SlideShare a Scribd company logo
1 of 35
Download to read offline
Ground Improvements for Challenging Sites in
Orange County
Compacted Aggregate Piers
(Geopier/Rammed Aggregate Pier)
Outline
1. Compacted aggregate pier basics
2. Two Case Studies
• The Park Apartments
• Park Place Apartments
3. Construction QA/QC
4. Questions and Discussion
Generic:
• compacted aggregate pier
• compacted aggregate caisson
• compacted aggregate column
Basic Concept
Proprietary (Trade Names):
• Geopier - Rammed Aggregate Pier
• TerraRam
• GeoRam
• VibroPier
• Earth Pier
• Etcetera Etcetera Pier
Geopier drill
Geopier Tamper
Skid steer
 Mobile crew (4 people, 3 machines)
 Rapid installations (30 – 50 per day)
 Safe, clean, dry process (no jetting!)
 Installation depths up to 30 feet
Geopier GP3™ Construction
Engineering Aspects
• Not a foundation system
• Improve near surface soil
• Increased bearing capacities below
foundations and slabs-on-grade
• Reduced settlements
Settlement Within Compacted Aggregate Zone
Design based on spring analogy:
 Rigid footing: Geopier deflection & matrix soil deflection
 Stiff spring (RAP element) takes more load than soft spring (matrix
soil).
 Use conventional geotechnical analysis
approaches:
 Estimate footing-induced stress
(Westergaard, Boussinesq, etc)
 Estimate soil compressibility
 Traditional elastic or consolidation
design methods.
 Add lower zone and upper zone for
total settlement
Settlement Below Aggregate Piers (Lower Zone)
B
2B
HLZ
HUZ
Design Process
• Foundation Loads
• Settlement tolerances
• Onsite soil properties
• Collaboration
– Geotechnical consultant
– Structural engineer
– Aggregate pier designer/builder
Two Project Applications
1.The Park
2.Park Place
The Park Apartments
The Park Project
• 1500 apartment units on 29-acres
• 4-story wood framed apartment buildings
over 2 levels of partial subterranean parking
(podium)
• Column loads 380 to 1156 KIPS
The Park---site conditions
• Relatively flat site
• Historically used for agriculture
• Explored with hollow-stem borings and CPT’s
• Groundwater wells.
• Underlain by deep alluvium
• Interlayered silts, sands, clays
• Groundwater at 15 to 30 feet BGS
Geotechnical Issues
• Groundwater below subterranean levels
(5 to 10 feet)
• Reduced bearing capacities
• Differential foundation loads and
differential settlements
Alternatives
× Piles infeasible
× Remedial Grading---groundwater
× Matt foundation ($7 million)
Ground improvement---aggregate piers
Geopiers at The Park
• 2,400 piers
• 30-inch diameter
• 11 to 13 feet deep
• 50 to 60 working days
• Savings over mat foundation: $3 million
Acknowledgements
Project Owner: Irvine Company
Specialty Contractor: Geopier
Structural Engineer: Van Dorp Chow
Park Place Apartments
Park
Place
San Diego Creek
Park Place Project
• 980 units on 14-acres
• 4-story wood framed buildings
• 2-levels, partially subterranean,
reinforced concrete parking below
• Column loads: 94 to 807 kips
• Wall loads: <12.5 kips/l.f.
Park Place --Site Conditions
• Relatively flat site
• Formerly MARSHLAND (swamps)
• Underlain by PEAT/organic clays, alluvium
• Groundwater at 20 to 30 feet BGS
MARSH DEPOSITS
Older Alluvium
Groundwater
Structure
Younger Alluvium
Geotechnical Issues
• Very low bearing capacities
• 4 inches total settlement in alluvium (2 inches
differential)
• Mat foundations infeasible over marsh soils
• Conventional aggregate piers inadequate in
marsh deposits (peat)
Geopiers at Park Place
• 4,798 piers
• 24-inch diameter
• 9 to 13 feet deep
• Cement Treated Piers (474)
in MARSH Deposit areas
• Cement Treated Piers---up to 30’ deep
Acknowledgements
Project Owner: Irvine Company
Specialty Contractor: Tensar-Geopier (Western Ground
Improvement)
Structural Engineer: HCDA Engineering, Inc.
Construction QA/QC
• Aggregate
properties
• Surface logging of
excavated soil
• Pier depths
• Pier locations
Purpose: Measure Stiffness (kg)
W-Beam
Uplift
Anchor
Rod
100 Ton Jack
Uplift
Anchor
PierTelltaleCompression Pier
Insitu Modulus Test
Discussion/Questions

More Related Content

What's hot

2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTUVATSAL PATEL
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge BearingsAyushHajare
 
Subrasante
SubrasanteSubrasante
Subrasantenevely
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTUVATSAL PATEL
 
Pavement Design (Transportation Engineering)
Pavement Design (Transportation Engineering)Pavement Design (Transportation Engineering)
Pavement Design (Transportation Engineering)Hossam Shafiq I
 
1. Pile foundations (SL 1-143).pdf
1. Pile foundations (SL 1-143).pdf1. Pile foundations (SL 1-143).pdf
1. Pile foundations (SL 1-143).pdfKRSrikrishnaSetty
 
Introduction and comparison of ground improvement techniques
Introduction and comparison of ground improvement techniquesIntroduction and comparison of ground improvement techniques
Introduction and comparison of ground improvement techniquesNouman Ijaz Chatha
 
Design of RCC slab two way continuous supported
Design of RCC slab two way continuous supportedDesign of RCC slab two way continuous supported
Design of RCC slab two way continuous supportedBhavik A Shah
 
Flyover Bridge construction project
Flyover Bridge construction projectFlyover Bridge construction project
Flyover Bridge construction projectAxay Sharma
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.ashrafdgrt
 
Clase N°01 EVOLUCIÓN HISTORICA DE LOS METODOS DE DISEÑO DE PAVIMENTOS.pptx
Clase N°01 EVOLUCIÓN HISTORICA DE LOS METODOS DE DISEÑO DE PAVIMENTOS.pptxClase N°01 EVOLUCIÓN HISTORICA DE LOS METODOS DE DISEÑO DE PAVIMENTOS.pptx
Clase N°01 EVOLUCIÓN HISTORICA DE LOS METODOS DE DISEÑO DE PAVIMENTOS.pptxEmersonCabelloZelaya
 
IRJET- Shore Pile and Rock Anchoring for Deep Excavation
IRJET- Shore Pile and Rock Anchoring for Deep ExcavationIRJET- Shore Pile and Rock Anchoring for Deep Excavation
IRJET- Shore Pile and Rock Anchoring for Deep ExcavationIRJET Journal
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compactionBegum Emte Ajom
 

What's hot (20)

2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU
 
Dam
DamDam
Dam
 
Hoover dam
Hoover damHoover dam
Hoover dam
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge Bearings
 
Subrasante
SubrasanteSubrasante
Subrasante
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
Pavement Design (Transportation Engineering)
Pavement Design (Transportation Engineering)Pavement Design (Transportation Engineering)
Pavement Design (Transportation Engineering)
 
1. Pile foundations (SL 1-143).pdf
1. Pile foundations (SL 1-143).pdf1. Pile foundations (SL 1-143).pdf
1. Pile foundations (SL 1-143).pdf
 
Introduction and comparison of ground improvement techniques
Introduction and comparison of ground improvement techniquesIntroduction and comparison of ground improvement techniques
Introduction and comparison of ground improvement techniques
 
2950 1
2950 12950 1
2950 1
 
Railway terminology
Railway terminologyRailway terminology
Railway terminology
 
Design of RCC slab two way continuous supported
Design of RCC slab two way continuous supportedDesign of RCC slab two way continuous supported
Design of RCC slab two way continuous supported
 
Flyover Bridge construction project
Flyover Bridge construction projectFlyover Bridge construction project
Flyover Bridge construction project
 
Chenab Bridge
Chenab BridgeChenab Bridge
Chenab Bridge
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.
 
Clase N°01 EVOLUCIÓN HISTORICA DE LOS METODOS DE DISEÑO DE PAVIMENTOS.pptx
Clase N°01 EVOLUCIÓN HISTORICA DE LOS METODOS DE DISEÑO DE PAVIMENTOS.pptxClase N°01 EVOLUCIÓN HISTORICA DE LOS METODOS DE DISEÑO DE PAVIMENTOS.pptx
Clase N°01 EVOLUCIÓN HISTORICA DE LOS METODOS DE DISEÑO DE PAVIMENTOS.pptx
 
IRJET- Shore Pile and Rock Anchoring for Deep Excavation
IRJET- Shore Pile and Rock Anchoring for Deep ExcavationIRJET- Shore Pile and Rock Anchoring for Deep Excavation
IRJET- Shore Pile and Rock Anchoring for Deep Excavation
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compaction
 
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of dams
 
MAX FAJARDO ESTIMATE.pdf
MAX FAJARDO ESTIMATE.pdfMAX FAJARDO ESTIMATE.pdf
MAX FAJARDO ESTIMATE.pdf
 

Similar to ASCE Geopier Presentation March 2015

Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...Onondaga County Save the Rain
 
Structural soil questions gresham
Structural soil questions greshamStructural soil questions gresham
Structural soil questions greshamMaria Cahill
 
Dynamic_compaction.pptx
Dynamic_compaction.pptxDynamic_compaction.pptx
Dynamic_compaction.pptxRam Deshpande
 
Parking Forest Questions from the City of Gresham
Parking Forest Questions from the City of GreshamParking Forest Questions from the City of Gresham
Parking Forest Questions from the City of GreshamMaria Cahill
 
Dim cs whynes_12.07
Dim cs whynes_12.07Dim cs whynes_12.07
Dim cs whynes_12.07Tensar
 
Emin sg sistema dimension caso west hynes tank farm
Emin sg   sistema dimension caso west hynes tank farmEmin sg   sistema dimension caso west hynes tank farm
Emin sg sistema dimension caso west hynes tank farmEMIN Sistemas Geotecnicos
 
Dim cs whynes_12.07-2
Dim cs whynes_12.07-2Dim cs whynes_12.07-2
Dim cs whynes_12.07-2Tensar
 
Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...mecocca5
 
A Contractor’s Perspective on Redeveloping Historical Landfills
A Contractor’s Perspective on Redeveloping Historical LandfillsA Contractor’s Perspective on Redeveloping Historical Landfills
A Contractor’s Perspective on Redeveloping Historical LandfillsIES / IAQM
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)DC Department of General Services
 
Mitigating foundation distress
Mitigating foundation distressMitigating foundation distress
Mitigating foundation distressInfocengrs63
 
hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxZakaria156221
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxZakaria156221
 
Building construction
Building constructionBuilding construction
Building constructionnhmurad
 
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación..."Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...Instituto del cemento y Hormigón de Chile
 

Similar to ASCE Geopier Presentation March 2015 (20)

ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
ASCE OC Geo-Institute Luncheon - ARTIC: Anaheim Regional Transportation Inter...
 
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff & ...
 
Structural soil questions gresham
Structural soil questions greshamStructural soil questions gresham
Structural soil questions gresham
 
Dynamic_compaction.pptx
Dynamic_compaction.pptxDynamic_compaction.pptx
Dynamic_compaction.pptx
 
GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES GROUND IMPROVEMENT TECHNIQUES
GROUND IMPROVEMENT TECHNIQUES
 
Parking Forest Questions from the City of Gresham
Parking Forest Questions from the City of GreshamParking Forest Questions from the City of Gresham
Parking Forest Questions from the City of Gresham
 
Dim cs whynes_12.07
Dim cs whynes_12.07Dim cs whynes_12.07
Dim cs whynes_12.07
 
Emin sg sistema dimension caso west hynes tank farm
Emin sg   sistema dimension caso west hynes tank farmEmin sg   sistema dimension caso west hynes tank farm
Emin sg sistema dimension caso west hynes tank farm
 
Dim cs whynes_12.07-2
Dim cs whynes_12.07-2Dim cs whynes_12.07-2
Dim cs whynes_12.07-2
 
Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...Assessing and constructing a cost effective bridge replacement christopher si...
Assessing and constructing a cost effective bridge replacement christopher si...
 
A Contractor’s Perspective on Redeveloping Historical Landfills
A Contractor’s Perspective on Redeveloping Historical LandfillsA Contractor’s Perspective on Redeveloping Historical Landfills
A Contractor’s Perspective on Redeveloping Historical Landfills
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)
 
Mitigating foundation distress
Mitigating foundation distressMitigating foundation distress
Mitigating foundation distress
 
Akash verma.pptx
Akash verma.pptxAkash verma.pptx
Akash verma.pptx
 
hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptx
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptx
 
Building construction
Building constructionBuilding construction
Building construction
 
Marks Sess13 102309
Marks Sess13 102309Marks Sess13 102309
Marks Sess13 102309
 
Interlocking pavement
Interlocking pavementInterlocking pavement
Interlocking pavement
 
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación..."Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
"Cómo el concreto y los pavimentos permeables ayudan a reducir la acumulación...
 

More from American Society of Civil Engineers, Orange County Branch

More from American Society of Civil Engineers, Orange County Branch (20)

ASCE OC Luncheon - Sustainability in Transportation Part 2
ASCE OC Luncheon - Sustainability in Transportation Part 2ASCE OC Luncheon - Sustainability in Transportation Part 2
ASCE OC Luncheon - Sustainability in Transportation Part 2
 
ASCE OC Sustainability in Transportation Presentation Part 1
ASCE OC Sustainability in Transportation Presentation Part 1ASCE OC Sustainability in Transportation Presentation Part 1
ASCE OC Sustainability in Transportation Presentation Part 1
 
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park ProjectASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project
 
ASCE OC Branch - T&DI Luncheon - Delivering the State's First Diverging Diamo...
ASCE OC Branch - T&DI Luncheon - Delivering the State's First Diverging Diamo...ASCE OC Branch - T&DI Luncheon - Delivering the State's First Diverging Diamo...
ASCE OC Branch - T&DI Luncheon - Delivering the State's First Diverging Diamo...
 
ASCE OC Branch - Geo-Institute Dinner Presentation: Fundamentals of Torque Do...
ASCE OC Branch - Geo-Institute Dinner Presentation: Fundamentals of Torque Do...ASCE OC Branch - Geo-Institute Dinner Presentation: Fundamentals of Torque Do...
ASCE OC Branch - Geo-Institute Dinner Presentation: Fundamentals of Torque Do...
 
ASCE OC Geo Institute - Dinner Presentation - 08-15-2017
ASCE OC Geo Institute - Dinner Presentation - 08-15-2017ASCE OC Geo Institute - Dinner Presentation - 08-15-2017
ASCE OC Geo Institute - Dinner Presentation - 08-15-2017
 
Interaction of MSE Abutments with Superstructures under Seismic Loading
Interaction of MSE Abutments with Superstructures under Seismic LoadingInteraction of MSE Abutments with Superstructures under Seismic Loading
Interaction of MSE Abutments with Superstructures under Seismic Loading
 
Wilshire Grand Redevelopment Project
Wilshire Grand Redevelopment ProjectWilshire Grand Redevelopment Project
Wilshire Grand Redevelopment Project
 
Jessica Cassman on ENVISION 10/20/16
Jessica Cassman on ENVISION 10/20/16Jessica Cassman on ENVISION 10/20/16
Jessica Cassman on ENVISION 10/20/16
 
Beth Breitenbach on ENVISION 10/20/16
Beth Breitenbach on ENVISION 10/20/16Beth Breitenbach on ENVISION 10/20/16
Beth Breitenbach on ENVISION 10/20/16
 
Doug Sereno on ENVISION 10/20/16
Doug Sereno on ENVISION 10/20/16Doug Sereno on ENVISION 10/20/16
Doug Sereno on ENVISION 10/20/16
 
The State of Orange County's Infrastructure - 2016 Report Card
The State of Orange County's Infrastructure - 2016 Report CardThe State of Orange County's Infrastructure - 2016 Report Card
The State of Orange County's Infrastructure - 2016 Report Card
 
Autonomous Vehicles and Reducing GHG
Autonomous Vehicles and Reducing GHGAutonomous Vehicles and Reducing GHG
Autonomous Vehicles and Reducing GHG
 
Hyperxite sponsor packet_v2.4 (4)
Hyperxite sponsor packet_v2.4 (4)Hyperxite sponsor packet_v2.4 (4)
Hyperxite sponsor packet_v2.4 (4)
 
Transforming Transportation at the Speed of Sound
Transforming Transportation at the Speed of SoundTransforming Transportation at the Speed of Sound
Transforming Transportation at the Speed of Sound
 
ASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
ASCE Seawater Desalination Project at Huntington Beach - Poseidon WaterASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
ASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
 
Hyperxite sponsor packet_v2.4
Hyperxite sponsor packet_v2.4Hyperxite sponsor packet_v2.4
Hyperxite sponsor packet_v2.4
 
TTG Luncheon 4.6.2016 - OC Streetcar
TTG Luncheon 4.6.2016 - OC StreetcarTTG Luncheon 4.6.2016 - OC Streetcar
TTG Luncheon 4.6.2016 - OC Streetcar
 
Can a GSA be formed within a Partially Adjudicated Basin? | Brian Powell, EMWD
Can a GSA be formed within a Partially Adjudicated Basin? | Brian Powell, EMWDCan a GSA be formed within a Partially Adjudicated Basin? | Brian Powell, EMWD
Can a GSA be formed within a Partially Adjudicated Basin? | Brian Powell, EMWD
 
How OCWD Plans to Comply with SGMA, Or Are We Already There? | Roy Herndon, OCWD
How OCWD Plans to Comply with SGMA, Or Are We Already There? | Roy Herndon, OCWDHow OCWD Plans to Comply with SGMA, Or Are We Already There? | Roy Herndon, OCWD
How OCWD Plans to Comply with SGMA, Or Are We Already There? | Roy Herndon, OCWD
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

ASCE Geopier Presentation March 2015

  • 1. Ground Improvements for Challenging Sites in Orange County Compacted Aggregate Piers (Geopier/Rammed Aggregate Pier)
  • 2. Outline 1. Compacted aggregate pier basics 2. Two Case Studies • The Park Apartments • Park Place Apartments 3. Construction QA/QC 4. Questions and Discussion
  • 3. Generic: • compacted aggregate pier • compacted aggregate caisson • compacted aggregate column
  • 5. Proprietary (Trade Names): • Geopier - Rammed Aggregate Pier • TerraRam • GeoRam • VibroPier • Earth Pier • Etcetera Etcetera Pier
  • 6. Geopier drill Geopier Tamper Skid steer  Mobile crew (4 people, 3 machines)  Rapid installations (30 – 50 per day)  Safe, clean, dry process (no jetting!)  Installation depths up to 30 feet Geopier GP3™ Construction
  • 7.
  • 8.
  • 9. Engineering Aspects • Not a foundation system • Improve near surface soil • Increased bearing capacities below foundations and slabs-on-grade • Reduced settlements
  • 10. Settlement Within Compacted Aggregate Zone Design based on spring analogy:  Rigid footing: Geopier deflection & matrix soil deflection  Stiff spring (RAP element) takes more load than soft spring (matrix soil).
  • 11.  Use conventional geotechnical analysis approaches:  Estimate footing-induced stress (Westergaard, Boussinesq, etc)  Estimate soil compressibility  Traditional elastic or consolidation design methods.  Add lower zone and upper zone for total settlement Settlement Below Aggregate Piers (Lower Zone) B 2B HLZ HUZ
  • 12. Design Process • Foundation Loads • Settlement tolerances • Onsite soil properties • Collaboration – Geotechnical consultant – Structural engineer – Aggregate pier designer/builder
  • 13.
  • 14.
  • 15. Two Project Applications 1.The Park 2.Park Place
  • 17. The Park Project • 1500 apartment units on 29-acres • 4-story wood framed apartment buildings over 2 levels of partial subterranean parking (podium) • Column loads 380 to 1156 KIPS
  • 18. The Park---site conditions • Relatively flat site • Historically used for agriculture • Explored with hollow-stem borings and CPT’s • Groundwater wells. • Underlain by deep alluvium • Interlayered silts, sands, clays • Groundwater at 15 to 30 feet BGS
  • 19. Geotechnical Issues • Groundwater below subterranean levels (5 to 10 feet) • Reduced bearing capacities • Differential foundation loads and differential settlements
  • 20. Alternatives × Piles infeasible × Remedial Grading---groundwater × Matt foundation ($7 million) Ground improvement---aggregate piers
  • 21. Geopiers at The Park • 2,400 piers • 30-inch diameter • 11 to 13 feet deep • 50 to 60 working days • Savings over mat foundation: $3 million
  • 22. Acknowledgements Project Owner: Irvine Company Specialty Contractor: Geopier Structural Engineer: Van Dorp Chow
  • 25. Park Place Project • 980 units on 14-acres • 4-story wood framed buildings • 2-levels, partially subterranean, reinforced concrete parking below • Column loads: 94 to 807 kips • Wall loads: <12.5 kips/l.f.
  • 26. Park Place --Site Conditions • Relatively flat site • Formerly MARSHLAND (swamps) • Underlain by PEAT/organic clays, alluvium • Groundwater at 20 to 30 feet BGS
  • 28. Geotechnical Issues • Very low bearing capacities • 4 inches total settlement in alluvium (2 inches differential) • Mat foundations infeasible over marsh soils • Conventional aggregate piers inadequate in marsh deposits (peat)
  • 29. Geopiers at Park Place • 4,798 piers • 24-inch diameter • 9 to 13 feet deep • Cement Treated Piers (474) in MARSH Deposit areas • Cement Treated Piers---up to 30’ deep
  • 30.
  • 31. Acknowledgements Project Owner: Irvine Company Specialty Contractor: Tensar-Geopier (Western Ground Improvement) Structural Engineer: HCDA Engineering, Inc.
  • 32. Construction QA/QC • Aggregate properties • Surface logging of excavated soil • Pier depths • Pier locations
  • 33.
  • 34. Purpose: Measure Stiffness (kg) W-Beam Uplift Anchor Rod 100 Ton Jack Uplift Anchor PierTelltaleCompression Pier Insitu Modulus Test