SlideShare a Scribd company logo
1 of 20
Nightingale Project Case Studies
Being Presented by:
Asad Ali Khan (005)
Faheem Abbas (006)
Meerub Shehzadi (009)
Content Structure
Brief summary of case 1
Solution of questions
Brief summary of case 2
Solution to questions
Nightingale project A
• We are acting as an assistant project manager
• Nightingale is the code name
• Development of a handheld electronic
medical reference guide, and it’s mainly
designed for the emergency medical
technicians and paramedics who need a quick
reference guide to use in emergency
situations
• Deadline of the project Is 25th of october.
Assumptions
• The project will begin the first working day in
January, 2010
• The following holidays are observed: January 1,
Memorial Day (last Monday in May), July 4, Labor
Day (first Monday in September), Thanksgiving
Day (fourth Thursday in November), December
25 and 26.
• If a holiday falls on a Saturday, then Friday will be
given as an extra day off; if it falls on a Sunday,
then Monday will be given as a day off.
• The project team works Monday through Friday.
Question 1
Will the project as planned meet the October
25th deadline?
Answer 1
• The total number of days taken by all 30
activities are: 366 days
• The total number of days from the first week
of January till October 25th: 298 days
• The number of off days (both the holidays and
the weekend): 85 days
Contd…
• After subtracting the number of off days from
the number of days from January till October
25th, the actual number of days, within which
the project is to be completed, are 213 days.
• So, the final answer is that the project won’t
be able to meet the deadline, as the duration
of the project (366 days) is much longer than
the actual number of days till the deadline
(213 days).
Question 2
What activities lie on the critical path?
Answer 2
• Those activities lie on the critical path that either have
the longest duration, or have a greater number of
activities succeeding it. In this case the activities that
lie on the critical path include:
• Activity 1
• Activity 4
• Activity 10
• Activity 16
• Activity 24
Question 3
How sensitive is this network?
Answer 3
• The project is to be completed within the
deadline but the duration of the project is
way long. So, the entire network is very
sensitive in a sense that if an activity takes
more time than its actual duration then the
whole project may not finish in time or it may
collapse.
Nightingale Case 2
Brief Overview of Case 2
• Rassy and the team were concerned with the
results of your analysis. They spent more time
on finding different ways to shorten the
project duration
• Rassy had a separate fund of $200,000, but
she was only willing to spend $100,00 of it.
After a lengthy discussion with her
teammates,
Contd…
• Development of voice recognition system could
be reduced from 15 days to 10 days at a cost of
$15,000.
• Creation of database could be reduced from 40
days to 35 days at a cost of $35,000.
• Document design could be reduced from 35 days
to 30 days at a cost of $25,000.
• External specifications could be reduced from 18
days to 12 days at a cost of $20,000.
• Procure prototype components could be reduced
from 20 days to 15 days at a cost of $30,000.
• Order stock parts could be reduced from 15 days
to 10 days at a cost of $20,000.
Additional information on the case
• If you choose to reduce the duration of any
one of the activities mentioned, then it must
be for the specified time and cost (i.e., you
cannot choose to reduce database to 37 days
at a reduced cost; you can only reduce it to 35
days at a cost of $35,000).
• You can only spend up to $100,000 to reduce
project activities; lags do not contain any
additional costs.
Contd…
• As the meeting adjourns, Rassy turns to you
and tells you to assess the options presented
and try to develop a schedule that will meet
the October 25th deadline. You are to prepare
a report to be presented to the project team
that answers the following questions
Question 1
Is it possible to meet the deadline?
Answer 1
• The following calculations were made to see whether
it’s possible to meet the deadline now:
• Development of voice recognition system reduced to: 5
days
• Creation of database reduced to: 5 days
• Document design reduced to: 5 days
• External specifications reduced to: 6 days
• Procure prototype components reduced to: 5 days
• Order stock parts reduced to: 5 days
Contd…
• To keep the funds at about $100,000, we have
removed the first and fifth activity. The
duration of the activities has now reduced
from 366 to 345 days.
• So, it is still not possible to meet the deadline
because even after the adjustments, the time
durations of all the project activities combined
exceeds the given time frame.
Question 2
If so, how would you recommend changing
the original schedule (Part A) and why? Assess
the relative impact of crashing activities versus
introducing lags to shorten project duration.
Answer 2
• We would recommend to try shortening the
activity durations and establish an optimal
project network, so that the project deadlines
could be met effectively and efficiently.
Question 3
What would the new schedule look like?
Answer 3
• It would comprise of updated activity duration
times, a well-defined project structure, and a
well-defined project network. The schedule
would have proper division of the resources as
well.
Question 4
What other factors should be considered before
finalizing the schedule?
Answer 4:
• Factors that are to be considered:
• Well-defined WBS (work breakdown structure)
• Accurate estimates
• Better division of resources
• Decisions regarding activity splitting
• Proper resource management
Thank You

More Related Content

What's hot

Reebok Supply Chain Mgmt Anaylsis
Reebok Supply Chain Mgmt AnaylsisReebok Supply Chain Mgmt Anaylsis
Reebok Supply Chain Mgmt Anaylsis
crmowbray
 
adidas assigment
adidas assigmentadidas assigment
adidas assigment
kibrom G
 

What's hot (20)

02_Brand Consultancy_Luxury Strategy Case Studies Zara Supply Chain Managemen...
02_Brand Consultancy_Luxury Strategy Case Studies Zara Supply Chain Managemen...02_Brand Consultancy_Luxury Strategy Case Studies Zara Supply Chain Managemen...
02_Brand Consultancy_Luxury Strategy Case Studies Zara Supply Chain Managemen...
 
Growth of Zara and Comparison with fabindia
Growth of Zara and Comparison with fabindiaGrowth of Zara and Comparison with fabindia
Growth of Zara and Comparison with fabindia
 
Godrej Brand Management
Godrej Brand ManagementGodrej Brand Management
Godrej Brand Management
 
Carlos ghosn at nissan
Carlos ghosn at nissanCarlos ghosn at nissan
Carlos ghosn at nissan
 
Pest analysis of textile industry
Pest analysis of textile industryPest analysis of textile industry
Pest analysis of textile industry
 
Strategic issues in Readymade Garments Supply Chain Management: A Study on Mo...
Strategic issues in Readymade Garments Supply Chain Management: A Study on Mo...Strategic issues in Readymade Garments Supply Chain Management: A Study on Mo...
Strategic issues in Readymade Garments Supply Chain Management: A Study on Mo...
 
ZARA
ZARAZARA
ZARA
 
Zara - case study --
Zara - case study --Zara - case study --
Zara - case study --
 
Reebok Supply Chain Mgmt Anaylsis
Reebok Supply Chain Mgmt AnaylsisReebok Supply Chain Mgmt Anaylsis
Reebok Supply Chain Mgmt Anaylsis
 
Raymond pestel & swot
Raymond pestel  & swotRaymond pestel  & swot
Raymond pestel & swot
 
adidas assigment
adidas assigmentadidas assigment
adidas assigment
 
Zara presentationppt
Zara presentationpptZara presentationppt
Zara presentationppt
 
Zara ppt
Zara pptZara ppt
Zara ppt
 
Fevicol so ppt
Fevicol so pptFevicol so ppt
Fevicol so ppt
 
Zara - Study Case
Zara - Study CaseZara - Study Case
Zara - Study Case
 
ZARA Supply chain and Logistics improvements
ZARA Supply chain and Logistics improvementsZARA Supply chain and Logistics improvements
ZARA Supply chain and Logistics improvements
 
Zara Inventory Management
Zara Inventory ManagementZara Inventory Management
Zara Inventory Management
 
Adidas
AdidasAdidas
Adidas
 
Zara Case Study presentation
Zara Case Study presentationZara Case Study presentation
Zara Case Study presentation
 
Zara: Fast Fashion at Affordable Prices
Zara: Fast Fashion at Affordable PricesZara: Fast Fashion at Affordable Prices
Zara: Fast Fashion at Affordable Prices
 

Similar to Nightingale Project Case Studies.pptx

Chapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdfChapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdf
FREDERICKOKPAISE
 

Similar to Nightingale Project Case Studies.pptx (20)

Successful Project Estimation: How to Get Your Weekends Back
Successful Project Estimation: How to Get Your Weekends BackSuccessful Project Estimation: How to Get Your Weekends Back
Successful Project Estimation: How to Get Your Weekends Back
 
Analytics in Action: Project Analytics: Visibility that Aids Risk Management
Analytics in Action: Project Analytics: Visibility that Aids Risk ManagementAnalytics in Action: Project Analytics: Visibility that Aids Risk Management
Analytics in Action: Project Analytics: Visibility that Aids Risk Management
 
Project Analytics: Visibility that Aids Risk Management
Project Analytics: Visibility that Aids Risk ManagementProject Analytics: Visibility that Aids Risk Management
Project Analytics: Visibility that Aids Risk Management
 
Introduction to Software Engineering
Introduction to Software EngineeringIntroduction to Software Engineering
Introduction to Software Engineering
 
EpM
EpMEpM
EpM
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Chapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdfChapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdf
 
Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2
 
Industrial.projects.Student.Level
Industrial.projects.Student.LevelIndustrial.projects.Student.Level
Industrial.projects.Student.Level
 
Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2
 
Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2Strayer bus 375 midterm exam part 2
Strayer bus 375 midterm exam part 2
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
 
BT4301 PPT.-converted.pdf
BT4301 PPT.-converted.pdfBT4301 PPT.-converted.pdf
BT4301 PPT.-converted.pdf
 
Chapter 4
Chapter 4 Chapter 4
Chapter 4
 
303 week 2
303 week 2303 week 2
303 week 2
 
Beyond projects
Beyond projectsBeyond projects
Beyond projects
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003
 
2010 06-07-sto-2010-intelligent-resource-scheduling-for-reduced-turnaround-du...
2010 06-07-sto-2010-intelligent-resource-scheduling-for-reduced-turnaround-du...2010 06-07-sto-2010-intelligent-resource-scheduling-for-reduced-turnaround-du...
2010 06-07-sto-2010-intelligent-resource-scheduling-for-reduced-turnaround-du...
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project Management
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project Management
 

Recently uploaded

SAUDI ARABIYA | +966572737505 |Jeddah Get Cytotec pills for Abortion pills
SAUDI ARABIYA | +966572737505 |Jeddah Get Cytotec pills for Abortion pillsSAUDI ARABIYA | +966572737505 |Jeddah Get Cytotec pills for Abortion pills
SAUDI ARABIYA | +966572737505 |Jeddah Get Cytotec pills for Abortion pills
Abortion pills in Riyadh +966572737505 get cytotec
 
一比一原版(UCSB毕业证书)圣塔芭芭拉社区大学毕业证成绩单学位证书
一比一原版(UCSB毕业证书)圣塔芭芭拉社区大学毕业证成绩单学位证书一比一原版(UCSB毕业证书)圣塔芭芭拉社区大学毕业证成绩单学位证书
一比一原版(UCSB毕业证书)圣塔芭芭拉社区大学毕业证成绩单学位证书
atedyxc
 
一比一原版(Concordia毕业证书)康卡迪亚大学毕业证成绩单学位证书
一比一原版(Concordia毕业证书)康卡迪亚大学毕业证成绩单学位证书一比一原版(Concordia毕业证书)康卡迪亚大学毕业证成绩单学位证书
一比一原版(Concordia毕业证书)康卡迪亚大学毕业证成绩单学位证书
atedyxc
 
一比一原版(SFU毕业证书)西蒙菲莎大学毕业证成绩单学位证书
一比一原版(SFU毕业证书)西蒙菲莎大学毕业证成绩单学位证书一比一原版(SFU毕业证书)西蒙菲莎大学毕业证成绩单学位证书
一比一原版(SFU毕业证书)西蒙菲莎大学毕业证成绩单学位证书
atedyxc
 
ASSESSING HRM EFFECTIVENESS AND PERFORMANCE ENHANCEMENT MEASURES IN THE BANKI...
ASSESSING HRM EFFECTIVENESS AND PERFORMANCE ENHANCEMENT MEASURES IN THE BANKI...ASSESSING HRM EFFECTIVENESS AND PERFORMANCE ENHANCEMENT MEASURES IN THE BANKI...
ASSESSING HRM EFFECTIVENESS AND PERFORMANCE ENHANCEMENT MEASURES IN THE BANKI...
indexPub
 
Prezentacja Q1 2024 EN strona www relacji
Prezentacja Q1 2024  EN strona www relacjiPrezentacja Q1 2024  EN strona www relacji
Prezentacja Q1 2024 EN strona www relacji
klaudiafilka
 
一比一原版(UC Davis毕业证书)加州大学戴维斯分校毕业证成绩单学位证书
一比一原版(UC Davis毕业证书)加州大学戴维斯分校毕业证成绩单学位证书一比一原版(UC Davis毕业证书)加州大学戴维斯分校毕业证成绩单学位证书
一比一原版(UC Davis毕业证书)加州大学戴维斯分校毕业证成绩单学位证书
atedyxc
 
一比一原版(Caltech毕业证书)加利福尼亚理工学院毕业证成绩单学位证书
一比一原版(Caltech毕业证书)加利福尼亚理工学院毕业证成绩单学位证书一比一原版(Caltech毕业证书)加利福尼亚理工学院毕业证成绩单学位证书
一比一原版(Caltech毕业证书)加利福尼亚理工学院毕业证成绩单学位证书
atedyxc
 

Recently uploaded (20)

SAUDI ARABIYA | +966572737505 |Jeddah Get Cytotec pills for Abortion pills
SAUDI ARABIYA | +966572737505 |Jeddah Get Cytotec pills for Abortion pillsSAUDI ARABIYA | +966572737505 |Jeddah Get Cytotec pills for Abortion pills
SAUDI ARABIYA | +966572737505 |Jeddah Get Cytotec pills for Abortion pills
 
一比一原版(UCSB毕业证书)圣塔芭芭拉社区大学毕业证成绩单学位证书
一比一原版(UCSB毕业证书)圣塔芭芭拉社区大学毕业证成绩单学位证书一比一原版(UCSB毕业证书)圣塔芭芭拉社区大学毕业证成绩单学位证书
一比一原版(UCSB毕业证书)圣塔芭芭拉社区大学毕业证成绩单学位证书
 
Big developments in Lesotho Butha-Buthe.
Big developments in Lesotho Butha-Buthe.Big developments in Lesotho Butha-Buthe.
Big developments in Lesotho Butha-Buthe.
 
NO1 Top Vashikaran Specialist in Uk Black Magic Specialist in Uk Black Magic ...
NO1 Top Vashikaran Specialist in Uk Black Magic Specialist in Uk Black Magic ...NO1 Top Vashikaran Specialist in Uk Black Magic Specialist in Uk Black Magic ...
NO1 Top Vashikaran Specialist in Uk Black Magic Specialist in Uk Black Magic ...
 
GIFT City Overview India's Gateway to Global Finance
GIFT City Overview  India's Gateway to Global FinanceGIFT City Overview  India's Gateway to Global Finance
GIFT City Overview India's Gateway to Global Finance
 
一比一原版(Concordia毕业证书)康卡迪亚大学毕业证成绩单学位证书
一比一原版(Concordia毕业证书)康卡迪亚大学毕业证成绩单学位证书一比一原版(Concordia毕业证书)康卡迪亚大学毕业证成绩单学位证书
一比一原版(Concordia毕业证书)康卡迪亚大学毕业证成绩单学位证书
 
Module 1 CCP - Introduction and LMS.pptx
Module 1 CCP  - Introduction and LMS.pptxModule 1 CCP  - Introduction and LMS.pptx
Module 1 CCP - Introduction and LMS.pptx
 
一比一原版(SFU毕业证书)西蒙菲莎大学毕业证成绩单学位证书
一比一原版(SFU毕业证书)西蒙菲莎大学毕业证成绩单学位证书一比一原版(SFU毕业证书)西蒙菲莎大学毕业证成绩单学位证书
一比一原版(SFU毕业证书)西蒙菲莎大学毕业证成绩单学位证书
 
Production and Cost of the firm with curves
Production and Cost of the firm with curvesProduction and Cost of the firm with curves
Production and Cost of the firm with curves
 
ASSESSING HRM EFFECTIVENESS AND PERFORMANCE ENHANCEMENT MEASURES IN THE BANKI...
ASSESSING HRM EFFECTIVENESS AND PERFORMANCE ENHANCEMENT MEASURES IN THE BANKI...ASSESSING HRM EFFECTIVENESS AND PERFORMANCE ENHANCEMENT MEASURES IN THE BANKI...
ASSESSING HRM EFFECTIVENESS AND PERFORMANCE ENHANCEMENT MEASURES IN THE BANKI...
 
Satoshi DEX Leverages Layer 2 To Transform DeFi Ecosystem.pdf
Satoshi DEX Leverages Layer 2 To Transform DeFi Ecosystem.pdfSatoshi DEX Leverages Layer 2 To Transform DeFi Ecosystem.pdf
Satoshi DEX Leverages Layer 2 To Transform DeFi Ecosystem.pdf
 
MARKETING PLAN COFFEE SHOP IN HO CHI MINH CITY
MARKETING PLAN COFFEE SHOP IN HO CHI MINH CITYMARKETING PLAN COFFEE SHOP IN HO CHI MINH CITY
MARKETING PLAN COFFEE SHOP IN HO CHI MINH CITY
 
Prezentacja Q1 2024 EN strona www relacji
Prezentacja Q1 2024  EN strona www relacjiPrezentacja Q1 2024  EN strona www relacji
Prezentacja Q1 2024 EN strona www relacji
 
20240514-Calibre-Q1-2024-Conference-Call-Presentation.pdf
20240514-Calibre-Q1-2024-Conference-Call-Presentation.pdf20240514-Calibre-Q1-2024-Conference-Call-Presentation.pdf
20240514-Calibre-Q1-2024-Conference-Call-Presentation.pdf
 
一比一原版(UC Davis毕业证书)加州大学戴维斯分校毕业证成绩单学位证书
一比一原版(UC Davis毕业证书)加州大学戴维斯分校毕业证成绩单学位证书一比一原版(UC Davis毕业证书)加州大学戴维斯分校毕业证成绩单学位证书
一比一原版(UC Davis毕业证书)加州大学戴维斯分校毕业证成绩单学位证书
 
一比一原版(Caltech毕业证书)加利福尼亚理工学院毕业证成绩单学位证书
一比一原版(Caltech毕业证书)加利福尼亚理工学院毕业证成绩单学位证书一比一原版(Caltech毕业证书)加利福尼亚理工学院毕业证成绩单学位证书
一比一原版(Caltech毕业证书)加利福尼亚理工学院毕业证成绩单学位证书
 
Slideshare - ONS Economic Forum Slidepack - 13 May 2024.pptx
Slideshare - ONS Economic Forum Slidepack - 13 May 2024.pptxSlideshare - ONS Economic Forum Slidepack - 13 May 2024.pptx
Slideshare - ONS Economic Forum Slidepack - 13 May 2024.pptx
 
Amil baba australia kala jadu in uk black magic in usa
Amil baba australia kala jadu in uk black magic in usaAmil baba australia kala jadu in uk black magic in usa
Amil baba australia kala jadu in uk black magic in usa
 
project ratio analysis of bcom studies .
project ratio analysis of bcom studies .project ratio analysis of bcom studies .
project ratio analysis of bcom studies .
 
amil baba kala jadu expert uk amil baba kala jadu removal uk amil baba in mal...
amil baba kala jadu expert uk amil baba kala jadu removal uk amil baba in mal...amil baba kala jadu expert uk amil baba kala jadu removal uk amil baba in mal...
amil baba kala jadu expert uk amil baba kala jadu removal uk amil baba in mal...
 

Nightingale Project Case Studies.pptx

  • 1. Nightingale Project Case Studies Being Presented by: Asad Ali Khan (005) Faheem Abbas (006) Meerub Shehzadi (009)
  • 2. Content Structure Brief summary of case 1 Solution of questions Brief summary of case 2 Solution to questions
  • 3. Nightingale project A • We are acting as an assistant project manager • Nightingale is the code name • Development of a handheld electronic medical reference guide, and it’s mainly designed for the emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations • Deadline of the project Is 25th of october.
  • 4.
  • 5. Assumptions • The project will begin the first working day in January, 2010 • The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4, Labor Day (first Monday in September), Thanksgiving Day (fourth Thursday in November), December 25 and 26. • If a holiday falls on a Saturday, then Friday will be given as an extra day off; if it falls on a Sunday, then Monday will be given as a day off. • The project team works Monday through Friday.
  • 6. Question 1 Will the project as planned meet the October 25th deadline? Answer 1 • The total number of days taken by all 30 activities are: 366 days • The total number of days from the first week of January till October 25th: 298 days • The number of off days (both the holidays and the weekend): 85 days
  • 7. Contd… • After subtracting the number of off days from the number of days from January till October 25th, the actual number of days, within which the project is to be completed, are 213 days. • So, the final answer is that the project won’t be able to meet the deadline, as the duration of the project (366 days) is much longer than the actual number of days till the deadline (213 days).
  • 8. Question 2 What activities lie on the critical path? Answer 2 • Those activities lie on the critical path that either have the longest duration, or have a greater number of activities succeeding it. In this case the activities that lie on the critical path include: • Activity 1 • Activity 4 • Activity 10 • Activity 16 • Activity 24
  • 9. Question 3 How sensitive is this network? Answer 3 • The project is to be completed within the deadline but the duration of the project is way long. So, the entire network is very sensitive in a sense that if an activity takes more time than its actual duration then the whole project may not finish in time or it may collapse.
  • 11. Brief Overview of Case 2 • Rassy and the team were concerned with the results of your analysis. They spent more time on finding different ways to shorten the project duration • Rassy had a separate fund of $200,000, but she was only willing to spend $100,00 of it. After a lengthy discussion with her teammates,
  • 12. Contd… • Development of voice recognition system could be reduced from 15 days to 10 days at a cost of $15,000. • Creation of database could be reduced from 40 days to 35 days at a cost of $35,000. • Document design could be reduced from 35 days to 30 days at a cost of $25,000. • External specifications could be reduced from 18 days to 12 days at a cost of $20,000. • Procure prototype components could be reduced from 20 days to 15 days at a cost of $30,000. • Order stock parts could be reduced from 15 days to 10 days at a cost of $20,000.
  • 13. Additional information on the case • If you choose to reduce the duration of any one of the activities mentioned, then it must be for the specified time and cost (i.e., you cannot choose to reduce database to 37 days at a reduced cost; you can only reduce it to 35 days at a cost of $35,000). • You can only spend up to $100,000 to reduce project activities; lags do not contain any additional costs.
  • 14. Contd… • As the meeting adjourns, Rassy turns to you and tells you to assess the options presented and try to develop a schedule that will meet the October 25th deadline. You are to prepare a report to be presented to the project team that answers the following questions
  • 15. Question 1 Is it possible to meet the deadline? Answer 1 • The following calculations were made to see whether it’s possible to meet the deadline now: • Development of voice recognition system reduced to: 5 days • Creation of database reduced to: 5 days • Document design reduced to: 5 days • External specifications reduced to: 6 days • Procure prototype components reduced to: 5 days • Order stock parts reduced to: 5 days
  • 16. Contd… • To keep the funds at about $100,000, we have removed the first and fifth activity. The duration of the activities has now reduced from 366 to 345 days. • So, it is still not possible to meet the deadline because even after the adjustments, the time durations of all the project activities combined exceeds the given time frame.
  • 17. Question 2 If so, how would you recommend changing the original schedule (Part A) and why? Assess the relative impact of crashing activities versus introducing lags to shorten project duration. Answer 2 • We would recommend to try shortening the activity durations and establish an optimal project network, so that the project deadlines could be met effectively and efficiently.
  • 18. Question 3 What would the new schedule look like? Answer 3 • It would comprise of updated activity duration times, a well-defined project structure, and a well-defined project network. The schedule would have proper division of the resources as well.
  • 19. Question 4 What other factors should be considered before finalizing the schedule? Answer 4: • Factors that are to be considered: • Well-defined WBS (work breakdown structure) • Accurate estimates • Better division of resources • Decisions regarding activity splitting • Proper resource management