1) Total float refers to the amount of time an activity can be delayed without delaying the project's estimated completion time. It assumes all preceding activities finish as early as possible and all succeeding activities start as late as possible. Total float can be calculated using the late start and early start or late finish and early finish of an activity. 2) Free float is the amount of time an activity can be delayed without impacting the project's estimated completion time or delaying succeeding activities. It is calculated using the early finish of an activity and the minimum early start of its successor activities. 3) Interfering float allows delaying an activity without impacting the project's completion, but it could delay one or more