and set out around the centre. The
excavation width is also marked by thread with pegs at appropriate positions.
e. The excavation width is then marked by lime or by making a furrow with a spade.
f. If the plan is much too complicated and follows a zig zag pattern, the centre pegs are kept at
suitable positions according to site conditions.
MID-TERM REVIEW, 2017
G
List of Equipment for Staking Out
• Ranging Rods
• Wooden Pegs with Nails on top
• Measuring Tape
• Thread or Rope
Ranging Rods
Wooden Pegs
Measuring Tape
Thread or Rope
MID-TERM REVIEW, 2017
G
3-4-5 Method
Note: Any Multiple of 3, 4, 5 can be used. Example: 6, 8, 10 or 12, 16, 20, etc.
MID-TERM REVIEW, 2017
G
3-4-5 Method
Source: http://auromafrenchvillaments.blogspot.com/2014/02/marking-of-excavation-pits.html
MID-TERM REVIEW, 2017
Setting Out of Buildings
Example:
Describe the procedure of setting out of a two storeyed building with 200 m thick load bearing
outer walls all around. The foundation width is 750 mm. The building is absolutely rectangular and
outside dimensions above plinth level are 12000 mm x 18000 mm. Draw the foundation plan of the
outer walls showing all the dimensions ( not to scale ). In the above plan show the positions of
different pegs required for setting out of the above building.
Solution:
The Outside Dimensions are 12000 mm x 18000 mm
Thickness of the wall: 200 mm
Center line dimensions are ( 12000 – 200 ) = 11800 mm and ( 18000 – 200 ) = 17800 mm
= 11800 mm x 17800 mm
With foundation width 750 mm, the outside dimensions of foundation wall are 12550 x 18550
Inside Dimensions are 11050 x 17050.
Here the OFFSET PEGS are used.
MID-TERM REVIEW, 2017
Setting Out of Buildings
Wall thickness 200 mm
MID-TERM REVIEW, 2017
Setting Out of Buildings
Reference line connected by Thread or Rope
Maintained at 2 m from the outer wall
MID-TERM REVIEW, 2017
Setting Out of Buildings
MID-TERM REVIEW, 2017
Setting Out of Buildings
MID-TERM REVIEW, 2017
Setting Out of Buildings
Steps:
• Mark the centerline of the longest wall on the ground by stretching a string between offset
pegs 1 – 1.
• Similarly stake strings along 2 – 2, 3 -3 and 4 – 4.
• Pegs marked as red dots in the figure are the reference pegs for all the other pegs.
• These pegs are marked at 2 m offset from all sides of the building plan. The pegs should project
25 to 50 mm above the ground level.
• The intersections are maintained at right angle using the 3:4:5 method or tri-square.
• Referring to the reference pegs ( marked red ) other temporary pegs are established ( marked
purple ).
• Once all the pegs are fixed, the lines are marked with lime.
• Once the lines are marked with the lime, the pegs are removed except for the reference pegs.

More Related Content

What's hot

1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
Rakesh Verma
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveyingMohammed_82
 
Theodolite report
Theodolite reportTheodolite report
Theodolite report
Shze Hwa Lee
 
Setting out work
Setting out workSetting out work
Setting out work
Shivam Mehta
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
GAURAV. H .TANDON
 
Tutor transferring levels
Tutor transferring levels Tutor transferring levels
Tutor transferring levels
Luke D'Arcy
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
ARUN KUMAR
 
INTRODUCTION TO SURVEYING
INTRODUCTION TO SURVEYINGINTRODUCTION TO SURVEYING
INTRODUCTION TO SURVEYING
farhana saiyed
 
Levelling
LevellingLevelling
Levelling
LevellingLevelling
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouring
Abdul Majid
 
Curves and there application in Survey
Curves and there application in SurveyCurves and there application in Survey
Curves and there application in Survey
Lord1911
 
Setting out of works
Setting out of worksSetting out of works
Setting out of works
Shubham Singh [NITK]
 
Curves
CurvesCurves
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
guasiya
 
Levelling
LevellingLevelling
Levelling
srinivas cnu
 
Tacheometry ppt
Tacheometry pptTacheometry ppt
Tacheometry ppt
Vilas Nikam
 
Chain surveying
Chain surveyingChain surveying
Chain surveying
JNTUK
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying
neharajpl
 

What's hot (20)

1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveying
 
Theodolite report
Theodolite reportTheodolite report
Theodolite report
 
Setting out work
Setting out workSetting out work
Setting out work
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
 
Tutor transferring levels
Tutor transferring levels Tutor transferring levels
Tutor transferring levels
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
INTRODUCTION TO SURVEYING
INTRODUCTION TO SURVEYINGINTRODUCTION TO SURVEYING
INTRODUCTION TO SURVEYING
 
Levelling
LevellingLevelling
Levelling
 
Levelling
LevellingLevelling
Levelling
 
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouring
 
Curves and there application in Survey
Curves and there application in SurveyCurves and there application in Survey
Curves and there application in Survey
 
Setting out of works
Setting out of worksSetting out of works
Setting out of works
 
Curves
CurvesCurves
Curves
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Levelling
LevellingLevelling
Levelling
 
Levelling
LevellingLevelling
Levelling
 
Tacheometry ppt
Tacheometry pptTacheometry ppt
Tacheometry ppt
 
Chain surveying
Chain surveyingChain surveying
Chain surveying
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying
 

Similar to Setting out of Building

SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2
Nhatz Marticio
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
Luke D'Arcy
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptx
GabrielBentil1
 
Presentation (4).pptx
Presentation (4).pptxPresentation (4).pptx
Presentation (4).pptx
SatyaNarayana135764
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
ECV All Chapters
ECV All ChaptersECV All Chapters
ECV All Chapters
Padmasinh Patil
 
Bridge survey
Bridge surveyBridge survey
Bridge survey
SAGAR KUMAR
 
Layout of a House Plan Foundation - Report
Layout of a House Plan Foundation - ReportLayout of a House Plan Foundation - Report
Layout of a House Plan Foundation - Report
Sarchia Khursheed
 
Bcs day-two-exam
Bcs day-two-examBcs day-two-exam
Bcs day-two-exam
John Beasley
 
Summer training report
Summer training reportSummer training report
Summer training report
aki8872233
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Aabid Ansar
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
Vijay325
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
lckr117
 
Unit 5
Unit 5Unit 5
CE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfCE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdf
JunaidMughal34
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
Padmasinh Patil
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
AMIT PAYAL
 
Principles of building construction, information and communication
Principles of building construction, information and communicationPrinciples of building construction, information and communication
Principles of building construction, information and communication
michael mcewan
 
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET Journal
 

Similar to Setting out of Building (20)

SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptx
 
Presentation (4).pptx
Presentation (4).pptxPresentation (4).pptx
Presentation (4).pptx
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
ECV All Chapters
ECV All ChaptersECV All Chapters
ECV All Chapters
 
Bridge survey
Bridge surveyBridge survey
Bridge survey
 
Layout of a House Plan Foundation - Report
Layout of a House Plan Foundation - ReportLayout of a House Plan Foundation - Report
Layout of a House Plan Foundation - Report
 
Bcs day-two-exam
Bcs day-two-examBcs day-two-exam
Bcs day-two-exam
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Unit 5
Unit 5Unit 5
Unit 5
 
Seminar
SeminarSeminar
Seminar
 
CE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfCE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdf
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
 
Principles of building construction, information and communication
Principles of building construction, information and communicationPrinciples of building construction, information and communication
Principles of building construction, information and communication
 
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
 

More from Phurba Tamang

Water sources and water quality parameters
Water sources and water quality parametersWater sources and water quality parameters
Water sources and water quality parameters
Phurba Tamang
 
Introduction to Environmental Engineering
Introduction to Environmental EngineeringIntroduction to Environmental Engineering
Introduction to Environmental Engineering
Phurba Tamang
 
Introduction to StaadPro
Introduction to StaadProIntroduction to StaadPro
Introduction to StaadPro
Phurba Tamang
 
Contouring
ContouringContouring
Contouring
Phurba Tamang
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveying
Phurba Tamang
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
Phurba Tamang
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil Engineers
Phurba Tamang
 
Design of Sewage Treatment Plant
Design of Sewage Treatment PlantDesign of Sewage Treatment Plant
Design of Sewage Treatment Plant
Phurba Tamang
 
Introduction to Surveying
Introduction to SurveyingIntroduction to Surveying
Introduction to Surveying
Phurba Tamang
 
Engineering Mechanics Manual
Engineering Mechanics ManualEngineering Mechanics Manual
Engineering Mechanics Manual
Phurba Tamang
 
Introduction to Types of Foundation
Introduction to Types of FoundationIntroduction to Types of Foundation
Introduction to Types of Foundation
Phurba Tamang
 
Autocad training
Autocad trainingAutocad training
Autocad training
Phurba Tamang
 

More from Phurba Tamang (12)

Water sources and water quality parameters
Water sources and water quality parametersWater sources and water quality parameters
Water sources and water quality parameters
 
Introduction to Environmental Engineering
Introduction to Environmental EngineeringIntroduction to Environmental Engineering
Introduction to Environmental Engineering
 
Introduction to StaadPro
Introduction to StaadProIntroduction to StaadPro
Introduction to StaadPro
 
Contouring
ContouringContouring
Contouring
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveying
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil Engineers
 
Design of Sewage Treatment Plant
Design of Sewage Treatment PlantDesign of Sewage Treatment Plant
Design of Sewage Treatment Plant
 
Introduction to Surveying
Introduction to SurveyingIntroduction to Surveying
Introduction to Surveying
 
Engineering Mechanics Manual
Engineering Mechanics ManualEngineering Mechanics Manual
Engineering Mechanics Manual
 
Introduction to Types of Foundation
Introduction to Types of FoundationIntroduction to Types of Foundation
Introduction to Types of Foundation
 
Autocad training
Autocad trainingAutocad training
Autocad training
 

Recently uploaded

RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 

Recently uploaded (20)

RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 

Setting out of Building

  • 1. Royal University of Bhutan Jigme Namgyel Engineering College Department of Civil Engineering & Surveying Tutor : Phurba Tamang Designation: Associate lecturer Department of Civil Engineering and Surveying SETTING OUT WORKS MODULE: SURVEYING Spring Semester 2020
  • 2. MID-TERM REVIEW, 2017 Setting Out Works Introduction Setting out is a survey undertaken in order to transfer onto the site, the plans prepared as a result of some previous survey. Here, instead of using data from the site to prepare plans, the plans and designs prepared by the designer are transferred accurately onto the actual site. It may be described as the fixing of well defined points in the filed showing the horizontal and vertical positions required by the plans. To build according to the plan, a contractor must have reference lines and points established in the field. This involves placing of pegs or marks to define the lines and levels of work where after, the construction proceeds according to these marks. Some factors to be considered during setting out works are: 1. The reference lines and points should be well defined, not easily perishable, close to the work yet out of way or actual construction operations. 2. A very high degree of accuracy should be maintained and only extremely low tolerances should be allowed. In order to achieve this, frequent and independent checking should be done. 3. The instrument used should be checked frequently and discrepancies if any should be removed.
  • 3. MID-TERM REVIEW, 2017 Setting Out of Buildings Setting out of a building involves the transfer of the architect’s plan form paper onto the actual site. The objective of setting out a building is to provide the builder with clearly defined outlines for excavation. Two methods are generally used for setting out a building. A. By Using a Circumscribing Rectangle
  • 4. MID-TERM REVIEW, 2017 Setting Out of Buildings A. By Using a Circumscribing Rectangle Since stakes cannot be set at the exact corner points of a building ( if set so, these will be lost during excavation , these are fixed at the corner of a bigger rectangle circumscribing the actual building. Any suitable distance of the outer rectangle from the building can be chosen, but a distance of usually 2 to 4 m is considered to be ideal. The actual procedure consist of the following steps. a. Preparation of the foundation trench plan showing the width of the foundation for various walls. b. Temporary pegs are driven at the actual corner points of the buildings. c. Then using these pegs as reference a parallel line say AB of required length is set out at an arbitrarily selected distance ( say 2 m ) from the actual center line. d. A chord is stretched between the pegs A and B. At A, a line is set out perpendicular to AB ( with a tape using 3, 4. 5 method ). On this line, the position D is marked by setting a peg. e. Set (d) is repeated at point B so as to obtain point C. f. Having now set out the reference rectangle ABCD, the actual corners can be marked using the sides of the reference rectangle ABCD. g. Once all the points are staked, a chord is passed around the periphery of the rectangle and the actual excavation lines are marked using lime.
  • 5. MID-TERM REVIEW, 2017 Setting Out of Buildings B. By Centerline Method
  • 6. MID-TERM REVIEW, 2017 Setting Out of Buildings B. By Centerline Method ( Commonly Preferred ) Procedure a. From the plan, the centre lines of the walls are calculated. Then the centre lines of the rooms are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points are A, B, C, D, E, F and G which are marked by pegs with nails on top. b. The setting of the corner points is checked according to diagonals AC, BD, CF and EG. c. During excavation, the centre points A, B, C,…. may be removed. Therefore, the centre lines are extended and the centre points marked about 2 m away from the outer edge of excavation. Thus, the points A1, A2, B1, B2 . . . . . are marked outside the trench. The centre lines are shown clearly by stretching thread or rope. d. From the plan, the width of excavation is found out and set out around the centre. The excavation width is also marked by thread with pegs at appropriate positions. e. The excavation width is then marked by lime or by making a furrow with a spade. f. If the plan is much too complicated and follows a zig zag pattern, the centre pegs are kept at suitable positions according to site conditions.
  • 7. MID-TERM REVIEW, 2017 G List of Equipment for Staking Out • Ranging Rods • Wooden Pegs with Nails on top • Measuring Tape • Thread or Rope Ranging Rods Wooden Pegs Measuring Tape Thread or Rope
  • 8. MID-TERM REVIEW, 2017 G 3-4-5 Method Note: Any Multiple of 3, 4, 5 can be used. Example: 6, 8, 10 or 12, 16, 20, etc.
  • 9. MID-TERM REVIEW, 2017 G 3-4-5 Method Source: http://auromafrenchvillaments.blogspot.com/2014/02/marking-of-excavation-pits.html
  • 10. MID-TERM REVIEW, 2017 Setting Out of Buildings Example: Describe the procedure of setting out of a two storeyed building with 200 m thick load bearing outer walls all around. The foundation width is 750 mm. The building is absolutely rectangular and outside dimensions above plinth level are 12000 mm x 18000 mm. Draw the foundation plan of the outer walls showing all the dimensions ( not to scale ). In the above plan show the positions of different pegs required for setting out of the above building. Solution: The Outside Dimensions are 12000 mm x 18000 mm Thickness of the wall: 200 mm Center line dimensions are ( 12000 – 200 ) = 11800 mm and ( 18000 – 200 ) = 17800 mm = 11800 mm x 17800 mm With foundation width 750 mm, the outside dimensions of foundation wall are 12550 x 18550 Inside Dimensions are 11050 x 17050. Here the OFFSET PEGS are used.
  • 11. MID-TERM REVIEW, 2017 Setting Out of Buildings Wall thickness 200 mm
  • 12. MID-TERM REVIEW, 2017 Setting Out of Buildings Reference line connected by Thread or Rope Maintained at 2 m from the outer wall
  • 13. MID-TERM REVIEW, 2017 Setting Out of Buildings
  • 14. MID-TERM REVIEW, 2017 Setting Out of Buildings
  • 15. MID-TERM REVIEW, 2017 Setting Out of Buildings Steps: • Mark the centerline of the longest wall on the ground by stretching a string between offset pegs 1 – 1. • Similarly stake strings along 2 – 2, 3 -3 and 4 – 4. • Pegs marked as red dots in the figure are the reference pegs for all the other pegs. • These pegs are marked at 2 m offset from all sides of the building plan. The pegs should project 25 to 50 mm above the ground level. • The intersections are maintained at right angle using the 3:4:5 method or tri-square. • Referring to the reference pegs ( marked red ) other temporary pegs are established ( marked purple ). • Once all the pegs are fixed, the lines are marked with lime. • Once the lines are marked with the lime, the pegs are removed except for the reference pegs.