SlideShare a Scribd company logo
1 of 6
Download to read offline
Nicholson Construction Company
12 McClane Street
Cuddy, PA 15031
Telephone: 412-221-4500
Facsimile: 412-221-3127
Rehabilitation of an Existing Mechanically Stabilized
Earth Wall Using Soil Nails
by
Daniel A. Thome, P.E.
Nicholson Construction Company, Kalamazoo, Michigan
Robert C. Janke P.E., S.E.
Applied Technologies, Inc., Lake Villa, Illinois and Brookfield, Wisconsin
Presented at:
DFI’s 30th Annual Conference on Deep Foundations
Chicago, Illinois
September 22-24, 2005
05-03-147
REHABILITATION OF AN EXISTING MECHANICALLY STABILIZED
EARTH WALL USING SOIL NAILS
Daniel A. Thome P.E., Nicholson Construction Company, Midwest District Office, Kalamazoo, Michigan, USA
Robert C. Janke P.E., S.E., Applied Technologies, Inc., Lake Villa, Illinois and Brookfield, Wisconsin, USA
Installation of permanent soil nails through distressed mechanically stabilized earth
retaining walls is a cost effective and aesthetically pleasing solution when using the
appropriate equipment and drilling methods for installation. A forensic investigation was
performed on an existing mechanically stabilized earth retaining wall to determine the
possible causes for the excessive horizontal displacements and visual structural flaws
found along a portion of the wall. Reports concluded that the visual shifting was due to a
number of factors including improper drainage in the vicinity of the wall and unsuitable
compaction of the backfill material. Conceptual designs were proposed to the owner and
the installation of permanent soil nails through the existing precast panels was
determined to be the most practical solution. A total of ninety-three permanent soil nails
were installed to lengths of up to 40 feet (12 m) through sand backfill and silty clay fill
using a hydraulic rotary percussion drill attached to a tract mounted excavator.
Introduction
The Illinois State Toll Highway Authority awarded
Contract RR-03-5144 in the summer of 2004.
Construction work for the project consisted of the
rehabilitation of two existing concrete culverts and
approximately 100 linear feet (31 m) of mechanically
stabilized earth (MSE) retaining wall. The retaining
wall is located below the southbound lanes of the
Tri-State Tollway near the intersection of Federal
Highway 41 in Wadsworth, Illinois as shown in
Figure 1.
Figure 1 Project Location Map
Reports were prepared by Applied Technologies in
cooperation with Giles Engineering Associates to
determine the condition of the MSE wall and
recommended conceptual designs to extend the
service life of the wall.
Nicholson Construction Company (Nicholson) was
selected as the design-build geotechnical
subcontractor to install the recommended
permanent soil nails through the existing precast
concrete panels of the MSE wall. Rehabilitation of
the wall involved the installation of ninety-three
permanent soil nails through the existing wall, along
with soil nail verification tests and proof tests on
production nails.
Background History
Construction of the MSE retaining wall was
completed in 1982. The total length of the MSE wall
is 740 feet (226 m) along the footprint of a horizontal
curve, with a radius of 1896 feet (578 m). The
maximum wall height is 24 feet (7 m) with the grade
in front of the wall being approximately 4 feet (1.2 m)
above the bottom of footing elevation. Galvanized
steel reinforcement straps either 14 feet (4.3 m) or
17 feet (5.2 m) long connect to the back of the
precast concrete panels.
A portion of the MSE wall was built directly over an
existing box culvert, 10 feet (3 m) wide and 7 feet
(2.1 m) high. An inlet for the highway was
Project Location
constructed directly behind the top of the MSE wall
and connected to a 15 inch (381 mm) diameter
storm sewer that ran perpendicular and away from
the retaining wall.
According to the wall manufacturer, displacements
were noted shortly after construction of the MSE wall
directly over the existing culvert. Unfortunately, a
monitoring system was not put into place and no
corrective measures were implemented on the wall
after the displacement had occurred. Refer to
Figure 2 for a typical cross sectional profile near
station 1346+00.
Geological Conditions
Backfill material for the MSE retaining wall consists
of fine to coarse sand and extends to the bottom of
the MSE wall panels. The sand backfill is very loose
to loose in the vicinity of the failing wall section and
medium dense within the remaining sections.
Stiff to very stiff silty clay fill was encountered below
the MSE wall backfill and within the retained soils
behind the retaining wall. The depths of this soil
ranged from 19 feet (5.8 m) to 33 feet (10 m) below
the ground surface. A very stiff to hard natural silty
clay soil was reported below the silty clay fill to the
maximum depths explored. A perched groundwater
table was determined to be near the ground surface
in front of the displaced MSE wall section. Figure 2
shows a typical geologic section for the MSE wall
near station 1346+00.
Figure 2 Typical Cross Section - Station 1346+00
Evaluation of Existing Wall
In 2003, Applied Technologies in cooperation with
Giles Engineering Associates prepared
documentation describing the condition of the
existing MSE retaining wall. The reports
summarized flaws within and surrounding the
retention system that seemed to be concentrated
between stations 1346+00 and 1347+00.
The following key information was contained within
the forensic reports:
• Approximately 2 to 11 inches (51 to 279
mm) of horizontal displacement was
reported within the height of the wall.
• The existing 15 inch (381 mm) storm sewer
pipe was obstructed with debris, causing
perched water near the ground surface in
front of the wall.
• Sand backfill accumulated in front of the wall
due to loss of ground within the MSE wall
backfill.
• Very loose to loose sand backfill was
sampled within the failing section while
medium dense sand backfill was
encountered in the remainder of the wall.
• Vehicular collision with concrete parapet
occurred directly above the failing wall
section.
• Concrete panels were grossly misaligned
due to excessive horizontal displacements
causing spalling at the edges near vertical
shear pins.
• Notable settlement of the Tri-State shoulder
above the wall indicated redistribution of soil
within the sand backfill.
Photo 1 Pre-Construction Condition
Exist Culvert T-13-15
Sand Backfill
Silty
Clay
Fill
14 to 17 Feet
(4.3 to 5.2 m)
Perched
Water
Table
Causes of the distress in the MSE wall were
inconclusive in the reports, but undoubtedly a
combination of the above factors caused the
horizontal displacements.
Conceptual Design Suggestions
Applied Technologies narrowed down a compiled list
of repair options to four, based on economics,
aesthetics and constructability. In all scenarios the
structural elements of the existing MSE retaining
wall were to be ignored. Option A-1 consisted of
installing one permanent soil nail per existing panel
and shooting a reinforced shotcrete facing in front of
the wall to adequately transfer the punching shear
force of the soil nails. Option A-2 was similar to
option A-1 with the exception of using a new
reinforced concrete wall rather than reinforced
shotcrete for punching shear resistance.
Options B and C entailed the installation of an
anchored soldier pile wall in front of the existing wall
using either sheet piling (option B) or precast
concrete (option C) as lagging to resist the
horizontal earth pressures.
Option A-2 was chosen because the cast-in-place
reinforced concrete maintained the existing
appearance of the MSE wall. Also, it was more
economical to build option A-2, when compared to
option A-1, based on preliminary cost estimates
performed by the owner’s engineer. Options B and
C were eliminated due to aesthetics and vibration
concerns based on conversations with the Illinois
State Toll Highway Authority.
Soil Nail Design
There were three objectives for the soil nail wall
design. One was to perform an internal wall
analysis to determine required soil nail lengths for
the existing ground conditions and wall geometry.
Another was to confirm adequate punching shear
resistance of the existing concrete panels for
temporary face support along with verifying the
design for bearing plate and studs. Finally, a global
stability analysis for bearing capacity, overturning
and sliding was performed.
Three design sections were used to economize the
nail lengths for various wall heights and access
constraints. The heights of the three design
sections were 19 feet (5.8 m), 22 feet (6.7 m) and 23
feet (7 m). The 22 foot (6.7m) high section had
horizontal soil nails over the existing box culvert.
The horizontal and vertical spacing for the soil nails
equaled the average dimension between precast
concrete panels, 4 feet 11 inches (1.5 m).
Unit weights and friction angles for all three soil
types were obtained from the design parameters in
the project specifications and checked against the
soil borings. Ultimate pullout resistances for each
soil type were chosen based on the project borings
and the geotechnical subcontractor’s experience.
Table 1 provides a summary of the design
parameters for each soil type.
Table 1 Summary of Soil Design Parameters
Soil Type
Friction
Angle
degrees
Unit
Weight
pcf
(kN/m
3
)
Ultimate
Pullout
kips/foot
(kN/m)
Allowable
Bearing
Pressure
psf
(kN/m
2
)
Sand
Backfill
34
125
(19.6)
5.3
(77.3)
N/A
Silty Clay
Fill
(Behind
Wall)
30
125
(19.6)
2.6
(37.9)
N/A
Silty Clay
Fill
(Below
Wall)
30 N/A N/A
5000
(239)
The GoldNail program was used to analyze each
design section for internal stability. GoldNail is a
slope stability model based on satisfying overall
limiting equilibrium defined by circular slip surfaces.
Steel area and yield stress are input into the
GoldNail program along with the proposed wall
geometry, reinforcement locations and soil
strengths.
Lengths of nails for each design section were
determined through program iterations. As per the
project specifications, a factor of safety for internal
stability of one and a half and a factor of safety for
soil nail pullout resistance of two were used as input
parameters for the analyses. Existing reinforcement
straps were ignored in the calculations as stated in
the project specifications.
Structural calculations were performed to confirm the
adequacy of the wall facing. Temporary punching
shear capacity of the precast concrete panels was
confirmed. Then, computations were completed for
the permanent punching shear capacity of the
headed stud connection with the reinforced concrete
facing. Lastly, the tensile strength of the studs was
verified.
A global stability analysis was also performed to
conclude that a factor of safety of one and a half or
greater existed for the revised retention system in
regards to overturning, sliding and bearing capacity.
Results showed that adequate safety factors were
indeed present for the potential external failure
modes.
Soil Nail Testing
Verification test nails were required according to the
project specifications. Test nails would be installed
toward the bottom of the existing wall for ease in
setting up and testing. Verification test nail #1 was
bonded into the silty clay fill with an unbonded
length within the sand backfill. Verification test nail
#2 was bonded only in the sand backfill material.
Test results from both verification nails showed a
lower ultimate pullout resistance than used in the
initial soil nail design.
The geotechnical subcontractor reviewed the test
results and had the following thoughts regarding the
unexpectedly low ultimate pullout resistances.
• Arching caused by the existing
reinforcement straps from the MSE wall was
reducing the confining stress to values
below overburden pressures.
• Lower confining stresses limited the ability to
effectively pressure grout the soil nails.
• Test nails installed near the bottom of the
existing MSE wall experienced lower pullout
capacities due to saturated/perched
groundwater conditions.
• The ultimate pullout resistance values for
the sand backfill and clay fill were
overestimated during the initial design based
on the existing soil conditions.
Three additional verification tests were performed to
confirm the lower ultimate pullout resistances in the
sand backfill and silty clay fill. Results of the
supplemental verification tests confirmed the lower
ultimate pullout resistances in both of the soil
stratums. They also confirmed that there was
indeed a saturated silty clay fill layer below the MSE
wall, which resulted in a significantly lower pullout
resistance for the bottom row of test nails. Table 2
summarizes the revised ultimate pullout resistances
based on the verification testing.
Results from the verification tests were compiled and
the soil nail wall design was reanalyzed. Ultimate
pullout resistances for the sand backfill and silty clay
fill were revised with the saturated silty clay fill added
to the analysis to represent the soil below the wall.
Revised soil nail lengths increased from the original
design by approximately thirty-three percent.
Table 2 Revised Ultimate Pullout Resistances
Soil Type
Initial Ultimate
Pullout
kips/foot
(kN/m)
Revised
Ultimate
Pullout
kips/foot
(kN/m)
Sand Backfill
5.3
(77.3)
3.3
(48.2)
Silty Clay Fill
(Behind Wall)
2.6
(37.9)
2.4
(35.0)
Silty Clay Fill
(Below Wall)
N/A
1.3
(19.0)
Construction
Project specific challenges for the soil nailing
operation included entry points approximately 20
feet (6.1 m) above working bench elevation.
Additional installation concerns were soil nails
through granular backfill and potential conflicts with
utilities, existing reinforcement straps and the
concrete box culvert located directly underneath the
wall.
The geotechnical subcontractor determined that a
conventional drill rig would not be able to install a
majority of the soil nails on this project due to the
extreme heights of some of their entry points. A
hydraulic excavator mounted drill was utilized in
order to install the higher soil nails without special
modifications being made to the work bench. The
excavator mounted drill was a rotary percussion tool
mounted on a mast which attached to a tract
mounted excavator. The versatility and reach of the
excavator drill mast allowed for proper soil nail
installation.
Photo 2 Soil Nail Installation
Existing granular backfill underneath an active
highway created concern for ground loss. The
geotechnical subcontractor decided to use the
duplex drilling method for soil nail installation. A
major advantage to duplex drilling is that intimate
contact between the bore hole and outer casing is
achieved, minimizing ground loss. Duplex drilling
uses an inner rod and an outer casing to
simultaneously advance the bore hole. Water or air
is circulated down through the center of the inner
drill rod and returns upward through the annulus
between the drill rod and outer casing removing drill
cuttings.
The construction site posed a few geometrical
constraints for the soil nail operation. An existing
fiber optic line ran across the bottom row of soil
nails. The fiber optic line was completely exposed
prior to commencing soil nail operations and
temporarily encased in a plastic sleeve during
construction operations. Particular soil nail locations
were adjusted in the field to miss the fiber optic line
with the drill equipment.
A typical precast concrete facing for MSE retaining
walls will have the reinforcement straps connect at
up to six evenly spaced locations to the back of the
panel. The reinforcement straps from the MSE wall
were avoided by centering the soil nails within the
individual concrete panels and allowing for only
vertical inclination where appropriate.
An existing concrete culvert T-13-15, which was to
be rehabilitated, was located directly below the
bottom of the existing MSE wall and across three
precast panel widths or an equivalent of 15 feet.
The project specifications required that soil nails
above the existing culvert were to be installed with
no vertical inclination. A device was fabricated that
attached to the precast panels and allowed for
drilling of the soil nails. In addition, the device could
be manipulated to retain the neat cement grout after
soil nail installation was completed.
Quality assurance during construction consisted of
testing five production nails to verify the allowable
pullout resistances for all three soil types. The proof
tests confirmed the allowable pullout resistances.
Specimens of neat cement grout from the soil nails
were also tested to confirm grout strength.
Conclusions
Permanent soil nails are a sensible solution for the
rehabilitation and strengthening of MSE retaining
walls that undergo serviceability failures. Installation
techniques, specialized equipment and a design-
build approach allow soil nails to be both an
economical and less intrusive means for repairing
MSE retention systems.
Photo 3 Post-Construction Condition
References
DESIGN CONCEPT REPORT, 2003. Applied
Technologies, Inc. Lake Villa, IL and Brookfield, WI,
77 p.
GEOTECHNICAL ENGINEERING CIRCULAR NO.
7, 2003. Soil Nail Walls. FHWA0-IF-03-017.
Federal Highway Administration, Washington, D.C.,
182 p.
ILLINOIS STATE HIGHWAY AUTHORITY Home
Page. 2 March 2005 <http://www.illinoistollway.com>
MILLER, J. S. and GILES, T. L., 2003. Geotechnical
Engineering Exploration and Retaining Wall Distress
Evaluation. Project Engineering Report No. 1G-
0310001. Giles Engineering Associates, Inc.
Waukesha, WI, 59 p.

More Related Content

What's hot

Indian Standard
Indian StandardIndian Standard
Indian Standardaman kumar
 
Soils Reinforcement Retaing walls- التربة المسلحة في الجدران الاستنادية
Soils Reinforcement Retaing walls- التربة المسلحة في الجدران الاستناديةSoils Reinforcement Retaing walls- التربة المسلحة في الجدران الاستنادية
Soils Reinforcement Retaing walls- التربة المسلحة في الجدران الاستناديةDr.Youssef Hammida
 
Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Sai Towers P Ltd.
 
Seismic Retrofitting On RC Structures-Pushover Analysis
Seismic Retrofitting On RC Structures-Pushover AnalysisSeismic Retrofitting On RC Structures-Pushover Analysis
Seismic Retrofitting On RC Structures-Pushover AnalysisRamesh M
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining WallJim McMullan
 
Case studies for strengthening of existing structures
Case studies for strengthening of existing structuresCase studies for strengthening of existing structures
Case studies for strengthening of existing structuresParamaAthmeka
 
Methods for seismic retrofitting of structures comments
Methods for seismic retrofitting of structures commentsMethods for seismic retrofitting of structures comments
Methods for seismic retrofitting of structures commentsGuille Campos
 
Seismic Retrofitting of Masonry Structures
Seismic Retrofitting of Masonry StructuresSeismic Retrofitting of Masonry Structures
Seismic Retrofitting of Masonry StructuresDr K M SONI
 
Ppt supersstructure
Ppt supersstructurePpt supersstructure
Ppt supersstructureShrafatBalti
 
Seismic retrofitting techniques of rcc
Seismic retrofitting techniques of rccSeismic retrofitting techniques of rcc
Seismic retrofitting techniques of rccKorrapati Pratyusha
 
Seismic retrofit for rcc structureslocal global consequences
Seismic retrofit for rcc structureslocal global consequencesSeismic retrofit for rcc structureslocal global consequences
Seismic retrofit for rcc structureslocal global consequencesHashim k abdul azeez
 
Seismic Retrofitting of a RC Building by Adding Steel Plate Shear Walls
Seismic Retrofitting of a RC Building by Adding Steel Plate Shear WallsSeismic Retrofitting of a RC Building by Adding Steel Plate Shear Walls
Seismic Retrofitting of a RC Building by Adding Steel Plate Shear WallsIOSR Journals
 
Masonry structures confined with concrete beams an dcolumns
Masonry structures confined with concrete beams an dcolumnsMasonry structures confined with concrete beams an dcolumns
Masonry structures confined with concrete beams an dcolumnshsaam hsaam
 
SEISMIC RETROFITTING
SEISMIC RETROFITTINGSEISMIC RETROFITTING
SEISMIC RETROFITTINGRamesh M
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Retrofitting sequences by mostafa sameer
Retrofitting sequences by mostafa sameerRetrofitting sequences by mostafa sameer
Retrofitting sequences by mostafa sameerMostafa Sameer
 

What's hot (20)

Indian Standard
Indian StandardIndian Standard
Indian Standard
 
Soils Reinforcement Retaing walls- التربة المسلحة في الجدران الاستنادية
Soils Reinforcement Retaing walls- التربة المسلحة في الجدران الاستناديةSoils Reinforcement Retaing walls- التربة المسلحة في الجدران الاستنادية
Soils Reinforcement Retaing walls- التربة المسلحة في الجدران الاستنادية
 
Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.
 
Seismic Retrofitting On RC Structures-Pushover Analysis
Seismic Retrofitting On RC Structures-Pushover AnalysisSeismic Retrofitting On RC Structures-Pushover Analysis
Seismic Retrofitting On RC Structures-Pushover Analysis
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining Wall
 
Case studies for strengthening of existing structures
Case studies for strengthening of existing structuresCase studies for strengthening of existing structures
Case studies for strengthening of existing structures
 
Methods for seismic retrofitting of structures comments
Methods for seismic retrofitting of structures commentsMethods for seismic retrofitting of structures comments
Methods for seismic retrofitting of structures comments
 
Seismic Retrofitting of Masonry Structures
Seismic Retrofitting of Masonry StructuresSeismic Retrofitting of Masonry Structures
Seismic Retrofitting of Masonry Structures
 
Ppt supersstructure
Ppt supersstructurePpt supersstructure
Ppt supersstructure
 
seismic retrofit
seismic retrofitseismic retrofit
seismic retrofit
 
Seismic retrofitting techniques of rcc
Seismic retrofitting techniques of rccSeismic retrofitting techniques of rcc
Seismic retrofitting techniques of rcc
 
Seismic retrofit for rcc structureslocal global consequences
Seismic retrofit for rcc structureslocal global consequencesSeismic retrofit for rcc structureslocal global consequences
Seismic retrofit for rcc structureslocal global consequences
 
Retrofitting
RetrofittingRetrofitting
Retrofitting
 
Retrofitting
Retrofitting Retrofitting
Retrofitting
 
Seismic Retrofitting of a RC Building by Adding Steel Plate Shear Walls
Seismic Retrofitting of a RC Building by Adding Steel Plate Shear WallsSeismic Retrofitting of a RC Building by Adding Steel Plate Shear Walls
Seismic Retrofitting of a RC Building by Adding Steel Plate Shear Walls
 
Lecture earthquake-4
Lecture earthquake-4Lecture earthquake-4
Lecture earthquake-4
 
Masonry structures confined with concrete beams an dcolumns
Masonry structures confined with concrete beams an dcolumnsMasonry structures confined with concrete beams an dcolumns
Masonry structures confined with concrete beams an dcolumns
 
SEISMIC RETROFITTING
SEISMIC RETROFITTINGSEISMIC RETROFITTING
SEISMIC RETROFITTING
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Retrofitting sequences by mostafa sameer
Retrofitting sequences by mostafa sameerRetrofitting sequences by mostafa sameer
Retrofitting sequences by mostafa sameer
 

Viewers also liked

Ares cs delaware_12.12
Ares cs delaware_12.12Ares cs delaware_12.12
Ares cs delaware_12.12Tensar
 
Design of mse walls for fully saturated conditions
Design of mse walls for fully saturated conditionsDesign of mse walls for fully saturated conditions
Design of mse walls for fully saturated conditionsCarlos Carrillo Delgado
 
Visista hospital
Visista hospitalVisista hospital
Visista hospitalvarma Ptr
 
Linalis UK introduction
Linalis UK introductionLinalis UK introduction
Linalis UK introductionSteve Adams
 
AutoLAP_Brochure
AutoLAP_BrochureAutoLAP_Brochure
AutoLAP_Brochuredfeldman55
 
Role of alternative medicine
Role of alternative medicineRole of alternative medicine
Role of alternative medicinevarma Ptr
 
Pdf academic performance-indicator(api)
Pdf academic performance-indicator(api)Pdf academic performance-indicator(api)
Pdf academic performance-indicator(api)Dr. Ganesh Kame
 
Car shifting services
Car shifting servicesCar shifting services
Car shifting servicesvarma Ptr
 
Public private partnership mode with AP Govt
Public private partnership mode with AP GovtPublic private partnership mode with AP Govt
Public private partnership mode with AP Govtvarma Ptr
 
Maharaja constructions rofile
Maharaja constructions rofileMaharaja constructions rofile
Maharaja constructions rofilevarma Ptr
 
Engineering educationreform
Engineering educationreformEngineering educationreform
Engineering educationreformDr. Ganesh Kame
 
programme for international student assessment
programme for international student assessmentprogramme for international student assessment
programme for international student assessmentCahaya Cita-Cita
 
Pendekatan pdp dlm bilik darjah
Pendekatan pdp dlm bilik darjahPendekatan pdp dlm bilik darjah
Pendekatan pdp dlm bilik darjahCahaya Cita-Cita
 

Viewers also liked (20)

Ares cs delaware_12.12
Ares cs delaware_12.12Ares cs delaware_12.12
Ares cs delaware_12.12
 
Workstation Bridge Cranes - O'Brien MET-TRACK
Workstation Bridge Cranes - O'Brien MET-TRACKWorkstation Bridge Cranes - O'Brien MET-TRACK
Workstation Bridge Cranes - O'Brien MET-TRACK
 
Design of mse walls for fully saturated conditions
Design of mse walls for fully saturated conditionsDesign of mse walls for fully saturated conditions
Design of mse walls for fully saturated conditions
 
Seismic reinforced
Seismic reinforcedSeismic reinforced
Seismic reinforced
 
Visista hospital
Visista hospitalVisista hospital
Visista hospital
 
Presentation1
Presentation1Presentation1
Presentation1
 
Linalis UK introduction
Linalis UK introductionLinalis UK introduction
Linalis UK introduction
 
AutoLAP_Brochure
AutoLAP_BrochureAutoLAP_Brochure
AutoLAP_Brochure
 
Hyd traffic
Hyd trafficHyd traffic
Hyd traffic
 
Role of alternative medicine
Role of alternative medicineRole of alternative medicine
Role of alternative medicine
 
Pdf academic performance-indicator(api)
Pdf academic performance-indicator(api)Pdf academic performance-indicator(api)
Pdf academic performance-indicator(api)
 
Car shifting services
Car shifting servicesCar shifting services
Car shifting services
 
Public private partnership mode with AP Govt
Public private partnership mode with AP GovtPublic private partnership mode with AP Govt
Public private partnership mode with AP Govt
 
Maharaja constructions rofile
Maharaja constructions rofileMaharaja constructions rofile
Maharaja constructions rofile
 
Engineering educationreform
Engineering educationreformEngineering educationreform
Engineering educationreform
 
Pecha Kucha
Pecha KuchaPecha Kucha
Pecha Kucha
 
Ciberassetjament acabat
Ciberassetjament acabatCiberassetjament acabat
Ciberassetjament acabat
 
programme for international student assessment
programme for international student assessmentprogramme for international student assessment
programme for international student assessment
 
Pendekatan pdp dlm bilik darjah
Pendekatan pdp dlm bilik darjahPendekatan pdp dlm bilik darjah
Pendekatan pdp dlm bilik darjah
 
Ppsmi vs mbmmbi (kump 5)
Ppsmi vs mbmmbi (kump 5)Ppsmi vs mbmmbi (kump 5)
Ppsmi vs mbmmbi (kump 5)
 

Similar to Rehab of an existing mse(1)

Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...ijtsrd
 
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptxMECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptxShahidAmeen10
 
Research study on Soil Structure Interaction of Integrated Earth Retaining Wa...
Research study on Soil Structure Interaction of Integrated Earth Retaining Wa...Research study on Soil Structure Interaction of Integrated Earth Retaining Wa...
Research study on Soil Structure Interaction of Integrated Earth Retaining Wa...IRJET Journal
 
Innovative Slope Stabilisation
Innovative Slope StabilisationInnovative Slope Stabilisation
Innovative Slope Stabilisationselvem
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation Davis Ciprikis
 
Comparative Study of RC Structures with Different Types of Infill Walls with ...
Comparative Study of RC Structures with Different Types of Infill Walls with ...Comparative Study of RC Structures with Different Types of Infill Walls with ...
Comparative Study of RC Structures with Different Types of Infill Walls with ...IRJET Journal
 
Diaphragm walls construction_and_design
Diaphragm walls construction_and_designDiaphragm walls construction_and_design
Diaphragm walls construction_and_designMuhammad iqbal
 
Module-5_sketch_Advanced Construction Technology
Module-5_sketch_Advanced Construction TechnologyModule-5_sketch_Advanced Construction Technology
Module-5_sketch_Advanced Construction TechnologyA Makwana
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignUmer Farooq
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation supportJim McMullan
 
earthquake resistant design
earthquake resistant designearthquake resistant design
earthquake resistant designAditya Sanyal
 
Rehabilitation of foundation
Rehabilitation of foundationRehabilitation of foundation
Rehabilitation of foundationABIRAMI G
 
Bathini_2022_IOP_Conf._Ser.__Earth_Environ._Sci._982_012047.pdf
Bathini_2022_IOP_Conf._Ser.__Earth_Environ._Sci._982_012047.pdfBathini_2022_IOP_Conf._Ser.__Earth_Environ._Sci._982_012047.pdf
Bathini_2022_IOP_Conf._Ser.__Earth_Environ._Sci._982_012047.pdfBnkvvnnnjn
 
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Andy Sugianto
 
Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Tensar
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationIshwar Chauhan
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wallHarsh Bothra
 

Similar to Rehab of an existing mse(1) (20)

Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
Study of Reinforced Retaining Wall Over Predictable Considering Different Hei...
 
sruthi ppt.pptx
sruthi ppt.pptxsruthi ppt.pptx
sruthi ppt.pptx
 
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptxMECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
 
seminar.pptx
seminar.pptxseminar.pptx
seminar.pptx
 
Research study on Soil Structure Interaction of Integrated Earth Retaining Wa...
Research study on Soil Structure Interaction of Integrated Earth Retaining Wa...Research study on Soil Structure Interaction of Integrated Earth Retaining Wa...
Research study on Soil Structure Interaction of Integrated Earth Retaining Wa...
 
Innovative Slope Stabilisation
Innovative Slope StabilisationInnovative Slope Stabilisation
Innovative Slope Stabilisation
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation
 
Comparative Study of RC Structures with Different Types of Infill Walls with ...
Comparative Study of RC Structures with Different Types of Infill Walls with ...Comparative Study of RC Structures with Different Types of Infill Walls with ...
Comparative Study of RC Structures with Different Types of Infill Walls with ...
 
Diaphragm walls construction_and_design
Diaphragm walls construction_and_designDiaphragm walls construction_and_design
Diaphragm walls construction_and_design
 
Module-5_sketch_Advanced Construction Technology
Module-5_sketch_Advanced Construction TechnologyModule-5_sketch_Advanced Construction Technology
Module-5_sketch_Advanced Construction Technology
 
2327
23272327
2327
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
 
earthquake resistant design
earthquake resistant designearthquake resistant design
earthquake resistant design
 
Rehabilitation of foundation
Rehabilitation of foundationRehabilitation of foundation
Rehabilitation of foundation
 
Bathini_2022_IOP_Conf._Ser.__Earth_Environ._Sci._982_012047.pdf
Bathini_2022_IOP_Conf._Ser.__Earth_Environ._Sci._982_012047.pdfBathini_2022_IOP_Conf._Ser.__Earth_Environ._Sci._982_012047.pdf
Bathini_2022_IOP_Conf._Ser.__Earth_Environ._Sci._982_012047.pdf
 
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
 
Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and Rehabilitation
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 

Rehab of an existing mse(1)

  • 1. Nicholson Construction Company 12 McClane Street Cuddy, PA 15031 Telephone: 412-221-4500 Facsimile: 412-221-3127 Rehabilitation of an Existing Mechanically Stabilized Earth Wall Using Soil Nails by Daniel A. Thome, P.E. Nicholson Construction Company, Kalamazoo, Michigan Robert C. Janke P.E., S.E. Applied Technologies, Inc., Lake Villa, Illinois and Brookfield, Wisconsin Presented at: DFI’s 30th Annual Conference on Deep Foundations Chicago, Illinois September 22-24, 2005 05-03-147
  • 2. REHABILITATION OF AN EXISTING MECHANICALLY STABILIZED EARTH WALL USING SOIL NAILS Daniel A. Thome P.E., Nicholson Construction Company, Midwest District Office, Kalamazoo, Michigan, USA Robert C. Janke P.E., S.E., Applied Technologies, Inc., Lake Villa, Illinois and Brookfield, Wisconsin, USA Installation of permanent soil nails through distressed mechanically stabilized earth retaining walls is a cost effective and aesthetically pleasing solution when using the appropriate equipment and drilling methods for installation. A forensic investigation was performed on an existing mechanically stabilized earth retaining wall to determine the possible causes for the excessive horizontal displacements and visual structural flaws found along a portion of the wall. Reports concluded that the visual shifting was due to a number of factors including improper drainage in the vicinity of the wall and unsuitable compaction of the backfill material. Conceptual designs were proposed to the owner and the installation of permanent soil nails through the existing precast panels was determined to be the most practical solution. A total of ninety-three permanent soil nails were installed to lengths of up to 40 feet (12 m) through sand backfill and silty clay fill using a hydraulic rotary percussion drill attached to a tract mounted excavator. Introduction The Illinois State Toll Highway Authority awarded Contract RR-03-5144 in the summer of 2004. Construction work for the project consisted of the rehabilitation of two existing concrete culverts and approximately 100 linear feet (31 m) of mechanically stabilized earth (MSE) retaining wall. The retaining wall is located below the southbound lanes of the Tri-State Tollway near the intersection of Federal Highway 41 in Wadsworth, Illinois as shown in Figure 1. Figure 1 Project Location Map Reports were prepared by Applied Technologies in cooperation with Giles Engineering Associates to determine the condition of the MSE wall and recommended conceptual designs to extend the service life of the wall. Nicholson Construction Company (Nicholson) was selected as the design-build geotechnical subcontractor to install the recommended permanent soil nails through the existing precast concrete panels of the MSE wall. Rehabilitation of the wall involved the installation of ninety-three permanent soil nails through the existing wall, along with soil nail verification tests and proof tests on production nails. Background History Construction of the MSE retaining wall was completed in 1982. The total length of the MSE wall is 740 feet (226 m) along the footprint of a horizontal curve, with a radius of 1896 feet (578 m). The maximum wall height is 24 feet (7 m) with the grade in front of the wall being approximately 4 feet (1.2 m) above the bottom of footing elevation. Galvanized steel reinforcement straps either 14 feet (4.3 m) or 17 feet (5.2 m) long connect to the back of the precast concrete panels. A portion of the MSE wall was built directly over an existing box culvert, 10 feet (3 m) wide and 7 feet (2.1 m) high. An inlet for the highway was Project Location
  • 3. constructed directly behind the top of the MSE wall and connected to a 15 inch (381 mm) diameter storm sewer that ran perpendicular and away from the retaining wall. According to the wall manufacturer, displacements were noted shortly after construction of the MSE wall directly over the existing culvert. Unfortunately, a monitoring system was not put into place and no corrective measures were implemented on the wall after the displacement had occurred. Refer to Figure 2 for a typical cross sectional profile near station 1346+00. Geological Conditions Backfill material for the MSE retaining wall consists of fine to coarse sand and extends to the bottom of the MSE wall panels. The sand backfill is very loose to loose in the vicinity of the failing wall section and medium dense within the remaining sections. Stiff to very stiff silty clay fill was encountered below the MSE wall backfill and within the retained soils behind the retaining wall. The depths of this soil ranged from 19 feet (5.8 m) to 33 feet (10 m) below the ground surface. A very stiff to hard natural silty clay soil was reported below the silty clay fill to the maximum depths explored. A perched groundwater table was determined to be near the ground surface in front of the displaced MSE wall section. Figure 2 shows a typical geologic section for the MSE wall near station 1346+00. Figure 2 Typical Cross Section - Station 1346+00 Evaluation of Existing Wall In 2003, Applied Technologies in cooperation with Giles Engineering Associates prepared documentation describing the condition of the existing MSE retaining wall. The reports summarized flaws within and surrounding the retention system that seemed to be concentrated between stations 1346+00 and 1347+00. The following key information was contained within the forensic reports: • Approximately 2 to 11 inches (51 to 279 mm) of horizontal displacement was reported within the height of the wall. • The existing 15 inch (381 mm) storm sewer pipe was obstructed with debris, causing perched water near the ground surface in front of the wall. • Sand backfill accumulated in front of the wall due to loss of ground within the MSE wall backfill. • Very loose to loose sand backfill was sampled within the failing section while medium dense sand backfill was encountered in the remainder of the wall. • Vehicular collision with concrete parapet occurred directly above the failing wall section. • Concrete panels were grossly misaligned due to excessive horizontal displacements causing spalling at the edges near vertical shear pins. • Notable settlement of the Tri-State shoulder above the wall indicated redistribution of soil within the sand backfill. Photo 1 Pre-Construction Condition Exist Culvert T-13-15 Sand Backfill Silty Clay Fill 14 to 17 Feet (4.3 to 5.2 m) Perched Water Table
  • 4. Causes of the distress in the MSE wall were inconclusive in the reports, but undoubtedly a combination of the above factors caused the horizontal displacements. Conceptual Design Suggestions Applied Technologies narrowed down a compiled list of repair options to four, based on economics, aesthetics and constructability. In all scenarios the structural elements of the existing MSE retaining wall were to be ignored. Option A-1 consisted of installing one permanent soil nail per existing panel and shooting a reinforced shotcrete facing in front of the wall to adequately transfer the punching shear force of the soil nails. Option A-2 was similar to option A-1 with the exception of using a new reinforced concrete wall rather than reinforced shotcrete for punching shear resistance. Options B and C entailed the installation of an anchored soldier pile wall in front of the existing wall using either sheet piling (option B) or precast concrete (option C) as lagging to resist the horizontal earth pressures. Option A-2 was chosen because the cast-in-place reinforced concrete maintained the existing appearance of the MSE wall. Also, it was more economical to build option A-2, when compared to option A-1, based on preliminary cost estimates performed by the owner’s engineer. Options B and C were eliminated due to aesthetics and vibration concerns based on conversations with the Illinois State Toll Highway Authority. Soil Nail Design There were three objectives for the soil nail wall design. One was to perform an internal wall analysis to determine required soil nail lengths for the existing ground conditions and wall geometry. Another was to confirm adequate punching shear resistance of the existing concrete panels for temporary face support along with verifying the design for bearing plate and studs. Finally, a global stability analysis for bearing capacity, overturning and sliding was performed. Three design sections were used to economize the nail lengths for various wall heights and access constraints. The heights of the three design sections were 19 feet (5.8 m), 22 feet (6.7 m) and 23 feet (7 m). The 22 foot (6.7m) high section had horizontal soil nails over the existing box culvert. The horizontal and vertical spacing for the soil nails equaled the average dimension between precast concrete panels, 4 feet 11 inches (1.5 m). Unit weights and friction angles for all three soil types were obtained from the design parameters in the project specifications and checked against the soil borings. Ultimate pullout resistances for each soil type were chosen based on the project borings and the geotechnical subcontractor’s experience. Table 1 provides a summary of the design parameters for each soil type. Table 1 Summary of Soil Design Parameters Soil Type Friction Angle degrees Unit Weight pcf (kN/m 3 ) Ultimate Pullout kips/foot (kN/m) Allowable Bearing Pressure psf (kN/m 2 ) Sand Backfill 34 125 (19.6) 5.3 (77.3) N/A Silty Clay Fill (Behind Wall) 30 125 (19.6) 2.6 (37.9) N/A Silty Clay Fill (Below Wall) 30 N/A N/A 5000 (239) The GoldNail program was used to analyze each design section for internal stability. GoldNail is a slope stability model based on satisfying overall limiting equilibrium defined by circular slip surfaces. Steel area and yield stress are input into the GoldNail program along with the proposed wall geometry, reinforcement locations and soil strengths. Lengths of nails for each design section were determined through program iterations. As per the project specifications, a factor of safety for internal stability of one and a half and a factor of safety for soil nail pullout resistance of two were used as input parameters for the analyses. Existing reinforcement straps were ignored in the calculations as stated in the project specifications. Structural calculations were performed to confirm the adequacy of the wall facing. Temporary punching shear capacity of the precast concrete panels was confirmed. Then, computations were completed for the permanent punching shear capacity of the headed stud connection with the reinforced concrete facing. Lastly, the tensile strength of the studs was verified. A global stability analysis was also performed to conclude that a factor of safety of one and a half or greater existed for the revised retention system in regards to overturning, sliding and bearing capacity. Results showed that adequate safety factors were
  • 5. indeed present for the potential external failure modes. Soil Nail Testing Verification test nails were required according to the project specifications. Test nails would be installed toward the bottom of the existing wall for ease in setting up and testing. Verification test nail #1 was bonded into the silty clay fill with an unbonded length within the sand backfill. Verification test nail #2 was bonded only in the sand backfill material. Test results from both verification nails showed a lower ultimate pullout resistance than used in the initial soil nail design. The geotechnical subcontractor reviewed the test results and had the following thoughts regarding the unexpectedly low ultimate pullout resistances. • Arching caused by the existing reinforcement straps from the MSE wall was reducing the confining stress to values below overburden pressures. • Lower confining stresses limited the ability to effectively pressure grout the soil nails. • Test nails installed near the bottom of the existing MSE wall experienced lower pullout capacities due to saturated/perched groundwater conditions. • The ultimate pullout resistance values for the sand backfill and clay fill were overestimated during the initial design based on the existing soil conditions. Three additional verification tests were performed to confirm the lower ultimate pullout resistances in the sand backfill and silty clay fill. Results of the supplemental verification tests confirmed the lower ultimate pullout resistances in both of the soil stratums. They also confirmed that there was indeed a saturated silty clay fill layer below the MSE wall, which resulted in a significantly lower pullout resistance for the bottom row of test nails. Table 2 summarizes the revised ultimate pullout resistances based on the verification testing. Results from the verification tests were compiled and the soil nail wall design was reanalyzed. Ultimate pullout resistances for the sand backfill and silty clay fill were revised with the saturated silty clay fill added to the analysis to represent the soil below the wall. Revised soil nail lengths increased from the original design by approximately thirty-three percent. Table 2 Revised Ultimate Pullout Resistances Soil Type Initial Ultimate Pullout kips/foot (kN/m) Revised Ultimate Pullout kips/foot (kN/m) Sand Backfill 5.3 (77.3) 3.3 (48.2) Silty Clay Fill (Behind Wall) 2.6 (37.9) 2.4 (35.0) Silty Clay Fill (Below Wall) N/A 1.3 (19.0) Construction Project specific challenges for the soil nailing operation included entry points approximately 20 feet (6.1 m) above working bench elevation. Additional installation concerns were soil nails through granular backfill and potential conflicts with utilities, existing reinforcement straps and the concrete box culvert located directly underneath the wall. The geotechnical subcontractor determined that a conventional drill rig would not be able to install a majority of the soil nails on this project due to the extreme heights of some of their entry points. A hydraulic excavator mounted drill was utilized in order to install the higher soil nails without special modifications being made to the work bench. The excavator mounted drill was a rotary percussion tool mounted on a mast which attached to a tract mounted excavator. The versatility and reach of the excavator drill mast allowed for proper soil nail installation. Photo 2 Soil Nail Installation
  • 6. Existing granular backfill underneath an active highway created concern for ground loss. The geotechnical subcontractor decided to use the duplex drilling method for soil nail installation. A major advantage to duplex drilling is that intimate contact between the bore hole and outer casing is achieved, minimizing ground loss. Duplex drilling uses an inner rod and an outer casing to simultaneously advance the bore hole. Water or air is circulated down through the center of the inner drill rod and returns upward through the annulus between the drill rod and outer casing removing drill cuttings. The construction site posed a few geometrical constraints for the soil nail operation. An existing fiber optic line ran across the bottom row of soil nails. The fiber optic line was completely exposed prior to commencing soil nail operations and temporarily encased in a plastic sleeve during construction operations. Particular soil nail locations were adjusted in the field to miss the fiber optic line with the drill equipment. A typical precast concrete facing for MSE retaining walls will have the reinforcement straps connect at up to six evenly spaced locations to the back of the panel. The reinforcement straps from the MSE wall were avoided by centering the soil nails within the individual concrete panels and allowing for only vertical inclination where appropriate. An existing concrete culvert T-13-15, which was to be rehabilitated, was located directly below the bottom of the existing MSE wall and across three precast panel widths or an equivalent of 15 feet. The project specifications required that soil nails above the existing culvert were to be installed with no vertical inclination. A device was fabricated that attached to the precast panels and allowed for drilling of the soil nails. In addition, the device could be manipulated to retain the neat cement grout after soil nail installation was completed. Quality assurance during construction consisted of testing five production nails to verify the allowable pullout resistances for all three soil types. The proof tests confirmed the allowable pullout resistances. Specimens of neat cement grout from the soil nails were also tested to confirm grout strength. Conclusions Permanent soil nails are a sensible solution for the rehabilitation and strengthening of MSE retaining walls that undergo serviceability failures. Installation techniques, specialized equipment and a design- build approach allow soil nails to be both an economical and less intrusive means for repairing MSE retention systems. Photo 3 Post-Construction Condition References DESIGN CONCEPT REPORT, 2003. Applied Technologies, Inc. Lake Villa, IL and Brookfield, WI, 77 p. GEOTECHNICAL ENGINEERING CIRCULAR NO. 7, 2003. Soil Nail Walls. FHWA0-IF-03-017. Federal Highway Administration, Washington, D.C., 182 p. ILLINOIS STATE HIGHWAY AUTHORITY Home Page. 2 March 2005 <http://www.illinoistollway.com> MILLER, J. S. and GILES, T. L., 2003. Geotechnical Engineering Exploration and Retaining Wall Distress Evaluation. Project Engineering Report No. 1G- 0310001. Giles Engineering Associates, Inc. Waukesha, WI, 59 p.