Work Completed
• Crash Analyses
– Summarizing 2005 to 2012
• Vehicular Counts
– Traffic Volume & Speed
• Pedestrian/Bicycle Counts
– Nine Zones at Peak Hours
• Qualitative Assessment
– Observations/
Recommendations
Crash
Analyses
Vehicular
Counts
Pedestrian/
Bicycle
Counts
Qualitative
Assessment
Slide 4
Immokalee Pedestrian Crosswalk Improvements Study
Crash Analyses
• Review & Analyses of Crash Reports
– Summarize 2005 to 2012
Pedestrian/Bicycle Crashes
– Graphically Show Places of Concern
• Convenience Store on 7th Street
• Restaurant & Theater/Game
Room on 3rd Street
Crash
Analyses
Vehicular
Counts
Pedestrian/
Bicycle
Counts
Qualitative
Assessment
Slide 5
Immokalee Pedestrian Crosswalk Improvements Study
2005-2012 Day Crashes
2
KEY
Driver at Fault Pedestrian/Bicycle at Fault (No Alcohol) Pedestrian/Bicycle at Fault(Alcohol-Related) Fatal Incident
N
Slide 6
TOTAL CRASHES = 13 CRASHES INVOLVING DUI = 4 FATAL = 0
Immokalee Pedestrian Crosswalk Improvements Study
2005-2012 Night Crashes
2
N
2 2 2
2
Slide 7
KEY
Driver at Fault Pedestrian/Bicycle at Fault (No Alcohol) Pedestrian/Bicycle at Fault(Alcohol-Related) Fatal Incident
TOTAL CRASHES = 29 CRASHES INVOLVING DUI = 13 FATAL = 3
Immokalee Pedestrian Crosswalk Improvements Study
2005-2012 Crash Analyses
TYPE TOTAL DUI FATAL
Day 13 4 0
Night 29 13 3
Total 42 17 3
Pedestrian 27 13 3
Bicyclist 15 4 0
Total 42 17 3
Slide 8
Immokalee Pedestrian Crosswalk Improvements Study
Vehicular Counts
• 72 Hour Bi-Directional Traffic Counts
– Collected Between January 9th to 11th & 16th to 18th
– Traffic Volumes & Vehicle Speeds
Crash
Analyses
Vehicular
Counts
Pedestrian/
Bicycle
Counts
Qualitative
Assessment
Slide 9
FDOT TRAFFIC ENGINEERING AND OPERATIONS OFFICE
“It is common traffic engineering knowledge that about 85 percent of all drivers travel at
reasonably safe speeds for the various roadway conditions they encounter, regardless of speed
limit signs. This leaves 15 percent of drivers who must be reminded of the maximum speed limit.
The Department uses the "85th percentile" method of determining appropriate and safe
posted speed limits in conjunction with the maximum statute based speeds. This method is
based on extensive nationally accepted studies and observations. By measuring the speed of
hundreds of vehicles at various points along the roadway, traffic engineers are able to use data to
determine a reasonable and safe maximum speed to post for all vehicles to travel.”
Immokalee Pedestrian Crosswalk Improvements Study
Vehicular Speed Analysis
DIRECTION
AVERAGE DAILY
TRAFFIC VOLUME
MEAN (AVERAGE)
SPEED
85TH PERCENTILE
SPEED
Main Street
Eastbound 6,350 26.05 mph 33.24 mph
Westbound 5,661 26.33 mph 33.24 mph
1st Street
Northbound 7,270 33.19 mph 39.53 mph
Southbound 7,751 33.67 mph 39.22 mph
Slide 10
Immokalee Pedestrian Crosswalk Improvements Study
Pedestrian/Bicycle Counts
• Pedestrian Counts Conducted at Nine Locations
– Zones Determined by Observations
– Weekday & Weekend
• 2 Hours AM Peak
• 2 Hours PM Peak
Crash
Analyses
Vehicular
Counts
Pedestrian/
Bicycle
Counts
Qualitative
Assessment
ZONE NUMBER
1 2 3 4 5 6 7 8 9
Total 161 280 487 19 1,390 343 326 90 759
Slide 11
Immokalee Pedestrian Crosswalk Improvements Study
Pedestrian/Bicycle Counts
161 280 487 19
1,390 343 326
90 759
# of Pedestrian/Bicycle Counts
Slide 12
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
• During Peak Hours During Harvest Season
– January 16th & 18th
• 5:00 AM – 8:00 AM
• 4:00 PM – 7:00 PM
• Summarize Observations & Recommendations
– Improve Pedestrian & Bicyclist Safety
Crash
Analyses
Vehicular
Counts
Pedestrian/
Bicycle
Counts
Qualitative
Assessment
Slide 13
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Pedestrians Cutting
Through Medians
Slide 14
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
RECOMMENDATION
• Install Fence/Railing in Median to
Direct Pedestrians to
Crosswalk/Median Openings
Slide 15
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Pedestrians Using Shortest Path of Travel
Slide 16
VEHICLE SPEED
ESTIMATED SURVIVAL
PERCENTAGE FOR
PEDESTRIAN
20 mph 95%
30 mph 60%
35 mph 40%
40 mph 20%
50 mph Nearly No Survival
NATIONAL HIGHWAY TRAFFIC SAFETY
ADMINISTRATION STUDY DATA
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
RECOMMENDATION
• Designate “Pedestrian Zone” &
Lower Speed to 30 mph
Slide 17
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Large Number of Signs & Flashing
Beacons Distract Drivers
RECOMMENDATION
• Remove Excessive Signing & Beacons
• Install In-Pavement Lighting
at Crosswalks w/ Flashing
Highlighted Signs
Slide 18
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Harvester Bus Pick Up Lot & Grocery/Café Generate High Volume of
Pedestrians Crossing at/or Between 2nd Street & 3rd Street
– Over 2,000 Pedestrians Crossing in Area for the AM & PM Studied Peak Hours
– 1,400 Pedestrians Using Crosswalk at 3rd Street
• Broken Fence Between 2nd Street & 3rd Street
Slide 19
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
RECOMMENDATION
• Coordinate w/ Owner to Fix Fence
• Install Fence/Railing in Median
• Install New Crosswalk at 2nd Street
Slide 20
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Narrow 6-Foot Wide Median Opening Prohibits Two-Way Bicyclists
from Crossing Simultaneously
6’
Slide 21
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
RECOMMENDATION
• Widen Median Opening to 10 Feet
Near 5th Street & 7th Street
Slide 22
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Many Bicyclists Do Not Have Lights
or Reflectors
RECOMMENDATION
• Coordinate w/ FDOT Community
Traffic Safety Team to Distribute Free
Lights through Bike Lights Program
Slide 23
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Large Number of School Students Crossing East of 7th Street During the
Week Between 2:15-2:30 PM & 3:45-4:00 PM
Slide 24
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
RECOMMENDATION
• Detailed Evaluation Needed to
Determine if Crosswalk at 7th
Street is Warranted
Slide 25
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Vehicles Not Yielding to Pedestrians in
Crosswalks During Saturday Evenings
• Vehicles Typically Yielding During the
Other Times
RECOMMENDATION
• Increase Enforcement During
Saturday Evening Hours
Slide 26
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Over 750 Pedestrians Documented Crossing Near 1st Street & Colorado
Avenue During Four AM & PM Peak Hours on Weekdays & Weekends
Slide 27
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
RECOMMENDATION
• Install Crosswalk on 1st Street North
of Colorado Avenue
Slide 28
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Street Planters & Trees Limit Motorists Visibility of Pedestrians
Slide 29
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
RECOMMENDATION
• Remove or Modify Landscaping to
Low Profile Plants, at a Minimum
100 Feet Near Crosswalks
Slide 30
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Various Street & Pedestrian Lighting
is Not Currently Working on Main
Street & 1st Street
RECOMMENDATION
• Coordinate w/ Maintenance to
Replace all Non-Functioning Lighting
Slide 31
Immokalee Pedestrian Crosswalk Improvements Study
Qualitative Assessment
OBSERVATION
• Limited Sight Distance at Main
Street/3rd Street Intersection
RECOMMENDATION
• Install High Emphasis Crosswalk
Slide 32
Immokalee Pedestrian Crosswalk Improvements Study
Summary (Interim Improvements)
• Main Street & 1st Street
– Landscaping Grant/Contract
• Install Fence/Railing/Barrier
• Widen Median Openings from 6 feet to 10 feet
• Modifying Landscaping in medians
– Coordinate w/ Maintenance to Fix Lighting
– Coordinate w/ FDOT Regarding the “Bike Lights Program”
– Coordinate w/ Law Enforcement to Increase Enforcement
for Motorists to Stop for Pedestrians in Crosswalks
Slide 33
Immokalee Pedestrian Crosswalk Improvements Study
Summary (Long-Term Improvements)
• Main Street (Coordinate w/ FDOT for Approval)
– Install In-Pavement Lights w/ Automatic Detection & Signing
– Add Mid-Block Crossing at 2nd Street & Possibly at 7th Street
– Lower Speed Limit to 30 mph & make it a “Pedestrian Zone”
– Remove Signs
– Install High Emphasis Crosswalks on Side Streets
• 1st Street
– Install In-Pavement Lights w/ Automatic Detection & Signing
– Add Mid-Block Crossing at Colorado Avenue
Slide 34
Immokalee Pedestrian Crosswalk Improvements Study
Any Questions?
Slide 35
Immokalee Pedestrian Crosswalk Improvements Study
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
Slide 37
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
Slide 38
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
Slide 39
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
Slide 40
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
Slide 41
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
Slide 42
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
Slide 43
Immokalee Pedestrian Crosswalk Improvements Study
Recommendations
Slide 44
Immokalee Pedestrian Crosswalk Improvements Study
Pedestrian/Bicycle Counts
DAY
PEAK
HOURS
ZONE NUMBER
1 2 3 4 5 6 7 8 9
Weekday AM 4 33 10 10 318 101 89 18 86
Weekday PM 85 81 145 2 380 49 65 24 235
Weekend AM 9 30 71 6 244 117 92 13 98
Weekend PM 63 136 261 1 448 76 80 35 340
Total 161 280 487 19 1,390 343 326 90 759
Slide 45

More Related Content

Viewers also liked

2. проект положения об оценке персонала
2. проект положения об оценке персонала2. проект положения об оценке персонала
2. проект положения об оценке персонала
Sokirianskiy&Lazerson School
 
Roombeek en veranderhuis
Roombeek en veranderhuisRoombeek en veranderhuis
Roombeek en veranderhuis
Ton
 
Lap trinh web dong voi php my sql
Lap trinh web dong voi php my sqlLap trinh web dong voi php my sql
Lap trinh web dong voi php my sql
Giang Nguyễn
 
Ratificados para 15 y 16
Ratificados para 15 y 16Ratificados para 15 y 16
Ratificados para 15 y 16
UTTA OSPAT
 
Saját Web rádió készitése .
Saját Web rádió készitése .Saját Web rádió készitése .
Saját Web rádió készitése .
karesz57
 
Overcoming contradictions mike-o_rourke
Overcoming contradictions mike-o_rourkeOvercoming contradictions mike-o_rourke
Overcoming contradictions mike-o_rourke
IBM
 

Viewers also liked (20)

2a comparisons of equality
2a comparisons of equality2a comparisons of equality
2a comparisons of equality
 
China newsweek
China newsweekChina newsweek
China newsweek
 
2. проект положения об оценке персонала
2. проект положения об оценке персонала2. проект положения об оценке персонала
2. проект положения об оценке персонала
 
Roombeek en veranderhuis
Roombeek en veranderhuisRoombeek en veranderhuis
Roombeek en veranderhuis
 
Zuqiu
ZuqiuZuqiu
Zuqiu
 
HTML5-Features
HTML5-FeaturesHTML5-Features
HTML5-Features
 
Resultados generales reunión nº 6 09 10-16
Resultados generales reunión nº 6  09 10-16Resultados generales reunión nº 6  09 10-16
Resultados generales reunión nº 6 09 10-16
 
Nurturing communities of Inquiry: a showcase of DojoIBL
Nurturing communities of Inquiry: a showcase of DojoIBLNurturing communities of Inquiry: a showcase of DojoIBL
Nurturing communities of Inquiry: a showcase of DojoIBL
 
Aprianti
ApriantiAprianti
Aprianti
 
the Business of Global Mis-Education
the Business of Global Mis-Educationthe Business of Global Mis-Education
the Business of Global Mis-Education
 
There's an app for that (revalidatie blinde en slechtziende mensen)
There's an app for that (revalidatie blinde en slechtziende mensen)There's an app for that (revalidatie blinde en slechtziende mensen)
There's an app for that (revalidatie blinde en slechtziende mensen)
 
Humanity Plus Presentation, ScienceForCitizens.net
Humanity Plus Presentation, ScienceForCitizens.netHumanity Plus Presentation, ScienceForCitizens.net
Humanity Plus Presentation, ScienceForCitizens.net
 
Ellie thankful
Ellie thankfulEllie thankful
Ellie thankful
 
Lap trinh web dong voi php my sql
Lap trinh web dong voi php my sqlLap trinh web dong voi php my sql
Lap trinh web dong voi php my sql
 
Ratificados para 15 y 16
Ratificados para 15 y 16Ratificados para 15 y 16
Ratificados para 15 y 16
 
Hope thankful
Hope thankfulHope thankful
Hope thankful
 
Classifying with non standard schemes for slideshare
Classifying with non standard schemes for slideshareClassifying with non standard schemes for slideshare
Classifying with non standard schemes for slideshare
 
Saját Web rádió készitése .
Saját Web rádió készitése .Saját Web rádió készitése .
Saját Web rádió készitése .
 
Overcoming contradictions mike-o_rourke
Overcoming contradictions mike-o_rourkeOvercoming contradictions mike-o_rourke
Overcoming contradictions mike-o_rourke
 
Contextualizalção e perfil do fórum
Contextualizalção e perfil do fórumContextualizalção e perfil do fórum
Contextualizalção e perfil do fórum
 

Similar to Immokalee's Crosswalk Future - Walkable Community

Bicyclist and Pedestrian Safety and Mobility in Europe
Bicyclist and Pedestrian Safety and Mobility in EuropeBicyclist and Pedestrian Safety and Mobility in Europe
Bicyclist and Pedestrian Safety and Mobility in Europe
Sharon Roerty
 

Similar to Immokalee's Crosswalk Future - Walkable Community (20)

Final power point pedestrian safety presentation se rl
Final power point pedestrian safety presentation se rlFinal power point pedestrian safety presentation se rl
Final power point pedestrian safety presentation se rl
 
NZC - Bracke
NZC - BrackeNZC - Bracke
NZC - Bracke
 
Ready, Set, Action: Active Lifestyle Cameras in Planning
Ready, Set, Action: Active Lifestyle Cameras in PlanningReady, Set, Action: Active Lifestyle Cameras in Planning
Ready, Set, Action: Active Lifestyle Cameras in Planning
 
2 cip infuse-ottawa-bennett
2 cip infuse-ottawa-bennett2 cip infuse-ottawa-bennett
2 cip infuse-ottawa-bennett
 
Revolutionise roundabout design
Revolutionise roundabout designRevolutionise roundabout design
Revolutionise roundabout design
 
Gm20151102 updatemeeting finaledited
Gm20151102 updatemeeting finaleditedGm20151102 updatemeeting finaledited
Gm20151102 updatemeeting finaledited
 
Strategies to reduce road traffic fatalities
Strategies to reduce road traffic fatalitiesStrategies to reduce road traffic fatalities
Strategies to reduce road traffic fatalities
 
Redesigning of Pochamma Maidan Junction, Warangal
Redesigning of Pochamma Maidan Junction, WarangalRedesigning of Pochamma Maidan Junction, Warangal
Redesigning of Pochamma Maidan Junction, Warangal
 
Proposed peak hour_extensions_public_meeting_presentation
Proposed peak hour_extensions_public_meeting_presentationProposed peak hour_extensions_public_meeting_presentation
Proposed peak hour_extensions_public_meeting_presentation
 
Traffic Control System, Traffic sign
Traffic Control System, Traffic signTraffic Control System, Traffic sign
Traffic Control System, Traffic sign
 
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia RoadProposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
Proposed Bicycle Facilities: VDOT Summer 2015 Repaving-Franconia Road
 
Traffic Engineering And Drainage
Traffic Engineering And DrainageTraffic Engineering And Drainage
Traffic Engineering And Drainage
 
Hywel Rowlands
Hywel RowlandsHywel Rowlands
Hywel Rowlands
 
Final 360 stakeholder_presentation_110515
Final 360 stakeholder_presentation_110515Final 360 stakeholder_presentation_110515
Final 360 stakeholder_presentation_110515
 
Bicyclist and Pedestrian Safety and Mobility in Europe
Bicyclist and Pedestrian Safety and Mobility in EuropeBicyclist and Pedestrian Safety and Mobility in Europe
Bicyclist and Pedestrian Safety and Mobility in Europe
 
#27 Road Diets – Improving Safety for Everyone - Dougherty
#27 Road Diets – Improving Safety for Everyone - Dougherty#27 Road Diets – Improving Safety for Everyone - Dougherty
#27 Road Diets – Improving Safety for Everyone - Dougherty
 
How Do We Measure Up? Performance Measures for Active Transportation--Perform...
How Do We Measure Up? Performance Measures for Active Transportation--Perform...How Do We Measure Up? Performance Measures for Active Transportation--Perform...
How Do We Measure Up? Performance Measures for Active Transportation--Perform...
 
Effect of Pedestrian Countdown Timer on Safety and Efficiency of Operations a...
Effect of Pedestrian Countdown Timer on Safety and Efficiency of Operations a...Effect of Pedestrian Countdown Timer on Safety and Efficiency of Operations a...
Effect of Pedestrian Countdown Timer on Safety and Efficiency of Operations a...
 
Bike Plan Presentation Planning Commission
Bike Plan Presentation   Planning CommissionBike Plan Presentation   Planning Commission
Bike Plan Presentation Planning Commission
 
Bike Plan Presentation Planning Commission
Bike Plan Presentation   Planning CommissionBike Plan Presentation   Planning Commission
Bike Plan Presentation Planning Commission
 

Recently uploaded

一比一原版(IC毕业证)帝国理工大学毕业证成绩单
一比一原版(IC毕业证)帝国理工大学毕业证成绩单一比一原版(IC毕业证)帝国理工大学毕业证成绩单
一比一原版(IC毕业证)帝国理工大学毕业证成绩单
exuyk
 
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our OrganizationUp the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
uptheratios
 
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
enbam
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 

Recently uploaded (20)

Item # 6 - 7001 Broadway Significance Review
Item # 6 - 7001 Broadway Significance ReviewItem # 6 - 7001 Broadway Significance Review
Item # 6 - 7001 Broadway Significance Review
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
Proposed Facility Types: Chesapeake Trails and Connectivity Plan
Proposed Facility Types: Chesapeake Trails and Connectivity PlanProposed Facility Types: Chesapeake Trails and Connectivity Plan
Proposed Facility Types: Chesapeake Trails and Connectivity Plan
 
Elderly Persons Midday Meal Program kurnool
Elderly Persons Midday Meal Program kurnoolElderly Persons Midday Meal Program kurnool
Elderly Persons Midday Meal Program kurnool
 
Counting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptxCounting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptx
 
CourseHero 9KLDFSKJKSJDFKSDKFJSDKSLFJKSJL
CourseHero 9KLDFSKJKSJDFKSDKFJSDKSLFJKSJLCourseHero 9KLDFSKJKSJDFKSDKFJSDKSLFJKSJL
CourseHero 9KLDFSKJKSJDFKSDKFJSDKSLFJKSJL
 
Creating an Effective Veteran Policy in Ukraine
Creating an Effective Veteran Policy in UkraineCreating an Effective Veteran Policy in Ukraine
Creating an Effective Veteran Policy in Ukraine
 
#Bepartoftheplan on International Day For Biological Diversity 2024
#Bepartoftheplan on International Day For Biological Diversity 2024#Bepartoftheplan on International Day For Biological Diversity 2024
#Bepartoftheplan on International Day For Biological Diversity 2024
 
一比一原版(IC毕业证)帝国理工大学毕业证成绩单
一比一原版(IC毕业证)帝国理工大学毕业证成绩单一比一原版(IC毕业证)帝国理工大学毕业证成绩单
一比一原版(IC毕业证)帝国理工大学毕业证成绩单
 
OilChange: Big Oil Reality Check May 2024
OilChange: Big Oil Reality Check May 2024OilChange: Big Oil Reality Check May 2024
OilChange: Big Oil Reality Check May 2024
 
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our OrganizationUp the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
 
“Educate an African fit for the 21st Century: Building resilient education sy...
“Educate an African fit for the 21st Century: Building resilient education sy...“Educate an African fit for the 21st Century: Building resilient education sy...
“Educate an African fit for the 21st Century: Building resilient education sy...
 
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
一比一原版(MQU毕业证)麦考瑞大学毕业证成绩单
 
The MEL Toolkit Launch Webinar Presentation
The MEL Toolkit Launch Webinar PresentationThe MEL Toolkit Launch Webinar Presentation
The MEL Toolkit Launch Webinar Presentation
 
Item # 8 -- Tuxedo Columbine 3--way Stop
Item # 8 -- Tuxedo Columbine 3--way StopItem # 8 -- Tuxedo Columbine 3--way Stop
Item # 8 -- Tuxedo Columbine 3--way Stop
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
Honeycomb for The Hive Design Inspirations
Honeycomb for The Hive Design InspirationsHoneycomb for The Hive Design Inspirations
Honeycomb for The Hive Design Inspirations
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
PPT Item # 2 -- Announcements Powerpoint
PPT Item # 2 -- Announcements PowerpointPPT Item # 2 -- Announcements Powerpoint
PPT Item # 2 -- Announcements Powerpoint
 

Immokalee's Crosswalk Future - Walkable Community

  • 1. Immokalee Pedestrian Crosswalk Improvements Study
  • 2. Immokalee Pedestrian Crosswalk Improvements Study Project Objective Goal is to Improve Pedestrian/Bicycle Safety! Slide 2
  • 3. Immokalee Pedestrian Crosswalk Improvements Study Project Location Map Slide 3
  • 4. Immokalee Pedestrian Crosswalk Improvements Study Work Completed • Crash Analyses – Summarizing 2005 to 2012 • Vehicular Counts – Traffic Volume & Speed • Pedestrian/Bicycle Counts – Nine Zones at Peak Hours • Qualitative Assessment – Observations/ Recommendations Crash Analyses Vehicular Counts Pedestrian/ Bicycle Counts Qualitative Assessment Slide 4
  • 5. Immokalee Pedestrian Crosswalk Improvements Study Crash Analyses • Review & Analyses of Crash Reports – Summarize 2005 to 2012 Pedestrian/Bicycle Crashes – Graphically Show Places of Concern • Convenience Store on 7th Street • Restaurant & Theater/Game Room on 3rd Street Crash Analyses Vehicular Counts Pedestrian/ Bicycle Counts Qualitative Assessment Slide 5
  • 6. Immokalee Pedestrian Crosswalk Improvements Study 2005-2012 Day Crashes 2 KEY Driver at Fault Pedestrian/Bicycle at Fault (No Alcohol) Pedestrian/Bicycle at Fault(Alcohol-Related) Fatal Incident N Slide 6 TOTAL CRASHES = 13 CRASHES INVOLVING DUI = 4 FATAL = 0
  • 7. Immokalee Pedestrian Crosswalk Improvements Study 2005-2012 Night Crashes 2 N 2 2 2 2 Slide 7 KEY Driver at Fault Pedestrian/Bicycle at Fault (No Alcohol) Pedestrian/Bicycle at Fault(Alcohol-Related) Fatal Incident TOTAL CRASHES = 29 CRASHES INVOLVING DUI = 13 FATAL = 3
  • 8. Immokalee Pedestrian Crosswalk Improvements Study 2005-2012 Crash Analyses TYPE TOTAL DUI FATAL Day 13 4 0 Night 29 13 3 Total 42 17 3 Pedestrian 27 13 3 Bicyclist 15 4 0 Total 42 17 3 Slide 8
  • 9. Immokalee Pedestrian Crosswalk Improvements Study Vehicular Counts • 72 Hour Bi-Directional Traffic Counts – Collected Between January 9th to 11th & 16th to 18th – Traffic Volumes & Vehicle Speeds Crash Analyses Vehicular Counts Pedestrian/ Bicycle Counts Qualitative Assessment Slide 9 FDOT TRAFFIC ENGINEERING AND OPERATIONS OFFICE “It is common traffic engineering knowledge that about 85 percent of all drivers travel at reasonably safe speeds for the various roadway conditions they encounter, regardless of speed limit signs. This leaves 15 percent of drivers who must be reminded of the maximum speed limit. The Department uses the "85th percentile" method of determining appropriate and safe posted speed limits in conjunction with the maximum statute based speeds. This method is based on extensive nationally accepted studies and observations. By measuring the speed of hundreds of vehicles at various points along the roadway, traffic engineers are able to use data to determine a reasonable and safe maximum speed to post for all vehicles to travel.”
  • 10. Immokalee Pedestrian Crosswalk Improvements Study Vehicular Speed Analysis DIRECTION AVERAGE DAILY TRAFFIC VOLUME MEAN (AVERAGE) SPEED 85TH PERCENTILE SPEED Main Street Eastbound 6,350 26.05 mph 33.24 mph Westbound 5,661 26.33 mph 33.24 mph 1st Street Northbound 7,270 33.19 mph 39.53 mph Southbound 7,751 33.67 mph 39.22 mph Slide 10
  • 11. Immokalee Pedestrian Crosswalk Improvements Study Pedestrian/Bicycle Counts • Pedestrian Counts Conducted at Nine Locations – Zones Determined by Observations – Weekday & Weekend • 2 Hours AM Peak • 2 Hours PM Peak Crash Analyses Vehicular Counts Pedestrian/ Bicycle Counts Qualitative Assessment ZONE NUMBER 1 2 3 4 5 6 7 8 9 Total 161 280 487 19 1,390 343 326 90 759 Slide 11
  • 12. Immokalee Pedestrian Crosswalk Improvements Study Pedestrian/Bicycle Counts 161 280 487 19 1,390 343 326 90 759 # of Pedestrian/Bicycle Counts Slide 12
  • 13. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment • During Peak Hours During Harvest Season – January 16th & 18th • 5:00 AM – 8:00 AM • 4:00 PM – 7:00 PM • Summarize Observations & Recommendations – Improve Pedestrian & Bicyclist Safety Crash Analyses Vehicular Counts Pedestrian/ Bicycle Counts Qualitative Assessment Slide 13
  • 14. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Pedestrians Cutting Through Medians Slide 14
  • 15. Immokalee Pedestrian Crosswalk Improvements Study Recommendations RECOMMENDATION • Install Fence/Railing in Median to Direct Pedestrians to Crosswalk/Median Openings Slide 15
  • 16. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Pedestrians Using Shortest Path of Travel Slide 16 VEHICLE SPEED ESTIMATED SURVIVAL PERCENTAGE FOR PEDESTRIAN 20 mph 95% 30 mph 60% 35 mph 40% 40 mph 20% 50 mph Nearly No Survival NATIONAL HIGHWAY TRAFFIC SAFETY ADMINISTRATION STUDY DATA
  • 17. Immokalee Pedestrian Crosswalk Improvements Study Recommendations RECOMMENDATION • Designate “Pedestrian Zone” & Lower Speed to 30 mph Slide 17
  • 18. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Large Number of Signs & Flashing Beacons Distract Drivers RECOMMENDATION • Remove Excessive Signing & Beacons • Install In-Pavement Lighting at Crosswalks w/ Flashing Highlighted Signs Slide 18
  • 19. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Harvester Bus Pick Up Lot & Grocery/Café Generate High Volume of Pedestrians Crossing at/or Between 2nd Street & 3rd Street – Over 2,000 Pedestrians Crossing in Area for the AM & PM Studied Peak Hours – 1,400 Pedestrians Using Crosswalk at 3rd Street • Broken Fence Between 2nd Street & 3rd Street Slide 19
  • 20. Immokalee Pedestrian Crosswalk Improvements Study Recommendations RECOMMENDATION • Coordinate w/ Owner to Fix Fence • Install Fence/Railing in Median • Install New Crosswalk at 2nd Street Slide 20
  • 21. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Narrow 6-Foot Wide Median Opening Prohibits Two-Way Bicyclists from Crossing Simultaneously 6’ Slide 21
  • 22. Immokalee Pedestrian Crosswalk Improvements Study Recommendations RECOMMENDATION • Widen Median Opening to 10 Feet Near 5th Street & 7th Street Slide 22
  • 23. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Many Bicyclists Do Not Have Lights or Reflectors RECOMMENDATION • Coordinate w/ FDOT Community Traffic Safety Team to Distribute Free Lights through Bike Lights Program Slide 23
  • 24. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Large Number of School Students Crossing East of 7th Street During the Week Between 2:15-2:30 PM & 3:45-4:00 PM Slide 24
  • 25. Immokalee Pedestrian Crosswalk Improvements Study Recommendations RECOMMENDATION • Detailed Evaluation Needed to Determine if Crosswalk at 7th Street is Warranted Slide 25
  • 26. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Vehicles Not Yielding to Pedestrians in Crosswalks During Saturday Evenings • Vehicles Typically Yielding During the Other Times RECOMMENDATION • Increase Enforcement During Saturday Evening Hours Slide 26
  • 27. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Over 750 Pedestrians Documented Crossing Near 1st Street & Colorado Avenue During Four AM & PM Peak Hours on Weekdays & Weekends Slide 27
  • 28. Immokalee Pedestrian Crosswalk Improvements Study Recommendations RECOMMENDATION • Install Crosswalk on 1st Street North of Colorado Avenue Slide 28
  • 29. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Street Planters & Trees Limit Motorists Visibility of Pedestrians Slide 29
  • 30. Immokalee Pedestrian Crosswalk Improvements Study Recommendations RECOMMENDATION • Remove or Modify Landscaping to Low Profile Plants, at a Minimum 100 Feet Near Crosswalks Slide 30
  • 31. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Various Street & Pedestrian Lighting is Not Currently Working on Main Street & 1st Street RECOMMENDATION • Coordinate w/ Maintenance to Replace all Non-Functioning Lighting Slide 31
  • 32. Immokalee Pedestrian Crosswalk Improvements Study Qualitative Assessment OBSERVATION • Limited Sight Distance at Main Street/3rd Street Intersection RECOMMENDATION • Install High Emphasis Crosswalk Slide 32
  • 33. Immokalee Pedestrian Crosswalk Improvements Study Summary (Interim Improvements) • Main Street & 1st Street – Landscaping Grant/Contract • Install Fence/Railing/Barrier • Widen Median Openings from 6 feet to 10 feet • Modifying Landscaping in medians – Coordinate w/ Maintenance to Fix Lighting – Coordinate w/ FDOT Regarding the “Bike Lights Program” – Coordinate w/ Law Enforcement to Increase Enforcement for Motorists to Stop for Pedestrians in Crosswalks Slide 33
  • 34. Immokalee Pedestrian Crosswalk Improvements Study Summary (Long-Term Improvements) • Main Street (Coordinate w/ FDOT for Approval) – Install In-Pavement Lights w/ Automatic Detection & Signing – Add Mid-Block Crossing at 2nd Street & Possibly at 7th Street – Lower Speed Limit to 30 mph & make it a “Pedestrian Zone” – Remove Signs – Install High Emphasis Crosswalks on Side Streets • 1st Street – Install In-Pavement Lights w/ Automatic Detection & Signing – Add Mid-Block Crossing at Colorado Avenue Slide 34
  • 35. Immokalee Pedestrian Crosswalk Improvements Study Any Questions? Slide 35
  • 36. Immokalee Pedestrian Crosswalk Improvements Study
  • 37. Immokalee Pedestrian Crosswalk Improvements Study Recommendations Slide 37
  • 38. Immokalee Pedestrian Crosswalk Improvements Study Recommendations Slide 38
  • 39. Immokalee Pedestrian Crosswalk Improvements Study Recommendations Slide 39
  • 40. Immokalee Pedestrian Crosswalk Improvements Study Recommendations Slide 40
  • 41. Immokalee Pedestrian Crosswalk Improvements Study Recommendations Slide 41
  • 42. Immokalee Pedestrian Crosswalk Improvements Study Recommendations Slide 42
  • 43. Immokalee Pedestrian Crosswalk Improvements Study Recommendations Slide 43
  • 44. Immokalee Pedestrian Crosswalk Improvements Study Recommendations Slide 44
  • 45. Immokalee Pedestrian Crosswalk Improvements Study Pedestrian/Bicycle Counts DAY PEAK HOURS ZONE NUMBER 1 2 3 4 5 6 7 8 9 Weekday AM 4 33 10 10 318 101 89 18 86 Weekday PM 85 81 145 2 380 49 65 24 235 Weekend AM 9 30 71 6 244 117 92 13 98 Weekend PM 63 136 261 1 448 76 80 35 340 Total 161 280 487 19 1,390 343 326 90 759 Slide 45