SlideShare a Scribd company logo
SETTING OUT OF BUILDING
BUILDING TECHNOLOGY AND MATERIALS III
TERM I
2
The operations carried out once the site is handed over
• Clearing the site
• Setting out the building
• Establishing a datum level
3
What is setting out ?
It is the process of developing the physical positions of corners and walls of a
building, and it’s done by transferring dimensions from the layout plan (also called
as setting out plan, demarcation plan) to the ground. The setting out clearly defines
the outline of the excavations and the centre line of the walls, so that the
construction can be carried out according to the plan.
When is setting out done ?
• when building a new house
• when renovating an already existing one, especially an extension.
The process of Setting out is done by a contractor, and overseen by the lead project
consultant engineer, architect or any other qualified member of the project team.
Function of setting out
• To establish the position of the trench and wall of the house as well as the
position of corners and rooms.
4
METHODS OF SETTING OUT
1. Peg or rope method (commonly used).
2. Dumpy Level (Best for big construction projects)
5
ITEMS REQUIRED IN SETTING OUT.
• Timber, 75mm by 50mm or any
appropriate size.
• Round poles/ timber to act as pegs or
steel for hard ground.
• Nylon threads (Manila rope).
• Ordinary nails inch and 2 inch.
• White chalk or lime.
• Clear hose pipe for determining
horizontal levels.
• Sledge hammer.
• Measuring tape
• Builder’s square
6
DATUM LEVEL
A point which serves as a reference or base for the measurement of other quantities
Where there are no benchmarks on or near the
site, a suitable datum must be established. A
site datum or temporary benchmark could be a
post set in concrete or a concrete plinth set up
on site.
7
PROCESS OF SETTING OUT.
• Setting out is done on the principle of whole to part. According to this principle
the largest possible rectangle of the building is found and set out. The rectangle
is further partitioned into small parts (internal rooms).
• The first thing we need to establish is a parallel/ reference/ base line, to which
all other lines can be related. This can be taken along an existing building close
to the proposed new structure/ boundary wall if existing/ kerb line etc.
8
9
PROCESS OF SETTING OUT
STEP 1: SETTING OUT THE BUILDING LINE
Two square offset lines are set from the kerb to the position of the building line. The
length of the line is greater than the width of the proposed building.
Pegs are positioned at these points and a ranging line is fixed to these, giving a
position of the building line .
10
STEP 2: SETTING OUT FRONTAGE LINE/ BASE LINE
After taking the dimensions from the drawing, the frontage line is set out. This can be
either on building line or behind it.
The first corner peg (A) will be positioned from dimensions given on the drawing which
relates to site features such as distance from kerb, gate post, boundary wall etc.
Eg: the point A is positioned a distance of (D) from the boundary.
Following the position of first peg, the second peg (B) is positioned after carefully
measuring the width along the frontage line.
The nail is knocked into each peg to determine the exact position of the corner.
11
STEP 3: SETTING OUT OF FIRST RIGHT ANGLE TO THE FRONTAGE LINE
Attach the taut line to the nail on the corner peg which will be extended well beyond the length of the
wall to be set out.
Adjust the line carefully to cross the frontage line at 90 degree by using a builder’s square or the
3:4:5 method.
When the line is correct, knock the peg with nail at the distance greater than the length of the wall.
12
RIGHT ANGLE TRINAGLE USED IN SETTING OUT
One of the most important procedure used in setting out is the process of ensuring that all
right angle corners are properly aligned. One of the simplest ways is to use the method
known as 3:4:5 triangle method.
PROCEDURE:
1. A peg with a nail is fixed exactly at 3m from
the corner peg on the fixed line.
2. A measuring tape is the hooked to the nail on
the corner peg and another tape is hooked to
the nail of the peg on the front line.
3. Both the tapes are pulled towards the end wall
and with distance of 4m showing on one tape
and 5m on the other tape. Where they cross
third peg will be fixed.
4. This will establish a line at 90 degree to the
front line.
13
STEP 4: SETTING OUT OF SECOND RIGHT ANGLE TO THE FRONTAGE
LINE
Measure the same length from the frontage line and set point D.
Check the ranging lines before proceeding.
14
STEP 5: SETTING OUT
OF FINAL BACK LINE
Measure the dimensions of
the building side wall from
the outer peg of the frontage
line and set pegs parallel to
the wall lines.
Attach ranging lines to the
pegs to establish the back
wall line.
Pegs can be positioned at G
and H, but this is not
essential.
15
STEP 6: CHECKING THE
BUILDING SETTING OUT
The setting out will be confirmed if
all measurements are correct and the
diagonals measure exactly the same.
Measure the dimensions from A to G
and B to H. these should be same if
the building has been set perfectly.
If there is some difference in the
measurement, adjust the back pegs
as per dimensions. The frontage line
should not be altered.
16
STEP 7: SET UP PROFILES AND ATTACH RANGING LINES
When the building has been set out and proved by checking the diagonals, profiles can be erected to
enable the corner points to be easily located after the trenches have been excavated.
The ranging lines attached to the pegs are extended by holding the line to pass over the peg to the
profile.
The wall position is then clearly marked on the profile.
17
POSITIONING OF PROFILE
The profiles are positioned well away from the proposed excavations to allow an adequate
working space. This is even more important when the excavations is to be carried out by a
mechanical means.
18
SETTING PROFILE LEVELS
While setting up profiles, it is essential that they are as level as possible. This avoids
inaccuracies when re measuring the walls and diagonals before commencing work.
The profile is most conveniently levelled to the DPC level of the proposed building.
19
BONING RODS
A boning rod is a simple device used to quickly position levelling pegs. It consist of two
pieces of timber nailed together at right angles. Boing rod can be used to transfer levels
between the two known points.
20
MARKING THE POSITION OF FOUNDATION TRENCH
Before excavation begins, the position of the foundation trench is marked on the ground.
The original corner pegs can be then removed. The foundation line is then marked using
lime or a spray paint.
21
22
THANK YOU
NEXT TOPIC
SOIL TYPES AND ITS BEHAVIOUR

More Related Content

What's hot

Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
KHUSHBU SHAH
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
Kishor Ade
 
Foundation
FoundationFoundation
Foundation
bakht zamin
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
Nabeel Joomun
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
Rithika Ravishankar
 
Roof truss
Roof trussRoof truss
Roof truss
Pankajkumar Singh
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
Aglaia Connect
 
Shoring
ShoringShoring
Foundations
FoundationsFoundations
Foundations
Aglaia Connect
 
Process of Building Construction
Process of Building ConstructionProcess of Building Construction
Process of Building Construction
AyushHajare
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
Aglaia Connect
 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
mohdasrimohdhasim
 
Building construction layout
Building construction layoutBuilding construction layout
Building construction layout
AliRaza1767
 
Defects in construction
Defects in constructionDefects in construction
Defects in construction
Shivangi Saini
 
What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioning
Charlie Gupta
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
Grace Henry
 
Building Components
Building ComponentsBuilding Components
Building Components
GAURAV. H .TANDON
 
Combined Footing
Combined FootingCombined Footing
Combined Footing
MD Shahnewaz Chayon
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
Aishwarya Deopujari
 

What's hot (20)

Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Foundation
FoundationFoundation
Foundation
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Formwork
FormworkFormwork
Formwork
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Roof truss
Roof trussRoof truss
Roof truss
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Shoring
ShoringShoring
Shoring
 
Foundations
FoundationsFoundations
Foundations
 
Process of Building Construction
Process of Building ConstructionProcess of Building Construction
Process of Building Construction
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
 
Building construction layout
Building construction layoutBuilding construction layout
Building construction layout
 
Defects in construction
Defects in constructionDefects in construction
Defects in construction
 
What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioning
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
 
Building Components
Building ComponentsBuilding Components
Building Components
 
Combined Footing
Combined FootingCombined Footing
Combined Footing
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 

Viewers also liked

CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
GLA University
 
Mortars and Plasters
Mortars and PlastersMortars and Plasters
Mortars and Plasters
GAURAV. H .TANDON
 
Non Ferrous Metal
Non Ferrous MetalNon Ferrous Metal
Non Ferrous Metal
GAURAV. H .TANDON
 
Plastic
PlasticPlastic
building material
building materialbuilding material
building materialnicocarlos
 
CIVIL ENGINEERING CONSTRUCTIONS MATERIALS
CIVIL ENGINEERING  CONSTRUCTIONS MATERIALS CIVIL ENGINEERING  CONSTRUCTIONS MATERIALS
CIVIL ENGINEERING CONSTRUCTIONS MATERIALS
LOUIS WAYNE
 
Timber-II
Timber-IITimber-II
Insulating material
Insulating materialInsulating material
Insulating material
GAURAV. H .TANDON
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Dexter Ng
 
Building materials elements of civil engineering
Building materials elements of civil engineeringBuilding materials elements of civil engineering
Building materials elements of civil engineering
Priyank Bhimani
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materialsAkash Patel
 
Green Building Construction in India
Green Building Construction in IndiaGreen Building Construction in India
Green Building Construction in Indiaintellobuild
 
Scaffolds ppt construction
Scaffolds ppt constructionScaffolds ppt construction
Scaffolding Power Point
Scaffolding Power PointScaffolding Power Point
Scaffolding Power PointAshlow
 
Construction Materials
Construction MaterialsConstruction Materials
Construction Materials
rocioyana
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materials
GAURAV. H .TANDON
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
gyan singh
 

Viewers also liked (20)

CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Mortars and Plasters
Mortars and PlastersMortars and Plasters
Mortars and Plasters
 
Glass
GlassGlass
Glass
 
Non Ferrous Metal
Non Ferrous MetalNon Ferrous Metal
Non Ferrous Metal
 
Plastic
PlasticPlastic
Plastic
 
building material
building materialbuilding material
building material
 
Scaffolding Technique
Scaffolding TechniqueScaffolding Technique
Scaffolding Technique
 
CIVIL ENGINEERING CONSTRUCTIONS MATERIALS
CIVIL ENGINEERING  CONSTRUCTIONS MATERIALS CIVIL ENGINEERING  CONSTRUCTIONS MATERIALS
CIVIL ENGINEERING CONSTRUCTIONS MATERIALS
 
Timber-II
Timber-IITimber-II
Timber-II
 
Insulating material
Insulating materialInsulating material
Insulating material
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
 
Building materials elements of civil engineering
Building materials elements of civil engineeringBuilding materials elements of civil engineering
Building materials elements of civil engineering
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materials
 
Green Building Construction in India
Green Building Construction in IndiaGreen Building Construction in India
Green Building Construction in India
 
Scaffolds ppt construction
Scaffolds ppt constructionScaffolds ppt construction
Scaffolds ppt construction
 
Scaffolding Power Point
Scaffolding Power PointScaffolding Power Point
Scaffolding Power Point
 
Construction Materials
Construction MaterialsConstruction Materials
Construction Materials
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materials
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 

Similar to Setting out of building

Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
Luke D'Arcy
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
Luke D'Arcy
 
Setting out of Building
Setting out of BuildingSetting out of Building
Setting out of Building
Phurba Tamang
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptx
GabrielBentil1
 
Apply set out work.pdf
Apply set out work.pdfApply set out work.pdf
Apply set out work.pdf
Danilign Mekonnen
 
Setting out work
Setting out workSetting out work
Setting out work
Shivam Mehta
 
SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2
Nhatz Marticio
 
S2 8 construction surveys
S2 8 construction surveysS2 8 construction surveys
S2 8 construction surveys
Est
 
Tutor brickwork below ground level
Tutor brickwork below ground levelTutor brickwork below ground level
Tutor brickwork below ground level
Luke D'Arcy
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level
Luke D'Arcy
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
LingWei11
 
How to install False Ceiling?
How to install False Ceiling?How to install False Ceiling?
How to install False Ceiling?
BuildingandInteriors.com
 
BuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
BuildBlock Insulating Concrete Form (ICF) Construction in 22 StepsBuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
BuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
Brian Corder
 
Plinth beam work procedure - checklist, protection
Plinth beam work procedure - checklist, protectionPlinth beam work procedure - checklist, protection
Plinth beam work procedure - checklist, protection
AkshayKamble94
 
procedures-for-mivan-formwork
procedures-for-mivan-formworkprocedures-for-mivan-formwork
procedures-for-mivan-formwork
Amrish Tyagi
 
CE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfCE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdf
JunaidMughal34
 
Construction Survey
Construction SurveyConstruction Survey
Construction Survey
halmifaizol
 
Bcs day-two-exam
Bcs day-two-examBcs day-two-exam
Bcs day-two-exam
John Beasley
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01
Rajesh Rajguru
 

Similar to Setting out of building (20)

Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Setting out of Building
Setting out of BuildingSetting out of Building
Setting out of Building
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptx
 
Apply set out work.pdf
Apply set out work.pdfApply set out work.pdf
Apply set out work.pdf
 
Setting out work
Setting out workSetting out work
Setting out work
 
SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2
 
S2 8 construction surveys
S2 8 construction surveysS2 8 construction surveys
S2 8 construction surveys
 
Tutor brickwork below ground level
Tutor brickwork below ground levelTutor brickwork below ground level
Tutor brickwork below ground level
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
How to install False Ceiling?
How to install False Ceiling?How to install False Ceiling?
How to install False Ceiling?
 
BuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
BuildBlock Insulating Concrete Form (ICF) Construction in 22 StepsBuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
BuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
 
Plinth beam work procedure - checklist, protection
Plinth beam work procedure - checklist, protectionPlinth beam work procedure - checklist, protection
Plinth beam work procedure - checklist, protection
 
procedures-for-mivan-formwork
procedures-for-mivan-formworkprocedures-for-mivan-formwork
procedures-for-mivan-formwork
 
CE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfCE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdf
 
Deck marking
Deck markingDeck marking
Deck marking
 
Construction Survey
Construction SurveyConstruction Survey
Construction Survey
 
Bcs day-two-exam
Bcs day-two-examBcs day-two-exam
Bcs day-two-exam
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01
 

Recently uploaded

Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
Confidence Ago
 
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Mansi Shah
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
h7j5io0
 
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
ameli25062005
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
7sd8fier
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
7sd8fier
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
ResDraft
 
CA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfCA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdf
SudhanshuMandlik
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
cy0krjxt
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
jyz59f4j
 
一比一原版(Bolton毕业证书)博尔顿大学毕业证成绩单如何办理
一比一原版(Bolton毕业证书)博尔顿大学毕业证成绩单如何办理一比一原版(Bolton毕业证书)博尔顿大学毕业证成绩单如何办理
一比一原版(Bolton毕业证书)博尔顿大学毕业证成绩单如何办理
h7j5io0
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
aaryangarg12
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
h7j5io0
 
Top 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsTop 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen Designs
Finzo Kitchens
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
9a93xvy
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
fabianavillanib
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
taqyed
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
PlanitIsrael
 

Recently uploaded (20)

Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
 
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
 
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
 
CA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfCA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdf
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
 
一比一原版(Bolton毕业证书)博尔顿大学毕业证成绩单如何办理
一比一原版(Bolton毕业证书)博尔顿大学毕业证成绩单如何办理一比一原版(Bolton毕业证书)博尔顿大学毕业证成绩单如何办理
一比一原版(Bolton毕业证书)博尔顿大学毕业证成绩单如何办理
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
 
Top 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsTop 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen Designs
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
 

Setting out of building

  • 1. SETTING OUT OF BUILDING BUILDING TECHNOLOGY AND MATERIALS III TERM I
  • 2. 2 The operations carried out once the site is handed over • Clearing the site • Setting out the building • Establishing a datum level
  • 3. 3 What is setting out ? It is the process of developing the physical positions of corners and walls of a building, and it’s done by transferring dimensions from the layout plan (also called as setting out plan, demarcation plan) to the ground. The setting out clearly defines the outline of the excavations and the centre line of the walls, so that the construction can be carried out according to the plan. When is setting out done ? • when building a new house • when renovating an already existing one, especially an extension. The process of Setting out is done by a contractor, and overseen by the lead project consultant engineer, architect or any other qualified member of the project team. Function of setting out • To establish the position of the trench and wall of the house as well as the position of corners and rooms.
  • 4. 4 METHODS OF SETTING OUT 1. Peg or rope method (commonly used). 2. Dumpy Level (Best for big construction projects)
  • 5. 5 ITEMS REQUIRED IN SETTING OUT. • Timber, 75mm by 50mm or any appropriate size. • Round poles/ timber to act as pegs or steel for hard ground. • Nylon threads (Manila rope). • Ordinary nails inch and 2 inch. • White chalk or lime. • Clear hose pipe for determining horizontal levels. • Sledge hammer. • Measuring tape • Builder’s square
  • 6. 6 DATUM LEVEL A point which serves as a reference or base for the measurement of other quantities Where there are no benchmarks on or near the site, a suitable datum must be established. A site datum or temporary benchmark could be a post set in concrete or a concrete plinth set up on site.
  • 7. 7 PROCESS OF SETTING OUT. • Setting out is done on the principle of whole to part. According to this principle the largest possible rectangle of the building is found and set out. The rectangle is further partitioned into small parts (internal rooms). • The first thing we need to establish is a parallel/ reference/ base line, to which all other lines can be related. This can be taken along an existing building close to the proposed new structure/ boundary wall if existing/ kerb line etc.
  • 8. 8
  • 9. 9 PROCESS OF SETTING OUT STEP 1: SETTING OUT THE BUILDING LINE Two square offset lines are set from the kerb to the position of the building line. The length of the line is greater than the width of the proposed building. Pegs are positioned at these points and a ranging line is fixed to these, giving a position of the building line .
  • 10. 10 STEP 2: SETTING OUT FRONTAGE LINE/ BASE LINE After taking the dimensions from the drawing, the frontage line is set out. This can be either on building line or behind it. The first corner peg (A) will be positioned from dimensions given on the drawing which relates to site features such as distance from kerb, gate post, boundary wall etc. Eg: the point A is positioned a distance of (D) from the boundary. Following the position of first peg, the second peg (B) is positioned after carefully measuring the width along the frontage line. The nail is knocked into each peg to determine the exact position of the corner.
  • 11. 11 STEP 3: SETTING OUT OF FIRST RIGHT ANGLE TO THE FRONTAGE LINE Attach the taut line to the nail on the corner peg which will be extended well beyond the length of the wall to be set out. Adjust the line carefully to cross the frontage line at 90 degree by using a builder’s square or the 3:4:5 method. When the line is correct, knock the peg with nail at the distance greater than the length of the wall.
  • 12. 12 RIGHT ANGLE TRINAGLE USED IN SETTING OUT One of the most important procedure used in setting out is the process of ensuring that all right angle corners are properly aligned. One of the simplest ways is to use the method known as 3:4:5 triangle method. PROCEDURE: 1. A peg with a nail is fixed exactly at 3m from the corner peg on the fixed line. 2. A measuring tape is the hooked to the nail on the corner peg and another tape is hooked to the nail of the peg on the front line. 3. Both the tapes are pulled towards the end wall and with distance of 4m showing on one tape and 5m on the other tape. Where they cross third peg will be fixed. 4. This will establish a line at 90 degree to the front line.
  • 13. 13 STEP 4: SETTING OUT OF SECOND RIGHT ANGLE TO THE FRONTAGE LINE Measure the same length from the frontage line and set point D. Check the ranging lines before proceeding.
  • 14. 14 STEP 5: SETTING OUT OF FINAL BACK LINE Measure the dimensions of the building side wall from the outer peg of the frontage line and set pegs parallel to the wall lines. Attach ranging lines to the pegs to establish the back wall line. Pegs can be positioned at G and H, but this is not essential.
  • 15. 15 STEP 6: CHECKING THE BUILDING SETTING OUT The setting out will be confirmed if all measurements are correct and the diagonals measure exactly the same. Measure the dimensions from A to G and B to H. these should be same if the building has been set perfectly. If there is some difference in the measurement, adjust the back pegs as per dimensions. The frontage line should not be altered.
  • 16. 16 STEP 7: SET UP PROFILES AND ATTACH RANGING LINES When the building has been set out and proved by checking the diagonals, profiles can be erected to enable the corner points to be easily located after the trenches have been excavated. The ranging lines attached to the pegs are extended by holding the line to pass over the peg to the profile. The wall position is then clearly marked on the profile.
  • 17. 17 POSITIONING OF PROFILE The profiles are positioned well away from the proposed excavations to allow an adequate working space. This is even more important when the excavations is to be carried out by a mechanical means.
  • 18. 18 SETTING PROFILE LEVELS While setting up profiles, it is essential that they are as level as possible. This avoids inaccuracies when re measuring the walls and diagonals before commencing work. The profile is most conveniently levelled to the DPC level of the proposed building.
  • 19. 19 BONING RODS A boning rod is a simple device used to quickly position levelling pegs. It consist of two pieces of timber nailed together at right angles. Boing rod can be used to transfer levels between the two known points.
  • 20. 20 MARKING THE POSITION OF FOUNDATION TRENCH Before excavation begins, the position of the foundation trench is marked on the ground. The original corner pegs can be then removed. The foundation line is then marked using lime or a spray paint.
  • 21. 21
  • 22. 22 THANK YOU NEXT TOPIC SOIL TYPES AND ITS BEHAVIOUR