SlideShare a Scribd company logo
PGBM01
Financial Management & Control
Lecture 9 Long-term decision making
By
Andy Turton.
andy.turton@sunderland.ac.uk
The University of Sunderland
School of Business & Law
Learning Objectives
 Characteristics of long-term decision making
 Processes of decision making
 Major techniques for decision making
 Advantages and disadvantages of these methods
 Other factors for decision making
2
Characteristics
 Commitment of a large amount of company resources
 Links to strategic and tactical business decisions
 Extremely expensive and difficult to reverse a long
term investment decision
 The risk and uncertainty of undertaking a long-term
investment can be high
3
Processes
 Initial investigation
 To determine if the investment proposal is a feasible
project (marketing; technical; legal and economic
feasibility studies)
 Factors to consider: resources required, technical and
commercial feasibility, risks of the project, and how the
project matches the firm’s strategic objectives
 Detailed evaluation
 To forecast the expected cash flows from the project, by
using NPV, IRR or other relevant techniques
 Simulation and sensitivity analysis may be used to assess
the degree of risk involved in the project
 Sources of finance and non-financial factors need to be
detailed
4
Processes
 Authorisation
 Ranking of proposals in order of priority
 The proposal meets the profitability criteria and is
compatible with the overall strategy of the business
 The decision should be made by senior management, or
the board of directors if necessary
 Project implementation
 The appointment of a project manager or assignment of
responsibility
 The required resources are allocated and the specified
targets are set to be achieved
5
Processes
 Monitoring the project
 Feedforward principles employed to reassess the
expected costs and benefits
 The corrective action taken to rectify any adverse
variance
 Post-completion audit
 To monitor and report on the progress and to identify
aspects which could be improved for future project
planning
6
Methods of Investment Appraisal
 Payback period (PP)
 The length of time: cash proceeds recover the initial capital
expenditure
 Accounting Rate of Return (ARR)
 A return measurement by using average annual profits
 Net Present Value (NPV)
 The present value of the net cash inflows less the initial
investment
 Internal Rate of Return (IRR)
 A return measurement takes into account the time value of
money
7
Example
There are two optional projects for your company to
choose. However, you can only choose one of them. The
data for the initial investments are in the following table.
You are required to calculate:
 PP
 ARR
 NPV
 IRR, and
 Your recommendation
8
Data for the Projects
Project A Project B
Initial investment £100,000 £100,000
Net cash inflows
Year 1 £45,000 £30,000
Year 2 £40,000 £30,000
Year 3 £25,000 £44,000
Year 4 £30,000 £46,000
9
• The depreciation is £20,000 per year.
• The residual value for both projects is the same, £20,000.
Payback Period
 The Payback period = the point in time at which
cash flows turn from negative to positive
Project A Cash flows Cumulative cash flow
Year 0 -100,000 -100,000
Year 1 45,000 -55,000
Year 2 40,000 -15,000
Year 3 25,000 +10,000
Year 4 50,000 +60,000
10
Payback Period
Project B Cash flows Cumulative cash flow
Year 0 -100,000 -100,000
Year 1 30,000 -70,000
Year 2 30,000 -40,000
Year 3 44,000 +4,000
Year 4 66,000 +70,000
11
Payback Period
 Payback period (A) = change in cash flow required to
reach zero/total cash flow in year
=15,000/25,000 = 0.60 + 2 years = 2.6 years
 Payback period (B) = 40,000/44,000 = 0.91 + 2 years =
2.91 years
 Which project is the better one based on payback period?
12
ARR
Step 1: calculate annual profit
 Annual profit = net cash inflow - depreciation
Step 2: calculate average profit
 Average profit = total profits / number of years
Step 3: calculate average capital invested
 Average capital invested = (initial cost + residual value) /2
Step 4: calculate ARR
 ARR = (average profit/average capital invested)x 100%
13
ARR
 Project A
 Average profit = (25,000 + 20,000 + 5,000 + 30,000)/4 =
80,000/4 = 20,000
 Average capital invested = (100,000+20,000) /2 = 60,000
 ARR = (20,000/60,000)x 100 = 33%
 Project B
 Average profit = (10,000 + 10,000 + 24,000 + 46,000)/4 =
22,500
 Average capital invested = (100,000 + 20,000)/2 = 60,000
 ARR = (22,500/60,000) x 100 = 38%
 Which project is the better one?
14
The Time Value of Money
 What is the difference between £1 now and £1 in a year’s
time?
 Factors change the value of money
 Interest lost (an opportunity cost)
 Inflation (loss of purchasing power)
 Other risks to materialise the money (the level of demand
for a given project)
15
The Time Value of Money
 For example: the annual interest rate is 10%, I lend you £1
now and will get it back after 1 year, how much worth of
that £1 in a year’s time?
? x (1+10%) = £1
? = £0.91
The formula is 1
(1 + r)n
 10% is called “cost of capital”; “0.91” is called the
“discount factor”
16
NPV
 Assume that your company’s cost of capital is 10%
 Discount factors at 10% are:
 Year 1 0.909
 Year 2 0.826
 Year 3 0.751
 Year 4 0.683
 Present value table distributed (page 559 in core textbook)
17
NPV
Project A Cash flow Disc. Factor (10%) Dis.d cash flow
Year 0 -100,000 1.00 (100,000)
Year 1 45,000 0.909 40,905
Year 2 40,000 0.826 33,040
Year 3 25,000 0.751 18,775
Year 4 50,000 0.683 34,150
NPV £26,870
18
NPV
Project B Cash flow Dis. Factor (10%) Dis.d cash flow
Year 0 -100,000 1.00 (100,000)
Year 1 30,000 0.909 27,270
Year 2 30,000 0.826 24,780
Year 3 44,000 0.751 33,044
Year 4 66,000 0.683 45,078
NPV £30,172
19
• Which project is the better one based on NPV?
IRR
 IRR: the discount rate that yields net present value of zero
 Project A
 NPV = £26,870 when the discount rate is 10%
 NPV = ? When the discount rate is 25%
Project A Cash flow Dis. factor (25%) Dis.d cash flow
Year 0 -100,000 1.00 (100,000)
Year 1 45,000 0.800 36,000
Year 2 40,000 0.640 25,600
Year 3 25,000 0.512 12,800
Year 4 50,000 0.410 20,500
NPV -5,100
20
IRR
 Project B
 NPV = £30,172 when the discount rate is 10%
 NPV = ? When the discount rate is 25%
Project B Cash flow Disc. factor (25%) Dis.d cash flow
Year 0 -100,000 1.00 (100,000)
Year 1 30,000 0.800 24,000
Year 2 30,000 0.640 19,200
Year 3 44,000 0.512 22,258
Year 4 66,000 0.410 27,060
NPV -7,482
21
IRR
Project A
Total change in NPV = 26,870 – (-5,100)
= 31,970
Total change in discount rate = 25% -
10% = 15%
IRR = 10% + {(26,870/31,970) x15%} =
23%
22
IRR
Project B
Total change in NPV = 30,172 – (-7,482)
= 37,654
Total change in discount rate = 25% -
10% = 15%
IRR = 10% + {(30,172/37,654) x15%} =
22%
23
Project Selection
Methods Single project Choice of projects A or B?
Payback Less than the target
period
Shortest payback
period
A
ARR Above the target
rate
With the highest
ARR
B
NPV A positive NPV With the highest
NPV
B
IRR Higher than the
target rate (cost of
capital)
With the highest IRR A
24
Advantages & Disadvantages
Method Advantages Disadvantages
Payback • Simple and easy to understand and
use
• Objective – using cash flows
• Liquidity – commercially realistic
• Cautious & risk averse – ignores
later cash flows
• Ignores the time value
of money
• Ignores cash flows
after the payback
period
ARR • Simple and easy to understand and
use
• Aids internal and external
comparisons
• Looks at the whole life of the project
•A useful tool to measure divisional
managerial performance
• Subjective – profit,
not cash flows
• Ignores the time value
of money
• Difficulty in use when
with same ARR and
various project sizes
25
Advantages & Disadvantages
Method Advantages Disadvantages
NPV • Takes account of the time value
of money
• Concerns of shareholder wealth
• Takes account of risk
• Looks at the whole life of the
project
• Difficult to be understood
by managers
• Adverse effects on
accounting profits in the
short run
• How to choose discount
rate?
IRR • Takes account of the time value
of money
• Easy to be understood by
managers
• Difficult to use in choosing
projects of varying sizes
• Difficult to choose when
have the same IRR
26
Conclusion
 Why NPV is more commonly used than ARR and PP?
 What are disadvantages of NPV and IRR?
 How to overcome disadvantages of NPV and IRR?
 What are other factors needed to consider for a long-
term investment?
27
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   long term decision making

More Related Content

What's hot

Risk Mitigation Strategy PowerPoint Presentation Slides
Risk Mitigation Strategy PowerPoint Presentation SlidesRisk Mitigation Strategy PowerPoint Presentation Slides
Risk Mitigation Strategy PowerPoint Presentation Slides
SlideTeam
 
Basic Risk Identification Techniques
Basic Risk Identification TechniquesBasic Risk Identification Techniques
Basic Risk Identification Techniques
Ricardo Viana Vargas
 
502331 capital budgeting and estimating cash flows
502331 capital budgeting and estimating cash flows502331 capital budgeting and estimating cash flows
502331 capital budgeting and estimating cash flows
Zahoor Khan
 
Project finance
Project financeProject finance
Project finance
Amit Gaurav
 
Investment decisions / capital Budgeting
Investment decisions / capital BudgetingInvestment decisions / capital Budgeting
Investment decisions / capital Budgeting
Raghav Jha
 
Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)
Mohamed Saeed
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and Appraisal
Jude Iheanacho
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
Ahmad Tariq Bhatti
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
SAJJAD KHUDHUR ABBAS
 
Why risk management services are vital to the oil and gas industry
Why risk management services are vital to the oil and gas industryWhy risk management services are vital to the oil and gas industry
Why risk management services are vital to the oil and gas industry
Lloyd's Register Energy
 
Weighted Average Cost of Capital
Weighted Average Cost of CapitalWeighted Average Cost of Capital
Weighted Average Cost of Capital
Rod Medallon
 
Strategic Risk Management in the Face of Uncertainty and Unexpected Risks
Strategic Risk Management in the Face of Uncertainty and Unexpected RisksStrategic Risk Management in the Face of Uncertainty and Unexpected Risks
Strategic Risk Management in the Face of Uncertainty and Unexpected Risks
International Federation of Accountants
 
Detailed Investment Analysis PowerPoint Presentation Slides
Detailed Investment Analysis PowerPoint Presentation SlidesDetailed Investment Analysis PowerPoint Presentation Slides
Detailed Investment Analysis PowerPoint Presentation Slides
SlideTeam
 
Real Options, Investment Analysis and Process
Real Options, Investment Analysis and Process Real Options, Investment Analysis and Process
Real Options, Investment Analysis and Process
PANKAJ PANDEY
 
Risk Assessment PowerPoint Presentation Slides
Risk Assessment PowerPoint Presentation Slides Risk Assessment PowerPoint Presentation Slides
Risk Assessment PowerPoint Presentation Slides
SlideTeam
 
Relative valuation
Relative valuationRelative valuation
Relative valuationariedler
 
CAPM Fama French
CAPM Fama FrenchCAPM Fama French
CAPM Fama FrenchAhmedSaba
 
Return On Investment Powerpoint Presentation Slides
Return On Investment Powerpoint Presentation SlidesReturn On Investment Powerpoint Presentation Slides
Return On Investment Powerpoint Presentation Slides
SlideTeam
 
Time Value of Money
Time Value of MoneyTime Value of Money
Time Value of Money
Mikee Bylss
 
Operational Risk Management Overview PowerPoint presentation Slides
Operational Risk Management Overview PowerPoint presentation SlidesOperational Risk Management Overview PowerPoint presentation Slides
Operational Risk Management Overview PowerPoint presentation Slides
SlideTeam
 

What's hot (20)

Risk Mitigation Strategy PowerPoint Presentation Slides
Risk Mitigation Strategy PowerPoint Presentation SlidesRisk Mitigation Strategy PowerPoint Presentation Slides
Risk Mitigation Strategy PowerPoint Presentation Slides
 
Basic Risk Identification Techniques
Basic Risk Identification TechniquesBasic Risk Identification Techniques
Basic Risk Identification Techniques
 
502331 capital budgeting and estimating cash flows
502331 capital budgeting and estimating cash flows502331 capital budgeting and estimating cash flows
502331 capital budgeting and estimating cash flows
 
Project finance
Project financeProject finance
Project finance
 
Investment decisions / capital Budgeting
Investment decisions / capital BudgetingInvestment decisions / capital Budgeting
Investment decisions / capital Budgeting
 
Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and Appraisal
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Why risk management services are vital to the oil and gas industry
Why risk management services are vital to the oil and gas industryWhy risk management services are vital to the oil and gas industry
Why risk management services are vital to the oil and gas industry
 
Weighted Average Cost of Capital
Weighted Average Cost of CapitalWeighted Average Cost of Capital
Weighted Average Cost of Capital
 
Strategic Risk Management in the Face of Uncertainty and Unexpected Risks
Strategic Risk Management in the Face of Uncertainty and Unexpected RisksStrategic Risk Management in the Face of Uncertainty and Unexpected Risks
Strategic Risk Management in the Face of Uncertainty and Unexpected Risks
 
Detailed Investment Analysis PowerPoint Presentation Slides
Detailed Investment Analysis PowerPoint Presentation SlidesDetailed Investment Analysis PowerPoint Presentation Slides
Detailed Investment Analysis PowerPoint Presentation Slides
 
Real Options, Investment Analysis and Process
Real Options, Investment Analysis and Process Real Options, Investment Analysis and Process
Real Options, Investment Analysis and Process
 
Risk Assessment PowerPoint Presentation Slides
Risk Assessment PowerPoint Presentation Slides Risk Assessment PowerPoint Presentation Slides
Risk Assessment PowerPoint Presentation Slides
 
Relative valuation
Relative valuationRelative valuation
Relative valuation
 
CAPM Fama French
CAPM Fama FrenchCAPM Fama French
CAPM Fama French
 
Return On Investment Powerpoint Presentation Slides
Return On Investment Powerpoint Presentation SlidesReturn On Investment Powerpoint Presentation Slides
Return On Investment Powerpoint Presentation Slides
 
Time Value of Money
Time Value of MoneyTime Value of Money
Time Value of Money
 
Operational Risk Management Overview PowerPoint presentation Slides
Operational Risk Management Overview PowerPoint presentation SlidesOperational Risk Management Overview PowerPoint presentation Slides
Operational Risk Management Overview PowerPoint presentation Slides
 

Viewers also liked

Capital budgeting 2
Capital budgeting 2Capital budgeting 2
Capital budgeting 2
vishal_jaswal
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8 sho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8  sho...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8  sho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8 sho...
Aquamarine Emerald
 
Capital budgeting techniques
Capital budgeting techniquesCapital budgeting techniques
Capital budgeting techniquesVJTI Production
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Akhil Sabu
 
Financial management at private universities in switzerland
Financial management at private universities in switzerlandFinancial management at private universities in switzerland
Financial management at private universities in switzerland
ainsley93
 
Accounting and financial management in switzerland university
Accounting and financial management in switzerland universityAccounting and financial management in switzerland university
Accounting and financial management in switzerland university
Monaliemily
 
Financial management for the ace school
Financial management for the ace schoolFinancial management for the ace school
Financial management for the ace school
S.S.Afemikhe Consulting
 
Financial management
Financial managementFinancial management
Financial management
Tharushika Ruwangi
 
Forex Market - an Perspective
Forex Market - an PerspectiveForex Market - an Perspective
Forex Market - an Perspective
Abhijeet Deshmukh
 
Financing decisions
Financing decisionsFinancing decisions
Financing decisionsfinanzas_uca
 
Equity market an overview
Equity market an overviewEquity market an overview
Equity market an overview
Amit Bhanj
 
Financial Decisions Presentation
Financial Decisions PresentationFinancial Decisions Presentation
Financial Decisions Presentationmbachnak
 
Financial Decision Making for Entrepreneurs
Financial Decision Making for EntrepreneursFinancial Decision Making for Entrepreneurs
Financial Decision Making for Entrepreneurs
Achuthan Rajagopal
 
Managerial decision making - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - ...
Managerial decision making -  ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - ...Managerial decision making -  ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - ...
Managerial decision making - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - ...
Barani Dharan
 
Steps in decision maKing - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - DR....
Steps in decision maKing - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - DR....Steps in decision maKing - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - DR....
Steps in decision maKing - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - DR....
Barani Dharan
 
FINANCING DECISIONS
FINANCING DECISIONSFINANCING DECISIONS
FINANCING DECISIONS
123vedapradha
 
Capital budgeting ppt
Capital budgeting pptCapital budgeting ppt
Capital budgeting ppt
Ruchi Jain
 
Behavioral economics and financial decision making
Behavioral economics and financial decision making Behavioral economics and financial decision making
Behavioral economics and financial decision making
Yumonomics
 
Currency derivatives
Currency derivativesCurrency derivatives
Currency derivatives
Huda Khan Durrani
 

Viewers also liked (20)

Capital budgeting 2
Capital budgeting 2Capital budgeting 2
Capital budgeting 2
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8 sho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8  sho...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8  sho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8 sho...
 
Capital budgeting techniques
Capital budgeting techniquesCapital budgeting techniques
Capital budgeting techniques
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Financial management at private universities in switzerland
Financial management at private universities in switzerlandFinancial management at private universities in switzerland
Financial management at private universities in switzerland
 
Accounting and financial management in switzerland university
Accounting and financial management in switzerland universityAccounting and financial management in switzerland university
Accounting and financial management in switzerland university
 
Financial management for the ace school
Financial management for the ace schoolFinancial management for the ace school
Financial management for the ace school
 
Financial management
Financial managementFinancial management
Financial management
 
Forex Market - an Perspective
Forex Market - an PerspectiveForex Market - an Perspective
Forex Market - an Perspective
 
Financing decisions
Financing decisionsFinancing decisions
Financing decisions
 
Equity market an overview
Equity market an overviewEquity market an overview
Equity market an overview
 
Financial Decisions Presentation
Financial Decisions PresentationFinancial Decisions Presentation
Financial Decisions Presentation
 
Financial Decision Making for Entrepreneurs
Financial Decision Making for EntrepreneursFinancial Decision Making for Entrepreneurs
Financial Decision Making for Entrepreneurs
 
Managerial decision making - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - ...
Managerial decision making -  ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - ...Managerial decision making -  ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - ...
Managerial decision making - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - ...
 
Steps in decision maKing - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - DR....
Steps in decision maKing - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - DR....Steps in decision maKing - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - DR....
Steps in decision maKing - ENGINEERING ECONOMICS & FINANCIAL ACCOUNTING - DR....
 
FINANCING DECISIONS
FINANCING DECISIONSFINANCING DECISIONS
FINANCING DECISIONS
 
Capital budgeting ppt
Capital budgeting pptCapital budgeting ppt
Capital budgeting ppt
 
Behavioral economics and financial decision making
Behavioral economics and financial decision making Behavioral economics and financial decision making
Behavioral economics and financial decision making
 
Currency derivatives
Currency derivativesCurrency derivatives
Currency derivatives
 

Similar to PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 long term decision making

781314.ppt
781314.ppt781314.ppt
781314.ppt
pisal3
 
Ch 4 Investment Appraisal.hjhuhfgjhegppt
Ch 4 Investment Appraisal.hjhuhfgjhegpptCh 4 Investment Appraisal.hjhuhfgjhegppt
Ch 4 Investment Appraisal.hjhuhfgjhegppt
fisahabirhane16
 
Priyankabba
PriyankabbaPriyankabba
Priyankabba
PriyankaSachdeva35
 
NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.ppt
SanthoshK757191
 
3 capital budgeting
3 capital budgeting3 capital budgeting
3 capital budgeting
Dr.R. SELVAM
 
Business Finance Chapter 8
Business Finance Chapter 8Business Finance Chapter 8
Business Finance Chapter 8
Tinku Kumar
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
premarhea
 
Faculty of Law and Management FUNDAMENTALS OF FINANCE .docx
Faculty of Law and Management FUNDAMENTALS OF FINANCE .docxFaculty of Law and Management FUNDAMENTALS OF FINANCE .docx
Faculty of Law and Management FUNDAMENTALS OF FINANCE .docx
mydrynan
 
Week 1 investment appraisal
Week 1  investment appraisalWeek 1  investment appraisal
Week 1 investment appraisal
Tishta Bachoo
 
LECTURE 4 (2).pptx
LECTURE 4 (2).pptxLECTURE 4 (2).pptx
LECTURE 4 (2).pptx
haiqamalik
 
Cf%20 Capital%20 Budgeting%206
Cf%20 Capital%20 Budgeting%206Cf%20 Capital%20 Budgeting%206
Cf%20 Capital%20 Budgeting%206
rajeevgupta
 
Cf Capital Budgeting 6
Cf Capital Budgeting 6Cf Capital Budgeting 6
Cf Capital Budgeting 6
rajeevgupta
 
Cf Capital Budgeting 6
Cf Capital Budgeting 6Cf Capital Budgeting 6
Cf Capital Budgeting 6
rajeevgupta
 
Capital budgeting decision criteria and risk analysis
Capital budgeting decision criteria and risk analysisCapital budgeting decision criteria and risk analysis
Capital budgeting decision criteria and risk analysis
Manuel Palcon II
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgetingyashpal01
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
MBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptxMBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptx
kwame Oduro Amoako (PhD)
 

Similar to PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 long term decision making (20)

781314.ppt
781314.ppt781314.ppt
781314.ppt
 
Ch 4 Investment Appraisal.hjhuhfgjhegppt
Ch 4 Investment Appraisal.hjhuhfgjhegpptCh 4 Investment Appraisal.hjhuhfgjhegppt
Ch 4 Investment Appraisal.hjhuhfgjhegppt
 
Priyankabba
PriyankabbaPriyankabba
Priyankabba
 
NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.ppt
 
3 capital budgeting
3 capital budgeting3 capital budgeting
3 capital budgeting
 
Business Finance Chapter 8
Business Finance Chapter 8Business Finance Chapter 8
Business Finance Chapter 8
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Faculty of Law and Management FUNDAMENTALS OF FINANCE .docx
Faculty of Law and Management FUNDAMENTALS OF FINANCE .docxFaculty of Law and Management FUNDAMENTALS OF FINANCE .docx
Faculty of Law and Management FUNDAMENTALS OF FINANCE .docx
 
Week 1 investment appraisal
Week 1  investment appraisalWeek 1  investment appraisal
Week 1 investment appraisal
 
LECTURE 4 (2).pptx
LECTURE 4 (2).pptxLECTURE 4 (2).pptx
LECTURE 4 (2).pptx
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Cf%20 Capital%20 Budgeting%206
Cf%20 Capital%20 Budgeting%206Cf%20 Capital%20 Budgeting%206
Cf%20 Capital%20 Budgeting%206
 
Cf Capital Budgeting 6
Cf Capital Budgeting 6Cf Capital Budgeting 6
Cf Capital Budgeting 6
 
Cf Capital Budgeting 6
Cf Capital Budgeting 6Cf Capital Budgeting 6
Cf Capital Budgeting 6
 
Capital budgeting decision criteria and risk analysis
Capital budgeting decision criteria and risk analysisCapital budgeting decision criteria and risk analysis
Capital budgeting decision criteria and risk analysis
 
Financial feasibility of a new business
Financial feasibility of a new businessFinancial feasibility of a new business
Financial feasibility of a new business
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
MBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptxMBA fin mgt Lecture 5 inv appraisal.pptx
MBA fin mgt Lecture 5 inv appraisal.pptx
 

More from Aquamarine Emerald

9 commercial law 2005
9  commercial law 20059  commercial law 2005
9 commercial law 2005
Aquamarine Emerald
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
Aquamarine Emerald
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
Aquamarine Emerald
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
Aquamarine Emerald
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
Aquamarine Emerald
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 7 bu...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 7   bu...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 7   bu...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 7 bu...
Aquamarine Emerald
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
Aquamarine Emerald
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Workshop 8 que...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Workshop 8 que...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Workshop 8 que...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Workshop 8 que...
Aquamarine Emerald
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
Aquamarine Emerald
 
Pgbm03 MBA OPERATION MANAGEMENT session 01 introduction to operations
Pgbm03 MBA OPERATION MANAGEMENT session 01 introduction to operationsPgbm03 MBA OPERATION MANAGEMENT session 01 introduction to operations
Pgbm03 MBA OPERATION MANAGEMENT session 01 introduction to operations
Aquamarine Emerald
 
Pgbm03 MBA OPERATION MANAGEMENT session 02 service operations management
Pgbm03 MBA OPERATION MANAGEMENT session 02 service operations managementPgbm03 MBA OPERATION MANAGEMENT session 02 service operations management
Pgbm03 MBA OPERATION MANAGEMENT session 02 service operations management
Aquamarine Emerald
 
Pgbm03 MBA OPERATION MANAGEMENT session 03 operations performance and strategy
Pgbm03 MBA OPERATION MANAGEMENT session 03 operations performance and strategyPgbm03 MBA OPERATION MANAGEMENT session 03 operations performance and strategy
Pgbm03 MBA OPERATION MANAGEMENT session 03 operations performance and strategy
Aquamarine Emerald
 
Pgbm03 MBA OPERATION MANAGEMENT session 04 process design
Pgbm03 MBA OPERATION MANAGEMENT session 04 process designPgbm03 MBA OPERATION MANAGEMENT session 04 process design
Pgbm03 MBA OPERATION MANAGEMENT session 04 process design
Aquamarine Emerald
 
Pgbm03 MBA OPERATION MANAGEMENT session 07 inventory and material management
Pgbm03 MBA OPERATION MANAGEMENT session 07 inventory and material managementPgbm03 MBA OPERATION MANAGEMENT session 07 inventory and material management
Pgbm03 MBA OPERATION MANAGEMENT session 07 inventory and material management
Aquamarine Emerald
 
Pgbm03 MBA OPERATION MANAGEMENT session 06 planning and managing capacity
Pgbm03 MBA OPERATION MANAGEMENT session 06 planning and managing capacityPgbm03 MBA OPERATION MANAGEMENT session 06 planning and managing capacity
Pgbm03 MBA OPERATION MANAGEMENT session 06 planning and managing capacity
Aquamarine Emerald
 
Pgbm03 MBA OPERATION MANAGEMENT session 08 supply chain management
Pgbm03 MBA OPERATION MANAGEMENT session 08 supply chain managementPgbm03 MBA OPERATION MANAGEMENT session 08 supply chain management
Pgbm03 MBA OPERATION MANAGEMENT session 08 supply chain management
Aquamarine Emerald
 
Pgbm03 MBA OPERATION MANAGEMENT session 05 design of product and service
Pgbm03 MBA OPERATION MANAGEMENT session 05 design of product and servicePgbm03 MBA OPERATION MANAGEMENT session 05 design of product and service
Pgbm03 MBA OPERATION MANAGEMENT session 05 design of product and service
Aquamarine Emerald
 
Ratio analysis question workshop 4 lorry plc updated
Ratio analysis question workshop 4 lorry plc updatedRatio analysis question workshop 4 lorry plc updated
Ratio analysis question workshop 4 lorry plc updated
Aquamarine Emerald
 

More from Aquamarine Emerald (18)

9 commercial law 2005
9  commercial law 20059  commercial law 2005
9 commercial law 2005
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm 01 worksho...
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 7 bu...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 7   bu...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 7   bu...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 7 bu...
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Pgbm01 workshop...
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Workshop 8 que...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Workshop 8 que...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Workshop 8 que...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Workshop 8 que...
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Pgbm 01 worksh...
 
Pgbm03 MBA OPERATION MANAGEMENT session 01 introduction to operations
Pgbm03 MBA OPERATION MANAGEMENT session 01 introduction to operationsPgbm03 MBA OPERATION MANAGEMENT session 01 introduction to operations
Pgbm03 MBA OPERATION MANAGEMENT session 01 introduction to operations
 
Pgbm03 MBA OPERATION MANAGEMENT session 02 service operations management
Pgbm03 MBA OPERATION MANAGEMENT session 02 service operations managementPgbm03 MBA OPERATION MANAGEMENT session 02 service operations management
Pgbm03 MBA OPERATION MANAGEMENT session 02 service operations management
 
Pgbm03 MBA OPERATION MANAGEMENT session 03 operations performance and strategy
Pgbm03 MBA OPERATION MANAGEMENT session 03 operations performance and strategyPgbm03 MBA OPERATION MANAGEMENT session 03 operations performance and strategy
Pgbm03 MBA OPERATION MANAGEMENT session 03 operations performance and strategy
 
Pgbm03 MBA OPERATION MANAGEMENT session 04 process design
Pgbm03 MBA OPERATION MANAGEMENT session 04 process designPgbm03 MBA OPERATION MANAGEMENT session 04 process design
Pgbm03 MBA OPERATION MANAGEMENT session 04 process design
 
Pgbm03 MBA OPERATION MANAGEMENT session 07 inventory and material management
Pgbm03 MBA OPERATION MANAGEMENT session 07 inventory and material managementPgbm03 MBA OPERATION MANAGEMENT session 07 inventory and material management
Pgbm03 MBA OPERATION MANAGEMENT session 07 inventory and material management
 
Pgbm03 MBA OPERATION MANAGEMENT session 06 planning and managing capacity
Pgbm03 MBA OPERATION MANAGEMENT session 06 planning and managing capacityPgbm03 MBA OPERATION MANAGEMENT session 06 planning and managing capacity
Pgbm03 MBA OPERATION MANAGEMENT session 06 planning and managing capacity
 
Pgbm03 MBA OPERATION MANAGEMENT session 08 supply chain management
Pgbm03 MBA OPERATION MANAGEMENT session 08 supply chain managementPgbm03 MBA OPERATION MANAGEMENT session 08 supply chain management
Pgbm03 MBA OPERATION MANAGEMENT session 08 supply chain management
 
Pgbm03 MBA OPERATION MANAGEMENT session 05 design of product and service
Pgbm03 MBA OPERATION MANAGEMENT session 05 design of product and servicePgbm03 MBA OPERATION MANAGEMENT session 05 design of product and service
Pgbm03 MBA OPERATION MANAGEMENT session 05 design of product and service
 
Ratio analysis question workshop 4 lorry plc updated
Ratio analysis question workshop 4 lorry plc updatedRatio analysis question workshop 4 lorry plc updated
Ratio analysis question workshop 4 lorry plc updated
 

Recently uploaded

Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 

Recently uploaded (20)

Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 

PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 long term decision making

  • 1. PGBM01 Financial Management & Control Lecture 9 Long-term decision making By Andy Turton. andy.turton@sunderland.ac.uk The University of Sunderland School of Business & Law
  • 2. Learning Objectives  Characteristics of long-term decision making  Processes of decision making  Major techniques for decision making  Advantages and disadvantages of these methods  Other factors for decision making 2
  • 3. Characteristics  Commitment of a large amount of company resources  Links to strategic and tactical business decisions  Extremely expensive and difficult to reverse a long term investment decision  The risk and uncertainty of undertaking a long-term investment can be high 3
  • 4. Processes  Initial investigation  To determine if the investment proposal is a feasible project (marketing; technical; legal and economic feasibility studies)  Factors to consider: resources required, technical and commercial feasibility, risks of the project, and how the project matches the firm’s strategic objectives  Detailed evaluation  To forecast the expected cash flows from the project, by using NPV, IRR or other relevant techniques  Simulation and sensitivity analysis may be used to assess the degree of risk involved in the project  Sources of finance and non-financial factors need to be detailed 4
  • 5. Processes  Authorisation  Ranking of proposals in order of priority  The proposal meets the profitability criteria and is compatible with the overall strategy of the business  The decision should be made by senior management, or the board of directors if necessary  Project implementation  The appointment of a project manager or assignment of responsibility  The required resources are allocated and the specified targets are set to be achieved 5
  • 6. Processes  Monitoring the project  Feedforward principles employed to reassess the expected costs and benefits  The corrective action taken to rectify any adverse variance  Post-completion audit  To monitor and report on the progress and to identify aspects which could be improved for future project planning 6
  • 7. Methods of Investment Appraisal  Payback period (PP)  The length of time: cash proceeds recover the initial capital expenditure  Accounting Rate of Return (ARR)  A return measurement by using average annual profits  Net Present Value (NPV)  The present value of the net cash inflows less the initial investment  Internal Rate of Return (IRR)  A return measurement takes into account the time value of money 7
  • 8. Example There are two optional projects for your company to choose. However, you can only choose one of them. The data for the initial investments are in the following table. You are required to calculate:  PP  ARR  NPV  IRR, and  Your recommendation 8
  • 9. Data for the Projects Project A Project B Initial investment £100,000 £100,000 Net cash inflows Year 1 £45,000 £30,000 Year 2 £40,000 £30,000 Year 3 £25,000 £44,000 Year 4 £30,000 £46,000 9 • The depreciation is £20,000 per year. • The residual value for both projects is the same, £20,000.
  • 10. Payback Period  The Payback period = the point in time at which cash flows turn from negative to positive Project A Cash flows Cumulative cash flow Year 0 -100,000 -100,000 Year 1 45,000 -55,000 Year 2 40,000 -15,000 Year 3 25,000 +10,000 Year 4 50,000 +60,000 10
  • 11. Payback Period Project B Cash flows Cumulative cash flow Year 0 -100,000 -100,000 Year 1 30,000 -70,000 Year 2 30,000 -40,000 Year 3 44,000 +4,000 Year 4 66,000 +70,000 11
  • 12. Payback Period  Payback period (A) = change in cash flow required to reach zero/total cash flow in year =15,000/25,000 = 0.60 + 2 years = 2.6 years  Payback period (B) = 40,000/44,000 = 0.91 + 2 years = 2.91 years  Which project is the better one based on payback period? 12
  • 13. ARR Step 1: calculate annual profit  Annual profit = net cash inflow - depreciation Step 2: calculate average profit  Average profit = total profits / number of years Step 3: calculate average capital invested  Average capital invested = (initial cost + residual value) /2 Step 4: calculate ARR  ARR = (average profit/average capital invested)x 100% 13
  • 14. ARR  Project A  Average profit = (25,000 + 20,000 + 5,000 + 30,000)/4 = 80,000/4 = 20,000  Average capital invested = (100,000+20,000) /2 = 60,000  ARR = (20,000/60,000)x 100 = 33%  Project B  Average profit = (10,000 + 10,000 + 24,000 + 46,000)/4 = 22,500  Average capital invested = (100,000 + 20,000)/2 = 60,000  ARR = (22,500/60,000) x 100 = 38%  Which project is the better one? 14
  • 15. The Time Value of Money  What is the difference between £1 now and £1 in a year’s time?  Factors change the value of money  Interest lost (an opportunity cost)  Inflation (loss of purchasing power)  Other risks to materialise the money (the level of demand for a given project) 15
  • 16. The Time Value of Money  For example: the annual interest rate is 10%, I lend you £1 now and will get it back after 1 year, how much worth of that £1 in a year’s time? ? x (1+10%) = £1 ? = £0.91 The formula is 1 (1 + r)n  10% is called “cost of capital”; “0.91” is called the “discount factor” 16
  • 17. NPV  Assume that your company’s cost of capital is 10%  Discount factors at 10% are:  Year 1 0.909  Year 2 0.826  Year 3 0.751  Year 4 0.683  Present value table distributed (page 559 in core textbook) 17
  • 18. NPV Project A Cash flow Disc. Factor (10%) Dis.d cash flow Year 0 -100,000 1.00 (100,000) Year 1 45,000 0.909 40,905 Year 2 40,000 0.826 33,040 Year 3 25,000 0.751 18,775 Year 4 50,000 0.683 34,150 NPV £26,870 18
  • 19. NPV Project B Cash flow Dis. Factor (10%) Dis.d cash flow Year 0 -100,000 1.00 (100,000) Year 1 30,000 0.909 27,270 Year 2 30,000 0.826 24,780 Year 3 44,000 0.751 33,044 Year 4 66,000 0.683 45,078 NPV £30,172 19 • Which project is the better one based on NPV?
  • 20. IRR  IRR: the discount rate that yields net present value of zero  Project A  NPV = £26,870 when the discount rate is 10%  NPV = ? When the discount rate is 25% Project A Cash flow Dis. factor (25%) Dis.d cash flow Year 0 -100,000 1.00 (100,000) Year 1 45,000 0.800 36,000 Year 2 40,000 0.640 25,600 Year 3 25,000 0.512 12,800 Year 4 50,000 0.410 20,500 NPV -5,100 20
  • 21. IRR  Project B  NPV = £30,172 when the discount rate is 10%  NPV = ? When the discount rate is 25% Project B Cash flow Disc. factor (25%) Dis.d cash flow Year 0 -100,000 1.00 (100,000) Year 1 30,000 0.800 24,000 Year 2 30,000 0.640 19,200 Year 3 44,000 0.512 22,258 Year 4 66,000 0.410 27,060 NPV -7,482 21
  • 22. IRR Project A Total change in NPV = 26,870 – (-5,100) = 31,970 Total change in discount rate = 25% - 10% = 15% IRR = 10% + {(26,870/31,970) x15%} = 23% 22
  • 23. IRR Project B Total change in NPV = 30,172 – (-7,482) = 37,654 Total change in discount rate = 25% - 10% = 15% IRR = 10% + {(30,172/37,654) x15%} = 22% 23
  • 24. Project Selection Methods Single project Choice of projects A or B? Payback Less than the target period Shortest payback period A ARR Above the target rate With the highest ARR B NPV A positive NPV With the highest NPV B IRR Higher than the target rate (cost of capital) With the highest IRR A 24
  • 25. Advantages & Disadvantages Method Advantages Disadvantages Payback • Simple and easy to understand and use • Objective – using cash flows • Liquidity – commercially realistic • Cautious & risk averse – ignores later cash flows • Ignores the time value of money • Ignores cash flows after the payback period ARR • Simple and easy to understand and use • Aids internal and external comparisons • Looks at the whole life of the project •A useful tool to measure divisional managerial performance • Subjective – profit, not cash flows • Ignores the time value of money • Difficulty in use when with same ARR and various project sizes 25
  • 26. Advantages & Disadvantages Method Advantages Disadvantages NPV • Takes account of the time value of money • Concerns of shareholder wealth • Takes account of risk • Looks at the whole life of the project • Difficult to be understood by managers • Adverse effects on accounting profits in the short run • How to choose discount rate? IRR • Takes account of the time value of money • Easy to be understood by managers • Difficult to use in choosing projects of varying sizes • Difficult to choose when have the same IRR 26
  • 27. Conclusion  Why NPV is more commonly used than ARR and PP?  What are disadvantages of NPV and IRR?  How to overcome disadvantages of NPV and IRR?  What are other factors needed to consider for a long- term investment? 27