Pillai HOC College of
Engineering
and Technology
Department of Civil
EngineeringSurveying-II
Presents
Setting Out
Works
Prepared by – Mr. Atul
Anand Dongre
Assistant Professor, PHCET, Rasayani
Setting out
Works
1. Setting out Foundation
plan using centre line
plan with batter board
2. Setting out Bridge
3. Setting out Sewer line
4. Setting out Culvert
5. Setting out Tunnel
1. Setting out Foundation plan using centre
line plan with batter board
Actual Site
Method
Of
Setting out
work for
Foundatio
n
Using
Batter
Board
RIVER RIVER
20 M
10
M
20
M
Setting out Sewer
Procedure
Fix stakes on the ground at the centre
line of the proposed sewer at 20m
intervals.
Set out a parallel line to the proposed
centre line of the sewer on one side at a
distance apart so that it may not get
disturbed during excavation.
Excavate the sewer trench of desired
width and depth
Erect cross heads at 30 m apart and
each change of gradient and direction.
Set the top edge of each sight rail truly
horizontal with the help of a spirit level.
Drive in a nail on the top edge at the
centre of the sight rail to define the
centre line of the sewer.
What is
Culvert?????
Actual
Structure
of Culvert
The axis (centre line)
XX1 and YY1 are set out
with O is the origin.
Along the line OX1,
points 1,2,3 and 4 are
marked at distance
x1,x2,x3 and x4 from
origin.
Now along OY, points
1’,2’,3’ and 4’ are marked
at distances y1,y2,y3 and
y4 from O.
Now two tapes are taken with their zero ends together and held at
P1 by the overseer in such a way that when two assistants hold
them fully stretched at 1 and 1’, the readings are exactly equal to
y1 and x1 (i.e. P1 1 = y1 and P1 1’ = x1). Then the point P1 is
marked with a stout peg.
Similarly the other pegs are fixed at P1,P2,P3 and P4. The pegs for
the right half are fixed according to the data available from the
table prepared for the left half. The culvert is symmetrically about
Setting Out Works in Surveying

Setting Out Works in Surveying

  • 1.
    Pillai HOC Collegeof Engineering and Technology Department of Civil EngineeringSurveying-II Presents Setting Out Works Prepared by – Mr. Atul Anand Dongre Assistant Professor, PHCET, Rasayani
  • 2.
    Setting out Works 1. Settingout Foundation plan using centre line plan with batter board 2. Setting out Bridge 3. Setting out Sewer line 4. Setting out Culvert 5. Setting out Tunnel
  • 3.
    1. Setting outFoundation plan using centre line plan with batter board
  • 4.
    Actual Site Method Of Setting out workfor Foundatio n Using Batter Board
  • 5.
  • 7.
    Setting out Sewer Procedure Fixstakes on the ground at the centre line of the proposed sewer at 20m intervals. Set out a parallel line to the proposed centre line of the sewer on one side at a distance apart so that it may not get disturbed during excavation. Excavate the sewer trench of desired width and depth Erect cross heads at 30 m apart and each change of gradient and direction. Set the top edge of each sight rail truly horizontal with the help of a spirit level. Drive in a nail on the top edge at the centre of the sight rail to define the centre line of the sewer.
  • 8.
  • 9.
  • 10.
    The axis (centreline) XX1 and YY1 are set out with O is the origin. Along the line OX1, points 1,2,3 and 4 are marked at distance x1,x2,x3 and x4 from origin. Now along OY, points 1’,2’,3’ and 4’ are marked at distances y1,y2,y3 and y4 from O. Now two tapes are taken with their zero ends together and held at P1 by the overseer in such a way that when two assistants hold them fully stretched at 1 and 1’, the readings are exactly equal to y1 and x1 (i.e. P1 1 = y1 and P1 1’ = x1). Then the point P1 is marked with a stout peg. Similarly the other pegs are fixed at P1,P2,P3 and P4. The pegs for the right half are fixed according to the data available from the table prepared for the left half. The culvert is symmetrically about