SlideShare a Scribd company logo
CONSTRUCTION AND
DESIGN OF EARTHEN
DAMS
-by Anand M Hulagabali
CONTENT :
 Site Identification
 Site Preparation
 Construction steps
 Design criteria
 Design of Components of dam
 Material and Machinery used
 Measures to be taken
SITE IDENTIFICATION
 Foundations : all types of foundation are suitable. rock type,
nature and extend of fault zones is investigated.
 Engineering surveys –topographic survey is done and various
contour plans are prepared
 Hydrological investigation- Water resources available ,
maximum flood discharge, fixation of storage capacity.
 Site for spillway – spillway is provided separately from dam
body and located in the flank.
 Quantity &quality of material available for dam construction.
considering above factors, best site is selected.
SITE PREPARATION
 Clearing:
It is the removal of tress, boulders, fences, buildings, and other
structures from the area. This is for the borrow pits and the area to
be occupied by the dam
 Grubbing:
It is the removal of roots, stumps and organic matter. Grubbing is
done only in the actual borrow pits and within the outline of
embankments
 Stripping:
It is the removal of all topsoil, organic materials and soft pockets
which are unsuitable for the borrow in the borrow pit areas or
unsuitable for supporting structure within the embankment outlines.
STEPS OF CONSTRUCTION
DIVERSION OF STREAM
 dewatering of place where construction is to be done.
 Firstly, temporary dam or cofferdam is constructed
which walls off and protects the site area.
 Secondly, diversion of stream is done either by
following two methods -:
 placing large pipes- if flow volume is less.
 tunnel or diversion ditch- if flow volume is large.
 diversion is done usually in summer season.
FOUNDATION PREPARATION
 Dewatering by pumping from sumps is done.
 For greatest economy an open excavation is used.
 Water table is be lowered so that there is never an
upward flow of water in to the excavation
 All loose materials and porous materials are
removed.
 Pits and crevices are cleaned out as deep as
possible.
 Clay or cement grouting is done if required.
Contd…
 Cutoff trench
A cutoff trench is excavated below the base of the fill
upstream of the centerline of the fill.
The cutoff trench is incorporated in the design for two
reasons:
 to anchor the dam to the base material.
 to prevent piping (seepage under the fill).
BORROW PIT EXCAVATION
 Excavation of the embankment materials,
processing them, and hauling them to the job are
important from considerations of both cost and the
quality of the materials delivered to the
embankment.
 Excavation is done either by hands or power driven
equipments.
FILL PLACEMENT
All objectionable materials are removed during and
immediately after the spreading operation.
• These include roots, clumps of grass and the other
organic matter, and large stones which would interfere
with compaction
• Mixing of various material is done as per design
&availability.
Moisture addition is done by sprinkling water several
hours before compaction.
SOIL COMPACTION
 Compaction is the process by which the required
density is obtained in an embankment. Compaction
is done to:
1) increase stiffness,
2) minimize settlements during and after
construction,
3) increase strength,
4) prevent sliding shear failure of embankment,
and
5) water tight, to obtain required imperviousness
of the core zone
 Contd…
 Compaction is done in stages.
 Compaction is done by following equipments :
1. Tampers
2. vibrating rollers
3. Sheep foot rollers
4. Heavy pneumatic-tired roller, etc.
Chimney drains, filters etc. are mounted in stages as dam
construction progress.
DESIGN CRITERIA
1. Safe against overtopping during design flood by
providing adequate spillway and outlet capacity.
2. Sufficient free board so that it is not overtopped by
wave action.
3. Seepage line should be well within d/s face so that
no sloughing of slope takes place.
4. Side slopes stable during construction and under all
condition of reservoir operation.
5.Upstream slope is safe against rapid drawdown.
6.Side slopes u/s and d/s are flat enough so that the
shear stress induced in the foundation is less then
the shear strength of material.
7.D/S slope is safe during steady seepage under full
reservoir condition.
8. d/s of the impervious core is provided by suitable
drainage system.
9.There is no possibility of free flow of water from
u/s through either the dam body or foundation.
10. Dam as a whole should be earthquake resistant.
DESIGN OF COMPONENTS OF
DAM
 Before the construction, preliminary design of
some of the components of dam is done. Following
are some of them :
 Top width
 Free board
 outer shell
 central impervious core
 D/s drainage system
TOP WIDTH :
 Top width is between 20-40ft.
 No dam should have top width less then 10ft (This is
minimum needed for an access road to permit
maintenance)
FREE BOARD :
 Sufficient freeboard must be provided so that there is no
danger of overtopping.
 The seepage line is well within the downstream face of
the dam.
 For any height of dam, minimum 2mtr and maximum
3mtr freeboard is provided over maximum flood level.
OUTER SHELL :
 Function : impart stability and protect core.
 Material : relatively pervious materials are
used which are not subjected to
cracking like SW, GW, SP, GP,
GC, etc
 Slope :
U/s slope : range – 2:1 to 4:1
D/s slope : range – 2:1 to 2.5:1
CORE :
 Function : core checks the seepage of water
through dam body.
 Material : material used should not have
high compressibility ,low liquid limit
& less or no organic content.
Materials like highly plastic tough
clay, silt or combination of above
can be used.
 Width of core at the crest should be minimum of 3mtr.
 Sloping cores can also be provided.
D/S DRAINAGE SYSTEM
 Function : reduce pore pressure in d/s portion
and checks the migration of the
particles.
 Material : sufficiently fine material to prevent
base material from clogging the
filter and coarser enough to
remove the water as early as
possible.
 3 types of drains are provided :
Toe drain.
Horizontal blanket drain.
Chimney drains.
MATERIALS USED
material for constructing dam is usually derived by
digging of nearby areas. Different type of materials are
used for different zones.
1. Outer shell – well graded or uniformly graded
gravel, sand, silty sand, etc...
2. Inner core – high to medium plastic clay, silt, silty
sand, etc…
3. Cut-off trench – concrete, same material as that used
in inner core (to maintain homogeneity)
4. Filter – sand and gravel placed in form of layers.
MACHINERY
Following are some the most widely used
machinery in construction of dam :
 Excavation - power shovel, dragline, scraper and
elevating grader
 hauling – trucks, wagons.
 Compaction –pneumatic tampers, sheep foot
roller, vibrating roller, heavy pneumatic-tired roller,
smooth steel drum roller.
MEASURES TO BE TAKEN
 Drainage is necessary for pits below ground water. This
should be done far enough in advance of the construction so
that the soil is not water logged.
 The operation of the borrow pit must be carefully
controlled for better quality
 Moisture should be controlled while placing the soil.
 Compaction must be done in layers and each layer should
be compacted to achieve about 95% of standard proctor
maximum.
 A testing laboratory is set up at the borrow pit where the
moisture content, gradation, and even plasticity can be
determined in minimum time.
Contd…
 Thickness of soil to be compacted in layer is
important to keep good quality of fill.
 Small compactors are effective near abutment
foundation.
THANK YOU…

More Related Content

What's hot

Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
SAGAR RAUT
 
Earthen dam
Earthen damEarthen dam
Gravity dam
Gravity damGravity dam
Canal headworks
Canal headworksCanal headworks
Canal headworks
Atul Hajong
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
Vidhi Khokhani
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
Sunny Agarwal
 
Boussinesq'S theory
Boussinesq'S theoryBoussinesq'S theory
Boussinesq'S theory
SANJEEV Wazir
 
Reservior planning
Reservior    planningReservior    planning
Dams 1
Dams 1Dams 1
Lecture 5
Lecture 5Lecture 5
Dams and spillways
Dams and spillwaysDams and spillways
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
Binu Karki
 
Reservoir sedimentation
Reservoir sedimentationReservoir sedimentation
Reservoir sedimentation
Pramoda Raj
 
hydropower water conveyance system
hydropower water conveyance systemhydropower water conveyance system
hydropower water conveyance system
marif tahayy
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
Divya Vishnoi
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]
Muhammad Irfan
 
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
India Water Portal
 
ogee design
ogee designogee design
ogee design
Vidhi Khokhani
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
Rajkumar G
 
Canal Fall
Canal FallCanal Fall
Canal Fall
GAURAV. H .TANDON
 

What's hot (20)

Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
Canal headworks
Canal headworksCanal headworks
Canal headworks
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
 
Boussinesq'S theory
Boussinesq'S theoryBoussinesq'S theory
Boussinesq'S theory
 
Reservior planning
Reservior    planningReservior    planning
Reservior planning
 
Dams 1
Dams 1Dams 1
Dams 1
 
Lecture 5
Lecture 5Lecture 5
Lecture 5
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
 
Reservoir sedimentation
Reservoir sedimentationReservoir sedimentation
Reservoir sedimentation
 
hydropower water conveyance system
hydropower water conveyance systemhydropower water conveyance system
hydropower water conveyance system
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
 
Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]Geotechnical Engineering-II [Lec #26: Slope Stability]
Geotechnical Engineering-II [Lec #26: Slope Stability]
 
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
Infrastructure for water resource development_ Sushil Kumar (NWA)_2011
 
ogee design
ogee designogee design
ogee design
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 

Similar to 4. Construction and design criteria Earthen Dams.pptx

Tunnel Engineering.pptx
Tunnel Engineering.pptxTunnel Engineering.pptx
Tunnel Engineering.pptx
Priya Sarita Mane
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
jamali husain
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
SuMitt MaNdla
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil Engineering
Sahl Buhary
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
DHAVASHANKARAN D
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
JackRider12
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
Vinay Vb
 
Construction considerations of Earthen Dams
Construction considerations of Earthen DamsConstruction considerations of Earthen Dams
Construction considerations of Earthen Dams
Uday kumar Devalla
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
KhawarSakhani
 
LECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdfLECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdf
DRJULAIDAKALIWON
 
Earthen dam
Earthen damEarthen dam
Earthen dam
amrutaware2
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
VATSAL PATEL
 
EARTHERN DAM
EARTHERN DAMEARTHERN DAM
EARTHERN DAM
Sree Srilatha
 
sample.pptx
sample.pptxsample.pptx
sample.pptx
HirenThakkar31
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
GAURAV. H .TANDON
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
Adib Ramli
 
CH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethiCH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethi
mulugetakassa1988
 
Well completion.
Well completion.Well completion.
Well completion.
Mawa James
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptx
HirenThakkar31
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
YingHongKang
 

Similar to 4. Construction and design criteria Earthen Dams.pptx (20)

Tunnel Engineering.pptx
Tunnel Engineering.pptxTunnel Engineering.pptx
Tunnel Engineering.pptx
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil Engineering
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
Construction considerations of Earthen Dams
Construction considerations of Earthen DamsConstruction considerations of Earthen Dams
Construction considerations of Earthen Dams
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
 
LECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdfLECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdf
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
EARTHERN DAM
EARTHERN DAMEARTHERN DAM
EARTHERN DAM
 
sample.pptx
sample.pptxsample.pptx
sample.pptx
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
CH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethiCH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethi
 
Well completion.
Well completion.Well completion.
Well completion.
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptx
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 

Recently uploaded

Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 

Recently uploaded (20)

Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 

4. Construction and design criteria Earthen Dams.pptx

  • 1. CONSTRUCTION AND DESIGN OF EARTHEN DAMS -by Anand M Hulagabali
  • 2. CONTENT :  Site Identification  Site Preparation  Construction steps  Design criteria  Design of Components of dam  Material and Machinery used  Measures to be taken
  • 3. SITE IDENTIFICATION  Foundations : all types of foundation are suitable. rock type, nature and extend of fault zones is investigated.  Engineering surveys –topographic survey is done and various contour plans are prepared  Hydrological investigation- Water resources available , maximum flood discharge, fixation of storage capacity.  Site for spillway – spillway is provided separately from dam body and located in the flank.  Quantity &quality of material available for dam construction. considering above factors, best site is selected.
  • 4. SITE PREPARATION  Clearing: It is the removal of tress, boulders, fences, buildings, and other structures from the area. This is for the borrow pits and the area to be occupied by the dam  Grubbing: It is the removal of roots, stumps and organic matter. Grubbing is done only in the actual borrow pits and within the outline of embankments  Stripping: It is the removal of all topsoil, organic materials and soft pockets which are unsuitable for the borrow in the borrow pit areas or unsuitable for supporting structure within the embankment outlines.
  • 6. DIVERSION OF STREAM  dewatering of place where construction is to be done.  Firstly, temporary dam or cofferdam is constructed which walls off and protects the site area.  Secondly, diversion of stream is done either by following two methods -:  placing large pipes- if flow volume is less.  tunnel or diversion ditch- if flow volume is large.  diversion is done usually in summer season.
  • 7. FOUNDATION PREPARATION  Dewatering by pumping from sumps is done.  For greatest economy an open excavation is used.  Water table is be lowered so that there is never an upward flow of water in to the excavation  All loose materials and porous materials are removed.  Pits and crevices are cleaned out as deep as possible.  Clay or cement grouting is done if required.
  • 8. Contd…  Cutoff trench A cutoff trench is excavated below the base of the fill upstream of the centerline of the fill. The cutoff trench is incorporated in the design for two reasons:  to anchor the dam to the base material.  to prevent piping (seepage under the fill).
  • 9.
  • 10. BORROW PIT EXCAVATION  Excavation of the embankment materials, processing them, and hauling them to the job are important from considerations of both cost and the quality of the materials delivered to the embankment.  Excavation is done either by hands or power driven equipments.
  • 11. FILL PLACEMENT All objectionable materials are removed during and immediately after the spreading operation. • These include roots, clumps of grass and the other organic matter, and large stones which would interfere with compaction • Mixing of various material is done as per design &availability. Moisture addition is done by sprinkling water several hours before compaction.
  • 12. SOIL COMPACTION  Compaction is the process by which the required density is obtained in an embankment. Compaction is done to: 1) increase stiffness, 2) minimize settlements during and after construction, 3) increase strength, 4) prevent sliding shear failure of embankment, and 5) water tight, to obtain required imperviousness of the core zone
  • 13.  Contd…  Compaction is done in stages.  Compaction is done by following equipments : 1. Tampers 2. vibrating rollers 3. Sheep foot rollers 4. Heavy pneumatic-tired roller, etc. Chimney drains, filters etc. are mounted in stages as dam construction progress.
  • 14. DESIGN CRITERIA 1. Safe against overtopping during design flood by providing adequate spillway and outlet capacity. 2. Sufficient free board so that it is not overtopped by wave action. 3. Seepage line should be well within d/s face so that no sloughing of slope takes place. 4. Side slopes stable during construction and under all condition of reservoir operation.
  • 15. 5.Upstream slope is safe against rapid drawdown. 6.Side slopes u/s and d/s are flat enough so that the shear stress induced in the foundation is less then the shear strength of material. 7.D/S slope is safe during steady seepage under full reservoir condition. 8. d/s of the impervious core is provided by suitable drainage system.
  • 16. 9.There is no possibility of free flow of water from u/s through either the dam body or foundation. 10. Dam as a whole should be earthquake resistant.
  • 17. DESIGN OF COMPONENTS OF DAM  Before the construction, preliminary design of some of the components of dam is done. Following are some of them :  Top width  Free board  outer shell  central impervious core  D/s drainage system
  • 18. TOP WIDTH :  Top width is between 20-40ft.  No dam should have top width less then 10ft (This is minimum needed for an access road to permit maintenance) FREE BOARD :  Sufficient freeboard must be provided so that there is no danger of overtopping.  The seepage line is well within the downstream face of the dam.  For any height of dam, minimum 2mtr and maximum 3mtr freeboard is provided over maximum flood level.
  • 19. OUTER SHELL :  Function : impart stability and protect core.  Material : relatively pervious materials are used which are not subjected to cracking like SW, GW, SP, GP, GC, etc  Slope : U/s slope : range – 2:1 to 4:1 D/s slope : range – 2:1 to 2.5:1
  • 20. CORE :  Function : core checks the seepage of water through dam body.  Material : material used should not have high compressibility ,low liquid limit & less or no organic content. Materials like highly plastic tough clay, silt or combination of above can be used.  Width of core at the crest should be minimum of 3mtr.  Sloping cores can also be provided.
  • 21. D/S DRAINAGE SYSTEM  Function : reduce pore pressure in d/s portion and checks the migration of the particles.  Material : sufficiently fine material to prevent base material from clogging the filter and coarser enough to remove the water as early as possible.  3 types of drains are provided : Toe drain. Horizontal blanket drain. Chimney drains.
  • 22.
  • 23.
  • 24. MATERIALS USED material for constructing dam is usually derived by digging of nearby areas. Different type of materials are used for different zones. 1. Outer shell – well graded or uniformly graded gravel, sand, silty sand, etc... 2. Inner core – high to medium plastic clay, silt, silty sand, etc… 3. Cut-off trench – concrete, same material as that used in inner core (to maintain homogeneity) 4. Filter – sand and gravel placed in form of layers.
  • 25.
  • 27. Following are some the most widely used machinery in construction of dam :  Excavation - power shovel, dragline, scraper and elevating grader  hauling – trucks, wagons.  Compaction –pneumatic tampers, sheep foot roller, vibrating roller, heavy pneumatic-tired roller, smooth steel drum roller.
  • 28. MEASURES TO BE TAKEN  Drainage is necessary for pits below ground water. This should be done far enough in advance of the construction so that the soil is not water logged.  The operation of the borrow pit must be carefully controlled for better quality  Moisture should be controlled while placing the soil.  Compaction must be done in layers and each layer should be compacted to achieve about 95% of standard proctor maximum.  A testing laboratory is set up at the borrow pit where the moisture content, gradation, and even plasticity can be determined in minimum time.
  • 29. Contd…  Thickness of soil to be compacted in layer is important to keep good quality of fill.  Small compactors are effective near abutment foundation.