SlideShare a Scribd company logo
DEPARTMENT OF CE
Roadway condition survey
COURSE TITLE : TRANSPORTATION ENGINEERING
SESSIONAL II COURSE NO : CE 452
COURSE TEACHER : MINHAJUL ISLAM KHAN
NUZHAT AZRA
GROUP 2
Group members Student ID
ZOBAER SALEHEEN SHAURAV 11.01.03.100
IMRAN UDDIN MAHMUD 11.01.03.106
SIAM MOHAMMAD AZMIH 11.01.03.107
ZAKIRUL ISLAM 11.01.03.108
MD. KAMRUZZAMAN MAHFUZ 11.01.03.109
MAKSHUD AL SHABIB 11.01.03.110
KAZI GOLAM MOSTOFA 11.01.03.116
MD. NAZMUL ISLAM 10.01.03.103
ABDULLAH IBNE FARUK 10.02.03.105
PRESENTATION OUTLINE
1. INTRODUCTION
2. OBJECTIVE OF STUDY
3. SCOPE OF STUDY
4. METHODOLOGY
5. DATA COLLECTION
a. GEOMETRIC CONDITION
b. OPERATION CONDITION
6. DATA ANALYSIS
7. RECOMMENDATION
INTRODUCTION
A ROADWAY CONDITION SURVEY IS DONE BY VISUAL
INSPECTION OF A ROADWAY. A ROADWAY CONDITION SURVEY IS
THE PROCESS OF COLLECTING DATA TO DETERMINE THE
STRUCTURAL INTEGRITY, DISTRESSES, SKID RESISTANCE, AND
OVERALL RIDING QUALITY OF THE PAVEMENT.
OBJECTIVE OF STUDY
 To draw detailed layout of roadway and intersection.
 For qualitative observation of potholes, elevated
or depressed manholes, speed breakers etc.
 To determine loss of effective width at different
locations due to loading or unloading, illegal
parking, construction utility etc.
SCOPE OF THE STUDY
 DESIGN AND PLANNING PURPOSE
 IMPROVEMENT PURPOSE
 DYNAMIC TRAFFIC MANAGEMENT AND PRIORITY SCHEDULE
 ACCIDENT RATE COMPUTATION
METHODOLOGY OF ROADWAY
CONDITION SURVEY
 MANUAL METHOD
 WALKING SURVEY
 WINDSHIELD SURVEY
 WALKING AND WINDSHIELD SURVEY
 AUTOMATIC METHOD
 VIDEO CAMERA
 DISTANCE MEASURING INSTRUMENT
 GIS METHOD
 AUTOMATED ROAD ANALYZER
MANUAL METHOD
 WALKING SURVEY
• Done by walking down by the side of
the pavement by a group of people.
• Provides the most correct data.
• Time consuming.
ABDULLAH RECORDING DATA
WINDSHIELD SURVEY
• Systematic observation is made from
a moving vehicle.
• Useful when particular section of
road segment is observed.
• Time saving.
Survey process by Windshield method
WALKING AND
WINDSHIELD
SURVEY
• Better method than the
single application.
• Achieve maximum
pavement data and
complete pavement
surveys.
• Require both
technological and human
activity.
Picture of walking and wind shield
survey
AUTOMATIC METHOD
VIDEO CAMERA
• Observe service
condition.
• Generally attached on
the post in the street.
• Doesn’t work at night.
Roadway condition survey using
street camera
AUTOMATED ROAD ANALYZER
• Technically complex
vehicle.
• Attached with sensor
machine.
• Take photo as well as
distance.
Road way condition survey by vehicle
DATA COLLECTION
• Observation – Roadway Condition Survey
• Method – Manual
• Equipment – Camera, Tape etc.
• Location – Panthapath to Russell Square
• Date - 14.12.2014
• Day - Sunday
• Time – 11.00 am -4:00 pm
• Weather condition – Sunny, Gentle Breeze
• Duration – 5 hrs. (short count)
• Number of Enumerator - 09
 GEOMETRIC CONDITION OBSERVATION
 Geometric layout of the roadway
Road Length = 970 meter
Road width = Road width varies along the direction starting from Panthapath to Russell Square.
Distance starting from panthpath(m) Width(m) of left approach Width (m) of right approach Lane
0 11.7 9.8 3
50 14.8 11.8 4
100 9.6 9.5 3
150 9.4 9.2 3
200 9 9.2 3
250 8.5 9.9 3
300 8.7 8.6 3
350 8.7 8.6 3
400 8.6 8.6 3
450 8.4 8.9 3
500 9.3 9.9 3
550 9 8.8 3
600 8.6 8.8 3
650 7.5 8.7 3
700 9 8.3 3
750 8.7 8.5 3
800 7.2 8.6 3
850 8.4 8.5 3
900 11.5 8.5 3
950 17.8 11 4
Median Dimension
Median dimension was taken
near panthapath signal
Width=1.6 meters = 5.25 feet
Height= .508 meters = 20 inch
Shoulder Dimension
Shoulder width was measured
in the midblock section in
front of a shop (Mr. Baker)
Width= 7 ft.
Height = 6 inch
 Geometric layout of the intersection
Geometric measurement and position of Channel/Island, pedestrian
refuge corner radius
Russell Square Intersection
Russell Square Intersection E-W W-E
Distance between median to channel 21.83 feet 22.5
Channel length
40 feet on straight 72 feet on Straight
42 feet on curve 75 feet on curve
Channel Width 17.5 feet 55 feet
Distance from channel to footpath 13.5 feet 21.5 feet
Pedestrian refuge
Length 10 feet Length 20 feet
Width 12 feet Width 15 feet
Panthapath Intersection
Panthapath Intersection E-W W-E
Distance between median to
channel
39 feet 22.5 feet
Channel length
22 feet on straight 24 feet on Straight
26 feet on curve 25 feet on curve
Channel Width 21 feet 11.5 feet
Distance from channel to
footpath
14 feet 13.5 feet
Pedestrian refuge
Length 11 feet Length 12 feet
Width 10 feet Width 10 feet
Dimension and Location
of pedestrian refuge
Besides intersection and near
opening of the road, to facilitate
the pedestrian crossing,
pedestrian refuge was provided.
6 inch height provided in
pedestrian refuge.
 Surface condition
Surface condition near high
speed location
Zebra crossing
At intersections
• Qualitative observation of Potholes , elevated / depressed manholes , speed
breakers etc. was counted and recorded .
Operating Condition Observation
 Location and Width of side roads
Along the direction Panthapath to Russell Square
Side road No. Chain age starting from Russell
square (m)
Width (m)
1 49.6 3.6
2 80 4.1
3 229.6 3
4 299.5 6
5 350 1.9
6 592.3 3
7 783 4.5
8 892.2 2
Side road No. Chain age starting from Panthapath (m) Width (m)
1 52.92 .97
2 63.13 2.61
3 86.88 1.9
4 109.25 3.19
5 278.9 4
6 311.9 4
7 357.91 3
8 372.61 3.31
9 379.41 3.5
10 447.92 4
11 665.92 4
Along the direction Russell Square to Panthapath
 Road side land-use pattern
The roadside land use pattern is highly dense with commercially developed area including Bank, Hospital
, School, Market, Shopping Mall, Showrooms etc. in the range of 2 storied up to 24 storied.
 Loss of road width
 Due to Parking & Parking Barrier
• Due to Passenger Loading/Unloading , Para transit & NMV Activity
• Presence of Dustbin/ Trash Disposal & Construction Materials
• Cutting , Digging ,Repair & Maintains work & Some Illegal
Activities
 Pedestrians Crossing Facilities
 Opening Median
Due to facilitate the pedestrian crossing, opening was
provided on top of the median at some intervals in
the mid block section. Near panthapath signal median
height was found to be approximately 20 inch. For
facilate as a pedestrian refuge ,this height was
reduced to 4-5 inch.
• Pedestrian Refuge
Besides near intersection and opening of the road, to facilitate the pedestrian
crossing, pedestrian refuge was provided.
 Location & Types of Traffic Control Device
 Road Sign & Marking
 Sign :Traffic signs or road signs are signs erected at the side or above roads to
give instructions or provide information to road users. In our survey road we
found sings in both intersection.
 Marking
Types of marking
Centre Line, Pavement Edge Lines, Stop Line, Pedestrian Crossings, Word
Marking/Message, Divisional Arrow
• Signal
Traffic signs control the flow of traffic, warn you of hazards ahead, guide you to
your destination, and inform you of roadway services.
 Primary traffic signal
 Secondary traffic signal
 Tertiary Traffic Signal
 Special Filter Signal
o Pedestrian Crossing Signal
o Timer signal
 Layout of Street lighting System
 Sodium Light Center, Two head/Double arms
 Solar Panel Light
DATA ANALYSIS
 Detailed Layout of Roadway & Intersection
Layout of Roadway, where geometric alignment and side roads are shown
 Layout of intersection
Panthapath intersection’s
layout when East-West &
North-South traffic flow
occurs. And also conflict
are shown
Russell Square intersection
 Stages of traffic movement at Panthapath Intersection
Three Stages Flow
 Stage 1
 Stage 2
 Stage 3
 Stages of traffic movement of Russell Square Intersection
Here Also three stages traffic flow occurs
 Stage 1
 Stage 2
 Stage 3
 Location of Bottleneck
 Due to indiscriminate bus stopping/Stand in both intersection bottleneck is
arises
 Due to Littering-car parking through the roadway bottleneck causes though the
roadway
 At side roads opening bottleneck causes
 Para transit & NMV activities in front of commercial centers like Hospital, Shopping
mall and also opening of side roads Bottleneck creates.
Due to cracking of edge road bottle neck also arises.
 Road Light Alignment
 Sodium light layout system mostly common in Dhaka city. The clear distance
between two street lights post or lamp post are approximately 100 feet. Total
number of street light found was 33.Through the roadway
 We also found some Solar panel
Light System which may provided by
Sponsor's in front of Square Hospital.
Control Device
Some of Control device found through the road way.
Pedestrian Crossing Signals found in both intersections
 Density of Side Friction’s
Different feature of roadway Bottleneck Cause Direction
E-W W-E
Density of side road 8 11
Density of opening 2 2
Density of Pedestrian crossing in median 24 24
Density of Street light 33 33
Density of Manhole 9 15
Density of Dustbin 0 1
Density of Bus stops 0 1
Density of speedbraker 0 0
Some other obstruction on the main road are indiscriminate goods loading and unloading
on the road, disturbed traffic flow due to non motorized vehicles entrance like rickshaw,
van, cycle and presence dustbin on the road. It should be must monitored
Loading or unloading goods Non motorized vehicle Dustbin blocks almost one
road lane
Erased road marks at intersections at channel head, Line Division, and
pedestrian crossing & Leder crossing signs are erased, invisible traffic
signal can create problem.
They must be monitored
Erased road marks/Sign at intersection At Channel Head
Invisible Leder crossing Invisible Pedestrian crossing
At intersections the Ghost islands are blocked or not facilities the
pedestrian and its head are broken
Road sign’s are covered by poster or erased and broken or disable street lights are
present in roadway . Some V-notch’s are broken & V-notch sign & marking are erased
Covered & Erased Sign & Slotted Sign Unmarked V-Notch
Surface condition of the road is not fair enough due to various kinds of
road cracking which decreases the skid resistances of the road and of the
road way
fatigue crack Ravelling
Some traffic law breaking
RECOMMENDATIONS
 The surface of roadway was not good enough and the medians were not geometrically right. The marks on
the road were invisible. So our recommendation is that we should be careful about regular maintenance
of road to avoid unwanted incidents such as accidents.
 The signs we observed on the roadway were old and not only covered by posters but also broken. So
replacing these old sign plates with new ones is highly recommended.
 We found different kind of small shops on the footpath or shoulder. So it is recommended that Dhaka City
Corporation should take essential step to clear the footpath so that pedestrian can move easily.
 There were no facilities for blind people ,people who use wheelchair and people who are not normal. So
extra facilities for these people are recommended.
Presentration 2

More Related Content

What's hot

Cc503 traffic managemant part1
Cc503   traffic managemant part1Cc503   traffic managemant part1
Cc503 traffic managemant part1
Syafiqah Jamian
 

What's hot (20)

Presentation on Roadway Condition Survey
Presentation on Roadway Condition Survey Presentation on Roadway Condition Survey
Presentation on Roadway Condition Survey
 
Road condition survey by ahmed ferdous - 1004137-buet
Road condition survey by ahmed ferdous - 1004137-buetRoad condition survey by ahmed ferdous - 1004137-buet
Road condition survey by ahmed ferdous - 1004137-buet
 
ROADWAY CONDITION SURVEY
ROADWAY CONDITION SURVEYROADWAY CONDITION SURVEY
ROADWAY CONDITION SURVEY
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 
Station Accessibility Plan(SAP) for Vijaynagar Metro Station by RK
Station Accessibility Plan(SAP) for Vijaynagar Metro Station by RKStation Accessibility Plan(SAP) for Vijaynagar Metro Station by RK
Station Accessibility Plan(SAP) for Vijaynagar Metro Station by RK
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
 
Cc503 traffic managemant part1
Cc503   traffic managemant part1Cc503   traffic managemant part1
Cc503 traffic managemant part1
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Chapter 3 characteristics of highway components
Chapter 3 characteristics of highway componentsChapter 3 characteristics of highway components
Chapter 3 characteristics of highway components
 
traffic singal design and model
traffic singal design and model traffic singal design and model
traffic singal design and model
 
Unseen heroes - SMART CITY MEASURES
Unseen heroes - SMART CITY MEASURESUnseen heroes - SMART CITY MEASURES
Unseen heroes - SMART CITY MEASURES
 
metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)
 
Cantonment metro station a case study1 rajkumar
Cantonment metro station   a case study1  rajkumarCantonment metro station   a case study1  rajkumar
Cantonment metro station a case study1 rajkumar
 
Development of a road network plan for sylhet agricultural university
Development of a road network plan for sylhet agricultural universityDevelopment of a road network plan for sylhet agricultural university
Development of a road network plan for sylhet agricultural university
 
Cal U Bicycle and Pedestrian Safety Improvements
Cal U Bicycle and Pedestrian Safety ImprovementsCal U Bicycle and Pedestrian Safety Improvements
Cal U Bicycle and Pedestrian Safety Improvements
 
Road marking
Road markingRoad marking
Road marking
 
chapter- 1
chapter- 1chapter- 1
chapter- 1
 
Road signs
Road signsRoad signs
Road signs
 
L10 Traffic Control Devices
L10 Traffic Control DevicesL10 Traffic Control Devices
L10 Traffic Control Devices
 

Viewers also liked (17)

Prueba: Mensajes de las redes sociales de tu escuela
Prueba: Mensajes de las redes sociales de tu escuelaPrueba: Mensajes de las redes sociales de tu escuela
Prueba: Mensajes de las redes sociales de tu escuela
 
DataDesigns™ © 2015®
DataDesigns™ © 2015®DataDesigns™ © 2015®
DataDesigns™ © 2015®
 
Điều gì ảnh hưởng đến chuyện chăn gối của đàn ông
Điều gì ảnh hưởng đến chuyện chăn gối của đàn ôngĐiều gì ảnh hưởng đến chuyện chăn gối của đàn ông
Điều gì ảnh hưởng đến chuyện chăn gối của đàn ông
 
frutas y flores
frutas y flores frutas y flores
frutas y flores
 
Wang's Journal
Wang's JournalWang's Journal
Wang's Journal
 
Penal especial
Penal especialPenal especial
Penal especial
 
Lý do gây thoái hóa thần kinh, suy giảm trí nhớ
Lý do gây thoái hóa thần kinh, suy giảm trí nhớLý do gây thoái hóa thần kinh, suy giảm trí nhớ
Lý do gây thoái hóa thần kinh, suy giảm trí nhớ
 
Ahmed Gameel_CV
Ahmed Gameel_CVAhmed Gameel_CV
Ahmed Gameel_CV
 
Giovanni's Diplomas
Giovanni's DiplomasGiovanni's Diplomas
Giovanni's Diplomas
 
Poppy’s adventures with Nika
Poppy’s adventures with NikaPoppy’s adventures with Nika
Poppy’s adventures with Nika
 
Japanese presentation
Japanese presentationJapanese presentation
Japanese presentation
 
Olga’s weekend with poppy
Olga’s weekend with poppyOlga’s weekend with poppy
Olga’s weekend with poppy
 
Ahmed-Nagm-CV
Ahmed-Nagm-CVAhmed-Nagm-CV
Ahmed-Nagm-CV
 
Wilma bowie cv
Wilma bowie cvWilma bowie cv
Wilma bowie cv
 
Evaluation Q6
Evaluation Q6Evaluation Q6
Evaluation Q6
 
Sill lit rev
Sill lit revSill lit rev
Sill lit rev
 
BUSINESS PROFILE
BUSINESS PROFILEBUSINESS PROFILE
BUSINESS PROFILE
 

Similar to Presentration 2

enc=encoded=8rAq3OHGhLaQwji-3KC1Haizk-eP_kNHJkXxJ1po_52GQl5r1irOG9o-BI9fQDI=.ppt
enc=encoded=8rAq3OHGhLaQwji-3KC1Haizk-eP_kNHJkXxJ1po_52GQl5r1irOG9o-BI9fQDI=.pptenc=encoded=8rAq3OHGhLaQwji-3KC1Haizk-eP_kNHJkXxJ1po_52GQl5r1irOG9o-BI9fQDI=.ppt
enc=encoded=8rAq3OHGhLaQwji-3KC1Haizk-eP_kNHJkXxJ1po_52GQl5r1irOG9o-BI9fQDI=.ppt
mohmmedsahil111
 
67-PPT on Road Safety road Safety .pptx
67-PPT on Road Safety road Safety  .pptx67-PPT on Road Safety road Safety  .pptx
67-PPT on Road Safety road Safety .pptx
PranchiJijo
 
Complete Street PVAL PUP430
Complete Street PVAL PUP430Complete Street PVAL PUP430
Complete Street PVAL PUP430
Peter Valenzuela
 

Similar to Presentration 2 (20)

Presentation on Roadway Condition Survey for the course CE 454
Presentation on Roadway Condition Survey for the course CE 454Presentation on Roadway Condition Survey for the course CE 454
Presentation on Roadway Condition Survey for the course CE 454
 
Case study on Majid Sarani & various streets
Case study on Majid Sarani & various streetsCase study on Majid Sarani & various streets
Case study on Majid Sarani & various streets
 
Redesigning of Pochamma Maidan Junction, Warangal
Redesigning of Pochamma Maidan Junction, WarangalRedesigning of Pochamma Maidan Junction, Warangal
Redesigning of Pochamma Maidan Junction, Warangal
 
enc=encoded=8rAq3OHGhLaQwji-3KC1Haizk-eP_kNHJkXxJ1po_52GQl5r1irOG9o-BI9fQDI=.ppt
enc=encoded=8rAq3OHGhLaQwji-3KC1Haizk-eP_kNHJkXxJ1po_52GQl5r1irOG9o-BI9fQDI=.pptenc=encoded=8rAq3OHGhLaQwji-3KC1Haizk-eP_kNHJkXxJ1po_52GQl5r1irOG9o-BI9fQDI=.ppt
enc=encoded=8rAq3OHGhLaQwji-3KC1Haizk-eP_kNHJkXxJ1po_52GQl5r1irOG9o-BI9fQDI=.ppt
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian
 
Pedestrians safety assessment & sidewalk quality study in a city
Pedestrians safety assessment & sidewalk quality study in a cityPedestrians safety assessment & sidewalk quality study in a city
Pedestrians safety assessment & sidewalk quality study in a city
 
Brendan Paulwels
Brendan PaulwelsBrendan Paulwels
Brendan Paulwels
 
L#7.pdf
L#7.pdfL#7.pdf
L#7.pdf
 
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM.
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM.PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM.
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM.
 
Chapter 3.pptx highway one civil engineering
Chapter 3.pptx highway one civil engineeringChapter 3.pptx highway one civil engineering
Chapter 3.pptx highway one civil engineering
 
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATION
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATIONPROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATION
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATION
 
ITS presentation final
ITS presentation final ITS presentation final
ITS presentation final
 
road safety audit of Aurangabad
 road safety audit of Aurangabad road safety audit of Aurangabad
road safety audit of Aurangabad
 
Immokalee's Crosswalk Future - Walkable Community
Immokalee's Crosswalk Future - Walkable CommunityImmokalee's Crosswalk Future - Walkable Community
Immokalee's Crosswalk Future - Walkable Community
 
2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf2. Geometric Design of Highways.pdf
2. Geometric Design of Highways.pdf
 
Presentation 1
Presentation 1Presentation 1
Presentation 1
 
EMBARQ Türkiye Yol Güvenliği Laboratuvarı-RSLab Projesi (EMBARQ Turkey Road S...
EMBARQ Türkiye Yol Güvenliği Laboratuvarı-RSLab Projesi (EMBARQ Turkey Road S...EMBARQ Türkiye Yol Güvenliği Laboratuvarı-RSLab Projesi (EMBARQ Turkey Road S...
EMBARQ Türkiye Yol Güvenliği Laboratuvarı-RSLab Projesi (EMBARQ Turkey Road S...
 
67-PPT on Road Safety road Safety .pptx
67-PPT on Road Safety road Safety  .pptx67-PPT on Road Safety road Safety  .pptx
67-PPT on Road Safety road Safety .pptx
 
Gm20151102 updatemeeting finaledited
Gm20151102 updatemeeting finaleditedGm20151102 updatemeeting finaledited
Gm20151102 updatemeeting finaledited
 
Complete Street PVAL PUP430
Complete Street PVAL PUP430Complete Street PVAL PUP430
Complete Street PVAL PUP430
 

Recently uploaded

Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
Atif Razi
 

Recently uploaded (20)

Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 

Presentration 2

  • 2. Roadway condition survey COURSE TITLE : TRANSPORTATION ENGINEERING SESSIONAL II COURSE NO : CE 452 COURSE TEACHER : MINHAJUL ISLAM KHAN NUZHAT AZRA
  • 3. GROUP 2 Group members Student ID ZOBAER SALEHEEN SHAURAV 11.01.03.100 IMRAN UDDIN MAHMUD 11.01.03.106 SIAM MOHAMMAD AZMIH 11.01.03.107 ZAKIRUL ISLAM 11.01.03.108 MD. KAMRUZZAMAN MAHFUZ 11.01.03.109 MAKSHUD AL SHABIB 11.01.03.110 KAZI GOLAM MOSTOFA 11.01.03.116 MD. NAZMUL ISLAM 10.01.03.103 ABDULLAH IBNE FARUK 10.02.03.105
  • 4. PRESENTATION OUTLINE 1. INTRODUCTION 2. OBJECTIVE OF STUDY 3. SCOPE OF STUDY 4. METHODOLOGY 5. DATA COLLECTION a. GEOMETRIC CONDITION b. OPERATION CONDITION 6. DATA ANALYSIS 7. RECOMMENDATION
  • 5. INTRODUCTION A ROADWAY CONDITION SURVEY IS DONE BY VISUAL INSPECTION OF A ROADWAY. A ROADWAY CONDITION SURVEY IS THE PROCESS OF COLLECTING DATA TO DETERMINE THE STRUCTURAL INTEGRITY, DISTRESSES, SKID RESISTANCE, AND OVERALL RIDING QUALITY OF THE PAVEMENT.
  • 6. OBJECTIVE OF STUDY  To draw detailed layout of roadway and intersection.  For qualitative observation of potholes, elevated or depressed manholes, speed breakers etc.  To determine loss of effective width at different locations due to loading or unloading, illegal parking, construction utility etc.
  • 7. SCOPE OF THE STUDY  DESIGN AND PLANNING PURPOSE  IMPROVEMENT PURPOSE  DYNAMIC TRAFFIC MANAGEMENT AND PRIORITY SCHEDULE  ACCIDENT RATE COMPUTATION
  • 8. METHODOLOGY OF ROADWAY CONDITION SURVEY  MANUAL METHOD  WALKING SURVEY  WINDSHIELD SURVEY  WALKING AND WINDSHIELD SURVEY  AUTOMATIC METHOD  VIDEO CAMERA  DISTANCE MEASURING INSTRUMENT  GIS METHOD  AUTOMATED ROAD ANALYZER
  • 9. MANUAL METHOD  WALKING SURVEY • Done by walking down by the side of the pavement by a group of people. • Provides the most correct data. • Time consuming. ABDULLAH RECORDING DATA
  • 10. WINDSHIELD SURVEY • Systematic observation is made from a moving vehicle. • Useful when particular section of road segment is observed. • Time saving. Survey process by Windshield method
  • 11. WALKING AND WINDSHIELD SURVEY • Better method than the single application. • Achieve maximum pavement data and complete pavement surveys. • Require both technological and human activity. Picture of walking and wind shield survey
  • 12. AUTOMATIC METHOD VIDEO CAMERA • Observe service condition. • Generally attached on the post in the street. • Doesn’t work at night. Roadway condition survey using street camera
  • 13. AUTOMATED ROAD ANALYZER • Technically complex vehicle. • Attached with sensor machine. • Take photo as well as distance. Road way condition survey by vehicle
  • 14. DATA COLLECTION • Observation – Roadway Condition Survey • Method – Manual • Equipment – Camera, Tape etc. • Location – Panthapath to Russell Square • Date - 14.12.2014 • Day - Sunday • Time – 11.00 am -4:00 pm • Weather condition – Sunny, Gentle Breeze • Duration – 5 hrs. (short count) • Number of Enumerator - 09
  • 15.  GEOMETRIC CONDITION OBSERVATION  Geometric layout of the roadway Road Length = 970 meter Road width = Road width varies along the direction starting from Panthapath to Russell Square. Distance starting from panthpath(m) Width(m) of left approach Width (m) of right approach Lane 0 11.7 9.8 3 50 14.8 11.8 4 100 9.6 9.5 3 150 9.4 9.2 3 200 9 9.2 3 250 8.5 9.9 3 300 8.7 8.6 3 350 8.7 8.6 3 400 8.6 8.6 3 450 8.4 8.9 3 500 9.3 9.9 3 550 9 8.8 3 600 8.6 8.8 3 650 7.5 8.7 3 700 9 8.3 3 750 8.7 8.5 3 800 7.2 8.6 3 850 8.4 8.5 3 900 11.5 8.5 3 950 17.8 11 4
  • 16. Median Dimension Median dimension was taken near panthapath signal Width=1.6 meters = 5.25 feet Height= .508 meters = 20 inch
  • 17. Shoulder Dimension Shoulder width was measured in the midblock section in front of a shop (Mr. Baker) Width= 7 ft. Height = 6 inch
  • 18.  Geometric layout of the intersection Geometric measurement and position of Channel/Island, pedestrian refuge corner radius Russell Square Intersection Russell Square Intersection E-W W-E Distance between median to channel 21.83 feet 22.5 Channel length 40 feet on straight 72 feet on Straight 42 feet on curve 75 feet on curve Channel Width 17.5 feet 55 feet Distance from channel to footpath 13.5 feet 21.5 feet Pedestrian refuge Length 10 feet Length 20 feet Width 12 feet Width 15 feet
  • 19. Panthapath Intersection Panthapath Intersection E-W W-E Distance between median to channel 39 feet 22.5 feet Channel length 22 feet on straight 24 feet on Straight 26 feet on curve 25 feet on curve Channel Width 21 feet 11.5 feet Distance from channel to footpath 14 feet 13.5 feet Pedestrian refuge Length 11 feet Length 12 feet Width 10 feet Width 10 feet
  • 20. Dimension and Location of pedestrian refuge Besides intersection and near opening of the road, to facilitate the pedestrian crossing, pedestrian refuge was provided. 6 inch height provided in pedestrian refuge.
  • 21.  Surface condition Surface condition near high speed location Zebra crossing
  • 22. At intersections • Qualitative observation of Potholes , elevated / depressed manholes , speed breakers etc. was counted and recorded .
  • 23. Operating Condition Observation  Location and Width of side roads Along the direction Panthapath to Russell Square Side road No. Chain age starting from Russell square (m) Width (m) 1 49.6 3.6 2 80 4.1 3 229.6 3 4 299.5 6 5 350 1.9 6 592.3 3 7 783 4.5 8 892.2 2
  • 24. Side road No. Chain age starting from Panthapath (m) Width (m) 1 52.92 .97 2 63.13 2.61 3 86.88 1.9 4 109.25 3.19 5 278.9 4 6 311.9 4 7 357.91 3 8 372.61 3.31 9 379.41 3.5 10 447.92 4 11 665.92 4 Along the direction Russell Square to Panthapath
  • 25.  Road side land-use pattern The roadside land use pattern is highly dense with commercially developed area including Bank, Hospital , School, Market, Shopping Mall, Showrooms etc. in the range of 2 storied up to 24 storied.
  • 26.
  • 27.  Loss of road width  Due to Parking & Parking Barrier
  • 28. • Due to Passenger Loading/Unloading , Para transit & NMV Activity
  • 29. • Presence of Dustbin/ Trash Disposal & Construction Materials
  • 30. • Cutting , Digging ,Repair & Maintains work & Some Illegal Activities
  • 31.  Pedestrians Crossing Facilities  Opening Median Due to facilitate the pedestrian crossing, opening was provided on top of the median at some intervals in the mid block section. Near panthapath signal median height was found to be approximately 20 inch. For facilate as a pedestrian refuge ,this height was reduced to 4-5 inch.
  • 32. • Pedestrian Refuge Besides near intersection and opening of the road, to facilitate the pedestrian crossing, pedestrian refuge was provided.
  • 33.  Location & Types of Traffic Control Device  Road Sign & Marking  Sign :Traffic signs or road signs are signs erected at the side or above roads to give instructions or provide information to road users. In our survey road we found sings in both intersection.
  • 34.  Marking Types of marking Centre Line, Pavement Edge Lines, Stop Line, Pedestrian Crossings, Word Marking/Message, Divisional Arrow
  • 35. • Signal Traffic signs control the flow of traffic, warn you of hazards ahead, guide you to your destination, and inform you of roadway services.  Primary traffic signal
  • 36.  Secondary traffic signal  Tertiary Traffic Signal
  • 37.  Special Filter Signal o Pedestrian Crossing Signal o Timer signal
  • 38.  Layout of Street lighting System  Sodium Light Center, Two head/Double arms  Solar Panel Light
  • 39. DATA ANALYSIS  Detailed Layout of Roadway & Intersection Layout of Roadway, where geometric alignment and side roads are shown
  • 40.  Layout of intersection Panthapath intersection’s layout when East-West & North-South traffic flow occurs. And also conflict are shown Russell Square intersection
  • 41.  Stages of traffic movement at Panthapath Intersection Three Stages Flow  Stage 1  Stage 2
  • 42.  Stage 3  Stages of traffic movement of Russell Square Intersection Here Also three stages traffic flow occurs  Stage 1
  • 43.  Stage 2  Stage 3
  • 44.  Location of Bottleneck  Due to indiscriminate bus stopping/Stand in both intersection bottleneck is arises
  • 45.  Due to Littering-car parking through the roadway bottleneck causes though the roadway  At side roads opening bottleneck causes
  • 46.  Para transit & NMV activities in front of commercial centers like Hospital, Shopping mall and also opening of side roads Bottleneck creates.
  • 47. Due to cracking of edge road bottle neck also arises.
  • 48.  Road Light Alignment  Sodium light layout system mostly common in Dhaka city. The clear distance between two street lights post or lamp post are approximately 100 feet. Total number of street light found was 33.Through the roadway  We also found some Solar panel Light System which may provided by Sponsor's in front of Square Hospital.
  • 49. Control Device Some of Control device found through the road way. Pedestrian Crossing Signals found in both intersections
  • 50.  Density of Side Friction’s Different feature of roadway Bottleneck Cause Direction E-W W-E Density of side road 8 11 Density of opening 2 2 Density of Pedestrian crossing in median 24 24 Density of Street light 33 33 Density of Manhole 9 15 Density of Dustbin 0 1 Density of Bus stops 0 1 Density of speedbraker 0 0
  • 51. Some other obstruction on the main road are indiscriminate goods loading and unloading on the road, disturbed traffic flow due to non motorized vehicles entrance like rickshaw, van, cycle and presence dustbin on the road. It should be must monitored Loading or unloading goods Non motorized vehicle Dustbin blocks almost one road lane
  • 52. Erased road marks at intersections at channel head, Line Division, and pedestrian crossing & Leder crossing signs are erased, invisible traffic signal can create problem. They must be monitored Erased road marks/Sign at intersection At Channel Head
  • 53. Invisible Leder crossing Invisible Pedestrian crossing At intersections the Ghost islands are blocked or not facilities the pedestrian and its head are broken
  • 54. Road sign’s are covered by poster or erased and broken or disable street lights are present in roadway . Some V-notch’s are broken & V-notch sign & marking are erased Covered & Erased Sign & Slotted Sign Unmarked V-Notch
  • 55. Surface condition of the road is not fair enough due to various kinds of road cracking which decreases the skid resistances of the road and of the road way fatigue crack Ravelling
  • 56. Some traffic law breaking
  • 57. RECOMMENDATIONS  The surface of roadway was not good enough and the medians were not geometrically right. The marks on the road were invisible. So our recommendation is that we should be careful about regular maintenance of road to avoid unwanted incidents such as accidents.  The signs we observed on the roadway were old and not only covered by posters but also broken. So replacing these old sign plates with new ones is highly recommended.  We found different kind of small shops on the footpath or shoulder. So it is recommended that Dhaka City Corporation should take essential step to clear the footpath so that pedestrian can move easily.  There were no facilities for blind people ,people who use wheelchair and people who are not normal. So extra facilities for these people are recommended.