Question 1
a. Power from a Small Source. Suppose 150 gpm of water is taken from a creek and
delivered through 1000 ft of 3-in.-diameter polyethylene pipe to a turbine 100 ft
lower than the source. Use the rule-of-thumb to estimate the power delivered by the
turbine/generator. In a 30-day month, how much electric energy would be generated?
I. Find the friction loss 3 mark
II.Find the net head available 3 mark
III.Find the electrical power delivered 3 mark
b. Explain the three types of turbine 5 mark
c. Find the optimum tilt angle for south-facing photovoltaic module in Tucson (Latitude
32.1°) at solar noon on March 17.
I.Find the solar declination 3 mark
II.Find the altitude angle 3 mark
III.Find The tilt angle 3 mark
Question 2
a. Explain the steps to be taken in order to design a STAND ALONE PV SYSTEM
4 mark
b. Mention how many types of inverter there is when we design of grid-connected pv
system 4 mark
c. Using the battery connection diagram, calculate the time of battery bank to supply 2
A loads if the batteries have
I. Find the 18% DOD 3 mark
II. Find the 23% DOD 3 mark
Student’s Name:________________________________________________ ____________ ID: ___________
Faculty: Engineering
Department:
Year: 3st
Class: _________
Lecturer: Eng Munasar Abdirahman Ali
Subject: Renewable Energy
Exam: three Hours
Date: ____/____2021
Hormuud University
Final exam
Academic Year
2021-2021
III. Find the 75% DOD 3 mark
d. explain the steps to be taken in when it comes to design grid connected pv system
4 mark
Question 3
a. define what is hypro power plant 4 mark
b. explain the classification of hypro power plant 4 mark
c. what are the requirement survey in order to obtain the river as hydro power plant
3 mark
d. explain the three method of water flow measurement 5 mark

More Related Content

What's hot

An improved luo converter for high power applications
An improved luo converter for high power applicationsAn improved luo converter for high power applications
An improved luo converter for high power applications
eSAT Journals
 

What's hot (20)

Boost converter
Boost converterBoost converter
Boost converter
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breaker
 
Losses in 3 phase induction motor
Losses in 3 phase induction motorLosses in 3 phase induction motor
Losses in 3 phase induction motor
 
Seminar airborne wind turbines
Seminar   airborne wind turbinesSeminar   airborne wind turbines
Seminar airborne wind turbines
 
Impulse test for power transformers
Impulse test for power transformersImpulse test for power transformers
Impulse test for power transformers
 
LINEAR VARIABLE DIFFERENTIAL TRANSFORMER
LINEAR VARIABLE DIFFERENTIAL TRANSFORMERLINEAR VARIABLE DIFFERENTIAL TRANSFORMER
LINEAR VARIABLE DIFFERENTIAL TRANSFORMER
 
Presentation about transformer and its types
Presentation about transformer and its types Presentation about transformer and its types
Presentation about transformer and its types
 
2b.pptx
2b.pptx2b.pptx
2b.pptx
 
Transformer Oil Testing.pptx
Transformer Oil Testing.pptxTransformer Oil Testing.pptx
Transformer Oil Testing.pptx
 
An improved luo converter for high power applications
An improved luo converter for high power applicationsAn improved luo converter for high power applications
An improved luo converter for high power applications
 
Active cell balancing of Li-Ion batteries using single capacitor and single L...
Active cell balancing of Li-Ion batteries using single capacitor and single L...Active cell balancing of Li-Ion batteries using single capacitor and single L...
Active cell balancing of Li-Ion batteries using single capacitor and single L...
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars
 
UJT (industrial electronic)
UJT (industrial electronic)UJT (industrial electronic)
UJT (industrial electronic)
 
33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
Adoption of Park’s Transformation for Inverter Fed Drive
Adoption of Park’s Transformation for Inverter Fed DriveAdoption of Park’s Transformation for Inverter Fed Drive
Adoption of Park’s Transformation for Inverter Fed Drive
 
High Frequency Transformer for Multi-Output SMPS Applications
High Frequency Transformer for Multi-Output SMPS ApplicationsHigh Frequency Transformer for Multi-Output SMPS Applications
High Frequency Transformer for Multi-Output SMPS Applications
 
Dc Motor
Dc MotorDc Motor
Dc Motor
 
Air circuit breaker (ACB) Low-Voltage Miduim-Voltage High Voltage
Air circuit breaker (ACB) Low-Voltage Miduim-Voltage High VoltageAir circuit breaker (ACB) Low-Voltage Miduim-Voltage High Voltage
Air circuit breaker (ACB) Low-Voltage Miduim-Voltage High Voltage
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch center
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION
 

Similar to Renewable energy re final exam 2021

Enhancement of the output power generated from a hybrid solar thermal system
Enhancement of the output power generated from a hybrid solar thermal systemEnhancement of the output power generated from a hybrid solar thermal system
Enhancement of the output power generated from a hybrid solar thermal system
eSAT Journals
 
remote power stand alone system
remote power stand alone systemremote power stand alone system
remote power stand alone system
debraj nath
 
[Challenge:Future] Apollo to the rescue!
[Challenge:Future] Apollo to the rescue![Challenge:Future] Apollo to the rescue!
[Challenge:Future] Apollo to the rescue!
Challenge:Future
 

Similar to Renewable energy re final exam 2021 (20)

Renewable microgrid operational results and economic evaluation using RETScre...
Renewable microgrid operational results and economic evaluation using RETScre...Renewable microgrid operational results and economic evaluation using RETScre...
Renewable microgrid operational results and economic evaluation using RETScre...
 
Hybrid renewable energy photovoltaic and darrieus VAWT as propulsion fuel of ...
Hybrid renewable energy photovoltaic and darrieus VAWT as propulsion fuel of ...Hybrid renewable energy photovoltaic and darrieus VAWT as propulsion fuel of ...
Hybrid renewable energy photovoltaic and darrieus VAWT as propulsion fuel of ...
 
Enhancement of the output power generated from a
Enhancement of the output power generated from aEnhancement of the output power generated from a
Enhancement of the output power generated from a
 
Enhancement of the output power generated from a hybrid solar thermal system
Enhancement of the output power generated from a hybrid solar thermal systemEnhancement of the output power generated from a hybrid solar thermal system
Enhancement of the output power generated from a hybrid solar thermal system
 
Torrent Power Plant Chimney
Torrent Power Plant Chimney Torrent Power Plant Chimney
Torrent Power Plant Chimney
 
cb
cbcb
cb
 
Construction of Solar Panel Laying System based on Genetic Algorithm
Construction of Solar Panel Laying System based on Genetic AlgorithmConstruction of Solar Panel Laying System based on Genetic Algorithm
Construction of Solar Panel Laying System based on Genetic Algorithm
 
Hc3512401245
Hc3512401245Hc3512401245
Hc3512401245
 
remote power stand alone system
remote power stand alone systemremote power stand alone system
remote power stand alone system
 
Solar Chimney Power Plant-A Review
Solar Chimney Power Plant-A ReviewSolar Chimney Power Plant-A Review
Solar Chimney Power Plant-A Review
 
solar chimney power plant
solar chimney power plantsolar chimney power plant
solar chimney power plant
 
Triz part 3
Triz part 3Triz part 3
Triz part 3
 
odunlami prese_033552.pptx
odunlami prese_033552.pptxodunlami prese_033552.pptx
odunlami prese_033552.pptx
 
Solar Chimney Power Plant-A Review
Solar Chimney Power Plant-A ReviewSolar Chimney Power Plant-A Review
Solar Chimney Power Plant-A Review
 
SFEE.ppt .
SFEE.ppt                                    .SFEE.ppt                                    .
SFEE.ppt .
 
Initial presentation on techno economic analysis of 3kWp stand alone solar ho...
Initial presentation on techno economic analysis of 3kWp stand alone solar ho...Initial presentation on techno economic analysis of 3kWp stand alone solar ho...
Initial presentation on techno economic analysis of 3kWp stand alone solar ho...
 
[Challenge:Future] Apollo to the rescue!
[Challenge:Future] Apollo to the rescue![Challenge:Future] Apollo to the rescue!
[Challenge:Future] Apollo to the rescue!
 
EXPERMENTATIONAL DATA ANALYSIS OF CHIMNEY OPERATED SOLAR POWER PLANT
EXPERMENTATIONAL DATA ANALYSIS OF CHIMNEY OPERATED SOLAR POWER PLANTEXPERMENTATIONAL DATA ANALYSIS OF CHIMNEY OPERATED SOLAR POWER PLANT
EXPERMENTATIONAL DATA ANALYSIS OF CHIMNEY OPERATED SOLAR POWER PLANT
 
Mfc Final Project Presentation
Mfc Final Project PresentationMfc Final Project Presentation
Mfc Final Project Presentation
 
A project report on Foot Step Power Generation By Indrakumar R Padwani
A project report on Foot Step Power Generation By Indrakumar R PadwaniA project report on Foot Step Power Generation By Indrakumar R Padwani
A project report on Foot Step Power Generation By Indrakumar R Padwani
 

Recently uploaded

Antenna efficency lecture course chapter 3.pdf
Antenna  efficency lecture course chapter 3.pdfAntenna  efficency lecture course chapter 3.pdf
Antenna efficency lecture course chapter 3.pdf
AbrahamGadissa
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
Kamal Acharya
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 

Recently uploaded (20)

Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Antenna efficency lecture course chapter 3.pdf
Antenna  efficency lecture course chapter 3.pdfAntenna  efficency lecture course chapter 3.pdf
Antenna efficency lecture course chapter 3.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 

Renewable energy re final exam 2021

  • 1. Question 1 a. Power from a Small Source. Suppose 150 gpm of water is taken from a creek and delivered through 1000 ft of 3-in.-diameter polyethylene pipe to a turbine 100 ft lower than the source. Use the rule-of-thumb to estimate the power delivered by the turbine/generator. In a 30-day month, how much electric energy would be generated? I. Find the friction loss 3 mark II.Find the net head available 3 mark III.Find the electrical power delivered 3 mark b. Explain the three types of turbine 5 mark c. Find the optimum tilt angle for south-facing photovoltaic module in Tucson (Latitude 32.1°) at solar noon on March 17. I.Find the solar declination 3 mark II.Find the altitude angle 3 mark III.Find The tilt angle 3 mark Question 2 a. Explain the steps to be taken in order to design a STAND ALONE PV SYSTEM 4 mark b. Mention how many types of inverter there is when we design of grid-connected pv system 4 mark c. Using the battery connection diagram, calculate the time of battery bank to supply 2 A loads if the batteries have I. Find the 18% DOD 3 mark II. Find the 23% DOD 3 mark Student’s Name:________________________________________________ ____________ ID: ___________ Faculty: Engineering Department: Year: 3st Class: _________ Lecturer: Eng Munasar Abdirahman Ali Subject: Renewable Energy Exam: three Hours Date: ____/____2021 Hormuud University Final exam Academic Year 2021-2021
  • 2. III. Find the 75% DOD 3 mark d. explain the steps to be taken in when it comes to design grid connected pv system 4 mark Question 3 a. define what is hypro power plant 4 mark b. explain the classification of hypro power plant 4 mark c. what are the requirement survey in order to obtain the river as hydro power plant 3 mark d. explain the three method of water flow measurement 5 mark