SlideShare a Scribd company logo
4. Project Cost Management
-

Cost is one of 3 Triple constraints of the project. Managing costs of the project is
very crucial and hardest part of the project. It spans across all phases of the project
right from conception to closure of the project.

-

Cost Management is not just controlling “Costs”; it involves definitive planning and
preparing budgets. Collecting cost associated data. Comparing the data to prepared
budgets and taking appropriate actions when needed.

-

The process involved in estimating, budgeting, and controlling cost so that the
project can be completed within approved budget.
Value analysis (value engineering)
 Looking at less costly way to do the same work within the same scope
Following table lists all 3 Processes in this Knowledge Area, spread across '2 out of 5
Process Groups'

-

5 Process
Groups

Initiation

Planning

Executi
on

Monitoring and
control

Closing

4.1. Cost Estimating
Processes

4.3. Cost Control
4.2. Cost Budgeting

4.1 Estimate Cost
- The process of developing approximation of the monetary resources needed to complete
project activities
 Cost trade-offs & risk must be considered


Cost estimates should be refined

Inputs

-

-

Scope baseline
Project schedule
Human resource plan
Risk register
Enterprise
environmental
factors
Organizational
process assets

Tools

-

Expert judgment
Analogous estimating
Parametric estimating
Bottom-up estimating
Three-point estimates
Reserve analysis
Cost of quality
Project management
estimating software
Vendor bid analysis

Outputs

- Activity cost estimates
- Basis of estimates
- Project document updates

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
There are 3 different types of estimation techniques listed over here under Tools section of Cost
Estimation.
- Analogous Estimation techniques
- Bottom-up approach technique
- Parametric approach technique
Analogous estimation
-It is mainly based on Expert Judgment or based on similar previous Projects. This approach is
very useful in early stages of the project where WBS and work packets are completely defined.
The expert judgment success factor depends on similarity of previous projects too. The main
disadvantage is that it is good for ball-park figures but not for precise project cost.
Parametric Estimation
- It considers different project characteristics to calculate total costs of the project. For example,
in the Telephone wire digging project, if we know cost per meter we can estimate it to whole
project. For a house construction, if we know cost to construct per square feet, we can estimate
total house project. For complex projects there will be multi dimensional parameters involved.
When historic information is available these parametric estimation will be more accurate.
Bottom-up approach
- It is elaborative estimation technique. We start estimating from the bottom most part of WBS
hierarchy which is work package. Work packages are divided into activities. Summing up work
packages to modules or groups, summing up different modules to stages, summing up different
stages to project is the bottom-up approach method. The people who will actually do this work
should create the estimates.
Types of Cost;

-

-

Variable Costs
 Change with the amount of production/work
 e.g. material, supplies, wages
Fixed Costs
 Do not change as production change


-

Direct Costs
 Directly attributable to the work of project


-

e.g. set-up, rental

e.g. team travel, recognition, team wages

Indirect Costs
 overhead or cost incurred for benefit of more than one project


e.g. taxes, fringe benefit, janitorial services

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
-

It is very important to understand “Cost Variability” that focuses on changing of
cost over time as well as over volume;


Inflation; cost of some items increase over time.



Deflation; cost of technology items decrease over time.

Direct Costs vs. Indirect Costs

-

when talking about “a new project team member”, the direct cost will be his salary
while the indirect costs may be the insurance premiums given to him, the paid pill
for his telephone calls, computer internet access cost, his disk or disk space that have
been given to him.

-

When talking about “a specific material needed”, the direct cost will be its price
while the indirect cost will be the transportation cost paid to receive such material as
well as the storing cost...etc.

Fixed Costs vs. Variable Costs

-

A fixed cost is like the cost of a unit has a certain nature which maybe a resource
such as a specific material or equipment used for the project. If you need to buy a
piece of equipment to allow the project to continue, that is simply a fixed cost
regardless it will be used for once or hundreds of times.

-

Variable costs are directly related to the level of work with each and every element
of the WBS. It is like the cost of water needed to drink or Gasoline needed to some
machinery.

Quality/Accuracy of Cost Estimation

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
4.2 Determine Budget
- Process of aggregating the estimated cost of individual activities or work packages to
establish an authorized cost baseline.
Inputs

- Activity cost estimates
- Basis of estimates
- Scope baselines
- Project schedule
- Resource calendars
- Contracts
- Organizational process
assets

Tools

-

Cost aggregation
Reserve analysis
Expert judgment
Historical relationship
Funding limit
reconciliation

Outputs

-

Cost performance
baseline
Project funding
requirements
Project document
updates

- The main goal of this process is to develop Cost Baseline. At the starting point of this Process,
you should have finished Project Cost Estimation and have a complete list of estimates of
individual
activities.
Cost Aggregation;
-

We use Cost Aggregation tools to sum up those low level activity costs to Work package to
higher levels of WBS hierarchy.

-

Reserves & risk management are important while estimating!



Contingency reserves/Cost Baseline (the cost impacts of the remaining risk)



Management reserves/Cost Budget (extra fund to cover surprising risks or
changes to the project).

The cost baseline
-

It is a reference point for the project to compare time to time. You will monitor and control
project costs comparing to the baseline and report any variations. Costs at work package
level are tied to financial systems using Chart of Accounts. Chart of accounts show cost
allocation categories.

Project manager is allowed to allocate extra resources (time or money) as a buffer for known
unknowns; we call it as Contingency Reserve.
Determines Budget: Other considerations

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
- High level parametric estimate as a rule of thumb
 E.g. testing cost 50% of development cost
- Funding limit reconciliation = checking cash flow
 When the money will be available?
- Reconciliation needed before proposed cost baseline and cost budget become final
 Such reconciliation is part of integration management

4.3 Control Cost
- The process of monitoring the status of the project to update the project budget and
managing changes to the cost baseline.
Inputs

- Project management
plan
- Project funding
requirement
- Work performance
information
- Organizational process
assets

Tools

-

Earned value
management
Forecasting
To-complete
performance index
Performance reviews
Variance analysis
Project management
software

Outputs

-

Work performance
measurement
Budget forecast
Organizational process
updates
Change requests
Project management plan
updates
Project document updates

Cost control:
Once you estimate Project costs as well as cost baseline and prepare a Budget, you will
be on cruise mode to control the costs. That doesn’t mean it is easy thereafter. No not at
all. You have to monitor your cost so closely. Your work performance information is key
input for this process. You should have clear set templates to report the work progress.
Otherwise all unwanted junk data might ruin the soup.

How to control cost?

-

Follow the cost management plan

-

Look at any organizational process asset that are available

-

Manage change


Recording all appropriate change

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD



Ensuring requested changes are agreed upon


-

Preventing incorrect change

Managing the actual changes when and as they occur

Measure and measure and measure (monitoring)

Project performance review is another Tools & Techniques provided. You will review

project progress with your baseline plans and will provide what you’ve earned against
what you have planned. This is known as Earned Value Analysis and helps you to track
your day to day progress. 3 possible scenarios are: you are progressing ahead of plan that
means you are getting more than what you have planned, or progress is as per the plan or
not getting enough worth for your investment. Based on these 3 scenarios you can take
according corrective actions. Corrective actions are what you are supposed to do in this
process.

You can use Project Management software of your choice to help you in this regard. MS
Project is popular one or even you can simply use well planned out Excel sheets to track
those costs.

First you will find variances and report those using Variance analysis. The terms you use
over here are Cost Variance (CV) and Schedule Variance (SV). From that point you
might required to forecast rest of the project. This involves estimating rest of the work.
You use terms like Estimation to Completion (ETC) and Estimate at Complete (EAC).
Those names are telling what you have to Estimate.
Other terms you use here are Cost Performance Index (CPI) and SPI (Schedule
Performance Index)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Earned Value Technique
Ex;

Cont. Earned Value Technique

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Earned Value Management
-

Method to measure project performance against scope, schedule and cost baseline
(performance measurement baseline).

-

Interpretation of basic EVM performance measures



Cost Performance Index (CPI)



Schedule Performance Index (SPI)

Exercise;

-

You have a project to build a box. The box is six sided. Each side is to take one day to
build and is budgeted for $1000 per side. The sides are planned to be completed one
after the other. Today is the end of day three.

-

Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV,
SPI, EAC, ETC, VAC.

-

Describe your interpretation based on the calculation!

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Solution;

Hence, based on the result table;
• Over budget, getting 0.88 dollar for every spent dollar,
• Ahead schedule, progressing 101% of the rate planned,
• Probably will spend $6818 at the end (estimation),
• need $3368 to complete,
• Over budget at the end for about $818 (estimation)
Performance Metrics;

-

Budget At Completion (BAC) “Total cost of the project.”

-

Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV)



-

The amount expressed in Pounds (or hours) of work to be performed as
per the schedule plan.
PV = BAC * % of planned work.

Budgeted Cost for Work Performed (BCWP) / Earned Value (EV)



-

The amount expressed in Pounds (or hours) on the actual worked
performed.
EV = BAC * % of Actual work

Actual Cost of Work Performed (ACWP) / Actual Cost (AC)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Cost Forecasting:

-

Estimate At Completion (EAC)

-

The expected TOTAL cost required to finish complete work.

-

EAC = BAC / CPI
= AC + (BAC - EV) (at typical case)
= AC + ((BAC - EV) / CPI) (The same performance will remain)
= AC + (BAC - EV) / (CPI* SPI) (The same performance will remain +
Extra loss due to delay in time)

* Here “typical” means it is assumed that similar variances will not occur in the future.

-

Estimate to complete (ETC)

-

The expected cost required to finish all the Remaining work.

-

ETC

= EAC - AC
= (BAC - EV) / CPI

Variances:


Cost Variances (CV)
Determine “How much under or over budget?”
CV = EV-AC
NEGATIVE is over budget, POSITIVE is under budget.



Schedule Variances (SV)
Determine “How much ahead or behind schedule?”.
SV = EV-PV
NEGATIVE is behind schedule, POSITIVE is ahead of schedule.



Variance At Completion (VAC)
Variance of “TOTAL” cost of the work and expected cost.
VAC = BAC - EAC

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Performance Indices:


Cost Performance Index
CPI = EV / AC
“Over (< 1) or under (> 1) budget”.



Schedule Performance Index
SPI = EV / PV
“Ahead (> 1) or behind (< 1) schedule”.

To-Complete Performance Index (TCPI)

-

Helps the team determine the efficiency that must be achieved on the remaining
work for a project to meet a specified endpoint, such as BAC or the team’s revised
EAC.
TCPI = Remaining Work (BAC – EV) / Funds Remaining (EAC - AC)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Problem: A project has a budget of £10M and schedule for 10 months. It is assumed that

the total budget will be spent equally each month until the 10th month is reached. After 2
months the project manager finds that only 5% of the work is finished and a total of £1M
spent.
Solution:
PV = £2M
EV = £10M * 0.05 = £0.5M
AV = £1M
CV = EV-AC = 0.5-1 = -0.5M
CV% = 100 * (CV/EV) = 100*(-0.5/0.5) = -100% overrun
SV = EV-PV = 0.5-2 = -1.5 months
SV% = 100 * (SV/PV) = 100*(-1.5/2) = -75% behind
CPI = EV/AC = 0.5/1 = 0.5
SPI = EV/PV = 0.5/2 = 0.25
EAC = BAC/CPI = 10/0.5 = £20M
ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = £19M
Time to compete = (10-0.5)/0.25 = 38 Months

This project will take TOTAL £20M (19+1) and 40 (38+2) Months to complete.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
Hints to remember;
-

EV comes in most of formulas specially regarding “Variance” & “Index”

-

If it’s variance, the formula is EV – something.

-

If it’s index, EV / something.

-

If it relates to cost, use Actual Cost.

-

If it relates to schedule, use PV.

-

Negative numbers are bad, positive is good.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD

More Related Content

What's hot

Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
Guhan M
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
Reetesh Gupta
 
Project Management
Project ManagementProject Management
Project Management
Hamdard University
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
BhuWan Khadka
 
Project planning
Project planning Project planning
Project planning
Dereje Jima
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
adeel hamid
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
tltiede
 
Project risk management
Project risk managementProject risk management
Project risk management
Yogender Singh Rana
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
Nishant Munjal
 
Critical path method
Critical path methodCritical path method
Critical path method
Dhruv Shah
 
Projectcontrol
ProjectcontrolProjectcontrol
Projectcontrol
Raj Sampat
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
Tùng Trần Thanh
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
ChandraShekhar Patel
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
NAVNEET KUMAR JHA
 
Project Control
Project ControlProject Control
Project Control
Martin Sillaots
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Saqib Raza
 

What's hot (20)

Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project Management
Project ManagementProject Management
Project Management
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Project planning
Project planning Project planning
Project planning
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Projectcontrol
ProjectcontrolProjectcontrol
Projectcontrol
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Project Control
Project ControlProject Control
Project Control
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 

Similar to 4. project cost management

Cost management
Cost managementCost management
Cost managementshkadry
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
ssuser9d62d6
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
Peter Cholakis
 
Term paper spm
Term paper spmTerm paper spm
Term paper spm
UDAY SHARMA
 
Project_cost_managment definition and tools
Project_cost_managment definition and toolsProject_cost_managment definition and tools
Project_cost_managment definition and tools
MaryMa75
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl90
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Kateri Manglicmot
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project Estimation
VandalRay
 
Sm presentation
Sm presentationSm presentation
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
Dr. ABEER KHALID MANSOUR
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
mohamed elashri
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
Zaur Ahmadov, PMP
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
Mubashir Ali
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
SHAZEBALIKHAN1
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
zohir khellouf
 

Similar to 4. project cost management (20)

Cost management
Cost managementCost management
Cost management
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
 
Term paper spm
Term paper spmTerm paper spm
Term paper spm
 
Project_cost_managment definition and tools
Project_cost_managment definition and toolsProject_cost_managment definition and tools
Project_cost_managment definition and tools
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project Estimation
 
Sm presentation
Sm presentationSm presentation
Sm presentation
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Project mgt
Project mgtProject mgt
Project mgt
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Project Mangement
Project MangementProject Mangement
Project Mangement
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 

More from Mohamed Salah Eldien Mohamed Ali

9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
Mohamed Salah Eldien Mohamed Ali
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
Mohamed Salah Eldien Mohamed Ali
 
7. project communications management
7. project communications management7. project communications management
7. project communications management
Mohamed Salah Eldien Mohamed Ali
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
Mohamed Salah Eldien Mohamed Ali
 
5. project quality management
5. project quality management5. project quality management
5. project quality management
Mohamed Salah Eldien Mohamed Ali
 
2. project scope management
2. project scope management2. project scope management
2. project scope management
Mohamed Salah Eldien Mohamed Ali
 
3. project time management
3. project time management3. project time management
3. project time management
Mohamed Salah Eldien Mohamed Ali
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
Mohamed Salah Eldien Mohamed Ali
 
0. project management framework (fundamentals)
0. project management framework (fundamentals)0. project management framework (fundamentals)
0. project management framework (fundamentals)
Mohamed Salah Eldien Mohamed Ali
 

More from Mohamed Salah Eldien Mohamed Ali (12)

Series_Certificate
Series_CertificateSeries_Certificate
Series_Certificate
 
Business Management Cert.
Business Management Cert.Business Management Cert.
Business Management Cert.
 
Business Management Cert.
Business Management Cert.Business Management Cert.
Business Management Cert.
 
9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
7. project communications management
7. project communications management7. project communications management
7. project communications management
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
 
5. project quality management
5. project quality management5. project quality management
5. project quality management
 
2. project scope management
2. project scope management2. project scope management
2. project scope management
 
3. project time management
3. project time management3. project time management
3. project time management
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
0. project management framework (fundamentals)
0. project management framework (fundamentals)0. project management framework (fundamentals)
0. project management framework (fundamentals)
 

Recently uploaded

Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
Kumar Satyam
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 

Recently uploaded (20)

Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 

4. project cost management

  • 1. 4. Project Cost Management - Cost is one of 3 Triple constraints of the project. Managing costs of the project is very crucial and hardest part of the project. It spans across all phases of the project right from conception to closure of the project. - Cost Management is not just controlling “Costs”; it involves definitive planning and preparing budgets. Collecting cost associated data. Comparing the data to prepared budgets and taking appropriate actions when needed. - The process involved in estimating, budgeting, and controlling cost so that the project can be completed within approved budget. Value analysis (value engineering)  Looking at less costly way to do the same work within the same scope Following table lists all 3 Processes in this Knowledge Area, spread across '2 out of 5 Process Groups' - 5 Process Groups Initiation Planning Executi on Monitoring and control Closing 4.1. Cost Estimating Processes 4.3. Cost Control 4.2. Cost Budgeting 4.1 Estimate Cost - The process of developing approximation of the monetary resources needed to complete project activities  Cost trade-offs & risk must be considered  Cost estimates should be refined Inputs - - Scope baseline Project schedule Human resource plan Risk register Enterprise environmental factors Organizational process assets Tools - Expert judgment Analogous estimating Parametric estimating Bottom-up estimating Three-point estimates Reserve analysis Cost of quality Project management estimating software Vendor bid analysis Outputs - Activity cost estimates - Basis of estimates - Project document updates By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 2. There are 3 different types of estimation techniques listed over here under Tools section of Cost Estimation. - Analogous Estimation techniques - Bottom-up approach technique - Parametric approach technique Analogous estimation -It is mainly based on Expert Judgment or based on similar previous Projects. This approach is very useful in early stages of the project where WBS and work packets are completely defined. The expert judgment success factor depends on similarity of previous projects too. The main disadvantage is that it is good for ball-park figures but not for precise project cost. Parametric Estimation - It considers different project characteristics to calculate total costs of the project. For example, in the Telephone wire digging project, if we know cost per meter we can estimate it to whole project. For a house construction, if we know cost to construct per square feet, we can estimate total house project. For complex projects there will be multi dimensional parameters involved. When historic information is available these parametric estimation will be more accurate. Bottom-up approach - It is elaborative estimation technique. We start estimating from the bottom most part of WBS hierarchy which is work package. Work packages are divided into activities. Summing up work packages to modules or groups, summing up different modules to stages, summing up different stages to project is the bottom-up approach method. The people who will actually do this work should create the estimates. Types of Cost; - - Variable Costs  Change with the amount of production/work  e.g. material, supplies, wages Fixed Costs  Do not change as production change  - Direct Costs  Directly attributable to the work of project  - e.g. set-up, rental e.g. team travel, recognition, team wages Indirect Costs  overhead or cost incurred for benefit of more than one project  e.g. taxes, fringe benefit, janitorial services By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 3. - It is very important to understand “Cost Variability” that focuses on changing of cost over time as well as over volume;  Inflation; cost of some items increase over time.  Deflation; cost of technology items decrease over time. Direct Costs vs. Indirect Costs - when talking about “a new project team member”, the direct cost will be his salary while the indirect costs may be the insurance premiums given to him, the paid pill for his telephone calls, computer internet access cost, his disk or disk space that have been given to him. - When talking about “a specific material needed”, the direct cost will be its price while the indirect cost will be the transportation cost paid to receive such material as well as the storing cost...etc. Fixed Costs vs. Variable Costs - A fixed cost is like the cost of a unit has a certain nature which maybe a resource such as a specific material or equipment used for the project. If you need to buy a piece of equipment to allow the project to continue, that is simply a fixed cost regardless it will be used for once or hundreds of times. - Variable costs are directly related to the level of work with each and every element of the WBS. It is like the cost of water needed to drink or Gasoline needed to some machinery. Quality/Accuracy of Cost Estimation By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 4. 4.2 Determine Budget - Process of aggregating the estimated cost of individual activities or work packages to establish an authorized cost baseline. Inputs - Activity cost estimates - Basis of estimates - Scope baselines - Project schedule - Resource calendars - Contracts - Organizational process assets Tools - Cost aggregation Reserve analysis Expert judgment Historical relationship Funding limit reconciliation Outputs - Cost performance baseline Project funding requirements Project document updates - The main goal of this process is to develop Cost Baseline. At the starting point of this Process, you should have finished Project Cost Estimation and have a complete list of estimates of individual activities. Cost Aggregation; - We use Cost Aggregation tools to sum up those low level activity costs to Work package to higher levels of WBS hierarchy. - Reserves & risk management are important while estimating!  Contingency reserves/Cost Baseline (the cost impacts of the remaining risk)  Management reserves/Cost Budget (extra fund to cover surprising risks or changes to the project). The cost baseline - It is a reference point for the project to compare time to time. You will monitor and control project costs comparing to the baseline and report any variations. Costs at work package level are tied to financial systems using Chart of Accounts. Chart of accounts show cost allocation categories. Project manager is allowed to allocate extra resources (time or money) as a buffer for known unknowns; we call it as Contingency Reserve. Determines Budget: Other considerations By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 5. - High level parametric estimate as a rule of thumb  E.g. testing cost 50% of development cost - Funding limit reconciliation = checking cash flow  When the money will be available? - Reconciliation needed before proposed cost baseline and cost budget become final  Such reconciliation is part of integration management 4.3 Control Cost - The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline. Inputs - Project management plan - Project funding requirement - Work performance information - Organizational process assets Tools - Earned value management Forecasting To-complete performance index Performance reviews Variance analysis Project management software Outputs - Work performance measurement Budget forecast Organizational process updates Change requests Project management plan updates Project document updates Cost control: Once you estimate Project costs as well as cost baseline and prepare a Budget, you will be on cruise mode to control the costs. That doesn’t mean it is easy thereafter. No not at all. You have to monitor your cost so closely. Your work performance information is key input for this process. You should have clear set templates to report the work progress. Otherwise all unwanted junk data might ruin the soup. How to control cost? - Follow the cost management plan - Look at any organizational process asset that are available - Manage change  Recording all appropriate change By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 6.   Ensuring requested changes are agreed upon  - Preventing incorrect change Managing the actual changes when and as they occur Measure and measure and measure (monitoring) Project performance review is another Tools & Techniques provided. You will review project progress with your baseline plans and will provide what you’ve earned against what you have planned. This is known as Earned Value Analysis and helps you to track your day to day progress. 3 possible scenarios are: you are progressing ahead of plan that means you are getting more than what you have planned, or progress is as per the plan or not getting enough worth for your investment. Based on these 3 scenarios you can take according corrective actions. Corrective actions are what you are supposed to do in this process. You can use Project Management software of your choice to help you in this regard. MS Project is popular one or even you can simply use well planned out Excel sheets to track those costs. First you will find variances and report those using Variance analysis. The terms you use over here are Cost Variance (CV) and Schedule Variance (SV). From that point you might required to forecast rest of the project. This involves estimating rest of the work. You use terms like Estimation to Completion (ETC) and Estimate at Complete (EAC). Those names are telling what you have to Estimate. Other terms you use here are Cost Performance Index (CPI) and SPI (Schedule Performance Index) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 7. Earned Value Technique Ex; Cont. Earned Value Technique By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 8. Earned Value Management - Method to measure project performance against scope, schedule and cost baseline (performance measurement baseline). - Interpretation of basic EVM performance measures  Cost Performance Index (CPI)  Schedule Performance Index (SPI) Exercise; - You have a project to build a box. The box is six sided. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planned to be completed one after the other. Today is the end of day three. - Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, VAC. - Describe your interpretation based on the calculation! By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 9. Solution; Hence, based on the result table; • Over budget, getting 0.88 dollar for every spent dollar, • Ahead schedule, progressing 101% of the rate planned, • Probably will spend $6818 at the end (estimation), • need $3368 to complete, • Over budget at the end for about $818 (estimation) Performance Metrics; - Budget At Completion (BAC) “Total cost of the project.” - Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV)   - The amount expressed in Pounds (or hours) of work to be performed as per the schedule plan. PV = BAC * % of planned work. Budgeted Cost for Work Performed (BCWP) / Earned Value (EV)   - The amount expressed in Pounds (or hours) on the actual worked performed. EV = BAC * % of Actual work Actual Cost of Work Performed (ACWP) / Actual Cost (AC) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 10. Cost Forecasting: - Estimate At Completion (EAC) - The expected TOTAL cost required to finish complete work. - EAC = BAC / CPI = AC + (BAC - EV) (at typical case) = AC + ((BAC - EV) / CPI) (The same performance will remain) = AC + (BAC - EV) / (CPI* SPI) (The same performance will remain + Extra loss due to delay in time) * Here “typical” means it is assumed that similar variances will not occur in the future. - Estimate to complete (ETC) - The expected cost required to finish all the Remaining work. - ETC = EAC - AC = (BAC - EV) / CPI Variances:  Cost Variances (CV) Determine “How much under or over budget?” CV = EV-AC NEGATIVE is over budget, POSITIVE is under budget.  Schedule Variances (SV) Determine “How much ahead or behind schedule?”. SV = EV-PV NEGATIVE is behind schedule, POSITIVE is ahead of schedule.  Variance At Completion (VAC) Variance of “TOTAL” cost of the work and expected cost. VAC = BAC - EAC By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 11. Performance Indices:  Cost Performance Index CPI = EV / AC “Over (< 1) or under (> 1) budget”.  Schedule Performance Index SPI = EV / PV “Ahead (> 1) or behind (< 1) schedule”. To-Complete Performance Index (TCPI) - Helps the team determine the efficiency that must be achieved on the remaining work for a project to meet a specified endpoint, such as BAC or the team’s revised EAC. TCPI = Remaining Work (BAC – EV) / Funds Remaining (EAC - AC) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 12. Problem: A project has a budget of £10M and schedule for 10 months. It is assumed that the total budget will be spent equally each month until the 10th month is reached. After 2 months the project manager finds that only 5% of the work is finished and a total of £1M spent. Solution: PV = £2M EV = £10M * 0.05 = £0.5M AV = £1M CV = EV-AC = 0.5-1 = -0.5M CV% = 100 * (CV/EV) = 100*(-0.5/0.5) = -100% overrun SV = EV-PV = 0.5-2 = -1.5 months SV% = 100 * (SV/PV) = 100*(-1.5/2) = -75% behind CPI = EV/AC = 0.5/1 = 0.5 SPI = EV/PV = 0.5/2 = 0.25 EAC = BAC/CPI = 10/0.5 = £20M ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = £19M Time to compete = (10-0.5)/0.25 = 38 Months This project will take TOTAL £20M (19+1) and 40 (38+2) Months to complete. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD
  • 13. Hints to remember; - EV comes in most of formulas specially regarding “Variance” & “Index” - If it’s variance, the formula is EV – something. - If it’s index, EV / something. - If it relates to cost, use Actual Cost. - If it relates to schedule, use PV. - Negative numbers are bad, positive is good. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMP®, DIT, MCAD