SlideShare a Scribd company logo
A Report On Trench & Excavation
Safety
SH16030 & SH16031 | PGP-HSEM
National Institute of Construction Management And Research, Hyderabad 1
A REPORT ON TRENCH AND EXCAVATION SAFETY
INTRODUCTION
Excavation and trenching are among the most hazardous construction operations. It
is generally used for foundation purpose, laying down sewer lines, electrical lines,
phone lines, etc. So while performing this activity safety precautions needs to be
taken because it can cause harm to life of worker and property as well. Most of the
times the accident is happened because of cave-ins which may sometimes leads to
death of worker.
Definitions
Excavation – Any man made cut, cavity, trench or depression made in the earth’s
surface formed by earth removal.
Trench – A narrow excavation made below ground surface.
In general, the depth is greater than width, but the width is no greater than 15 feet.
Shoring – A structure such as a metal hydraulic, mechanical or timber system that
supports the side of excavation and designed to prevent cave-ins.
Shield - A structure able to withstand a cave-in and protect employees
Sloping - A technique that employs a specific angle of incline on the sides of the
excavation. The angle varies based on assessment of impacting site factors
METHODOLOGY
The extent of soil and rock strata is found by making trial pits in the construction
site. The excavation and depth is decided according to the following guidelines in
the site
i. For Isolated footing the depth to be one and half times the width of the foundation
National Institute of Construction Management And Research, Hyderabad 2
A REPORT ON TRENCH AND EXCAVATION SAFETY
ii. For adjacent footings with clear spacing less than twice the width (i.e.) one and
half times the length
iii. 1.5m in general and 3.5 m in black cotton soils.
Setting out or ground tracing is the process of laying down the excavation lines and
centre lines etc. on the ground before the excavation is started. The centre line ofthe
longest outer wall of the building is marked on the ground by stretching a string
between wooden or mild steel pegs. Each peg may be projected about 25 to 50 mm
form the ground level and 2m from the edge of the excavation. The boundary is
marked with the chalk powder. Similarly, outer lines ofthe foundation trench ofeach
cross walls and are set out
Removal of Excess Soil
Estimate the excavated stuff to be re-utilized in filling, gardening, preparing roads,
etc. As far as possible try to carry excavation and filling simultaneously to avoid
double handling. Select and stack the required material in such a place that it should
not obstruct other construction activities. The excess or unwanted material should
immediately be carried away and disposed off by employing any of the following
methods.
 Departmental labour.
 Tractor.
 Trucks.
QUALITY CHECKS FOR EXCAVATION
 Recording initial ground level and check size of bottom.
 Disposal of unsuitable material for filling.
 Stacking suitable material for backfilling to avoid double handling.
 Strata classification approval by competent authority.
 Necessary safety measures observed.
National Institute of Construction Management And Research, Hyderabad 3
A REPORT ON TRENCH AND EXCAVATION SAFETY
QUALITY CHECKS FOR FILLING
 Recording initial ground level
 Sample is approved for back filling.
 Necessary marking/ reference points are established for final level of backfilling.
 Back filling is being carried out in layers (15cm to 20cm).
 Required watering, compaction is done.
 Required density is achieved.
EXCAVATION HAZARDS
 Soil collapse or cave-ins
 Underground utilities
 Hazardous atmosphere
 Stability of adjacent structures
 Falls / falling loads
 Access and egress
 Vehicle traffic and mobile equipment
 Water accumulation hazards
SOIL CLASSIFICATION
■ Stable rock;
■ Type A soil;
■ Type B soil;
■ Type C soil.
National Institute of Construction Management And Research, Hyderabad 4
A REPORT ON TRENCH AND EXCAVATION SAFETY
Stable Rock –
Natural solid mineral matter that can be excavated with vertical
sides and remain intact while exposed.
Type A –
Cohesive soils with an unconfined compressive strength of 1.5 tons
per square foot (tsf)(144 kPa) or greater.
Examples include: clay, silty clay, sandy clay, and clay loam. Certain conditions
preclude soil from being classified as Type A. Forexample, no soil is Type A if it is
fissured or has been previously disturbed.
Type B –
Includes cohesive soil with an unconfined compressive strength
greater than 0.5 tsf (48 kPa) but less than 1.5 tsf (144 kPa) and granular cohesion-
less soils (such as angular gravel, similar to crushed rock, silt, silt loam, sandyloam,
and, in some cases, silty clay loam and sandy clay loam).
Type C –
Cohesive soilwith an unconfined compressive strength of 0.5 tsf (48
kPa) or less, granular soils (including gravel, sand, and loamy sand), submerged soil
or soil from which water is freely seeping, submerged rock that is not stable, or
material in a sloped, layered system where the layers dip into the excavation or with
a slope of four horizontal to one vertical (4H:1V) or steeper.
PROTECTIVE SYSTEMS
■ Sloping and benching the sides of the excavation;
■ Supporting the sides of the excavation; or
■ Placing a shield between the side of the excavation and the work area.
National Institute of Construction Management And Research, Hyderabad 5
A REPORT ON TRENCH AND EXCAVATION SAFETY
I. Sloping system
Maximum allowable slope for excavation less than 20 feet
Soil type Height/depth Slope angle (degree)
Stable rock Vertical 90
Type A ¾ : 1 53
Type B 1 : 1 45
Type C 1½ :1 34
TYPE B SOIL
National Institute of Construction Management And Research, Hyderabad 6
A REPORT ON TRENCH AND EXCAVATION SAFETY
II. Benching system
 This method is applicable only for type A and type B soil.
 Two basic types of benching are used
a. Simple and
b. Multiple
 The type of soil determines the horizontal to vertical ratio of benched side
 As a general rule, the bottom vertical height of the trench must not exceed 4
feet (1.2 m) for the first bench. Subsequent benches may be up to maximum
of 5 feet (1.5 m) vertical in type A and 4 feet (1.2 m) in type B to total trench
depth of 20 feet.
 All subsequent benches must be below the maximum allowable slope for that
soil type.
 For the type B soil, the trench excavation is permitted in cohesive soil only.
TYPE C SOIL
National Institute of Construction Management And Research, Hyderabad 7
A REPORT ON TRENCH AND EXCAVATION SAFETY
III. Shoring system
 Shoring is the provision of support system for trench faces used to prevent
movement of soil, underground utilities, roadways, and foundations.
 Shoring or shielding is used when the location or depth of the cut makes
sloping back to the maximum allowable slope impractical.
 Shoring system consists of posts, wales, struts and sheets.
 There are two type of shoring available
a. Hydraulic shoring
b. Pneumatic shoring
National Institute of Construction Management And Research, Hyderabad 8
A REPORT ON TRENCH AND EXCAVATION SAFETY
 Hydraulic shoring
i. The trend todayis towards the use of hydraulic shoring, a prefabricated
strut and/or wale system manufactured of Al or steel.
ii. Hydraulic shoring provides a critical safety advantage over timber
shoring because workers don’t have to enter trench to install shoring.
iii. All shoring should be installed from the top-down and removed from
bottom-up.
 Pneumatic shoring
i. Works in similar manner to hydraulic shoring. The primary difference
is that pneumatic shoring uses air pressure in place of hydraulic
pressure.
National Institute of Construction Management And Research, Hyderabad 9
A REPORT ON TRENCH AND EXCAVATION SAFETY
IV. Shielding system
 They are different from shoring because instead of shoring up or otherwise
supporting the trench face they are intended primarily to protectworkers from
cave-ins and similar incidents.
 The excavated area between the outside of trench box and the face of trench
should be as small as possible.
 The spacebetween trench boxes and excavation side are backfilled to prevent
lateral movement of the box.
 Trench boxes are generally used in open areas but they also may used in
combination with sloping and benching.
 The box should extend at least 18 inches above surrounding area if there is
sloping towards excavation.
 This can be accomplished by providing a benched area adjacent to the box.
Fig. Trench Shields
National Institute of Construction Management And Research, Hyderabad 10
A REPORT ON TRENCH AND EXCAVATION SAFETY
Additional Hazards and Protections
In addition to cave-ins and related hazards, workers involved in excavation
work are exposed to hazards involving falling loads and mobile equipment.
To protect workers from these hazards, employers must take certain
precautions. For example, employers must:
■ Protect workers from excavated or other materials or equipment that could
pose a hazard by falling or rolling inside the excavation by placing and
keeping such materials or equipment at least 2 feet (0.61 meters) from the
edge and/or by using a retaining device to keep the materials or equipment
from falling or rolling into the excavation.
■ Provide a warning system (such as barricades, hand or mechanical signals,
or stop logs) when mobile equipment is operated adjacent to an excavation,
or when such equipment must approach the edge of an excavation, and the
operator does not have a clear and direct view of the edge.
■ Protect workers from loose rock or soil that could fall or roll from an
excavation face by scaling to remove loose material, installing protective
barricades at appropriate intervals, or using other equivalent forms of
protection.
■ Institute and enforce work rules prohibiting workers from working on faces
of sloped or benched excavations at levels above other workers unless the
workers at the lower levels are adequately protected from the hazards of
falling, rolling, or sliding material or equipment.
■ Institute and enforce work rules prohibiting workers from standing or
working under loads being handled by lifting or digging equipment.
■ Require workers to stand away from vehicles being loaded or unloaded to
protect them from being struck by any spillage or falling materials.
Water accumulation
Water in an excavation can undermine the sides of the excavation and make
it more difficult for workers to get out of the excavation.
Precautions can include special Trenching and Excavation Safety supportor
shield systems to prevent cave-ins, water removal to control the water level,
or the use of a safety harness and lifeline.
National Institute of Construction Management And Research, Hyderabad 11
A REPORT ON TRENCH AND EXCAVATION SAFETY
Hazardous atmosphere
Atmospheric testing is required before workers enter an excavation greater
than 4 feet (1.22 meters) in depth where an oxygen deficiency or a hazardous
atmosphere is present orcould reasonably be expected, suchas in excavations
in landfill areas orexcavations in areas where hazardous substances are stored
nearby.
If there are any hazardous conditions present, the employer must ensure that
adequate precautions are taken to prevent employee exposure to those
conditions.
Such precautions include providing workers with proper respiratory
protection or ventilation.
In addition, when controls are used to reduce the level of atmospheric
contaminants to acceptable levels, testing must be conducted as often as
necessary to ensure that the atmosphere remains safe.
Access and Egress
Worker generally enter into excavation by ladder. So separate ladders should
be provided for access and egress.
No worker shall move more than 15 feet in excavation area.
Trenches more than 4 feet in depth should be provided with fixed means of
egress.
Ladders must be secured and extended minimum of 36 inches above landing.
Metal ladders should beused with caution particularly when electrical utilities
are present.
Underground utilities
Such as sewer, water, gas lines, communication and electrical lines must be
identified and physically located.
If any utility line is passing through the excavation then first relocate it and
then give work permit for them.
National Institute of Construction Management And Research, Hyderabad 12
A REPORT ON TRENCH AND EXCAVATION SAFETY
When to conduct site inspections?
i. After rain, competent personshould inspect the site before giving work
permit for further work, becausethere is chance of hazard due to water
seepage and loose soil.
ii. Daily and before start of each shift.
iii. When there is change in size, location or placement of the soil.
iv. When there is any indication of change or movement of adjacent
structures.
Checklist of excavation work
National Institute of Construction Management And Research, Hyderabad 13
A REPORT ON TRENCH AND EXCAVATION SAFETY
CONCLUSION
When employers share the details of their safety and health programs with workers,
they should emphasize the critical role workers play in keeping the jobsite safe.
Employers also need to emphasize specific practices that will help reduce the risk of
on-the-job injuries at excavation sites. Such practices can include the following:
■ Know where underground utilities are located before digging.
■ Keep excavated soil (spoils) and other materials at least 2 feet (0.61 meters) from
trench edges.
■ Keep heavy equipment away from trench edges.
■ Identify any equipment or activities that could affect trench stability.
■ Test for atmospheric hazards such as low oxygen, hazardous fumes, and toxic
gases when workers are more than 4 feet deep.
■ Inspect trenches at the start of each shift.
■ Inspect trenches following a rainstorm or other water intrusion.
■ Inspect trenches after any occurrence that could have changed conditions in the
trench.
■ Do not work under suspended or raised loads and materials.
■ Ensure that personnel wear high-visibility or other suitable clothing when
exposed to vehicular traffic.
REFERENCES
1. IS 3764 : CODE OF SAFETY FOR EXCAVATION WORK
2. OSHA 2226 : TRENCHING AND EXCAVATION SAFETY
3. www.osha.gov
4. Google

More Related Content

What's hot

Road construction ppt
Road construction pptRoad construction ppt
Road construction ppt
mohammad danish anwar
 
Test On Bitumen
Test On BitumenTest On Bitumen
Test On Bitumen
Ujas Patel
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
Imrul Quesh
 
Concrete Technology Study Notes
Concrete Technology Study NotesConcrete Technology Study Notes
Concrete Technology Study Notes
SHAMJITH KM
 
Field Compaction
Field CompactionField Compaction
Slope stability
Slope stabilitySlope stability
Slope stability
Dr. Pallavi Badry
 
Vertical Drain
Vertical Drain Vertical Drain
Vertical Drain
Sanchari Halder
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
David H Moloney
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
Vikas Sukhwal
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
Ved Jangid
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
Rafi Khan
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
Abhishek Singh
 
Sub grade preperation
Sub grade preperationSub grade preperation
Sub grade preperation
EPA Infrastructure Pvt. Ltd.
 
Highway construction or Road work
Highway construction or Road work Highway construction or Road work
Highway construction or Road work
Abdul rahman kureshi
 
Bearing failure
Bearing failureBearing failure
Bearing failure
galaly12345
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
Himanshu Gupta
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
Fresher Thinking
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
GAURAV. H .TANDON
 
Is code 456 2000
Is code 456 2000Is code 456 2000
Is code 456 2000
shashank kumar
 
Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concrete
Aglaia Connect
 

What's hot (20)

Road construction ppt
Road construction pptRoad construction ppt
Road construction ppt
 
Test On Bitumen
Test On BitumenTest On Bitumen
Test On Bitumen
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
 
Concrete Technology Study Notes
Concrete Technology Study NotesConcrete Technology Study Notes
Concrete Technology Study Notes
 
Field Compaction
Field CompactionField Compaction
Field Compaction
 
Slope stability
Slope stabilitySlope stability
Slope stability
 
Vertical Drain
Vertical Drain Vertical Drain
Vertical Drain
 
Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Sub grade preperation
Sub grade preperationSub grade preperation
Sub grade preperation
 
Highway construction or Road work
Highway construction or Road work Highway construction or Road work
Highway construction or Road work
 
Bearing failure
Bearing failureBearing failure
Bearing failure
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Is code 456 2000
Is code 456 2000Is code 456 2000
Is code 456 2000
 
Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concrete
 

Viewers also liked

Yashar Pourang Portfolio
Yashar Pourang Portfolio Yashar Pourang Portfolio
Yashar Pourang Portfolio
Yashar Pourang MIEAust
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
Ashif AR
 
ACH 122 F2011 syllabus
ACH 122  F2011 syllabusACH 122  F2011 syllabus
ACH 122 F2011 syllabus
Richard Luxenburg
 
Tutor site clearance
Tutor site clearance Tutor site clearance
Tutor site clearance
Luke D'Arcy
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
Anne Allan
 
Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)
Jyoti Khatiwada
 
Earthwork notes
Earthwork notesEarthwork notes
Earthwork notes
Adilen Del
 
Mat Foundation Presentation Abhijatrik-28C
Mat Foundation Presentation Abhijatrik-28C Mat Foundation Presentation Abhijatrik-28C
Mat Foundation Presentation Abhijatrik-28C
Team-AbacuS
 
Earthwork
EarthworkEarthwork
Earthwork
EarthworkEarthwork
Earthwork
Rajiva Gupta
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
Rizwan Khurram
 
Excavations ppt
Excavations pptExcavations ppt
Excavations ppt
Colleen True
 
Excavation & Trenching Safety
Excavation & Trenching Safety Excavation & Trenching Safety
Excavation & Trenching Safety
Reliance
 
ACH 122 Lecture 04a (Excavation & Foundations P1)
ACH 122 Lecture 04a (Excavation & Foundations P1)ACH 122 Lecture 04a (Excavation & Foundations P1)
ACH 122 Lecture 04a (Excavation & Foundations P1)
Anne Arundel Community College
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
Thananchayan Theivendra
 

Viewers also liked (15)

Yashar Pourang Portfolio
Yashar Pourang Portfolio Yashar Pourang Portfolio
Yashar Pourang Portfolio
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
ACH 122 F2011 syllabus
ACH 122  F2011 syllabusACH 122  F2011 syllabus
ACH 122 F2011 syllabus
 
Tutor site clearance
Tutor site clearance Tutor site clearance
Tutor site clearance
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
 
Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)
 
Earthwork notes
Earthwork notesEarthwork notes
Earthwork notes
 
Mat Foundation Presentation Abhijatrik-28C
Mat Foundation Presentation Abhijatrik-28C Mat Foundation Presentation Abhijatrik-28C
Mat Foundation Presentation Abhijatrik-28C
 
Earthwork
EarthworkEarthwork
Earthwork
 
Earthwork
EarthworkEarthwork
Earthwork
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Excavations ppt
Excavations pptExcavations ppt
Excavations ppt
 
Excavation & Trenching Safety
Excavation & Trenching Safety Excavation & Trenching Safety
Excavation & Trenching Safety
 
ACH 122 Lecture 04a (Excavation & Foundations P1)
ACH 122 Lecture 04a (Excavation & Foundations P1)ACH 122 Lecture 04a (Excavation & Foundations P1)
ACH 122 Lecture 04a (Excavation & Foundations P1)
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 

Similar to Report on excavation

Excavation and Demolition powerpoint presentation
Excavation  and Demolition powerpoint presentationExcavation  and Demolition powerpoint presentation
Excavation and Demolition powerpoint presentation
ShivKumar794683
 
Excavation and trenching
Excavation and trenchingExcavation and trenching
Excavation and trenching
Cervelliere Limited
 
OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
The Windsdor Consulting Group, Inc.
 
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Muizz Anibire
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
Osho Shemil Baba
 
Trench excavationsafety
Trench excavationsafetyTrench excavationsafety
Trench excavationsafety
Shaik Mushtaq
 
038 Trenching and Shoring.PPT
038 Trenching and Shoring.PPT038 Trenching and Shoring.PPT
038 Trenching and Shoring.PPT
PremPratap5
 
NIOSH - Preventing Worker Deaths from Trench Cave-ins
NIOSH - Preventing Worker Deaths from Trench Cave-ins NIOSH - Preventing Worker Deaths from Trench Cave-ins
NIOSH - Preventing Worker Deaths from Trench Cave-ins
Robson Peixoto
 
Construction safety manual
Construction safety manualConstruction safety manual
Construction safety manual
Bimal Chandra Das
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations
Amol Pawar
 
Ct2 presentation
Ct2 presentationCt2 presentation
Ct2 presentation
qayyum23
 
Hazardous Work Practices in Construction
Hazardous Work Practices in ConstructionHazardous Work Practices in Construction
Hazardous Work Practices in Construction
The Windsdor Consulting Group, Inc.
 
Excavation.ppt
Excavation.pptExcavation.ppt
Excavation.ppt
SumanthGundeti2
 
Bcon final
Bcon finalBcon final
Bcon final
dicky177
 
Excavation eschenasy
Excavation eschenasyExcavation eschenasy
Excavation eschenasy
q q
 
12 trenching and excavation safety
12 trenching and excavation safety12 trenching and excavation safety
12 trenching and excavation safety
Cervelliere Limited
 
Excavation and-trenching safety 03
Excavation and-trenching safety 03Excavation and-trenching safety 03
Excavation and-trenching safety 03
vppradeepkumar
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
ssuser2c065e
 
osha3252.pdf
osha3252.pdfosha3252.pdf
osha3252.pdf
RajkumarArikumar
 
4. Construction and design criteria Earthen Dams.pptx
4. Construction and design criteria Earthen Dams.pptx4. Construction and design criteria Earthen Dams.pptx
4. Construction and design criteria Earthen Dams.pptx
Abhilashvishwakrama
 

Similar to Report on excavation (20)

Excavation and Demolition powerpoint presentation
Excavation  and Demolition powerpoint presentationExcavation  and Demolition powerpoint presentation
Excavation and Demolition powerpoint presentation
 
Excavation and trenching
Excavation and trenchingExcavation and trenching
Excavation and trenching
 
OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
 
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
Trench excavationsafety
Trench excavationsafetyTrench excavationsafety
Trench excavationsafety
 
038 Trenching and Shoring.PPT
038 Trenching and Shoring.PPT038 Trenching and Shoring.PPT
038 Trenching and Shoring.PPT
 
NIOSH - Preventing Worker Deaths from Trench Cave-ins
NIOSH - Preventing Worker Deaths from Trench Cave-ins NIOSH - Preventing Worker Deaths from Trench Cave-ins
NIOSH - Preventing Worker Deaths from Trench Cave-ins
 
Construction safety manual
Construction safety manualConstruction safety manual
Construction safety manual
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations
 
Ct2 presentation
Ct2 presentationCt2 presentation
Ct2 presentation
 
Hazardous Work Practices in Construction
Hazardous Work Practices in ConstructionHazardous Work Practices in Construction
Hazardous Work Practices in Construction
 
Excavation.ppt
Excavation.pptExcavation.ppt
Excavation.ppt
 
Bcon final
Bcon finalBcon final
Bcon final
 
Excavation eschenasy
Excavation eschenasyExcavation eschenasy
Excavation eschenasy
 
12 trenching and excavation safety
12 trenching and excavation safety12 trenching and excavation safety
12 trenching and excavation safety
 
Excavation and-trenching safety 03
Excavation and-trenching safety 03Excavation and-trenching safety 03
Excavation and-trenching safety 03
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
osha3252.pdf
osha3252.pdfosha3252.pdf
osha3252.pdf
 
4. Construction and design criteria Earthen Dams.pptx
4. Construction and design criteria Earthen Dams.pptx4. Construction and design criteria Earthen Dams.pptx
4. Construction and design criteria Earthen Dams.pptx
 

Recently uploaded

A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 

Recently uploaded (20)

A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 

Report on excavation

  • 1. A Report On Trench & Excavation Safety SH16030 & SH16031 | PGP-HSEM
  • 2. National Institute of Construction Management And Research, Hyderabad 1 A REPORT ON TRENCH AND EXCAVATION SAFETY INTRODUCTION Excavation and trenching are among the most hazardous construction operations. It is generally used for foundation purpose, laying down sewer lines, electrical lines, phone lines, etc. So while performing this activity safety precautions needs to be taken because it can cause harm to life of worker and property as well. Most of the times the accident is happened because of cave-ins which may sometimes leads to death of worker. Definitions Excavation – Any man made cut, cavity, trench or depression made in the earth’s surface formed by earth removal. Trench – A narrow excavation made below ground surface. In general, the depth is greater than width, but the width is no greater than 15 feet. Shoring – A structure such as a metal hydraulic, mechanical or timber system that supports the side of excavation and designed to prevent cave-ins. Shield - A structure able to withstand a cave-in and protect employees Sloping - A technique that employs a specific angle of incline on the sides of the excavation. The angle varies based on assessment of impacting site factors METHODOLOGY The extent of soil and rock strata is found by making trial pits in the construction site. The excavation and depth is decided according to the following guidelines in the site i. For Isolated footing the depth to be one and half times the width of the foundation
  • 3. National Institute of Construction Management And Research, Hyderabad 2 A REPORT ON TRENCH AND EXCAVATION SAFETY ii. For adjacent footings with clear spacing less than twice the width (i.e.) one and half times the length iii. 1.5m in general and 3.5 m in black cotton soils. Setting out or ground tracing is the process of laying down the excavation lines and centre lines etc. on the ground before the excavation is started. The centre line ofthe longest outer wall of the building is marked on the ground by stretching a string between wooden or mild steel pegs. Each peg may be projected about 25 to 50 mm form the ground level and 2m from the edge of the excavation. The boundary is marked with the chalk powder. Similarly, outer lines ofthe foundation trench ofeach cross walls and are set out Removal of Excess Soil Estimate the excavated stuff to be re-utilized in filling, gardening, preparing roads, etc. As far as possible try to carry excavation and filling simultaneously to avoid double handling. Select and stack the required material in such a place that it should not obstruct other construction activities. The excess or unwanted material should immediately be carried away and disposed off by employing any of the following methods.  Departmental labour.  Tractor.  Trucks. QUALITY CHECKS FOR EXCAVATION  Recording initial ground level and check size of bottom.  Disposal of unsuitable material for filling.  Stacking suitable material for backfilling to avoid double handling.  Strata classification approval by competent authority.  Necessary safety measures observed.
  • 4. National Institute of Construction Management And Research, Hyderabad 3 A REPORT ON TRENCH AND EXCAVATION SAFETY QUALITY CHECKS FOR FILLING  Recording initial ground level  Sample is approved for back filling.  Necessary marking/ reference points are established for final level of backfilling.  Back filling is being carried out in layers (15cm to 20cm).  Required watering, compaction is done.  Required density is achieved. EXCAVATION HAZARDS  Soil collapse or cave-ins  Underground utilities  Hazardous atmosphere  Stability of adjacent structures  Falls / falling loads  Access and egress  Vehicle traffic and mobile equipment  Water accumulation hazards SOIL CLASSIFICATION ■ Stable rock; ■ Type A soil; ■ Type B soil; ■ Type C soil.
  • 5. National Institute of Construction Management And Research, Hyderabad 4 A REPORT ON TRENCH AND EXCAVATION SAFETY Stable Rock – Natural solid mineral matter that can be excavated with vertical sides and remain intact while exposed. Type A – Cohesive soils with an unconfined compressive strength of 1.5 tons per square foot (tsf)(144 kPa) or greater. Examples include: clay, silty clay, sandy clay, and clay loam. Certain conditions preclude soil from being classified as Type A. Forexample, no soil is Type A if it is fissured or has been previously disturbed. Type B – Includes cohesive soil with an unconfined compressive strength greater than 0.5 tsf (48 kPa) but less than 1.5 tsf (144 kPa) and granular cohesion- less soils (such as angular gravel, similar to crushed rock, silt, silt loam, sandyloam, and, in some cases, silty clay loam and sandy clay loam). Type C – Cohesive soilwith an unconfined compressive strength of 0.5 tsf (48 kPa) or less, granular soils (including gravel, sand, and loamy sand), submerged soil or soil from which water is freely seeping, submerged rock that is not stable, or material in a sloped, layered system where the layers dip into the excavation or with a slope of four horizontal to one vertical (4H:1V) or steeper. PROTECTIVE SYSTEMS ■ Sloping and benching the sides of the excavation; ■ Supporting the sides of the excavation; or ■ Placing a shield between the side of the excavation and the work area.
  • 6. National Institute of Construction Management And Research, Hyderabad 5 A REPORT ON TRENCH AND EXCAVATION SAFETY I. Sloping system Maximum allowable slope for excavation less than 20 feet Soil type Height/depth Slope angle (degree) Stable rock Vertical 90 Type A ¾ : 1 53 Type B 1 : 1 45 Type C 1½ :1 34 TYPE B SOIL
  • 7. National Institute of Construction Management And Research, Hyderabad 6 A REPORT ON TRENCH AND EXCAVATION SAFETY II. Benching system  This method is applicable only for type A and type B soil.  Two basic types of benching are used a. Simple and b. Multiple  The type of soil determines the horizontal to vertical ratio of benched side  As a general rule, the bottom vertical height of the trench must not exceed 4 feet (1.2 m) for the first bench. Subsequent benches may be up to maximum of 5 feet (1.5 m) vertical in type A and 4 feet (1.2 m) in type B to total trench depth of 20 feet.  All subsequent benches must be below the maximum allowable slope for that soil type.  For the type B soil, the trench excavation is permitted in cohesive soil only. TYPE C SOIL
  • 8. National Institute of Construction Management And Research, Hyderabad 7 A REPORT ON TRENCH AND EXCAVATION SAFETY III. Shoring system  Shoring is the provision of support system for trench faces used to prevent movement of soil, underground utilities, roadways, and foundations.  Shoring or shielding is used when the location or depth of the cut makes sloping back to the maximum allowable slope impractical.  Shoring system consists of posts, wales, struts and sheets.  There are two type of shoring available a. Hydraulic shoring b. Pneumatic shoring
  • 9. National Institute of Construction Management And Research, Hyderabad 8 A REPORT ON TRENCH AND EXCAVATION SAFETY  Hydraulic shoring i. The trend todayis towards the use of hydraulic shoring, a prefabricated strut and/or wale system manufactured of Al or steel. ii. Hydraulic shoring provides a critical safety advantage over timber shoring because workers don’t have to enter trench to install shoring. iii. All shoring should be installed from the top-down and removed from bottom-up.  Pneumatic shoring i. Works in similar manner to hydraulic shoring. The primary difference is that pneumatic shoring uses air pressure in place of hydraulic pressure.
  • 10. National Institute of Construction Management And Research, Hyderabad 9 A REPORT ON TRENCH AND EXCAVATION SAFETY IV. Shielding system  They are different from shoring because instead of shoring up or otherwise supporting the trench face they are intended primarily to protectworkers from cave-ins and similar incidents.  The excavated area between the outside of trench box and the face of trench should be as small as possible.  The spacebetween trench boxes and excavation side are backfilled to prevent lateral movement of the box.  Trench boxes are generally used in open areas but they also may used in combination with sloping and benching.  The box should extend at least 18 inches above surrounding area if there is sloping towards excavation.  This can be accomplished by providing a benched area adjacent to the box. Fig. Trench Shields
  • 11. National Institute of Construction Management And Research, Hyderabad 10 A REPORT ON TRENCH AND EXCAVATION SAFETY Additional Hazards and Protections In addition to cave-ins and related hazards, workers involved in excavation work are exposed to hazards involving falling loads and mobile equipment. To protect workers from these hazards, employers must take certain precautions. For example, employers must: ■ Protect workers from excavated or other materials or equipment that could pose a hazard by falling or rolling inside the excavation by placing and keeping such materials or equipment at least 2 feet (0.61 meters) from the edge and/or by using a retaining device to keep the materials or equipment from falling or rolling into the excavation. ■ Provide a warning system (such as barricades, hand or mechanical signals, or stop logs) when mobile equipment is operated adjacent to an excavation, or when such equipment must approach the edge of an excavation, and the operator does not have a clear and direct view of the edge. ■ Protect workers from loose rock or soil that could fall or roll from an excavation face by scaling to remove loose material, installing protective barricades at appropriate intervals, or using other equivalent forms of protection. ■ Institute and enforce work rules prohibiting workers from working on faces of sloped or benched excavations at levels above other workers unless the workers at the lower levels are adequately protected from the hazards of falling, rolling, or sliding material or equipment. ■ Institute and enforce work rules prohibiting workers from standing or working under loads being handled by lifting or digging equipment. ■ Require workers to stand away from vehicles being loaded or unloaded to protect them from being struck by any spillage or falling materials. Water accumulation Water in an excavation can undermine the sides of the excavation and make it more difficult for workers to get out of the excavation. Precautions can include special Trenching and Excavation Safety supportor shield systems to prevent cave-ins, water removal to control the water level, or the use of a safety harness and lifeline.
  • 12. National Institute of Construction Management And Research, Hyderabad 11 A REPORT ON TRENCH AND EXCAVATION SAFETY Hazardous atmosphere Atmospheric testing is required before workers enter an excavation greater than 4 feet (1.22 meters) in depth where an oxygen deficiency or a hazardous atmosphere is present orcould reasonably be expected, suchas in excavations in landfill areas orexcavations in areas where hazardous substances are stored nearby. If there are any hazardous conditions present, the employer must ensure that adequate precautions are taken to prevent employee exposure to those conditions. Such precautions include providing workers with proper respiratory protection or ventilation. In addition, when controls are used to reduce the level of atmospheric contaminants to acceptable levels, testing must be conducted as often as necessary to ensure that the atmosphere remains safe. Access and Egress Worker generally enter into excavation by ladder. So separate ladders should be provided for access and egress. No worker shall move more than 15 feet in excavation area. Trenches more than 4 feet in depth should be provided with fixed means of egress. Ladders must be secured and extended minimum of 36 inches above landing. Metal ladders should beused with caution particularly when electrical utilities are present. Underground utilities Such as sewer, water, gas lines, communication and electrical lines must be identified and physically located. If any utility line is passing through the excavation then first relocate it and then give work permit for them.
  • 13. National Institute of Construction Management And Research, Hyderabad 12 A REPORT ON TRENCH AND EXCAVATION SAFETY When to conduct site inspections? i. After rain, competent personshould inspect the site before giving work permit for further work, becausethere is chance of hazard due to water seepage and loose soil. ii. Daily and before start of each shift. iii. When there is change in size, location or placement of the soil. iv. When there is any indication of change or movement of adjacent structures. Checklist of excavation work
  • 14. National Institute of Construction Management And Research, Hyderabad 13 A REPORT ON TRENCH AND EXCAVATION SAFETY CONCLUSION When employers share the details of their safety and health programs with workers, they should emphasize the critical role workers play in keeping the jobsite safe. Employers also need to emphasize specific practices that will help reduce the risk of on-the-job injuries at excavation sites. Such practices can include the following: ■ Know where underground utilities are located before digging. ■ Keep excavated soil (spoils) and other materials at least 2 feet (0.61 meters) from trench edges. ■ Keep heavy equipment away from trench edges. ■ Identify any equipment or activities that could affect trench stability. ■ Test for atmospheric hazards such as low oxygen, hazardous fumes, and toxic gases when workers are more than 4 feet deep. ■ Inspect trenches at the start of each shift. ■ Inspect trenches following a rainstorm or other water intrusion. ■ Inspect trenches after any occurrence that could have changed conditions in the trench. ■ Do not work under suspended or raised loads and materials. ■ Ensure that personnel wear high-visibility or other suitable clothing when exposed to vehicular traffic. REFERENCES 1. IS 3764 : CODE OF SAFETY FOR EXCAVATION WORK 2. OSHA 2226 : TRENCHING AND EXCAVATION SAFETY 3. www.osha.gov 4. Google