SlideShare a Scribd company logo
STRAYER BUS 375 Midterm Exam Part 2 (2 Set)
NEW
Check this A+ tutorial guideline at
http://www.uopassignments.com/bus-375-
strayer/bus-375-midterm-exam-part-2-2-set-
recent
For more classes visit
http://www.uopassignments.com
• Question 1 Which of the following is NOT one of
the recommended guidelines for developing useful
work package estimates? .
• Question 2 Janet is forecasting how much money
her department needs to support a new project.
She estimates that two people and $25,000 in
expenses will cover her needs. Because
management typically insists on reducing
forecasts by 20 percent, she increases her
estimates to allow for that reduction. Which of the
following factors is illustrated in this situation?
• Question 3 Ed is looking over the actual results
of projects and comparing them to what was
estimated. He notices that the projects that took
six months or longer to complete were noticeably
more off the estimates. Which of the following
factors is he recognizing?
• Question 4 Refining estimates may be necessary
for a number of reasons. For example, resource
shortages, in the form of people, equipment, or
materials, can extend original estimates. This is a
good example of
• Question 5 Refining estimates may be necessary
for a number of reasons. For example, a manager
getting further into a project and obtaining a
better understanding of what needs to be done to
accomplish a project and meet the needs of the
customer is an example of
• Question 6 Which of the following is NOT true in
regard to the level of detail estimates should
contain?
• Question 7 Jose is forecasting project time and
cost for constructing a new building by multiplying
the total square footage by a given dollar amount.
Which of the following methods is he using?
• Question 8 The bottom-up approach for
estimating times and costs that uses costs from
past projects that were similar to the current
project is known as
• Question 9 Which of the following is NOT one of
the bottom-up approaches to estimating project
time and cost?
• Question 10 Richard is collecting estimates for a
house that he will have the funding to build in 12
months. Which of the following factors does
Richard need to consider in regard to the quality
of these estimates?
• Question 11 Which of the following top-down
methods is used when projects closely follow past
projects in regard to features and costs of those
features, and result in costs being assigned by
percentages to major segments of the project?
• Question 12 Which of the following is a good
condition for bottom-up estimating?
• Question 13 What is the relationship between
organizational culture and estimating?
• Question 14 Tom is responsible for ordering
hardware for a custom home his company is
building. The contractor installing the hardware is
scheduled to start in 5 working days, but the
hardware is on backorder and will not arrive for
another 9 working days. Fortunately, Tom has 10
days of slack; however, he shares this slack with
the hardware installer. He will have to let the
contactor know that the hardware will be ready 4
days later than expected and that the slack for the
installer has been reduced by 4 days. Tom and the
installer share 10 days of
• Question 15 System documentation cannot end
until three days after testing has started. This is an
example of which kind of lag?
• Question 16 Which of the following will correctly
calculate the total slack in an activity?
• Question 17 Which of the following is NOT one of
the basic rules to follow when developing project
networks?
• Question 18 When translated into a project
network, a work package will become
• Question 19 Bill is building a project network
that involves testing a prototype. He must design
the prototype (activity 1), build the prototype
(activity 2), and test the prototype (activity 3).
Activity 1 is the predecessor for activity 2 and
activity 2 is the predecessor for activity 3. If the
prototype fails testing, Bill must redesign the
prototype; therefore, activity 3 is a predecessor for
activity 1. This is an example of
• Question 20 Which of the following correctly
calculates the late start for an activity?
• Question 21 ________ activities must be completed
immediately before a particular activity.
• Question 22 The backward pass in project
network calculations determines all of the
following EXCEPT
• Question 23 The critical path in a project
network is the
• Question 24 Which of the following correctly
calculates the early finish for an activity?
• Question 25 If a project has more than one
activity that can begin when the project is to start,
a common start node should be used to indicate a
clear project beginning on the network. Without a
common start node, each path is a
Set 2
• Question 1 The likelihood the original critical
path(s) will change once the project is initiated is
referred to as
• Question 2 Bill is building a project network that
involves testing a prototype. He must design the
prototype (activity 1), build the prototype (activity
2), and test the prototype (activity 3). Activity 1 is
the predecessor for activity 2 and activity 2 is the
predecessor for activity 3. If the prototype fails
testing, Bill must redesign the prototype;
therefore, activity 3 is a predecessor for activity 1.
This is an example of
• Question 3 The assumption that all immediate
preceding activities must be 100% complete is too
restrictive in some situations. When an activity is
broken down into smaller segments in order to
start the succeeding activity sooner, this is called
• Question 4 The minimum amount of time a
dependent activity must be delayed to begin or
end is referred to as
• Question 5 Which of the following represents an
activity on an activity-on-node (AON) project
network?
• Question 6 ________ activities must be completed
immediately before a particular activity.
• Question 7 If, for some reason, the project must
be expedited to meet an earlier date, which of the
following actions would the project manager take
first?
• Question 8 Which of the following can be used
without coordinating with managers of succeeding
activities?
• Question 9 An activity that has more than one
dependency arrow flowing into it is termed a(n)
• Question 10 A(n) _________ activity has more than
one dependency arrow flowing from it.
• Question 11 Which of the following does NOT
help describe a project network?
• Question 12 Arrows on an activity-on-node
(AON) project network represent
• Question 13 Companies are using which of the
following for improving the estimating process for
future projects?
• Question 14 Which of the following describes the
consensus method?
• Question 15 The process of forecasting or
approximating the time and cost of completing
project deliverables is called
• Question 16 What is the relationship between
organizational culture and estimating?
• Question 17 Which of the following is a good
condition for top-down estimating?
• Question 18 In practice, estimating processes
are frequently classified as
• Question 19 Refining estimates may be
necessary for a number of reasons. For example,
people working on prototype development
needing time to interact with the design engineers
after the design is completed is a good example of
• Question 20 Refining estimates may be
necessary for a number of reasons. For example,
resource shortages, in the form of people,
equipment, or materials, can extend original
estimates. This is a good example of
• Question 21 Which of the following is NOT true
in regard to the level of detail estimates should
contain?
• Question 22 Which of the following top-down
methods is used when projects closely follow past
projects in regard to features and costs of those
features, and result in costs being assigned by
percentages to major segments of the project?
• Question 23 Rob is responsible for estimating a
work package that has a significant amount of
uncertainty associated with the time and cost to
complete. Due to the uncertainty involved he will
be making a low, an average and a high estimate.
Rob is using which estimating approach?
• Question 24 Ed is looking over the actual results
of projects and comparing them to what was
estimated. He notices that the projects that took
six months or longer to complete were noticeably
more off the estimates. Which of the following
factors is he recognizing?
• Question 25 The bottom-up approach for
estimating times and costs that uses costs from
past projects that were similar to the current
project is known as
• Question 23 Rob is responsible for estimating a
work package that has a significant amount of
uncertainty associated with the time and cost to
complete. Due to the uncertainty involved he will
be making a low, an average and a high estimate.
Rob is using which estimating approach?
• Question 24 Ed is looking over the actual results
of projects and comparing them to what was
estimated. He notices that the projects that took
six months or longer to complete were noticeably
more off the estimates. Which of the following
factors is he recognizing?
• Question 25 The bottom-up approach for
estimating times and costs that uses costs from
past projects that were similar to the current
project is known as

More Related Content

What's hot

Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Project Estimation Presentation - Donte's 8th level of estimating level of ef...Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Promet Source
 
Room to Breathe: The BA's role in project estimation
Room to Breathe: The BA's role in project estimationRoom to Breathe: The BA's role in project estimation
Room to Breathe: The BA's role in project estimation
ufunctional
 
Pmi rmp
Pmi rmpPmi rmp
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
Abdullah Ahmed, PMP, RMP
 
Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and cons
Pragnendra Rahevar
 
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementEVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program Management
IRJET Journal
 
Slides 2015 for contact 1
Slides 2015 for contact 1Slides 2015 for contact 1
Slides 2015 for contact 1
YourhighnessJordaan
 
Narrated Version Dallas MPUG
Narrated Version Dallas MPUGNarrated Version Dallas MPUG
Narrated Version Dallas MPUG
Glen Alleman
 
Daniel dumitrescu
Daniel dumitrescuDaniel dumitrescu
Daniel dumitrescu
Daniel Dumitrescu
 
PMI Global Congress North America 2013 - Improving Focus and Predictability o...
PMI Global Congress North America 2013 - Improving Focus and Predictability o...PMI Global Congress North America 2013 - Improving Focus and Predictability o...
PMI Global Congress North America 2013 - Improving Focus and Predictability o...
Joe Cooper
 
CAPM Study Session 2
CAPM Study Session 2CAPM Study Session 2
CAPM Study Session 2
Kinetic Potential
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
Shyam Kerkar
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
Artonline Home
 
Stepwise Project planning in software development
Stepwise Project planning in software developmentStepwise Project planning in software development
Stepwise Project planning in software development
Prof Ansari
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
Mohamed Saeed
 
Pmp test 01
Pmp test 01Pmp test 01
Pmp test 01
Mohamed Saeed
 

What's hot (16)

Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Project Estimation Presentation - Donte's 8th level of estimating level of ef...Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Project Estimation Presentation - Donte's 8th level of estimating level of ef...
 
Room to Breathe: The BA's role in project estimation
Room to Breathe: The BA's role in project estimationRoom to Breathe: The BA's role in project estimation
Room to Breathe: The BA's role in project estimation
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Cost and time estimation methods pros and cons
Cost and time estimation methods pros and consCost and time estimation methods pros and cons
Cost and time estimation methods pros and cons
 
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementEVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program Management
 
Slides 2015 for contact 1
Slides 2015 for contact 1Slides 2015 for contact 1
Slides 2015 for contact 1
 
Narrated Version Dallas MPUG
Narrated Version Dallas MPUGNarrated Version Dallas MPUG
Narrated Version Dallas MPUG
 
Daniel dumitrescu
Daniel dumitrescuDaniel dumitrescu
Daniel dumitrescu
 
PMI Global Congress North America 2013 - Improving Focus and Predictability o...
PMI Global Congress North America 2013 - Improving Focus and Predictability o...PMI Global Congress North America 2013 - Improving Focus and Predictability o...
PMI Global Congress North America 2013 - Improving Focus and Predictability o...
 
CAPM Study Session 2
CAPM Study Session 2CAPM Study Session 2
CAPM Study Session 2
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
Stepwise Project planning in software development
Stepwise Project planning in software developmentStepwise Project planning in software development
Stepwise Project planning in software development
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
 
Pmp test 01
Pmp test 01Pmp test 01
Pmp test 01
 

Similar to Strayer bus 375 midterm exam part 2

Strayer bus 375 final exam part 1
Strayer bus 375 final exam part 1Strayer bus 375 final exam part 1
Strayer bus 375 final exam part 1
aaronabrahhaam
 
Strayer bus 375 final exam part 1
Strayer bus 375 final exam part 1Strayer bus 375 final exam part 1
Strayer bus 375 final exam part 1
eyavagal
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
nikig6806
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
eyavagal
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
eyavagal
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
eyavagal
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
eyavagal
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
nikig6806
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Song Love
 
1587310189-week6.pptx
1587310189-week6.pptx1587310189-week6.pptx
1587310189-week6.pptx
KAVIPRIYAMANALAN
 
Bus 517 midterm
Bus 517 midtermBus 517 midterm
Bus 517 midterm
Homework Help Online
 
Liberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers keyLiberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers key
Matt Smith
 
Bus 517 midterm exam 1 2
Bus 517 midterm exam 1 2Bus 517 midterm exam 1 2
Bus 517 midterm exam 1 2
Homework Help Online
 
Bus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsBus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questions
Homework Help Online
 
Bus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsBus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questions
Homework Help Online
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
IRESH3
 
Microsoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case StudiesMicrosoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case Studies
meritweb
 
Pmbok 6th edition_practice_questions
Pmbok 6th edition_practice_questionsPmbok 6th edition_practice_questions
Pmbok 6th edition_practice_questions
OlgaZelenina2
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?
Phil Comelio
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
IRESH3
 

Similar to Strayer bus 375 midterm exam part 2 (20)

Strayer bus 375 final exam part 1
Strayer bus 375 final exam part 1Strayer bus 375 final exam part 1
Strayer bus 375 final exam part 1
 
Strayer bus 375 final exam part 1
Strayer bus 375 final exam part 1Strayer bus 375 final exam part 1
Strayer bus 375 final exam part 1
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
 
Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2Strayer bus 375 final exam part 2
Strayer bus 375 final exam part 2
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
 
Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1Strayer bus 375 midterm exam part 1
Strayer bus 375 midterm exam part 1
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
 
1587310189-week6.pptx
1587310189-week6.pptx1587310189-week6.pptx
1587310189-week6.pptx
 
Bus 517 midterm
Bus 517 midtermBus 517 midterm
Bus 517 midterm
 
Liberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers keyLiberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers key
 
Bus 517 midterm exam 1 2
Bus 517 midterm exam 1 2Bus 517 midterm exam 1 2
Bus 517 midterm exam 1 2
 
Bus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsBus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questions
 
Bus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questionsBus 517 midterm exam 1 2 all possible questions
Bus 517 midterm exam 1 2 all possible questions
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Microsoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case StudiesMicrosoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case Studies
 
Pmbok 6th edition_practice_questions
Pmbok 6th edition_practice_questionsPmbok 6th edition_practice_questions
Pmbok 6th edition_practice_questions
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
 

More from eyavagal

Hcr 230 week 3 check point working with medicaid
Hcr 230 week 3 check point working with medicaidHcr 230 week 3 check point working with medicaid
Hcr 230 week 3 check point working with medicaid
eyavagal
 
Hcr 230 complete class
Hcr 230 complete classHcr 230 complete class
Hcr 230 complete class
eyavagal
 
Hcr 220 complete class
Hcr 220 complete classHcr 220 complete class
Hcr 220 complete class
eyavagal
 
Uop mpa 573 week 5 city council advisement part iii recent
Uop mpa 573 week 5 city council advisement part iii recentUop mpa 573 week 5 city council advisement part iii recent
Uop mpa 573 week 5 city council advisement part iii recent
eyavagal
 
Uop mpa 573 week 2 policy presentation (forecasting) recent
Uop mpa 573 week 2 policy presentation (forecasting) recentUop mpa 573 week 2 policy presentation (forecasting) recent
Uop mpa 573 week 2 policy presentation (forecasting) recent
eyavagal
 
Mktg 522 week 8 final exam guide
Mktg 522 week 8 final exam guideMktg 522 week 8 final exam guide
Mktg 522 week 8 final exam guide
eyavagal
 
Strayer mis 535 week 6 course project proposal paper
Strayer mis 535 week 6 course project proposal paperStrayer mis 535 week 6 course project proposal paper
Strayer mis 535 week 6 course project proposal paper
eyavagal
 
Strayer mis 535 week 6 course project proposal
Strayer mis 535 week 6 course project proposalStrayer mis 535 week 6 course project proposal
Strayer mis 535 week 6 course project proposal
eyavagal
 
Strayer mis 535 week 6 course project proposal paper (certify for employees)
Strayer mis 535 week 6 course project proposal paper (certify for employees)Strayer mis 535 week 6 course project proposal paper (certify for employees)
Strayer mis 535 week 6 course project proposal paper (certify for employees)
eyavagal
 
Ash ece 405 week 3 assignment 1 e
Ash ece 405 week 3 assignment 1 eAsh ece 405 week 3 assignment 1 e
Ash ece 405 week 3 assignment 1 e
eyavagal
 
Ash ece 353 week 5 discussions 1 cognitive development and learning new
Ash ece 353 week 5 discussions 1 cognitive development and learning newAsh ece 353 week 5 discussions 1 cognitive development and learning new
Ash ece 353 week 5 discussions 1 cognitive development and learning new
eyavagal
 
Ash ece 353 week 4 discussions 2 relationships between cognitive
Ash ece 353 week 4 discussions 2 relationships between cognitiveAsh ece 353 week 4 discussions 2 relationships between cognitive
Ash ece 353 week 4 discussions 2 relationships between cognitive
eyavagal
 
Msu ece 345 week 5 final paper new
Msu ece 345 week 5 final paper newMsu ece 345 week 5 final paper new
Msu ece 345 week 5 final paper new
eyavagal
 
Ese 633 week 5 dq 1 discussion on co teaching
Ese 633 week 5 dq 1 discussion on co teachingEse 633 week 5 dq 1 discussion on co teaching
Ese 633 week 5 dq 1 discussion on co teaching
eyavagal
 
Ese 633 week 5 assignment collaborative problem solving
Ese 633 week 5 assignment collaborative problem solvingEse 633 week 5 assignment collaborative problem solving
Ese 633 week 5 assignment collaborative problem solving
eyavagal
 
Ese 633 week 4 dq 1 transition planning
Ese 633 week 4 dq 1 transition planningEse 633 week 4 dq 1 transition planning
Ese 633 week 4 dq 1 transition planning
eyavagal
 
Ese 633 week 4 assignment helping parents promote independence
Ese 633 week 4 assignment helping parents promote independenceEse 633 week 4 assignment helping parents promote independence
Ese 633 week 4 assignment helping parents promote independence
eyavagal
 
Ese 633 week 3 dq 2 collaborative consultation model
Ese 633 week 3 dq 2 collaborative consultation modelEse 633 week 3 dq 2 collaborative consultation model
Ese 633 week 3 dq 2 collaborative consultation model
eyavagal
 
Ese 633 week 2 assignment developing curriculum design
Ese 633 week 2 assignment developing curriculum designEse 633 week 2 assignment developing curriculum design
Ese 633 week 2 assignment developing curriculum design
eyavagal
 
Ese 633 week 1 assignment assessing conflict styles
Ese 633 week 1 assignment assessing conflict stylesEse 633 week 1 assignment assessing conflict styles
Ese 633 week 1 assignment assessing conflict styles
eyavagal
 

More from eyavagal (20)

Hcr 230 week 3 check point working with medicaid
Hcr 230 week 3 check point working with medicaidHcr 230 week 3 check point working with medicaid
Hcr 230 week 3 check point working with medicaid
 
Hcr 230 complete class
Hcr 230 complete classHcr 230 complete class
Hcr 230 complete class
 
Hcr 220 complete class
Hcr 220 complete classHcr 220 complete class
Hcr 220 complete class
 
Uop mpa 573 week 5 city council advisement part iii recent
Uop mpa 573 week 5 city council advisement part iii recentUop mpa 573 week 5 city council advisement part iii recent
Uop mpa 573 week 5 city council advisement part iii recent
 
Uop mpa 573 week 2 policy presentation (forecasting) recent
Uop mpa 573 week 2 policy presentation (forecasting) recentUop mpa 573 week 2 policy presentation (forecasting) recent
Uop mpa 573 week 2 policy presentation (forecasting) recent
 
Mktg 522 week 8 final exam guide
Mktg 522 week 8 final exam guideMktg 522 week 8 final exam guide
Mktg 522 week 8 final exam guide
 
Strayer mis 535 week 6 course project proposal paper
Strayer mis 535 week 6 course project proposal paperStrayer mis 535 week 6 course project proposal paper
Strayer mis 535 week 6 course project proposal paper
 
Strayer mis 535 week 6 course project proposal
Strayer mis 535 week 6 course project proposalStrayer mis 535 week 6 course project proposal
Strayer mis 535 week 6 course project proposal
 
Strayer mis 535 week 6 course project proposal paper (certify for employees)
Strayer mis 535 week 6 course project proposal paper (certify for employees)Strayer mis 535 week 6 course project proposal paper (certify for employees)
Strayer mis 535 week 6 course project proposal paper (certify for employees)
 
Ash ece 405 week 3 assignment 1 e
Ash ece 405 week 3 assignment 1 eAsh ece 405 week 3 assignment 1 e
Ash ece 405 week 3 assignment 1 e
 
Ash ece 353 week 5 discussions 1 cognitive development and learning new
Ash ece 353 week 5 discussions 1 cognitive development and learning newAsh ece 353 week 5 discussions 1 cognitive development and learning new
Ash ece 353 week 5 discussions 1 cognitive development and learning new
 
Ash ece 353 week 4 discussions 2 relationships between cognitive
Ash ece 353 week 4 discussions 2 relationships between cognitiveAsh ece 353 week 4 discussions 2 relationships between cognitive
Ash ece 353 week 4 discussions 2 relationships between cognitive
 
Msu ece 345 week 5 final paper new
Msu ece 345 week 5 final paper newMsu ece 345 week 5 final paper new
Msu ece 345 week 5 final paper new
 
Ese 633 week 5 dq 1 discussion on co teaching
Ese 633 week 5 dq 1 discussion on co teachingEse 633 week 5 dq 1 discussion on co teaching
Ese 633 week 5 dq 1 discussion on co teaching
 
Ese 633 week 5 assignment collaborative problem solving
Ese 633 week 5 assignment collaborative problem solvingEse 633 week 5 assignment collaborative problem solving
Ese 633 week 5 assignment collaborative problem solving
 
Ese 633 week 4 dq 1 transition planning
Ese 633 week 4 dq 1 transition planningEse 633 week 4 dq 1 transition planning
Ese 633 week 4 dq 1 transition planning
 
Ese 633 week 4 assignment helping parents promote independence
Ese 633 week 4 assignment helping parents promote independenceEse 633 week 4 assignment helping parents promote independence
Ese 633 week 4 assignment helping parents promote independence
 
Ese 633 week 3 dq 2 collaborative consultation model
Ese 633 week 3 dq 2 collaborative consultation modelEse 633 week 3 dq 2 collaborative consultation model
Ese 633 week 3 dq 2 collaborative consultation model
 
Ese 633 week 2 assignment developing curriculum design
Ese 633 week 2 assignment developing curriculum designEse 633 week 2 assignment developing curriculum design
Ese 633 week 2 assignment developing curriculum design
 
Ese 633 week 1 assignment assessing conflict styles
Ese 633 week 1 assignment assessing conflict stylesEse 633 week 1 assignment assessing conflict styles
Ese 633 week 1 assignment assessing conflict styles
 

Recently uploaded

How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
Celine George
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
WaniBasim
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
adhitya5119
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
TechSoup
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
RitikBhardwaj56
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
amberjdewit93
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
Colégio Santa Teresinha
 
Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 

Recently uploaded (20)

How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
 
Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
 

Strayer bus 375 midterm exam part 2

  • 1. STRAYER BUS 375 Midterm Exam Part 2 (2 Set) NEW Check this A+ tutorial guideline at http://www.uopassignments.com/bus-375- strayer/bus-375-midterm-exam-part-2-2-set- recent For more classes visit http://www.uopassignments.com • Question 1 Which of the following is NOT one of the recommended guidelines for developing useful work package estimates? . • Question 2 Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation? • Question 3 Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that the projects that took six months or longer to complete were noticeably
  • 2. more off the estimates. Which of the following factors is he recognizing? • Question 4 Refining estimates may be necessary for a number of reasons. For example, resource shortages, in the form of people, equipment, or materials, can extend original estimates. This is a good example of • Question 5 Refining estimates may be necessary for a number of reasons. For example, a manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project and meet the needs of the customer is an example of • Question 6 Which of the following is NOT true in regard to the level of detail estimates should contain? • Question 7 Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. Which of the following methods is he using? • Question 8 The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as
  • 3. • Question 9 Which of the following is NOT one of the bottom-up approaches to estimating project time and cost? • Question 10 Richard is collecting estimates for a house that he will have the funding to build in 12 months. Which of the following factors does Richard need to consider in regard to the quality of these estimates? • Question 11 Which of the following top-down methods is used when projects closely follow past projects in regard to features and costs of those features, and result in costs being assigned by percentages to major segments of the project? • Question 12 Which of the following is a good condition for bottom-up estimating? • Question 13 What is the relationship between organizational culture and estimating? • Question 14 Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with
  • 4. the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of • Question 15 System documentation cannot end until three days after testing has started. This is an example of which kind of lag? • Question 16 Which of the following will correctly calculate the total slack in an activity? • Question 17 Which of the following is NOT one of the basic rules to follow when developing project networks? • Question 18 When translated into a project network, a work package will become • Question 19 Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of
  • 5. • Question 20 Which of the following correctly calculates the late start for an activity? • Question 21 ________ activities must be completed immediately before a particular activity. • Question 22 The backward pass in project network calculations determines all of the following EXCEPT • Question 23 The critical path in a project network is the • Question 24 Which of the following correctly calculates the early finish for an activity? • Question 25 If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a Set 2 • Question 1 The likelihood the original critical path(s) will change once the project is initiated is referred to as • Question 2 Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity
  • 6. 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of • Question 3 The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called • Question 4 The minimum amount of time a dependent activity must be delayed to begin or end is referred to as • Question 5 Which of the following represents an activity on an activity-on-node (AON) project network? • Question 6 ________ activities must be completed immediately before a particular activity. • Question 7 If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
  • 7. • Question 8 Which of the following can be used without coordinating with managers of succeeding activities? • Question 9 An activity that has more than one dependency arrow flowing into it is termed a(n) • Question 10 A(n) _________ activity has more than one dependency arrow flowing from it. • Question 11 Which of the following does NOT help describe a project network? • Question 12 Arrows on an activity-on-node (AON) project network represent • Question 13 Companies are using which of the following for improving the estimating process for future projects? • Question 14 Which of the following describes the consensus method? • Question 15 The process of forecasting or approximating the time and cost of completing project deliverables is called • Question 16 What is the relationship between organizational culture and estimating?
  • 8. • Question 17 Which of the following is a good condition for top-down estimating? • Question 18 In practice, estimating processes are frequently classified as • Question 19 Refining estimates may be necessary for a number of reasons. For example, people working on prototype development needing time to interact with the design engineers after the design is completed is a good example of • Question 20 Refining estimates may be necessary for a number of reasons. For example, resource shortages, in the form of people, equipment, or materials, can extend original estimates. This is a good example of • Question 21 Which of the following is NOT true in regard to the level of detail estimates should contain? • Question 22 Which of the following top-down methods is used when projects closely follow past projects in regard to features and costs of those features, and result in costs being assigned by percentages to major segments of the project?
  • 9. • Question 23 Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach? • Question 24 Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognizing? • Question 25 The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as
  • 10. • Question 23 Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach? • Question 24 Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognizing? • Question 25 The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as