PRESIDENTIAL DECREE 1586
THE PHILIPPINE ENVIRONMENTAL IMPACT
STATEMENT SYSTEM
Hiyas ng Bulacan Convention Center, Capitol Compound,
City of Malolos,Bulacan
September 23, 2019
ENVIRONMENTAL MANAGEMENT BUREAU (emb)
• Executive Order (EO) 192: [Sections 4 & 5] “Providing for the
Reorganization of Department of Environment, Energy and Natural
Resources (DEENR) renaming it as the Department of
Environment and Natural Resources (DENR), and for other
Purposes”
• Section 16: Creation of the Environmental Management Bureau
(EMB)
ENVIRONMENTAL MANAGEMENT BUREAU (emb)
> VISION
A nation empowered to protect our
finite resources, attuned to the
pursuit of sustainable development,
for a clean and healthy environment
that enhances the Filipino quality of
life for present and future generations
> MISSION
To restore, protect and enhance
environmental quality towards
good public health,
environmental integrity and
economic viability.
P.D. 1586: The Philippine Environmental Impact
Statement (EIS) System of 1978
R.A. 8749: The Philippine Clean Air Act of 1990
R.A. 9003: The Ecological Solid Waste Management
Act of 2000
R.A. 9275: The Philippine Clean Water Act of 2004
R.A. 6969: Toxic Substances and Hazardous and
Nuclear Waste Control Act of 1990
R.A. 9512: Environmental Awareness and Education
Act of 2008
Under E.O. 192, EMB is also mandated to provide research and laboratory services, and serve as secretariat in the
adjudication of pollution cases.
MANDATES
ENVIRONMENTAL IMPACT
STATEMENT SYSTEM OF
1978 (PD 1586)
- Requires all government agencies,
government-owned or controlled
corporation and private companies
to prepare an environmental
impact assessment for all
development projects and
undertaking that will significantly
affect the quality of the environment
prior issuance of Environmental
Compliance Certificate (ECC) by
DENR
- It is a planning tool (environmental
costs must be considered during
the conduct of the Feasibility Study)
IMPLEMENTING RULES AND REGULATIONS
> DAO 2003-30: “Revised Procedural Manual for the Implementation of the Philippine
Environmental Impact Statement System(PEISS)”
> EMB Memorandum Circular 2007-02: “Guidelines on the Screening for Coverage
and other Application Requirements under the PEISS”
> DENR Memorandum Circular 2010-14: “Standardization of Requirements in the
Implementation of the PEISS”
> EMB Memorandum Circular 2014-05: “Guidelines for Coverage Screening and
Standardized Requirements under PEISS amending relevant portions of EMB MC
2007-02”
ACRONYMS
> ECPs – Environmentally Critical Projects (under Presidential Proclamation 1981-2146)
> ECAs – Environmentally Critical Areas (under Presidential Proclamation 1981-2146)
> EIA Report – Environmental Impact Assessment Report (in the form of an EIS)
> IEE – Initial Environmental Examination
> EPRMP – Environmental Performance Report and Management Plan
> CNC – Certificate of Non-Coverage
> EMP – Environmental Management Plan
PROCESS/PROCEDURE
> SCOPING
- Public Scoping (initial preparatory meeting with the host community[ies])
- Technical Scoping (presentation by the proponent to the Review Committee [RevCom] of
the proposed project)
> CONSULTATION/HEARING
- Public consultation with the Stakeholders (Proponent & Review Committee Members) on
the proposed Project to determine its Social Acceptability)
> REVIEW
- EMB convenes a Multi-disciplinary Experts to be member of the RevCom
> MONITORING AND VALIDATION
> APPROVAL/DENIAL
EMB Memorandum Circular 2014-05: “Guidelines for Coverage Screening
and Standardized Requirements under PEISS amending relevant portions
of EMB MC 2007-02”
> Section 1. Screening to determine coverage………..
- Categories of Project ( A to D)
> Section 2. Standard requirements
- Document requirements (EIS, IEE, IEE Checklist, EPRMP)
- Responsible Office to Process (Central Office or Regional
Office concerned)
> Section 3. Repealing Clause
FOUR CATEGORIES OF
ENVIRONMENTALLY
CRITICAL PROJECTS
- Non Ferrous Metal
Industries
- Iron and Steel Mills
- Petroleum and
Petrochemical
Industries
- Smelting Plants
11
HEAVY INDUSTRIES
- Mining and
Quarrying Projects
- Forestry Projects
- Dikes for/and
Fishpond
Development
Projects
12
RESOURCE EXTRACTIVE
INDUSTRIES
INFRASTRUCTURE
PROJECTS
13
- Dams
- Power Plants
- Reclamation
Projects
- Roads and
Bridges
14
GOLF COURSE AND
OTHER TOURISM PROJECTS
- GOLF COURSE
- RESORTS
- OTHER LEISURE
Projects
15
Projects mayrequireEITHER an
EnvironmentalCompliance
Certificate ORCertificateof
Non-Coverage,dependingon
thethreshold or capacity.
http://eia.emb.gov.ph/wpcontent/
uploads/2016/06/Revised-
Guidelines-for-Coverage-
Screening-and-
Standardized-Reqts.pdf
EMB Memorandum
Circular 005 July
2014
16
Tablet project
Show and explain your
web, app or software
projects using these
gadget templates.
- Office Buildings with a gross floor area of more
than 10,000 square meters
- Commercial Establishments with a gross floor
area of more than 10,000 square meters
- New Road Construction and Road
Rehabilitations with a length of more than 2
kilometres
- Cemeteries/Memorial Parks with a gross floor
area of more than 10,000 kilometers
Project Covered by PD 1586
A document issued by the DENR-EMB after a
positive review of an application, certifying
that the proposed project has complied with
all the requirements of the Environmental
Impact Statement System
What is an ECC?
DENR-PENRO-Bulacan-Presentation Philippine EIS
DENR-PENRO-Bulacan-Presentation Philippine EIS
DENR-PENRO-Bulacan-Presentation Philippine EIS
22
Go to emb.gov.ph and click the link to ECC Online
Application.
23
It certifies that, based on the submitted
Project Description Report, the project is not
covered by the EIS System and is not required
to secure an ECC. Further, the CNC advises
the Proponent on coverage to other
requirements by other DENR offices, LGUs or
other government agencies.
What is a Certificate of Non-Coverage (CNC)?
DENR-PENRO-Bulacan-Presentation Philippine EIS
25
Go to emb.gov.ph, then click the link to CNC Online
Application.
26
Verify the coverage of the Project
27
Indicate the location of the project and project
component
28
29
Determine the Project Category
30
31
Answer the four (4) questions
32
Apply for CNC
33
Fill-up the Project Information
34
Download and print the Order of Payment
35
Update the payment
36
Enter the Application Reference Number
37
Upload the receipt and valid ID
38
Track the status
3
9
Please Visit the ff site:-emb.gov.ph
-http://119.92.161.13/projectchecker.aspx (For CNC
application only)
-Project Layout
-Government ID
-Bank Receipt
Requirements of cnc application
-Proof of Compatibility with the existing Land Use Plan (zoning)
-Proof of authority over the Project Site (Title, Lease or Contract, etc.)
-Accountability Statement of Proponents (see attached form) and the
preparation (if any, ff. annexes of revised procedural manual for DAO 2003-30)
-Photographs of plates/Site Dev't Plan/Vicinity map of the project site showing
impact areas and affected areas and communities.
-Duly Accomplished Project Environmental Monitoring &Audit
Prioritization Scheme (PEMAPS) Questionnaire (see Annex 2-7d of revised
procedural manual for DAO 2003-30
Requirements of ECC application
Streamlined Environmental Impact Assessment Process
- Fast tracked ECC Processing
- 40 days - Environmentally Critical Projects (ECP)
- 20 days - Non-ECPs
- Seven (7) days CNC online processing
- ECA and Industrial Mapping
- Posting of ECC in the Internet and Online Project
Screening for non-coverage
43
Thank you
and
have a good day!

More Related Content

Similar to DENR-PENRO-Bulacan-Presentation Philippine EIS

ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, ECENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
B. BHASKAR
 
Env training ppt rev01
Env training ppt rev01Env training ppt rev01
Env training ppt rev01
Indonesia Infrastructure Initiative
 
The-EIS-System-in-Phillipine.ppt
The-EIS-System-in-Phillipine.pptThe-EIS-System-in-Phillipine.ppt
The-EIS-System-in-Phillipine.ppt
sheenamaedadodave
 
KISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAKISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIA
MNIT,JAIPUR
 
Final booklet
Final bookletFinal booklet
Final booklet
Probodh Mallick
 
cwa
cwacwa
EIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
EIA FE COURSE Lecture for Aspiring Field Engineers in the PhilippinesEIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
EIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
MakrisMontejoMalinam
 
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)
Palash Mehar
 
Basic concept of environment safeguard
Basic concept of environment safeguardBasic concept of environment safeguard
Basic concept of environment safeguard
Dr Deepak Kumar Tripathi
 
Group-10.pptx
Group-10.pptxGroup-10.pptx
Group-10.pptx
KhennGarofil
 
draftstadiumeir
draftstadiumeirdraftstadiumeir
draftstadiumeir
Lynette Leighton
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
SonikaPawar
 
Construction management
Construction managementConstruction management
Construction management
vhjadhav
 
Cuyahoga County Municipal Energy Workshop
Cuyahoga County Municipal Energy WorkshopCuyahoga County Municipal Energy Workshop
Cuyahoga County Municipal Energy Workshop
Cuyahoga County Planning Commission
 
LESCO- EIA report
LESCO- EIA reportLESCO- EIA report
LESCO- EIA report
Ash Hassan
 
Eia regulations
Eia regulationsEia regulations
Eia regulations
Maham Basharat
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
Shubhranshu Upadhyay
 
Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997
Abdullah Saif
 
Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997
Abdullah Saif
 
The Environment Conservation Rules, 1997
The Environment Conservation Rules, 1997 The Environment Conservation Rules, 1997
The Environment Conservation Rules, 1997
Priodeep Chowdhury
 

Similar to DENR-PENRO-Bulacan-Presentation Philippine EIS (20)

ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, ECENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
 
Env training ppt rev01
Env training ppt rev01Env training ppt rev01
Env training ppt rev01
 
The-EIS-System-in-Phillipine.ppt
The-EIS-System-in-Phillipine.pptThe-EIS-System-in-Phillipine.ppt
The-EIS-System-in-Phillipine.ppt
 
KISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAKISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIA
 
Final booklet
Final bookletFinal booklet
Final booklet
 
cwa
cwacwa
cwa
 
EIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
EIA FE COURSE Lecture for Aspiring Field Engineers in the PhilippinesEIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
EIA FE COURSE Lecture for Aspiring Field Engineers in the Philippines
 
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)
 
Basic concept of environment safeguard
Basic concept of environment safeguardBasic concept of environment safeguard
Basic concept of environment safeguard
 
Group-10.pptx
Group-10.pptxGroup-10.pptx
Group-10.pptx
 
draftstadiumeir
draftstadiumeirdraftstadiumeir
draftstadiumeir
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Construction management
Construction managementConstruction management
Construction management
 
Cuyahoga County Municipal Energy Workshop
Cuyahoga County Municipal Energy WorkshopCuyahoga County Municipal Energy Workshop
Cuyahoga County Municipal Energy Workshop
 
LESCO- EIA report
LESCO- EIA reportLESCO- EIA report
LESCO- EIA report
 
Eia regulations
Eia regulationsEia regulations
Eia regulations
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997
 
Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997Bangladesh environmental conservation rules,1997
Bangladesh environmental conservation rules,1997
 
The Environment Conservation Rules, 1997
The Environment Conservation Rules, 1997 The Environment Conservation Rules, 1997
The Environment Conservation Rules, 1997
 

Recently uploaded

Delhi Girls Call WhatsApp Numbers 🫦9711199171🫦 List For Friendship Girls Service
Delhi Girls Call WhatsApp Numbers 🫦9711199171🫦 List For Friendship Girls ServiceDelhi Girls Call WhatsApp Numbers 🫦9711199171🫦 List For Friendship Girls Service
Delhi Girls Call WhatsApp Numbers 🫦9711199171🫦 List For Friendship Girls Service
janvikumar4133
 
News Clippings and Newspapers related to Climate Change
News Clippings and Newspapers related to Climate ChangeNews Clippings and Newspapers related to Climate Change
News Clippings and Newspapers related to Climate Change
parasfahimshehri
 
Top Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
Top Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...Top Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
Top Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
janvikumar4133
 
Mumbai Girls Call WhatsApp Numbers 🫦9967584737🫦 List For Friendship Girls Ser...
Mumbai Girls Call WhatsApp Numbers 🫦9967584737🫦 List For Friendship Girls Ser...Mumbai Girls Call WhatsApp Numbers 🫦9967584737🫦 List For Friendship Girls Ser...
Mumbai Girls Call WhatsApp Numbers 🫦9967584737🫦 List For Friendship Girls Ser...
radhika sharma
 
Relation between tourism and environment in development
Relation between tourism and environment in developmentRelation between tourism and environment in development
Relation between tourism and environment in development
bikramkunwar2020d
 
WORLD POPULATION AND YOUTH DAY 2024.....
WORLD POPULATION AND YOUTH DAY 2024.....WORLD POPULATION AND YOUTH DAY 2024.....
WORLD POPULATION AND YOUTH DAY 2024.....
geetikamehta1998
 
University of Miami degree offer diploma Transcript
University of Miami degree offer diploma TranscriptUniversity of Miami degree offer diploma Transcript
University of Miami degree offer diploma Transcript
etwvyv
 
Dating Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 ...
Dating Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 ...Dating Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 ...
Dating Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 ...
sonamrawat5631
 
Tax Audit and Investigation in Poor Documentation Environment - Prof Oyedokun...
Tax Audit and Investigation in Poor Documentation Environment - Prof Oyedokun...Tax Audit and Investigation in Poor Documentation Environment - Prof Oyedokun...
Tax Audit and Investigation in Poor Documentation Environment - Prof Oyedokun...
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
PREDICTION OF WATER PORTABILITY USING CLASSIFICATION TECHNIQUES.docx
PREDICTION OF WATER PORTABILITY USING CLASSIFICATION TECHNIQUES.docxPREDICTION OF WATER PORTABILITY USING CLASSIFICATION TECHNIQUES.docx
PREDICTION OF WATER PORTABILITY USING CLASSIFICATION TECHNIQUES.docx
saisruthikunduru
 
Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in City
Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in CityGirls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in City
Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in City
janvikumar4133
 
Detachment, distinguishing proof of bacterial pathogens from infected Shing (...
Detachment, distinguishing proof of bacterial pathogens from infected Shing (...Detachment, distinguishing proof of bacterial pathogens from infected Shing (...
Detachment, distinguishing proof of bacterial pathogens from infected Shing (...
Open Access Research Paper
 
George Washington University degree offer diploma Transcript
George Washington University degree offer diploma TranscriptGeorge Washington University degree offer diploma Transcript
George Washington University degree offer diploma Transcript
etwvyv
 
VIP Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
VIP Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...VIP Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
VIP Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
janvikumar4133
 
Novel biosynthesized nanosilver impregnated heat modified montmorillonite cla...
Novel biosynthesized nanosilver impregnated heat modified montmorillonite cla...Novel biosynthesized nanosilver impregnated heat modified montmorillonite cla...
Novel biosynthesized nanosilver impregnated heat modified montmorillonite cla...
Open Access Research Paper
 
naturalfarmingdr-240528124201-7ebd8d09.pdf
naturalfarmingdr-240528124201-7ebd8d09.pdfnaturalfarmingdr-240528124201-7ebd8d09.pdf
naturalfarmingdr-240528124201-7ebd8d09.pdf
HARKESHMEENA15
 
Global Climate Change Presentation of the world
Global Climate Change Presentation of the worldGlobal Climate Change Presentation of the world
Global Climate Change Presentation of the world
tkubatbekov
 
The Bank of Punjab: The Official Website
The Bank of Punjab: The Official WebsiteThe Bank of Punjab: The Official Website
The Bank of Punjab: The Official Website
reema kushawaha
 
Best Soil For Vertical Garden: A Complete Guide
Best Soil For Vertical Garden: A Complete GuideBest Soil For Vertical Garden: A Complete Guide
Best Soil For Vertical Garden: A Complete Guide
Jakariya sarkar
 
300169310-Seminar-Report-on-hydrogen-as-the-future-fuel.docx
300169310-Seminar-Report-on-hydrogen-as-the-future-fuel.docx300169310-Seminar-Report-on-hydrogen-as-the-future-fuel.docx
300169310-Seminar-Report-on-hydrogen-as-the-future-fuel.docx
harshitkulshrestha02
 

Recently uploaded (20)

Delhi Girls Call WhatsApp Numbers 🫦9711199171🫦 List For Friendship Girls Service
Delhi Girls Call WhatsApp Numbers 🫦9711199171🫦 List For Friendship Girls ServiceDelhi Girls Call WhatsApp Numbers 🫦9711199171🫦 List For Friendship Girls Service
Delhi Girls Call WhatsApp Numbers 🫦9711199171🫦 List For Friendship Girls Service
 
News Clippings and Newspapers related to Climate Change
News Clippings and Newspapers related to Climate ChangeNews Clippings and Newspapers related to Climate Change
News Clippings and Newspapers related to Climate Change
 
Top Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
Top Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...Top Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
Top Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
 
Mumbai Girls Call WhatsApp Numbers 🫦9967584737🫦 List For Friendship Girls Ser...
Mumbai Girls Call WhatsApp Numbers 🫦9967584737🫦 List For Friendship Girls Ser...Mumbai Girls Call WhatsApp Numbers 🫦9967584737🫦 List For Friendship Girls Ser...
Mumbai Girls Call WhatsApp Numbers 🫦9967584737🫦 List For Friendship Girls Ser...
 
Relation between tourism and environment in development
Relation between tourism and environment in developmentRelation between tourism and environment in development
Relation between tourism and environment in development
 
WORLD POPULATION AND YOUTH DAY 2024.....
WORLD POPULATION AND YOUTH DAY 2024.....WORLD POPULATION AND YOUTH DAY 2024.....
WORLD POPULATION AND YOUTH DAY 2024.....
 
University of Miami degree offer diploma Transcript
University of Miami degree offer diploma TranscriptUniversity of Miami degree offer diploma Transcript
University of Miami degree offer diploma Transcript
 
Dating Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 ...
Dating Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 ...Dating Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 ...
Dating Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 ...
 
Tax Audit and Investigation in Poor Documentation Environment - Prof Oyedokun...
Tax Audit and Investigation in Poor Documentation Environment - Prof Oyedokun...Tax Audit and Investigation in Poor Documentation Environment - Prof Oyedokun...
Tax Audit and Investigation in Poor Documentation Environment - Prof Oyedokun...
 
PREDICTION OF WATER PORTABILITY USING CLASSIFICATION TECHNIQUES.docx
PREDICTION OF WATER PORTABILITY USING CLASSIFICATION TECHNIQUES.docxPREDICTION OF WATER PORTABILITY USING CLASSIFICATION TECHNIQUES.docx
PREDICTION OF WATER PORTABILITY USING CLASSIFICATION TECHNIQUES.docx
 
Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in City
Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in CityGirls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in City
Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in City
 
Detachment, distinguishing proof of bacterial pathogens from infected Shing (...
Detachment, distinguishing proof of bacterial pathogens from infected Shing (...Detachment, distinguishing proof of bacterial pathogens from infected Shing (...
Detachment, distinguishing proof of bacterial pathogens from infected Shing (...
 
George Washington University degree offer diploma Transcript
George Washington University degree offer diploma TranscriptGeorge Washington University degree offer diploma Transcript
George Washington University degree offer diploma Transcript
 
VIP Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
VIP Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...VIP Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
VIP Girls Call Delhi 9711199171 Provide Best And Top Girl Service And No1 in ...
 
Novel biosynthesized nanosilver impregnated heat modified montmorillonite cla...
Novel biosynthesized nanosilver impregnated heat modified montmorillonite cla...Novel biosynthesized nanosilver impregnated heat modified montmorillonite cla...
Novel biosynthesized nanosilver impregnated heat modified montmorillonite cla...
 
naturalfarmingdr-240528124201-7ebd8d09.pdf
naturalfarmingdr-240528124201-7ebd8d09.pdfnaturalfarmingdr-240528124201-7ebd8d09.pdf
naturalfarmingdr-240528124201-7ebd8d09.pdf
 
Global Climate Change Presentation of the world
Global Climate Change Presentation of the worldGlobal Climate Change Presentation of the world
Global Climate Change Presentation of the world
 
The Bank of Punjab: The Official Website
The Bank of Punjab: The Official WebsiteThe Bank of Punjab: The Official Website
The Bank of Punjab: The Official Website
 
Best Soil For Vertical Garden: A Complete Guide
Best Soil For Vertical Garden: A Complete GuideBest Soil For Vertical Garden: A Complete Guide
Best Soil For Vertical Garden: A Complete Guide
 
300169310-Seminar-Report-on-hydrogen-as-the-future-fuel.docx
300169310-Seminar-Report-on-hydrogen-as-the-future-fuel.docx300169310-Seminar-Report-on-hydrogen-as-the-future-fuel.docx
300169310-Seminar-Report-on-hydrogen-as-the-future-fuel.docx
 

DENR-PENRO-Bulacan-Presentation Philippine EIS

  • 1. PRESIDENTIAL DECREE 1586 THE PHILIPPINE ENVIRONMENTAL IMPACT STATEMENT SYSTEM Hiyas ng Bulacan Convention Center, Capitol Compound, City of Malolos,Bulacan September 23, 2019
  • 2. ENVIRONMENTAL MANAGEMENT BUREAU (emb) • Executive Order (EO) 192: [Sections 4 & 5] “Providing for the Reorganization of Department of Environment, Energy and Natural Resources (DEENR) renaming it as the Department of Environment and Natural Resources (DENR), and for other Purposes” • Section 16: Creation of the Environmental Management Bureau (EMB)
  • 3. ENVIRONMENTAL MANAGEMENT BUREAU (emb) > VISION A nation empowered to protect our finite resources, attuned to the pursuit of sustainable development, for a clean and healthy environment that enhances the Filipino quality of life for present and future generations > MISSION To restore, protect and enhance environmental quality towards good public health, environmental integrity and economic viability.
  • 4. P.D. 1586: The Philippine Environmental Impact Statement (EIS) System of 1978 R.A. 8749: The Philippine Clean Air Act of 1990 R.A. 9003: The Ecological Solid Waste Management Act of 2000 R.A. 9275: The Philippine Clean Water Act of 2004 R.A. 6969: Toxic Substances and Hazardous and Nuclear Waste Control Act of 1990 R.A. 9512: Environmental Awareness and Education Act of 2008 Under E.O. 192, EMB is also mandated to provide research and laboratory services, and serve as secretariat in the adjudication of pollution cases. MANDATES
  • 5. ENVIRONMENTAL IMPACT STATEMENT SYSTEM OF 1978 (PD 1586) - Requires all government agencies, government-owned or controlled corporation and private companies to prepare an environmental impact assessment for all development projects and undertaking that will significantly affect the quality of the environment prior issuance of Environmental Compliance Certificate (ECC) by DENR - It is a planning tool (environmental costs must be considered during the conduct of the Feasibility Study)
  • 6. IMPLEMENTING RULES AND REGULATIONS > DAO 2003-30: “Revised Procedural Manual for the Implementation of the Philippine Environmental Impact Statement System(PEISS)” > EMB Memorandum Circular 2007-02: “Guidelines on the Screening for Coverage and other Application Requirements under the PEISS” > DENR Memorandum Circular 2010-14: “Standardization of Requirements in the Implementation of the PEISS” > EMB Memorandum Circular 2014-05: “Guidelines for Coverage Screening and Standardized Requirements under PEISS amending relevant portions of EMB MC 2007-02”
  • 7. ACRONYMS > ECPs – Environmentally Critical Projects (under Presidential Proclamation 1981-2146) > ECAs – Environmentally Critical Areas (under Presidential Proclamation 1981-2146) > EIA Report – Environmental Impact Assessment Report (in the form of an EIS) > IEE – Initial Environmental Examination > EPRMP – Environmental Performance Report and Management Plan > CNC – Certificate of Non-Coverage > EMP – Environmental Management Plan
  • 8. PROCESS/PROCEDURE > SCOPING - Public Scoping (initial preparatory meeting with the host community[ies]) - Technical Scoping (presentation by the proponent to the Review Committee [RevCom] of the proposed project) > CONSULTATION/HEARING - Public consultation with the Stakeholders (Proponent & Review Committee Members) on the proposed Project to determine its Social Acceptability) > REVIEW - EMB convenes a Multi-disciplinary Experts to be member of the RevCom > MONITORING AND VALIDATION > APPROVAL/DENIAL
  • 9. EMB Memorandum Circular 2014-05: “Guidelines for Coverage Screening and Standardized Requirements under PEISS amending relevant portions of EMB MC 2007-02” > Section 1. Screening to determine coverage……….. - Categories of Project ( A to D) > Section 2. Standard requirements - Document requirements (EIS, IEE, IEE Checklist, EPRMP) - Responsible Office to Process (Central Office or Regional Office concerned) > Section 3. Repealing Clause
  • 11. - Non Ferrous Metal Industries - Iron and Steel Mills - Petroleum and Petrochemical Industries - Smelting Plants 11 HEAVY INDUSTRIES
  • 12. - Mining and Quarrying Projects - Forestry Projects - Dikes for/and Fishpond Development Projects 12 RESOURCE EXTRACTIVE INDUSTRIES
  • 13. INFRASTRUCTURE PROJECTS 13 - Dams - Power Plants - Reclamation Projects - Roads and Bridges
  • 14. 14 GOLF COURSE AND OTHER TOURISM PROJECTS - GOLF COURSE - RESORTS - OTHER LEISURE Projects
  • 15. 15 Projects mayrequireEITHER an EnvironmentalCompliance Certificate ORCertificateof Non-Coverage,dependingon thethreshold or capacity.
  • 16. http://eia.emb.gov.ph/wpcontent/ uploads/2016/06/Revised- Guidelines-for-Coverage- Screening-and- Standardized-Reqts.pdf EMB Memorandum Circular 005 July 2014 16 Tablet project Show and explain your web, app or software projects using these gadget templates.
  • 17. - Office Buildings with a gross floor area of more than 10,000 square meters - Commercial Establishments with a gross floor area of more than 10,000 square meters - New Road Construction and Road Rehabilitations with a length of more than 2 kilometres - Cemeteries/Memorial Parks with a gross floor area of more than 10,000 kilometers Project Covered by PD 1586
  • 18. A document issued by the DENR-EMB after a positive review of an application, certifying that the proposed project has complied with all the requirements of the Environmental Impact Statement System What is an ECC?
  • 22. 22 Go to emb.gov.ph and click the link to ECC Online Application.
  • 23. 23 It certifies that, based on the submitted Project Description Report, the project is not covered by the EIS System and is not required to secure an ECC. Further, the CNC advises the Proponent on coverage to other requirements by other DENR offices, LGUs or other government agencies. What is a Certificate of Non-Coverage (CNC)?
  • 25. 25 Go to emb.gov.ph, then click the link to CNC Online Application.
  • 26. 26 Verify the coverage of the Project
  • 27. 27 Indicate the location of the project and project component
  • 28. 28
  • 30. 30
  • 31. 31 Answer the four (4) questions
  • 33. 33 Fill-up the Project Information
  • 34. 34 Download and print the Order of Payment
  • 36. 36 Enter the Application Reference Number
  • 37. 37 Upload the receipt and valid ID
  • 39. 3 9 Please Visit the ff site:-emb.gov.ph -http://119.92.161.13/projectchecker.aspx (For CNC application only) -Project Layout -Government ID -Bank Receipt Requirements of cnc application
  • 40. -Proof of Compatibility with the existing Land Use Plan (zoning) -Proof of authority over the Project Site (Title, Lease or Contract, etc.) -Accountability Statement of Proponents (see attached form) and the preparation (if any, ff. annexes of revised procedural manual for DAO 2003-30) -Photographs of plates/Site Dev't Plan/Vicinity map of the project site showing impact areas and affected areas and communities. -Duly Accomplished Project Environmental Monitoring &Audit Prioritization Scheme (PEMAPS) Questionnaire (see Annex 2-7d of revised procedural manual for DAO 2003-30 Requirements of ECC application
  • 41. Streamlined Environmental Impact Assessment Process - Fast tracked ECC Processing - 40 days - Environmentally Critical Projects (ECP) - 20 days - Non-ECPs - Seven (7) days CNC online processing - ECA and Industrial Mapping - Posting of ECC in the Internet and Online Project Screening for non-coverage