SlideShare a Scribd company logo
DRIVE DIRECTIVE FOR TUNNEL
EXECUTION IN MANIPUR REGION
(NORTH-EAST ) INDIA
By
Mr. Pradeep Goswami
Chief Geologist, Coastal Projects Ltd. Manipur
Presented in Jiribam-Tupul(Manipur) New BG Line,
North-East Frontier Railway
P. Goswami
Introduction
The NATM method has been developed basically in
Austria so its name make use of providing flexible
primary lining in shape of shotcrete, wire mesh, rock
bolts ,lattice girder. In case of weaker rock mass the
use of pipe forepole/pipe roofing is also restricted for
crown support which in turn lead to less over break as
well as ensure safety during the execution. The main
aspect of the approach is dynamic design based on
rock mass classification as well as the in situ
deformation observed. Hence more economical use of
the tunnel support system along with the rational
approach of execution.
P. Goswami
The name New Austrian Tunneling method (NATM) is a
misnomer as it is not a method of tunneling but a
strategy for tunneling which does has a considerable
uniformity and sequence. The NATM is based on
philosophy of ‘Building as you go’ approach with the
following caution. “Not too stiff, nor too flexible
Not too early, nor too late”.
The NATM accomplishes tunnel stabilization by
controlled stress release. The surrounding rock is
thereby transformed from a complex load system to a
self-supporting structure together with the installed
support elements, provided that the detrimental
loosening, resulting in a substantial loss of strength, is
avoided.
P. Goswami
Cont…
The self stabilization by controlled stress release is
achieved by the introduction of the so called
“semi-Rigid Lining” i.e. systematic rock bolting
with the application of shotcrete lining. On one
side, this offers a certain degree of immediate
support, and the flexibility to allow stress release
through radical deformation on the other hand.
The development of shear stress in shotcrete lining
in ached roof is thus reduced to minimum.
P. Goswami
History of NATM
The term New Austrian Tunneling Method
Popularly Known as NATM got its name from
Salzburg (Austria). It was first used by Mr.
Rabcewicz in 1962. It got world wise recognition
in1964. This method has been evolved as a result of
experience gained in Austrian Alpine tunneling
condition. The first use of NATM in soft ground
tunneling is done in Frankfurt metro in 1969. The
basic aim of NATM is for getting stable and
economic tunnel support systems. This method
has been very useful in complex diversified
geological condition where forecasting of the rock
mass is difficult due to rapidly changing geology.
P. Goswami
The Basic principles of NATM
I. Mobilization rock mass strength
II. Shotcrete protection to preserve the load-carrying
capacity of the rock mass,
III. Monitoring the deformation of the excavated rock
mass.
IV. Providing flexibility but active supports, and
V. Closing of invert to form a load-bearing support ring
to control deformation of the rock mass.
P. Goswami
Rock support system based on Rock
Classification
NATM Support Elements
 Fore Poling
 Drilling
 Loading
 Blasting
 Mucking
 Scaling/Chipping
 Face Sealing
 Wire Mesh
 Steel Rib/Lattice
 Shotcrete
 Systematic Rock Bolting
Forepoling
Function:
Forepoling and lagging are support measures
installed in the tunnel longitudinal direction prior
to excavation. They shorten the FREE SPAN of the
unsupported excavation surface. Forepoling and
lagging are only support aids for the excavation
and will have less function after installation of
initial supports(Rib, Shotcrete, Wire Mesh, Rock
bolt etc.).
Forepoling Driving Method
Start drilling out of the center with two booms. Prepare
Grouting Equipment now. As soon as the gap between
the booms is as big that the bucket will fit in, go up with
the loaded forepole bars at the basket and start installing
them, after you have filled up the Drilled-holes with the
grout. As soon as one boom is finished with drilling for
Forepoling it will switch over immediately to drill blasting
holes. The second boom will push forpoling bars into the
deepest depth as possible into the hole, if necessary, than it
will switch over also to drilling for blasting. Amount and
depth of the needed holes find in present site instruction
and follow instructions strictly.
Fixing of Forepoling
P. Goswami
Types of Forepoling
 Pipes (Diameter 1¼ - 1¾ inch)
 Rods ( Diameter around 32mm)
 Self drilling bolts
 Channel Forepoling
P. Goswami
Three different methods of forepoling
can be mentioned-
1. Sub- horizontal jet grouting method
2. Spiling method
3. Pipe roof method
Forepoling is generally employed under the following
conditions :
- The existence of shallow overburden above the
tunnel
- The need to restrict ground surface settlement
- Poor ground conditions
P. Goswami
The Jet grouting method
Jet grouting is used in especially difficult conditions
where both weak soils and thin over burden occur. Jet
grouting is normally used in sandy or gravel
formations. It should be noted that jet grouted,
reinforced column and a drilled or driven pipe ( pipe
roof method) work as a beam, while treated soil in the
spiling method makes the structure function as an
arch.
P. Goswami
The Spiling Method
The Spiling method consists of four different parts:
- Drilled steel pipe
- Grout inside the pipes and in voids outside
- Treated ground by permeation or fracture grouting
- Steel arch supports
P. Goswami
Drilling for Blasting
Both booms start drilling profile out of the top centre,
one left, and one right down to knee hole. After
finished Profile Line start again on the Top centre
drilling from inside to out side horizontal for open up
ASAP gap for basket. Then finish middle and lower
part including Cut. Meanwhile drilling Lower Point,
the bottom area needs to be cleaned out by hand.
After that drill bottom-line. Make sure that all holes
are cleaned nicely to have easy charging after. Depths
of drilling holes find into present site instruction and
follow instruction strictly.
P. Goswami
Drilling in Progress
P. Goswami
Charging
Start charging face at least 15 minutes after start
drilling out a safe position. Charging should be done
always from the top to bottom (above booms, about
safety reasons) charging upto 2m heights should be
done always in safety distance to drilling boom. Take
blasting cord with in the basket and correct detonator
straight after hole is finished charged. As soon as
charging out of the basket is done prepare ignition-
cable and correct electrical dets. Wheel-loader and
Dumper trucks have to be organized before
blasting and placed inside Tunnel.
P. Goswami
Explosive Loading in Progress
P. Goswami
Drilled Hole Ready to Loading
P. Goswami
Mucking
Important during mucking is to have enough Dump Truck
running, so that there is no delay in between mucking
itself while waiting for Trucks. Truck has to be as close as
possible to Muck Pile(Max.10m) waiting trucks have to be
placed close to loading bay to guaranty that the replacing
of unloaded and loaded truck is possible meanwhile the
wheel-loader is loading itself at Muck Pile. Mucking has to
be not lower than the bottom plate of last lattice girder.
Latest after 50% of mucking time it needs to organize
the shotcrete robot and the shotcrete itself, so that the
robot is connect and transits miller is standing
behind robot close to the face when the excavator,
after scaling, is leaving the face.
P. Goswami
Mucking in Progress
P. Goswami
Scaling/Chipping
The Excavator is standing more or less close to the
face. As soon as the wheel-loader is moving out, it’s
going in and start scaling loose rocks down from the
face and preparing the rough profile so that there is no
“under-profile”. Then preparing also a rough stand for
the robot and if necessary a small drainage etc.
P. Goswami
Scaling/Chipping in Progress
P. Goswami
Pre Shotcrete/Face sealing
First the profile and the after needs to be washed down so
that there will be a good connection between rock and
shotcrete. Areas where are over break situations should be
sparyed first with a thin layer(max 10 cm). The shotcrete
needs to be sprayed from the bottom upwards to have a
good abutment for upper shotcrete. After a while it needs
to go back to “over Break” area for the next thin layer. Two
third of the face needs to be sprayed I between as face
support. Pre shotcrete has to finish at least 80% of the total
needed shotcrete, preparing the rough profile as much as
possible, so that after wire mesh and lattice girder the
second shotcrete is more or less only the final polishing.
Maximum thickness of shotcrete read out of present site
instruction.
P. Goswami
Face recently opened sealed
with Shotcrete
P. Goswami
WIRE MESH
FUNCTION:
1. Stabilization of applied shotcrete until setting and
hardening
2. Increase of shear strength
3. Reinforcement of construction joints
4. Reduction and limitation of shotcrete cracking due
to creep and overstressing
5. Preventing dropping of shotcrete portion after
cracking or failing of the lining.
SIZE:
Standard size is 150 x 150 x 6 mm
P. Goswami
Wire mesh placing method
Place wire mesh at the bottom of left hand profile and
connect with overlapping from last wire mesh. Lift up
Jumbo Basket and bring it into the finally position.
Press it close to the rock and tie it with 2 mm wire at
the overlapping. Do the same with the right hand
profile. Last wire mesh needs to be installed on top
with overlapping of three squares to left and right
hand wire mesh. Don’t wire up the three units in
between, just at the overlapping area!! Wire mesh
needs to be movable during the installing of the
lattice girder.
P. Goswami
Wire Mesh
P. Goswami
Wire Mesh Fixing
P. Goswami
Method of Placing Lattice
Girder
Lift up the LG by basket and chain around two meter
and drop it against the face. Release chain install “T-
Piece” at basket and lift up LG exactly to centerline
check correct heights by supervisor. Install
immediately spacers in Top-shoulder and bottom area
hold these position by basket and right-hand shoulder
area should hold in present position by right-hand
boom. Now bring the left-hand shoulder with left-
hand boom into the position given by the supervisor.
Measure from the marked centerline at face the
needed space between centerline and left-hand
bottom plate of L.G.(3.03m).
P. Goswami
Bring bottom plate to exact position and secure it with
stones, timber etc. elevation is not relevant at this
moment. Still hold the position by basket and now
left-hand shoulder area should hold correct position
by left-hand boom. Now bring the right-hand
shoulder with right-hand boom into the position given
by surveyor.
Measure from the marked centerline at face the
needed space between centerline and right-hand
bottom plate of L.G.(3.03m). Bring bottom plate to
exact position and secure it with stones, timber etc.
elevation is not relevant at this moment. Connect the
wiremesh at LG, tie the spacers to the wiremesh .
P. Goswami
Lattice Girder
P. Goswami
Functions of Lattice Girder
1. Steel Rib/Lattice Girder Composite structure of
lattice girder and concrete confined to load
distribution.
2. Carrying of “Green” shotcrete.
3. Profile control
4. Support for forepoling
P. Goswami
SECOND SHOTCRETE
Start spraying at the bottom area of previous lattice
girder move in direction to new lattice girder to secure
the girder at bottom area first. Spray around 1m high,
than switch over to other side of Lattice Girder and do
the same over there. Without doing these, the
possible overloading with shotcrete at one side,will
push the whole Lattice Girder out of direction. Now
spray the area of the old LG and old overlapping first to
secure the new Wiremesh. After that do the same with
the area at new LG.ter the LG is covered nicely with
shotcrete spray the profile from one side bottom to
another side bottom, so that the wiremesh is covered
with shotcrete max. 3 m inside. Make sure that the
thickness of shotcrete is as written in present site
instruction. P. Goswami
FUNCTIONS OF SECOND SHOTCRETE
1. As sealing Shotcrete:
 Avoids first loosening of the surrounding ground.
 Closes joints and prevents fall-downs; so activating
the rock arch.
 Seals the surrounding ground (air sensitive grounds).
2. As main shotcrete (carrying member)
 To carry the load introduced by the ground in the
lining (mainly normal forces, no bending moments
if tunnel shape optimal).
P. Goswami
Shotcreteing in Progress
Rock Bolting
Mark the position of rockbolts with spraypoint. Start
drilling from the top down, so that the basket is able to
work above the boom, as soon as the first hole is
drilled. Depend on what kind of rockbolt needs to be
installed carry on like explained below -
Types of Rock Bolts
SN-Bolt:
Fill up the holes with a stiff grout. Install the rockbolt by hand or by
boom. Install the plate and screw the nut on by hand.
SDR-Bolts:
Install the Rockbolt at the Boom and drill it in the full length, after
that pull back 5 cm to make sure that the grout is able to squeeze out of
the drill bit. Disconnect SDR FROM hammer and do the next SDR the
same way. Now you have to close the gap around the installed SDR
(empty cement bag etc.) so that no Grout is flowing out. Than
Grouting Crew is connecting Grout hose to SDR and is pumping in the
Grout into the SDR until Grout is flowing out through the “cement
bag”. Then place and tie the Nut by spanner. Now pump again until the
Grout will squeeze out between Rock and Plate.
SYSTEMATIC ROCK BOLTING
ANCHOR MORTAR:
1. Rock bolts must be fully grouted(except expansion bolts)
2. Behavior of the anchor mortar is of significance:
 Its ultimate strength must not be reduced to any great
extent as result of displacements, affecting the mortar
during the setting time.
 The quality of the mortar influence considerably the
success of the anchoring system.
MORTAR TYPES:
 Special anchor mortar with expanding agent
 Cement – sand mixture(1:2)
 Net Cement (for injection bolts)
DIRECTION OF ROCK BOLTS
In general the direction of rock bolts shall be radial, i.e.
perpendicular to the lining (±10 degrees). It may deviate from the
general radial direction to cope with unfavorable bedding, etc.
P. Goswami
Systematic Rock Bolting In Progress
with Rocket Boomer
Drive Direction for 1.00M Pull
Sr. No. Item Works Duration Remarks
1 Fore Poling 1 Hour
2 Drilling For
Blasting
1 Hour
3 Charging, Blasting
& Defuming
1 Hour and 40
Minutes
Wheel-loader & Dump Trucks have to be organized
before blasting & placed inside Tunnel.
4 Mucking 3 Hour Latest after 50% of Mucking Time it needs to organize the
shotcrtete Robot and the shotcrete itself, so that the robot is
connect and the Mix Truck is standing behind Robot close to
the Face when the Excavator, after scaling , is leaving the
face.
5 Scaling 20 Minutes
6 Pre
Shotcrete/Face
Scaling
1 Hour As soon as the Pre shotcrete is running wire mesh and Lattice
Girder has to be prepared and placed close to the face,
needed equipment (Jumbo) has to be arranged as close as
possible to Plugbox.
7 Wire Mesh 30 Minutes Don’t wire up the three unites in between, just at the
overlapping area! Wire mesh needs to be movable during the
installing of the lattice girder.
8 Lattice Girder 1 Hour Meanwhile the lattice girder will set up into right position
make sure that the robot is waiting close to the switchbox &
Mixtruck with shotcrete is inside tunnel.
9 Second Shotcrete 30 Minutes During spraying the second layer of shotcrete prepare
Rockbolts, Plates etc. and place everything close to Face.
Make sure that the Equipment like Grout pump and Jumbo is
as close as possible to the switchbox, ready to be connected.
10 Rock Bolting 45 Minutes
Total Duration 10 Hr. 45 Min.
TIME CYCLE PATHS
Start at Point one the Next cycle!!
These directives has to be seen more as Guide Line than as
Directive. It shows the standard Cycle in standard
conditions. Depends on different rock conditions and other
circumstances it may change into other priorities of doing
the cycle. In the summary of experience it will help to set
up a system in doing tunnel the NEW AUSTRIAN
TUNNELING METHOD.
CHIEF ENGINEERING GEOLOGIST
PRADEEP GOSWAMI
Coastal Projects Ltd.
MANIPUR (India)
THANK YOU
P. Goswami

More Related Content

What's hot

tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machine
Naquiakhter
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
rutuldave
 
Tunneling
TunnelingTunneling
Tunneling
Safdar Ali
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
SuMitt MaNdla
 
Rock bolt and anchoring
Rock bolt and anchoringRock bolt and anchoring
Rock bolt and anchoring
Amit Jagtap
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Hitesh Khanna
 
rock anchor methodology
rock anchor methodologyrock anchor methodology
rock anchor methodologyGautam Sharma
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnelling
TunnellingTunnelling
Tunnelling
Usama Zia
 
Tunnel boring machine ppt
Tunnel boring machine pptTunnel boring machine ppt
Tunnel boring machine ppt
RohitGhosh42
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
Mahesh Raj Bhatt
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
Himanshu Batra
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
Jyoti Khatiwada
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
akjain_mkt
 
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Hamed Zarei
 
sylvester prop withdrawal underground mining
 sylvester prop withdrawal underground mining sylvester prop withdrawal underground mining
sylvester prop withdrawal underground mining
Aditya Verma
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
kamariya keyur
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
GAURAV. H .TANDON
 

What's hot (20)

tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machine
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Tunneling
TunnelingTunneling
Tunneling
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Rock bolt and anchoring
Rock bolt and anchoringRock bolt and anchoring
Rock bolt and anchoring
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
rock anchor methodology
rock anchor methodologyrock anchor methodology
rock anchor methodology
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Loads on tunnels (1)
Loads on tunnels (1)Loads on tunnels (1)
Loads on tunnels (1)
 
Tunnel boring machine ppt
Tunnel boring machine pptTunnel boring machine ppt
Tunnel boring machine ppt
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
 
Rock burst presentation
Rock burst presentationRock burst presentation
Rock burst presentation
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
 
sylvester prop withdrawal underground mining
 sylvester prop withdrawal underground mining sylvester prop withdrawal underground mining
sylvester prop withdrawal underground mining
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 

Viewers also liked

Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge Hakkim Shajahan
 
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiUrsachi Răzvan
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
Grace Henry
 
mats underground mining training report
mats underground mining training reportmats underground mining training report
mats underground mining training report
Vijayant Singh
 
Preliminary design for natm tunnel support in soil
Preliminary design for natm tunnel support in soilPreliminary design for natm tunnel support in soil
Preliminary design for natm tunnel support in soil
mukulkuriyal
 
CCL Points of View on Leadership Development Through the Lens of Relational L...
CCL Points of View on Leadership Development Through the Lens of Relational L...CCL Points of View on Leadership Development Through the Lens of Relational L...
CCL Points of View on Leadership Development Through the Lens of Relational L...
Charles Palus
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesVR M
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesVR M
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
Austrian Standards
 
Stability analysis of rigid frames
Stability analysis of rigid framesStability analysis of rigid frames
Stability analysis of rigid framesor2517
 
Struc lec. no.444
Struc lec. no.444Struc lec. no.444
Struc lec. no.444LovelyRomio
 
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
SHUBHAM DABHADE
 
Q-Value (Q method handbook by NGI)
Q-Value (Q method handbook by NGI)Q-Value (Q method handbook by NGI)
Q-Value (Q method handbook by NGI)
zeeshan Ahmad
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
Shashank Gaurav
 
Lecture 2 s.s. iii continuare Design of Steel Structures - Faculty of Civil E...
Lecture 2 s.s. iii continuare Design of Steel Structures - Faculty of Civil E...Lecture 2 s.s. iii continuare Design of Steel Structures - Faculty of Civil E...
Lecture 2 s.s. iii continuare Design of Steel Structures - Faculty of Civil E...Ursachi Răzvan
 
Tensile structures for architects
Tensile structures for architectsTensile structures for architects
Tensile structures for architects
Deepak KUMAR
 
Portal frame 1
Portal  frame 1Portal  frame 1
Portal frame 1
Est
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
Akshay Gawade
 

Viewers also liked (20)

Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge
 
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 6 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
 
mats underground mining training report
mats underground mining training reportmats underground mining training report
mats underground mining training report
 
Preliminary design for natm tunnel support in soil
Preliminary design for natm tunnel support in soilPreliminary design for natm tunnel support in soil
Preliminary design for natm tunnel support in soil
 
CCL Points of View on Leadership Development Through the Lens of Relational L...
CCL Points of View on Leadership Development Through the Lens of Relational L...CCL Points of View on Leadership Development Through the Lens of Relational L...
CCL Points of View on Leadership Development Through the Lens of Relational L...
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal mines
 
Reduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal minesReduction of risk from roof and side fall in Indian coal mines
Reduction of risk from roof and side fall in Indian coal mines
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
 
Stability analysis of rigid frames
Stability analysis of rigid framesStability analysis of rigid frames
Stability analysis of rigid frames
 
Struc lec. no.444
Struc lec. no.444Struc lec. no.444
Struc lec. no.444
 
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
 
Q-Value (Q method handbook by NGI)
Q-Value (Q method handbook by NGI)Q-Value (Q method handbook by NGI)
Q-Value (Q method handbook by NGI)
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Lecture 2 s.s. iii continuare Design of Steel Structures - Faculty of Civil E...
Lecture 2 s.s. iii continuare Design of Steel Structures - Faculty of Civil E...Lecture 2 s.s. iii continuare Design of Steel Structures - Faculty of Civil E...
Lecture 2 s.s. iii continuare Design of Steel Structures - Faculty of Civil E...
 
Tensile structures for architects
Tensile structures for architectsTensile structures for architects
Tensile structures for architects
 
Portal frame 1
Portal  frame 1Portal  frame 1
Portal frame 1
 
Tensile
TensileTensile
Tensile
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 

Similar to NATM-Time cycle presentation (2)

Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
Er.Sunil Wasade
 
Shaft boring methods
Shaft boring methodsShaft boring methods
Shaft boring methods
Rishabh Ranjan
 
Grp installation procedure
Grp installation procedureGrp installation procedure
Grp installation procedure
kaustav mukherjee
 
DMC piling
DMC pilingDMC piling
DMC piling
Sagnik Datta
 
2.pile foundation 2.ppt
2.pile foundation 2.ppt2.pile foundation 2.ppt
2.pile foundation 2.ppt
DAYANANDWANDRE
 
Packer milling
Packer millingPacker milling
Packer milling
Luciano Oscar Fucello
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
ssuser480182
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
LingWei11
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
ChinnuNinan
 
Ash creation report
Ash creation reportAsh creation report
Ash creation report
AshwinPrajapat
 
Well abandonment process procedures
Well abandonment process proceduresWell abandonment process procedures
Well abandonment process procedures
Drilling Manual
 
Summer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman NigamSummer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman Nigam
Raju kumar Gautam
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
jamali husain
 
High Wall Mining
High Wall MiningHigh Wall Mining
High Wall Mining
Prateek Sharma
 
Shrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat StopingShrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat Stoping
Geology Department, Faculty of Science, Tanta University
 
Tunnelling Methods.pdf
Tunnelling Methods.pdfTunnelling Methods.pdf
Tunnelling Methods.pdf
SuryoNegoro3
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
Onur Tuncay
 
Bored piles production method
Bored piles   production methodBored piles   production method
Bored piles production methodNguyen Bao
 
Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case studyMD.Suresh Kumar
 

Similar to NATM-Time cycle presentation (2) (20)

Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
 
Shaft boring methods
Shaft boring methodsShaft boring methods
Shaft boring methods
 
Grp installation procedure
Grp installation procedureGrp installation procedure
Grp installation procedure
 
DMC Piling
DMC PilingDMC Piling
DMC Piling
 
DMC piling
DMC pilingDMC piling
DMC piling
 
2.pile foundation 2.ppt
2.pile foundation 2.ppt2.pile foundation 2.ppt
2.pile foundation 2.ppt
 
Packer milling
Packer millingPacker milling
Packer milling
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
 
Ash creation report
Ash creation reportAsh creation report
Ash creation report
 
Well abandonment process procedures
Well abandonment process proceduresWell abandonment process procedures
Well abandonment process procedures
 
Summer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman NigamSummer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman Nigam
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
High Wall Mining
High Wall MiningHigh Wall Mining
High Wall Mining
 
Shrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat StopingShrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat Stoping
 
Tunnelling Methods.pdf
Tunnelling Methods.pdfTunnelling Methods.pdf
Tunnelling Methods.pdf
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
 
Bored piles production method
Bored piles   production methodBored piles   production method
Bored piles production method
 
Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case study
 

NATM-Time cycle presentation (2)

  • 1. DRIVE DIRECTIVE FOR TUNNEL EXECUTION IN MANIPUR REGION (NORTH-EAST ) INDIA By Mr. Pradeep Goswami Chief Geologist, Coastal Projects Ltd. Manipur Presented in Jiribam-Tupul(Manipur) New BG Line, North-East Frontier Railway P. Goswami
  • 2. Introduction The NATM method has been developed basically in Austria so its name make use of providing flexible primary lining in shape of shotcrete, wire mesh, rock bolts ,lattice girder. In case of weaker rock mass the use of pipe forepole/pipe roofing is also restricted for crown support which in turn lead to less over break as well as ensure safety during the execution. The main aspect of the approach is dynamic design based on rock mass classification as well as the in situ deformation observed. Hence more economical use of the tunnel support system along with the rational approach of execution. P. Goswami
  • 3. The name New Austrian Tunneling method (NATM) is a misnomer as it is not a method of tunneling but a strategy for tunneling which does has a considerable uniformity and sequence. The NATM is based on philosophy of ‘Building as you go’ approach with the following caution. “Not too stiff, nor too flexible Not too early, nor too late”. The NATM accomplishes tunnel stabilization by controlled stress release. The surrounding rock is thereby transformed from a complex load system to a self-supporting structure together with the installed support elements, provided that the detrimental loosening, resulting in a substantial loss of strength, is avoided. P. Goswami
  • 4. Cont… The self stabilization by controlled stress release is achieved by the introduction of the so called “semi-Rigid Lining” i.e. systematic rock bolting with the application of shotcrete lining. On one side, this offers a certain degree of immediate support, and the flexibility to allow stress release through radical deformation on the other hand. The development of shear stress in shotcrete lining in ached roof is thus reduced to minimum. P. Goswami
  • 5. History of NATM The term New Austrian Tunneling Method Popularly Known as NATM got its name from Salzburg (Austria). It was first used by Mr. Rabcewicz in 1962. It got world wise recognition in1964. This method has been evolved as a result of experience gained in Austrian Alpine tunneling condition. The first use of NATM in soft ground tunneling is done in Frankfurt metro in 1969. The basic aim of NATM is for getting stable and economic tunnel support systems. This method has been very useful in complex diversified geological condition where forecasting of the rock mass is difficult due to rapidly changing geology. P. Goswami
  • 6. The Basic principles of NATM I. Mobilization rock mass strength II. Shotcrete protection to preserve the load-carrying capacity of the rock mass, III. Monitoring the deformation of the excavated rock mass. IV. Providing flexibility but active supports, and V. Closing of invert to form a load-bearing support ring to control deformation of the rock mass. P. Goswami
  • 7. Rock support system based on Rock Classification
  • 8. NATM Support Elements  Fore Poling  Drilling  Loading  Blasting  Mucking  Scaling/Chipping  Face Sealing  Wire Mesh  Steel Rib/Lattice  Shotcrete  Systematic Rock Bolting
  • 9. Forepoling Function: Forepoling and lagging are support measures installed in the tunnel longitudinal direction prior to excavation. They shorten the FREE SPAN of the unsupported excavation surface. Forepoling and lagging are only support aids for the excavation and will have less function after installation of initial supports(Rib, Shotcrete, Wire Mesh, Rock bolt etc.).
  • 10. Forepoling Driving Method Start drilling out of the center with two booms. Prepare Grouting Equipment now. As soon as the gap between the booms is as big that the bucket will fit in, go up with the loaded forepole bars at the basket and start installing them, after you have filled up the Drilled-holes with the grout. As soon as one boom is finished with drilling for Forepoling it will switch over immediately to drill blasting holes. The second boom will push forpoling bars into the deepest depth as possible into the hole, if necessary, than it will switch over also to drilling for blasting. Amount and depth of the needed holes find in present site instruction and follow instructions strictly.
  • 12. Types of Forepoling  Pipes (Diameter 1¼ - 1¾ inch)  Rods ( Diameter around 32mm)  Self drilling bolts  Channel Forepoling P. Goswami
  • 13. Three different methods of forepoling can be mentioned- 1. Sub- horizontal jet grouting method 2. Spiling method 3. Pipe roof method Forepoling is generally employed under the following conditions : - The existence of shallow overburden above the tunnel - The need to restrict ground surface settlement - Poor ground conditions P. Goswami
  • 14. The Jet grouting method Jet grouting is used in especially difficult conditions where both weak soils and thin over burden occur. Jet grouting is normally used in sandy or gravel formations. It should be noted that jet grouted, reinforced column and a drilled or driven pipe ( pipe roof method) work as a beam, while treated soil in the spiling method makes the structure function as an arch. P. Goswami
  • 15. The Spiling Method The Spiling method consists of four different parts: - Drilled steel pipe - Grout inside the pipes and in voids outside - Treated ground by permeation or fracture grouting - Steel arch supports P. Goswami
  • 16. Drilling for Blasting Both booms start drilling profile out of the top centre, one left, and one right down to knee hole. After finished Profile Line start again on the Top centre drilling from inside to out side horizontal for open up ASAP gap for basket. Then finish middle and lower part including Cut. Meanwhile drilling Lower Point, the bottom area needs to be cleaned out by hand. After that drill bottom-line. Make sure that all holes are cleaned nicely to have easy charging after. Depths of drilling holes find into present site instruction and follow instruction strictly. P. Goswami
  • 18. Charging Start charging face at least 15 minutes after start drilling out a safe position. Charging should be done always from the top to bottom (above booms, about safety reasons) charging upto 2m heights should be done always in safety distance to drilling boom. Take blasting cord with in the basket and correct detonator straight after hole is finished charged. As soon as charging out of the basket is done prepare ignition- cable and correct electrical dets. Wheel-loader and Dumper trucks have to be organized before blasting and placed inside Tunnel. P. Goswami
  • 19. Explosive Loading in Progress P. Goswami
  • 20. Drilled Hole Ready to Loading P. Goswami
  • 21. Mucking Important during mucking is to have enough Dump Truck running, so that there is no delay in between mucking itself while waiting for Trucks. Truck has to be as close as possible to Muck Pile(Max.10m) waiting trucks have to be placed close to loading bay to guaranty that the replacing of unloaded and loaded truck is possible meanwhile the wheel-loader is loading itself at Muck Pile. Mucking has to be not lower than the bottom plate of last lattice girder. Latest after 50% of mucking time it needs to organize the shotcrete robot and the shotcrete itself, so that the robot is connect and transits miller is standing behind robot close to the face when the excavator, after scaling, is leaving the face. P. Goswami
  • 23. Scaling/Chipping The Excavator is standing more or less close to the face. As soon as the wheel-loader is moving out, it’s going in and start scaling loose rocks down from the face and preparing the rough profile so that there is no “under-profile”. Then preparing also a rough stand for the robot and if necessary a small drainage etc. P. Goswami
  • 25. Pre Shotcrete/Face sealing First the profile and the after needs to be washed down so that there will be a good connection between rock and shotcrete. Areas where are over break situations should be sparyed first with a thin layer(max 10 cm). The shotcrete needs to be sprayed from the bottom upwards to have a good abutment for upper shotcrete. After a while it needs to go back to “over Break” area for the next thin layer. Two third of the face needs to be sprayed I between as face support. Pre shotcrete has to finish at least 80% of the total needed shotcrete, preparing the rough profile as much as possible, so that after wire mesh and lattice girder the second shotcrete is more or less only the final polishing. Maximum thickness of shotcrete read out of present site instruction. P. Goswami
  • 26. Face recently opened sealed with Shotcrete P. Goswami
  • 27. WIRE MESH FUNCTION: 1. Stabilization of applied shotcrete until setting and hardening 2. Increase of shear strength 3. Reinforcement of construction joints 4. Reduction and limitation of shotcrete cracking due to creep and overstressing 5. Preventing dropping of shotcrete portion after cracking or failing of the lining. SIZE: Standard size is 150 x 150 x 6 mm P. Goswami
  • 28. Wire mesh placing method Place wire mesh at the bottom of left hand profile and connect with overlapping from last wire mesh. Lift up Jumbo Basket and bring it into the finally position. Press it close to the rock and tie it with 2 mm wire at the overlapping. Do the same with the right hand profile. Last wire mesh needs to be installed on top with overlapping of three squares to left and right hand wire mesh. Don’t wire up the three units in between, just at the overlapping area!! Wire mesh needs to be movable during the installing of the lattice girder. P. Goswami
  • 31. Method of Placing Lattice Girder Lift up the LG by basket and chain around two meter and drop it against the face. Release chain install “T- Piece” at basket and lift up LG exactly to centerline check correct heights by supervisor. Install immediately spacers in Top-shoulder and bottom area hold these position by basket and right-hand shoulder area should hold in present position by right-hand boom. Now bring the left-hand shoulder with left- hand boom into the position given by the supervisor. Measure from the marked centerline at face the needed space between centerline and left-hand bottom plate of L.G.(3.03m). P. Goswami
  • 32. Bring bottom plate to exact position and secure it with stones, timber etc. elevation is not relevant at this moment. Still hold the position by basket and now left-hand shoulder area should hold correct position by left-hand boom. Now bring the right-hand shoulder with right-hand boom into the position given by surveyor. Measure from the marked centerline at face the needed space between centerline and right-hand bottom plate of L.G.(3.03m). Bring bottom plate to exact position and secure it with stones, timber etc. elevation is not relevant at this moment. Connect the wiremesh at LG, tie the spacers to the wiremesh . P. Goswami
  • 34. Functions of Lattice Girder 1. Steel Rib/Lattice Girder Composite structure of lattice girder and concrete confined to load distribution. 2. Carrying of “Green” shotcrete. 3. Profile control 4. Support for forepoling P. Goswami
  • 35. SECOND SHOTCRETE Start spraying at the bottom area of previous lattice girder move in direction to new lattice girder to secure the girder at bottom area first. Spray around 1m high, than switch over to other side of Lattice Girder and do the same over there. Without doing these, the possible overloading with shotcrete at one side,will push the whole Lattice Girder out of direction. Now spray the area of the old LG and old overlapping first to secure the new Wiremesh. After that do the same with the area at new LG.ter the LG is covered nicely with shotcrete spray the profile from one side bottom to another side bottom, so that the wiremesh is covered with shotcrete max. 3 m inside. Make sure that the thickness of shotcrete is as written in present site instruction. P. Goswami
  • 36. FUNCTIONS OF SECOND SHOTCRETE 1. As sealing Shotcrete:  Avoids first loosening of the surrounding ground.  Closes joints and prevents fall-downs; so activating the rock arch.  Seals the surrounding ground (air sensitive grounds). 2. As main shotcrete (carrying member)  To carry the load introduced by the ground in the lining (mainly normal forces, no bending moments if tunnel shape optimal). P. Goswami
  • 38. Rock Bolting Mark the position of rockbolts with spraypoint. Start drilling from the top down, so that the basket is able to work above the boom, as soon as the first hole is drilled. Depend on what kind of rockbolt needs to be installed carry on like explained below -
  • 39. Types of Rock Bolts SN-Bolt: Fill up the holes with a stiff grout. Install the rockbolt by hand or by boom. Install the plate and screw the nut on by hand. SDR-Bolts: Install the Rockbolt at the Boom and drill it in the full length, after that pull back 5 cm to make sure that the grout is able to squeeze out of the drill bit. Disconnect SDR FROM hammer and do the next SDR the same way. Now you have to close the gap around the installed SDR (empty cement bag etc.) so that no Grout is flowing out. Than Grouting Crew is connecting Grout hose to SDR and is pumping in the Grout into the SDR until Grout is flowing out through the “cement bag”. Then place and tie the Nut by spanner. Now pump again until the Grout will squeeze out between Rock and Plate.
  • 40. SYSTEMATIC ROCK BOLTING ANCHOR MORTAR: 1. Rock bolts must be fully grouted(except expansion bolts) 2. Behavior of the anchor mortar is of significance:  Its ultimate strength must not be reduced to any great extent as result of displacements, affecting the mortar during the setting time.  The quality of the mortar influence considerably the success of the anchoring system. MORTAR TYPES:  Special anchor mortar with expanding agent  Cement – sand mixture(1:2)  Net Cement (for injection bolts)
  • 41. DIRECTION OF ROCK BOLTS In general the direction of rock bolts shall be radial, i.e. perpendicular to the lining (±10 degrees). It may deviate from the general radial direction to cope with unfavorable bedding, etc. P. Goswami
  • 42. Systematic Rock Bolting In Progress with Rocket Boomer
  • 43. Drive Direction for 1.00M Pull Sr. No. Item Works Duration Remarks 1 Fore Poling 1 Hour 2 Drilling For Blasting 1 Hour 3 Charging, Blasting & Defuming 1 Hour and 40 Minutes Wheel-loader & Dump Trucks have to be organized before blasting & placed inside Tunnel. 4 Mucking 3 Hour Latest after 50% of Mucking Time it needs to organize the shotcrtete Robot and the shotcrete itself, so that the robot is connect and the Mix Truck is standing behind Robot close to the Face when the Excavator, after scaling , is leaving the face. 5 Scaling 20 Minutes 6 Pre Shotcrete/Face Scaling 1 Hour As soon as the Pre shotcrete is running wire mesh and Lattice Girder has to be prepared and placed close to the face, needed equipment (Jumbo) has to be arranged as close as possible to Plugbox. 7 Wire Mesh 30 Minutes Don’t wire up the three unites in between, just at the overlapping area! Wire mesh needs to be movable during the installing of the lattice girder. 8 Lattice Girder 1 Hour Meanwhile the lattice girder will set up into right position make sure that the robot is waiting close to the switchbox & Mixtruck with shotcrete is inside tunnel. 9 Second Shotcrete 30 Minutes During spraying the second layer of shotcrete prepare Rockbolts, Plates etc. and place everything close to Face. Make sure that the Equipment like Grout pump and Jumbo is as close as possible to the switchbox, ready to be connected. 10 Rock Bolting 45 Minutes Total Duration 10 Hr. 45 Min.
  • 45. Start at Point one the Next cycle!! These directives has to be seen more as Guide Line than as Directive. It shows the standard Cycle in standard conditions. Depends on different rock conditions and other circumstances it may change into other priorities of doing the cycle. In the summary of experience it will help to set up a system in doing tunnel the NEW AUSTRIAN TUNNELING METHOD. CHIEF ENGINEERING GEOLOGIST PRADEEP GOSWAMI Coastal Projects Ltd. MANIPUR (India)