SlideShare a Scribd company logo
Week 3 Lecture: Preliminary Works
1
Stages of building construction
1. Preliminary works
2. Foundations
3. Ground floors
4. Frames and upper floors
5. Stairs
6. Roofs
7. Walls and partitions with doors and windows
8. Mechanical and electrical works
9. Internal and external wall, floor and ceiling finishes
10. External works
2
Topics
 Site and soil investigation
 Site clearance and setting out
 Site facilities
 Excavation and timbering
 Site plant and equipment
 Health and safety measures on site
 Scaffolding
3
References
 Chudley, R & Greeno, R 2005, Construction Technology
 Part 1.1 Site Works and Setting Out
 Part 1.4 Excavations and Timbering
 Part 1.5 Scaffolding
 Part 2.1 Trench and Basement Excavation
 Chudley, R & Greeno, R 2006, Advanced Construction
Technology, Part 2 Plant and Equipment
 Chudley, R & Greeno, R 2010, Building Construction
Handbook
 Part 2 Site Works
 Part 3 Builders Plant
 Part 4 Substructure 4
Week 3 Lecture: Preliminary Works
Site & Soil Investigation
5
 _site investigation__ is to collect systematically
and record all the necessary data which will be
needed or will help in the design and construction
processes of the proposed work.
 The collected data should be presented in the form
of fully annotated and dimensioned plans and
sections.
 Anything on adjacent sites which may affect the
proposed works or conversely anything
appertaining to the proposed works which may
affect an adjacent site should also be recorded.
6
7
 Site investigation is all-embracing, taking into
account such factors as location, topography,
accessibility, space, existing services and any local
restrictions.
 Soil investigation could be part of or separate from
the site investigation.
 Soil investigation_ is a means of obtaining data
regarding the characteristics of subsoils by
providing samples for testing or providing a means
of access for visual inspection.
8
 Purposes of soil investigation:
 To determine the suitability of site for the
proposed construction project.
 To determine an adequate and economic
foundation design.
 To determine the difficulties which may arise
during the construction process and period.
 To determine the occurrence and/or cause of all
changes in subsoil conditions.
9
 During the soil investigation, soil samples should
be taken from positions on the site which are truly
representative of the area but are not taken from
the actual position of the proposed foundations.
 Soil samples can be obtained as disturbed or
undisturbed samples.
10
__disturb soil sample___
 These are soil samples obtained from trial pits and
boreholes.
 The method of extraction disturbs the natural
structure of the subsoil.
__undisturb soil sample____
 These are soil samples obtained using sampling shells.
 The method of extraction preserves the natural
structure and properties of the subsoil.
 This method of obtaining soil samples is suitable for
rock and clay subsoils only.
 But difficulties can be experienced in trying to obtain
undisturbed soil samples in other types of subsoil. 11
_disturb soil sample_ _undisturb soil sample_
12
 The test results of
soil samples are
usually shown on a
drawing which gives
the location of each
sample and in the
form of a hatched
section.
 As a general guide,
the cost of site and
soil investigation
should not exceed
1% of estimated
project costs.
13
 The nature and bearing capacity of subsoils can be
determined by the following soil investigation
methods:
 Trial pits
 boreholes
14
 Method chosen will depend on several factors:
 Size of contract
 Type of proposed foundation
 Type of soil sample required
 Type of subsoil which may be encounter
 As a general guide, the most suitable methods in
terms of investigation depth are:
 _trial pits_: small contracts where foundation
depths are not likely to exceed 3m;
 _boreholes__: medium to large contracts with
foundations up to 30m deep.
15
_trial pits__
 The pits can be hand- or machine-excavated to a
plan size of 1.2 x 1.2m.
 Subsoil can be visually examined in-situ on the
faces of the excavated pit, and samples taken for
further laboratory tests.
 The spoil removed will provide disturbed samples
for testing purposes, whereas undisturbed samples
can be cut and extracted from the walls of the pit.
 Suitable for dry ground which requires little or no
temporary support to sides of excavation.
 For exploration of shallow depth up to 3m, this is
usually more economical than boreholes. 16
__trial pits__
17
__boreholes____
 These enable disturbed or undisturbed samples to
be removed for testing.
 Disturbed samples can be obtained by using a
rotary flight auger fixed to a tripod .
 Undisturbed samples can be obtained from
cohesive soils using 450mm long x 100mm
diameter sampling shells, which are driven into the
soil to collect the sample; upon removal the tube is
capped, labelled and sent off to laboratory for
testing.
18
__borehole____
19
__boreholes_____
20
__boreholes___
21
Week 3 Lecture: Preliminary Works
Site Clearance & Setting Out
22
 When a contractor is given possession of a
construction site, he will be provided with the site
layout plan and the detailed drawings necessary
for him to construct the building.
 _site clearance_ shall be undertaken first, which
may involve the demolition of existing buildings,
grubbing out of bushes and trees, and removal of
soil to reduced levels.
 Then the precise placing of a building on a
construction site is determined by _setting out__.
23
1. The first task of setting out is to establish a
baseline from which the whole building can be
referred to.
2. A steel or linen tape (30m would be a suitable
length) can be used for on site measuring.
24
3. After the baseline has been set out, marked and
checked, the main lines of building can be set
out by having each building corner being marked
with a timber peg fixed with nail and string.
25
4. A check should now be made of the setting out
lines for right angles and correct lengths.
5. There are several methods of checking whether a
right angle has been established:
26
_3-4-5 triangle
Theorem of pythagorus_
_builder’s square____
27
__theodolite__
28
Week 3 Lecture: Preliminary Works
Site Facilities
29
 Before the
commencement of
construction works, the
contractor shall set up
the following facilities
at the construction site:
30
Week 3 Lecture: Preliminary Works
Excavation & Timbering
31
 Before a foundation can be constructed, it is
necessary to undertake excavation and timbering.
32
Types of excavation
 Excavation is carried out to remove earth to form a
cavity in the ground.
 Excavations may be classified as shallow, medium
or deep as follows:
 Shallow – up to 1.5m deep;
 Medium – 1.5 – 3.0m deep;
 Deep – over 3.0m deep.
33
1. _oversite excavation
 The removal of topsoil.
34
Oversite excavation
35
2. __ reduce level excavation ____
 Carried out below oversite level to form a level
surface on which to build.
 Consists of cutting and filling operations.
 The level to which the ground is reduced is called
the formation level.
36
_reduce level excavation____
37
3. __trench excavation____
 Long and narrow
excavation primarily
for strip foundations,
ground beams and
buried services.
 Excavation can be
carried out by hand or
mechanical plant.
 Sides of excavation can
be battered or straight.
38
_battered vs straight
39
battered vs straight _
40
4. _pit excavation__
 Isolated holes primarily for column stumps, pad
footings, pile caps and basements.
41
____________________
42
Types of timbering
 Timbering is the temporary supports to the sides
of excavation.
 Sometimes called planking and strutting.
 Purposes of timbering to sides of excavation:
 To uphold the sides of excavation to avoid
collapse of sides.
 To protect the labours while in the excavation.
 To avoid the wasteful labour of constantly
clearing falling earth from the excavation
bottom.
43
 The material most used for temporary support to
the sides of excavation is rough sawn timber.
 The timbers used are struts fixed across the width
of trench, supporting walings and vertical sheeting.
 Whichever system of timbering is used, there
should be as few struts fixed across the width of
trench as possible as these obstruct ease of working
in the trench.
 Struts should be cut to fit tightly between walings
and secured with wedges so that they are not easily
knocked out of place.
44
Trench timbering in loose wet soils
45
Trench excavation & timbering
 Long and narrow trenches in firm soil may be
excavated to the full depth by mechanical
excavators first, then enabling the support
timbering to be placed in one continuous
operation.
 Weak and waterlogged ground must be supported
before excavation commences by driving timber
runners or steel trench sheeting to a position
below the formation level, or by a ____________
procedure.
46
 In the drive and dig procedure, the runners can be
driven to a reasonable depth of approximately 1.5m
followed by an excavation cut of 1.2m and then the
operation repeated until the required level has been
reached.
 This will make the driving of runners easier and
enable a smaller driving appliance to be used.
47
Week 3 Lecture: Preliminary Works
Site Plant & Equipment
48
 Plant and equipment available for use at a construction
site can be classified into: small powered equipment,
earth moving and excavation plant, transportation
plant and concreting plant.
 The choice of site plant and equipment to be used in
any construction activity is a complex matter taking
into account many factors such as volume of soil
involved, nature of site and time elements.
 At this stage, only the basic types of site plant for
excavation activities will be considered here.
 On small contracts such as house extensions,
excavation is effectively carried out by hand, but on
large works it will be more economic to use some form
of plant. 49
__oversit excavation___
50
_mechanical
shovel__
bulldozer__ dumper
 _mechanical shovel___
 Take off layers of soil in buckets.
 It can be raised, lowered or tilted to deposit the earth
into a dumper and removed elsewhere on site.
 __bulldozer_
 Push the soil layer by layer to one side and pile it up
nearby.
 It does not dig or lift out the soil.
 __dumper___
 This truck can perform many tasks on a building site,
including the movement of soil over short distances.
 The body of dumper can dip forward and deposit the
soil in the required position.
51
_reduce level excavation____
52
Mechanical
shovel
bulldozer__
_trench and pit excavation___
53
Backactor_
_face
shovel_
 _backactor___
 These machines are designed to excavate in a
backward motion and are suitable for bulk
excavation work.
 These machines are available as cable rigged or
hydraulic excavators.
 Cable rigged backactors are usually available
with larger bucket sizes and deeper digging
capacities than the hydraulic machines.
 But hydraulic machines have a more positive
control and digging operation and are also easier
to operate.
54
 _face shovel___
 These machines are designed to excavate
forward above their own wheel or track level and
are suitable for bulk excavation work.
 In basement work, they will require a ramp
approach unless they are to be lifted out of the
excavation area by means of a crane.
 Face shovels are available as cable rigged or
hydraulic machines.
55
_trench and pit excavation__
_backactor__ _face shovel_
56
Week 3 Lecture: Preliminary Works
Health & Safety Measures on Site
57
 Possible accidents during
the excavation & timbering
works:
 Falls
 Cave-ins
 Drowning
 Materials/equipments
falling into excavation
 Damage of underground
services
 Explosions
58
 A suitable fence or barrier must be provided to the
sides of excavation.
 Timber or other suitable material must be
provided and used to prevent danger from the fall
or dislodgement of materials forming the sides of
excavation.
 Excavation support need to be installed or
supervised by adequately trained, suitably
knowledgeable and experienced personnel.
 Prior to general access being given, an inspection
of excavation by a competent person (usually the
main contractor’s safety supervisor) must be made
to ensure that work can proceed safely. 59
Barriers to excavation
60
Barriers to excavation
61
 Materials must not be placed near the edge of any
excavation, nor must plant be placed or moved
near excavation so that persons working in the
excavation are endangered.
 For small pits, such as manholes and other limited
excavation, the void may be covered.
 Underground services must be foreseen, located,
identified and assessed for risk to labours working
in excavation.
62
Week 3 Lecture: Preliminary Works
Scaffolding
63
 Scaffoldings are temporary working platforms
erected around the perimeter of a building or
structure to provide a safe working place at a height.
 They are usually required when the working height
is 1.5m or more above the ground level.
 Scaffolding can be of tubular steel, tubular
aluminium alloy, timber or bamboo.
 There are TWO (2) basic forms of scaffolding
namely putlog scaffolds and independent scaffolds.
 Special scaffolds are also available for use, such as
slung, suspended, truss-out and gantry scaffolds, as
well as the easy to erect system scaffolds.
64
Steel vs bamboo scaffolding
65
Basic components of scaffolding
66
Any questions ???
67

More Related Content

What's hot

Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
KHUSHBU SHAH
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
ARUN KUMAR
 
Beams and columns
Beams and columns Beams and columns
Beams and columns
Prabhat chhirolya
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
ANKITAARORA85
 
Shoring
ShoringShoring
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
kamariya keyur
 
Building foundation
Building foundationBuilding foundation
Building foundation
Divya Vishnoi
 
Brickwork Bonding (basics)
Brickwork Bonding (basics)Brickwork Bonding (basics)
Brickwork Bonding (basics)
Steve Jarvis
 
R.C.C. STAIRS
R.C.C. STAIRSR.C.C. STAIRS
R.C.C. STAIRS
Abhishek Mewada
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
Anas Adel
 
Shear wall
Shear wallShear wall
Shear wall
Uma M
 
Roof truss
Roof trussRoof truss
Roof truss
Pankajkumar Singh
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
David H Moloney
 
Piles, Piers and Caissons
Piles, Piers and CaissonsPiles, Piers and Caissons
Piles, Piers and Caissons
Kalokwera Samuel
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
aframawal
 
Pile foundation
Pile foundationPile foundation
Pile foundation
Parth Desani
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methods
DP NITHIN
 

What's hot (20)

Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Beams and columns
Beams and columns Beams and columns
Beams and columns
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Shoring
ShoringShoring
Shoring
 
Rcc fondation
Rcc fondationRcc fondation
Rcc fondation
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Building foundation
Building foundationBuilding foundation
Building foundation
 
Brickwork Bonding (basics)
Brickwork Bonding (basics)Brickwork Bonding (basics)
Brickwork Bonding (basics)
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
R.C.C. STAIRS
R.C.C. STAIRSR.C.C. STAIRS
R.C.C. STAIRS
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
Shear wall
Shear wallShear wall
Shear wall
 
Roof truss
Roof trussRoof truss
Roof truss
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Piles, Piers and Caissons
Piles, Piers and CaissonsPiles, Piers and Caissons
Piles, Piers and Caissons
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methods
 

Similar to (S) Week 3 - Preliminary Works.pptx

CHAP - 1 SOIL INVESTIGATION.ppt civil engineering
CHAP - 1 SOIL INVESTIGATION.ppt civil engineeringCHAP - 1 SOIL INVESTIGATION.ppt civil engineering
CHAP - 1 SOIL INVESTIGATION.ppt civil engineering
teseraaddis1
 
1. Site Investgation.pptxDebre Markos University Technology College Departmen...
1. Site Investgation.pptxDebre Markos University Technology College Departmen...1. Site Investgation.pptxDebre Markos University Technology College Departmen...
1. Site Investgation.pptxDebre Markos University Technology College Departmen...
teseraaddis1
 
Chapter-1-Soil Exploration.ppt
Chapter-1-Soil Exploration.pptChapter-1-Soil Exploration.ppt
Chapter-1-Soil Exploration.ppt
estifanosdemeke1
 
ch-1 foundation.pdf
ch-1 foundation.pdfch-1 foundation.pdf
ch-1 foundation.pdf
semere yilma
 
Hand auger
Hand augerHand auger
Hand auger
Natalie Ulza
 
Site inveswtigation vandana miss
Site inveswtigation vandana missSite inveswtigation vandana miss
Site inveswtigation vandana miss
SHAMJITH KM
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
vietcgxd
 
Module- 3 Subsurface Investigation.pptx
Module- 3 Subsurface Investigation.pptxModule- 3 Subsurface Investigation.pptx
Module- 3 Subsurface Investigation.pptx
SilasChaudhari
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
Sheau Hui Tan
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
RAKESHPANDEY754083
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdfwzhen77
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101
SHAZEBALIKHAN1
 
Bcon final
Bcon finalBcon final
Bcon final
dicky177
 
Foundation
FoundationFoundation
Foundation
Parth Malhotra
 
Subsurface exploration of soil
Subsurface exploration of soilSubsurface exploration of soil
Subsurface exploration of soil
Latif Hyder Wadho
 
Foundation engineering
Foundation engineeringFoundation engineering
Foundation engineering
Shaker Krupa
 
IS 4453: 2009 METHODS OF SUBSURFACE EXPLORATION
IS 4453: 2009 METHODS OF SUBSURFACE EXPLORATIONIS 4453: 2009 METHODS OF SUBSURFACE EXPLORATION
IS 4453: 2009 METHODS OF SUBSURFACE EXPLORATION
Sakshi Rai
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
DHAVASHANKARAN D
 
Geotechnical Engineering-I [Lec #28: Soil Exploration]
Geotechnical Engineering-I [Lec #28: Soil Exploration]Geotechnical Engineering-I [Lec #28: Soil Exploration]
Geotechnical Engineering-I [Lec #28: Soil Exploration]
Muhammad Irfan
 
Machineries and Maintenance Question Patterns for Mining students
Machineries and Maintenance Question Patterns for Mining studentsMachineries and Maintenance Question Patterns for Mining students
Machineries and Maintenance Question Patterns for Mining students
Jessore University of Science & Technology
 

Similar to (S) Week 3 - Preliminary Works.pptx (20)

CHAP - 1 SOIL INVESTIGATION.ppt civil engineering
CHAP - 1 SOIL INVESTIGATION.ppt civil engineeringCHAP - 1 SOIL INVESTIGATION.ppt civil engineering
CHAP - 1 SOIL INVESTIGATION.ppt civil engineering
 
1. Site Investgation.pptxDebre Markos University Technology College Departmen...
1. Site Investgation.pptxDebre Markos University Technology College Departmen...1. Site Investgation.pptxDebre Markos University Technology College Departmen...
1. Site Investgation.pptxDebre Markos University Technology College Departmen...
 
Chapter-1-Soil Exploration.ppt
Chapter-1-Soil Exploration.pptChapter-1-Soil Exploration.ppt
Chapter-1-Soil Exploration.ppt
 
ch-1 foundation.pdf
ch-1 foundation.pdfch-1 foundation.pdf
ch-1 foundation.pdf
 
Hand auger
Hand augerHand auger
Hand auger
 
Site inveswtigation vandana miss
Site inveswtigation vandana missSite inveswtigation vandana miss
Site inveswtigation vandana miss
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
Module- 3 Subsurface Investigation.pptx
Module- 3 Subsurface Investigation.pptxModule- 3 Subsurface Investigation.pptx
Module- 3 Subsurface Investigation.pptx
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdf
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101
 
Bcon final
Bcon finalBcon final
Bcon final
 
Foundation
FoundationFoundation
Foundation
 
Subsurface exploration of soil
Subsurface exploration of soilSubsurface exploration of soil
Subsurface exploration of soil
 
Foundation engineering
Foundation engineeringFoundation engineering
Foundation engineering
 
IS 4453: 2009 METHODS OF SUBSURFACE EXPLORATION
IS 4453: 2009 METHODS OF SUBSURFACE EXPLORATIONIS 4453: 2009 METHODS OF SUBSURFACE EXPLORATION
IS 4453: 2009 METHODS OF SUBSURFACE EXPLORATION
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Geotechnical Engineering-I [Lec #28: Soil Exploration]
Geotechnical Engineering-I [Lec #28: Soil Exploration]Geotechnical Engineering-I [Lec #28: Soil Exploration]
Geotechnical Engineering-I [Lec #28: Soil Exploration]
 
Machineries and Maintenance Question Patterns for Mining students
Machineries and Maintenance Question Patterns for Mining studentsMachineries and Maintenance Question Patterns for Mining students
Machineries and Maintenance Question Patterns for Mining students
 

Recently uploaded

Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
a0966109726
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
World Resources Institute (WRI)
 
Silent nights: The essential role of Nocturnal Pollinators - .pptx
Silent nights: The essential role of Nocturnal Pollinators - .pptxSilent nights: The essential role of Nocturnal Pollinators - .pptx
Silent nights: The essential role of Nocturnal Pollinators - .pptx
Archita Das
 
Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...
Open Access Research Paper
 
Climate Change All over the World .pptx
Climate Change All over the World  .pptxClimate Change All over the World  .pptx
Climate Change All over the World .pptx
sairaanwer024
 
Global Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation AtlasGlobal Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation Atlas
Global Landscapes Forum (GLF)
 
DENR-PENRO-Bulacan-Presentation Philippine EIS
DENR-PENRO-Bulacan-Presentation Philippine EISDENR-PENRO-Bulacan-Presentation Philippine EIS
DENR-PENRO-Bulacan-Presentation Philippine EIS
MarlonJayBayag
 
Overview of the Global Peatlands Assessment
Overview of the Global Peatlands AssessmentOverview of the Global Peatlands Assessment
Overview of the Global Peatlands Assessment
Global Landscapes Forum (GLF)
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
rohankumarsinghrore1
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
JulietMogola
 
Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.
EpconLP
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
Open Access Research Paper
 
Drip Irrigation technology with solar power
Drip Irrigation technology with solar powerDrip Irrigation technology with solar power
Drip Irrigation technology with solar power
anikchanda4
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
BanitaDsouza
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
MMariSelvam4
 
Wildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environmentWildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environment
amishajha2407
 
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Global Landscapes Forum (GLF)
 
ENVIRONMENT~ Renewable Energy Sources and their future prospects.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.ENVIRONMENT~ Renewable Energy Sources and their future prospects.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.
tiwarimanvi3129
 
Peatlands of Latin America and the Caribbean
Peatlands of Latin America and the CaribbeanPeatlands of Latin America and the Caribbean
Peatlands of Latin America and the Caribbean
Global Landscapes Forum (GLF)
 
Peatland Management in Indonesia, Science to Policy and Knowledge Education
Peatland Management in Indonesia, Science to Policy and Knowledge EducationPeatland Management in Indonesia, Science to Policy and Knowledge Education
Peatland Management in Indonesia, Science to Policy and Knowledge Education
Global Landscapes Forum (GLF)
 

Recently uploaded (20)

Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
 
Silent nights: The essential role of Nocturnal Pollinators - .pptx
Silent nights: The essential role of Nocturnal Pollinators - .pptxSilent nights: The essential role of Nocturnal Pollinators - .pptx
Silent nights: The essential role of Nocturnal Pollinators - .pptx
 
Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...Improving the viability of probiotics by encapsulation methods for developmen...
Improving the viability of probiotics by encapsulation methods for developmen...
 
Climate Change All over the World .pptx
Climate Change All over the World  .pptxClimate Change All over the World  .pptx
Climate Change All over the World .pptx
 
Global Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation AtlasGlobal Peatlands Map and Hotspot Explanation Atlas
Global Peatlands Map and Hotspot Explanation Atlas
 
DENR-PENRO-Bulacan-Presentation Philippine EIS
DENR-PENRO-Bulacan-Presentation Philippine EISDENR-PENRO-Bulacan-Presentation Philippine EIS
DENR-PENRO-Bulacan-Presentation Philippine EIS
 
Overview of the Global Peatlands Assessment
Overview of the Global Peatlands AssessmentOverview of the Global Peatlands Assessment
Overview of the Global Peatlands Assessment
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
 
Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.Epcon is One of the World's leading Manufacturing Companies.
Epcon is One of the World's leading Manufacturing Companies.
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
 
Drip Irrigation technology with solar power
Drip Irrigation technology with solar powerDrip Irrigation technology with solar power
Drip Irrigation technology with solar power
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
 
Wildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environmentWildlife-AnIntroduction.pdf so that you know more about our environment
Wildlife-AnIntroduction.pdf so that you know more about our environment
 
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...Improving the Management of Peatlands and the Capacities of Stakeholders in I...
Improving the Management of Peatlands and the Capacities of Stakeholders in I...
 
ENVIRONMENT~ Renewable Energy Sources and their future prospects.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.ENVIRONMENT~ Renewable Energy Sources and their future prospects.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.
 
Peatlands of Latin America and the Caribbean
Peatlands of Latin America and the CaribbeanPeatlands of Latin America and the Caribbean
Peatlands of Latin America and the Caribbean
 
Peatland Management in Indonesia, Science to Policy and Knowledge Education
Peatland Management in Indonesia, Science to Policy and Knowledge EducationPeatland Management in Indonesia, Science to Policy and Knowledge Education
Peatland Management in Indonesia, Science to Policy and Knowledge Education
 

(S) Week 3 - Preliminary Works.pptx

  • 1. Week 3 Lecture: Preliminary Works 1
  • 2. Stages of building construction 1. Preliminary works 2. Foundations 3. Ground floors 4. Frames and upper floors 5. Stairs 6. Roofs 7. Walls and partitions with doors and windows 8. Mechanical and electrical works 9. Internal and external wall, floor and ceiling finishes 10. External works 2
  • 3. Topics  Site and soil investigation  Site clearance and setting out  Site facilities  Excavation and timbering  Site plant and equipment  Health and safety measures on site  Scaffolding 3
  • 4. References  Chudley, R & Greeno, R 2005, Construction Technology  Part 1.1 Site Works and Setting Out  Part 1.4 Excavations and Timbering  Part 1.5 Scaffolding  Part 2.1 Trench and Basement Excavation  Chudley, R & Greeno, R 2006, Advanced Construction Technology, Part 2 Plant and Equipment  Chudley, R & Greeno, R 2010, Building Construction Handbook  Part 2 Site Works  Part 3 Builders Plant  Part 4 Substructure 4
  • 5. Week 3 Lecture: Preliminary Works Site & Soil Investigation 5
  • 6.  _site investigation__ is to collect systematically and record all the necessary data which will be needed or will help in the design and construction processes of the proposed work.  The collected data should be presented in the form of fully annotated and dimensioned plans and sections.  Anything on adjacent sites which may affect the proposed works or conversely anything appertaining to the proposed works which may affect an adjacent site should also be recorded. 6
  • 7. 7
  • 8.  Site investigation is all-embracing, taking into account such factors as location, topography, accessibility, space, existing services and any local restrictions.  Soil investigation could be part of or separate from the site investigation.  Soil investigation_ is a means of obtaining data regarding the characteristics of subsoils by providing samples for testing or providing a means of access for visual inspection. 8
  • 9.  Purposes of soil investigation:  To determine the suitability of site for the proposed construction project.  To determine an adequate and economic foundation design.  To determine the difficulties which may arise during the construction process and period.  To determine the occurrence and/or cause of all changes in subsoil conditions. 9
  • 10.  During the soil investigation, soil samples should be taken from positions on the site which are truly representative of the area but are not taken from the actual position of the proposed foundations.  Soil samples can be obtained as disturbed or undisturbed samples. 10
  • 11. __disturb soil sample___  These are soil samples obtained from trial pits and boreholes.  The method of extraction disturbs the natural structure of the subsoil. __undisturb soil sample____  These are soil samples obtained using sampling shells.  The method of extraction preserves the natural structure and properties of the subsoil.  This method of obtaining soil samples is suitable for rock and clay subsoils only.  But difficulties can be experienced in trying to obtain undisturbed soil samples in other types of subsoil. 11
  • 12. _disturb soil sample_ _undisturb soil sample_ 12
  • 13.  The test results of soil samples are usually shown on a drawing which gives the location of each sample and in the form of a hatched section.  As a general guide, the cost of site and soil investigation should not exceed 1% of estimated project costs. 13
  • 14.  The nature and bearing capacity of subsoils can be determined by the following soil investigation methods:  Trial pits  boreholes 14
  • 15.  Method chosen will depend on several factors:  Size of contract  Type of proposed foundation  Type of soil sample required  Type of subsoil which may be encounter  As a general guide, the most suitable methods in terms of investigation depth are:  _trial pits_: small contracts where foundation depths are not likely to exceed 3m;  _boreholes__: medium to large contracts with foundations up to 30m deep. 15
  • 16. _trial pits__  The pits can be hand- or machine-excavated to a plan size of 1.2 x 1.2m.  Subsoil can be visually examined in-situ on the faces of the excavated pit, and samples taken for further laboratory tests.  The spoil removed will provide disturbed samples for testing purposes, whereas undisturbed samples can be cut and extracted from the walls of the pit.  Suitable for dry ground which requires little or no temporary support to sides of excavation.  For exploration of shallow depth up to 3m, this is usually more economical than boreholes. 16
  • 18. __boreholes____  These enable disturbed or undisturbed samples to be removed for testing.  Disturbed samples can be obtained by using a rotary flight auger fixed to a tripod .  Undisturbed samples can be obtained from cohesive soils using 450mm long x 100mm diameter sampling shells, which are driven into the soil to collect the sample; upon removal the tube is capped, labelled and sent off to laboratory for testing. 18
  • 22. Week 3 Lecture: Preliminary Works Site Clearance & Setting Out 22
  • 23.  When a contractor is given possession of a construction site, he will be provided with the site layout plan and the detailed drawings necessary for him to construct the building.  _site clearance_ shall be undertaken first, which may involve the demolition of existing buildings, grubbing out of bushes and trees, and removal of soil to reduced levels.  Then the precise placing of a building on a construction site is determined by _setting out__. 23
  • 24. 1. The first task of setting out is to establish a baseline from which the whole building can be referred to. 2. A steel or linen tape (30m would be a suitable length) can be used for on site measuring. 24
  • 25. 3. After the baseline has been set out, marked and checked, the main lines of building can be set out by having each building corner being marked with a timber peg fixed with nail and string. 25
  • 26. 4. A check should now be made of the setting out lines for right angles and correct lengths. 5. There are several methods of checking whether a right angle has been established: 26 _3-4-5 triangle Theorem of pythagorus_
  • 29. Week 3 Lecture: Preliminary Works Site Facilities 29
  • 30.  Before the commencement of construction works, the contractor shall set up the following facilities at the construction site: 30
  • 31. Week 3 Lecture: Preliminary Works Excavation & Timbering 31
  • 32.  Before a foundation can be constructed, it is necessary to undertake excavation and timbering. 32
  • 33. Types of excavation  Excavation is carried out to remove earth to form a cavity in the ground.  Excavations may be classified as shallow, medium or deep as follows:  Shallow – up to 1.5m deep;  Medium – 1.5 – 3.0m deep;  Deep – over 3.0m deep. 33
  • 34. 1. _oversite excavation  The removal of topsoil. 34
  • 36. 2. __ reduce level excavation ____  Carried out below oversite level to form a level surface on which to build.  Consists of cutting and filling operations.  The level to which the ground is reduced is called the formation level. 36
  • 38. 3. __trench excavation____  Long and narrow excavation primarily for strip foundations, ground beams and buried services.  Excavation can be carried out by hand or mechanical plant.  Sides of excavation can be battered or straight. 38
  • 41. 4. _pit excavation__  Isolated holes primarily for column stumps, pad footings, pile caps and basements. 41
  • 43. Types of timbering  Timbering is the temporary supports to the sides of excavation.  Sometimes called planking and strutting.  Purposes of timbering to sides of excavation:  To uphold the sides of excavation to avoid collapse of sides.  To protect the labours while in the excavation.  To avoid the wasteful labour of constantly clearing falling earth from the excavation bottom. 43
  • 44.  The material most used for temporary support to the sides of excavation is rough sawn timber.  The timbers used are struts fixed across the width of trench, supporting walings and vertical sheeting.  Whichever system of timbering is used, there should be as few struts fixed across the width of trench as possible as these obstruct ease of working in the trench.  Struts should be cut to fit tightly between walings and secured with wedges so that they are not easily knocked out of place. 44
  • 45. Trench timbering in loose wet soils 45
  • 46. Trench excavation & timbering  Long and narrow trenches in firm soil may be excavated to the full depth by mechanical excavators first, then enabling the support timbering to be placed in one continuous operation.  Weak and waterlogged ground must be supported before excavation commences by driving timber runners or steel trench sheeting to a position below the formation level, or by a ____________ procedure. 46
  • 47.  In the drive and dig procedure, the runners can be driven to a reasonable depth of approximately 1.5m followed by an excavation cut of 1.2m and then the operation repeated until the required level has been reached.  This will make the driving of runners easier and enable a smaller driving appliance to be used. 47
  • 48. Week 3 Lecture: Preliminary Works Site Plant & Equipment 48
  • 49.  Plant and equipment available for use at a construction site can be classified into: small powered equipment, earth moving and excavation plant, transportation plant and concreting plant.  The choice of site plant and equipment to be used in any construction activity is a complex matter taking into account many factors such as volume of soil involved, nature of site and time elements.  At this stage, only the basic types of site plant for excavation activities will be considered here.  On small contracts such as house extensions, excavation is effectively carried out by hand, but on large works it will be more economic to use some form of plant. 49
  • 51.  _mechanical shovel___  Take off layers of soil in buckets.  It can be raised, lowered or tilted to deposit the earth into a dumper and removed elsewhere on site.  __bulldozer_  Push the soil layer by layer to one side and pile it up nearby.  It does not dig or lift out the soil.  __dumper___  This truck can perform many tasks on a building site, including the movement of soil over short distances.  The body of dumper can dip forward and deposit the soil in the required position. 51
  • 53. _trench and pit excavation___ 53 Backactor_ _face shovel_
  • 54.  _backactor___  These machines are designed to excavate in a backward motion and are suitable for bulk excavation work.  These machines are available as cable rigged or hydraulic excavators.  Cable rigged backactors are usually available with larger bucket sizes and deeper digging capacities than the hydraulic machines.  But hydraulic machines have a more positive control and digging operation and are also easier to operate. 54
  • 55.  _face shovel___  These machines are designed to excavate forward above their own wheel or track level and are suitable for bulk excavation work.  In basement work, they will require a ramp approach unless they are to be lifted out of the excavation area by means of a crane.  Face shovels are available as cable rigged or hydraulic machines. 55
  • 56. _trench and pit excavation__ _backactor__ _face shovel_ 56
  • 57. Week 3 Lecture: Preliminary Works Health & Safety Measures on Site 57
  • 58.  Possible accidents during the excavation & timbering works:  Falls  Cave-ins  Drowning  Materials/equipments falling into excavation  Damage of underground services  Explosions 58
  • 59.  A suitable fence or barrier must be provided to the sides of excavation.  Timber or other suitable material must be provided and used to prevent danger from the fall or dislodgement of materials forming the sides of excavation.  Excavation support need to be installed or supervised by adequately trained, suitably knowledgeable and experienced personnel.  Prior to general access being given, an inspection of excavation by a competent person (usually the main contractor’s safety supervisor) must be made to ensure that work can proceed safely. 59
  • 62.  Materials must not be placed near the edge of any excavation, nor must plant be placed or moved near excavation so that persons working in the excavation are endangered.  For small pits, such as manholes and other limited excavation, the void may be covered.  Underground services must be foreseen, located, identified and assessed for risk to labours working in excavation. 62
  • 63. Week 3 Lecture: Preliminary Works Scaffolding 63
  • 64.  Scaffoldings are temporary working platforms erected around the perimeter of a building or structure to provide a safe working place at a height.  They are usually required when the working height is 1.5m or more above the ground level.  Scaffolding can be of tubular steel, tubular aluminium alloy, timber or bamboo.  There are TWO (2) basic forms of scaffolding namely putlog scaffolds and independent scaffolds.  Special scaffolds are also available for use, such as slung, suspended, truss-out and gantry scaffolds, as well as the easy to erect system scaffolds. 64
  • 65. Steel vs bamboo scaffolding 65
  • 66. Basic components of scaffolding 66