SlideShare a Scribd company logo
CHANGES IN GEOTECHNICAL ENGINEERING
Chua Tong Seng
Managing Director, Kiso-Jiban Singapore Pte Ltd
GeoSS
CHANGES IN SINGAPORE
6000 year ago
Pre-Jurassic age
2013 - Future1960
Root of Trees: Geotechnical Engineering
CHANGES IN CAREER PATH
Knowledge & Happiness
Specialist Contractor
Soil Nails & Ground anchors Ground anchor and soil nails
Deep Excavation in Built-up Area
Geotechnical Consultant
Supervision & Analysis of KPE, Kallang Paya Lebar Expressway
Longest road tunnel in Singapore & South East Asia
KPE, Kallang Paya Lebar Expressway
One of the toughest projects in the world, The Straits Times, 2004
KPE Tunnel & Pelton Canal
36 ~ 55 m
10 m
5 m
~ 6 m
Song,2006
South Bound North Bound
18 – 27m canal
Blk
125
Blk
126
Blk
122
Blk
121
70m
Near Existing Structures & Tight Corridor
Chan,2006
HDB
Blk
HDB
Blk
Soft Soil
Old Alluvium
1m thick D/ Walls
South BoundNorth Bound
1m thick Cross-Wall using
Diaphragm Panel (7m c/c)0.8m thick Center D/ Wall
Sheet Pile + soldier piles
1.4m thick D/ Walls
Bored Pile
Soft Soil
Chan,2006
Cross Section
~RL70
~RL103
Blk
122
Blk
125 Construction of
Southbound Tunnel
Half Box Construction
First Stage
Song,2006
Cross-Wall @7m c/c
Blk
122
Blk
125
Excavation up to
formation level
(with Strutting System)
Half Box Construction
Second Stage
Song,2006
Completed tunnel
2- Stage Construction (Half-box)
First Stage excavation: SB Second stage excavation: NB
SB
SB
NBSB
Construction is Imperfect (No Change)
• need to factor construction imperfection in
design
• close supervision together with finer
understanding of the geotechnical behaviour
through Analysis is important
Geotechnical Consultant
LTA, Circle Line Project, PPJ Station
North D-wall Construction Top Deck Slab Construction
P24
Cross-wall Section
Cross wall
Layout Plan
P20 P25P21 P22 P23 P24
Site Inspection of Cross-wall
UNIQUE METHODS
Across the Causeway: JB,Malaysia
Further North: Kuala Lumpur Limestone
Oversea Project: Philippine
25m
Middle East Project: Saudi Arabia
Features of Coralline Limestone
MEETING PEOPLE
Kepple Land International Limited
Keppel AlNumu Development Ltd
(A Keppel Land – SEDCO Joint Venture)
Saudi Diyar Consultants
Kiso-Jiban Consultants Co Ltd
CHANGES IN TECHNOLOGY
Some Observed Trends
Ground Anchors
60 T 150T
Reclamation
Method of Placing and Type of Materials
Shore Protection
Shallow: Armour Rocks Deeper: Caisson
Pile Load Testing
Anchors, Kentledge, Reaction Frame, Rapid Load Test, Proof Coring
SOIL INVESTIGATION
Borehole Image Processor, BIP
interesting and game changing
CHANGES IN METHOD OF ANALYSIS
Trends toward “finding the full picture myself”
2-D 3-DEmpirical
• i.e. Terzaghi
& Peck, 1967
• Based on
“what others
tell you”
Building Information Modeling, BIM
in Geotechnical Works
BIM, 4-D (time dimension) Holistic Approach including Analysis & Design
CHANGES IN LAWS & PUBLIC
EXPECTATION
Intersecting Trends
Impact of Nicoll Highway Collapse
Site photo KY Yong & SL Lee, 2008
Changes in Building Control (Amendment) Act 2007
• Any projects that involved:
• Deep excavation for depth >6m
• Foundations for buildings more than 30 storey
• Bored tunnel with diameter more than 2m
• Slope with height more than 6m
Require specialist PE(Geo) and specialist AC(Geo)
• New definition of Temporary buildings
• Does not include any earth retaining structure
• Temporary Works and Permanent Works are treated with
the same level of importance
Role of Specialist PE(Geo) and AC(Geo)
Building Control (Amendment No.2) Regulations 2008
• Specialist Professional Engineer (Geo)
– Determine the SI, namely type, extent (which shall include
quantity, layout, and depth) method of sampling, coring and
laboratory test results for the design and construction of earth
retaining structure including earth slope;
– Analyse the SI results and determine the geotechnical parameters
for the design of the earth retaining structure including
consideration of onerous water conditions, seepage pressures and
surcharge, earth, water, construction and accidental loadings;
– Determine and adopt appropriate method or model for the
analysis and design including the consideration of drained,
undrained and consolidation analyses, and appropriate drainage
conditions;
– Determine suitability of earth retaining structure types and
scheme, and the method and sequence of construction;
– Analyse the stability of the excavation work, taking into
consideration ground water, drainage and seepage conditions,
basal heave, hydraulic uplift and piping, and determine the ground
stabilisation or improvement works as appropriate;
– Determine allowable limits of ground deformation and changes in
ground water and piezometric levels, and measures to control
groundwater where required;
– Design tie-backs, soil or rock reinforcement, where applicable,
including the consideration of the structural and geotechnical
capacity;
– Ensure that drawings of the earth retaining structure, including
earth slope, are consist with the calculation relating to the
geotechnical aspects;
– Determine the instrumentation and monitoring of geotechnical
engineering parameters such as pore pressure, water table levels,
ground deformation and stresses including the consideration of
location, type and number of instruments, and frequency of
monitoring and reporting; and
– Assess monitoring results and sit condition to ensure that the
geotechnical aspects during construction are within design
assumptions and parameters at every critical stage of construction
and review or modify the design so as to ensure its adequacy as
appropriate.
• Specialist Accredited Checker AC (Geo)
– Review the adequacy of the SI, namely type, extent (which shall
include quantity, location and depth) and laboratory tests results
relating to the design and construction of the earth retaining
structure (inc earth slopes);
– Review SI results and the geotechnical parameters for the design
of the earth retaining structures, including consideration of
onerous water conditions, seepage pressures, surcharge, earth,
water, construction and accidental loadings;
– Review the method or model adopted for analysis and design,
including the consideration of drained, undrained and
consolidation analyses, and appropriate drainage conditions;
– Review suitability of earth retaining structure types and scheme,
and the method and sequence of construction to be applied;
– Review the stability of the excavation work, taking into
consideration groundwater, drainage and seepage conditions,
basal heave, hydraulic uplift and piping, and any ground
stabilisation or improvement works as appropriate;
– Review allowable limit of ground deformation and changes in
groundwater and piezometric levels, and measures to control
groundwater where required;
– Review the design of tie-backs, soil or rock reinforcement, where
applicable, including the consideration of the structural and
geotechnical capacity;
– Review the instrumentation and monitoring of geotechnical
engineering parameters (such as pore pressure, water table levels,
ground deformation and stresses) including the consideration of
location, type and number of instruments, and frequency of
monitoring and reporting;
– Review instrumentation and monitoring results and performance
of the earth retaining structure (including any earth slope), and
ground condition at the site to ensure tat there is no inadequacy in
the geotechnical aspects during the construction if carried out in
accordance with the plans of the underground buildings works;
and
– Review the adequacy of the founding or penetration depth of any
embedded earth retaining wall
WHAT LIES AHEAD OF US?
Inspirations to keep Spirit Up
Public Housing Project
12 &25 storey More than 40 storey
“Interaction and Iteration” to Integration
Plaxis 3D Foundation V2 ETABS V9.7
Initial spring constant
Loadings
Springs
Infrastructure Projects more Complex
Typical depth = 20-25m Deeper
Wen,2012
CHANGES IN TRADITIONS /
CUSTOMS
CHANGES IN HABITS
Plaxis Colour
Coding to
Improve
Productivity
and Efficiency
(QP,AC & BCA)
CHANGES IN PILING PRACTICES
Large Diameter
Piles with Bell-out
HOW DO WE COPE WITH
CHANGES?
Learn from Others
LEARN FROM MISTAKE
“Engineers shall hold
paramount the safety,
health and welfare of
the Public”, …
Prof R. Gilbert, USA
GeoSS-BCA Hong Kong Educational Visit
18-21 March 2012
• GeoSS
• BCA
• HDB
• Consultants
• Piling Specialists
GeoSS-BCA Taiwan Industry Learning Trip
17-20 March 2013
Passion, Passion, Passion
for things you do
Passionate about your Profession / Society
GeoSS-BCA-TGS, Taiwan, 2013 5YGEC, Japan, 2012
Empowering the Youth, SYGeoSS
• Founded on 25 May 2012
– Cham Wee Meng (Chairman)
– Lim Shiyi (Vice Chairman)
– Michelle Lew (Secretary)
– Dr. Yang Haibo (Treasurer)
– Goh Kok Hun
– Edward Koh Cho Meng
– Zhang Yunho
– Tran Vu Quoc
FACE THE CHANGES TOGETHER
Thank you
SYGeoSS Alumni Industry GeoSS
GeoSS

More Related Content

What's hot

GSG Project Experience
GSG Project ExperienceGSG Project Experience
GSG Project Experience
Kalyan (Kal) S. Chandhuri, P.E.
 
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi
 
Jason Abendroth Resume_10_2015
Jason Abendroth Resume_10_2015Jason Abendroth Resume_10_2015
Jason Abendroth Resume_10_2015
Jason Abendroth, PE
 
SOFE Poster 2013
SOFE Poster 2013SOFE Poster 2013
SOFE Poster 2013
Neway Atnafu, PE, PMP
 
Max Sommers CV 2017
Max Sommers CV 2017Max Sommers CV 2017
Max Sommers CV 2017
Max Sommers
 
Zupt Inertial Metrology - SUT / THS Subsea Metrology Seminar
Zupt Inertial Metrology - SUT / THS Subsea Metrology SeminarZupt Inertial Metrology - SUT / THS Subsea Metrology Seminar
Zupt Inertial Metrology - SUT / THS Subsea Metrology Seminar
Zupt, LLC
 
Geotechnical Engineering - Dams
Geotechnical Engineering - DamsGeotechnical Engineering - Dams
Geotechnical Engineering - Dams
Nebraska Transportation Center
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16
Don Dwyer
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
IJERA Editor
 
ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002
William Godwin
 
CV ASIF MAHMOOD
CV ASIF MAHMOODCV ASIF MAHMOOD
CV ASIF MAHMOOD
ASIF MAHMOOD FIDA
 
Cv asif mahmood
Cv asif mahmoodCv asif mahmood
Cv asif mahmood
ASIF MAHMOOD FIDA
 
IRJET- An Innovative Method of Electricity Generation from Speed-Breakers of ...
IRJET- An Innovative Method of Electricity Generation from Speed-Breakers of ...IRJET- An Innovative Method of Electricity Generation from Speed-Breakers of ...
IRJET- An Innovative Method of Electricity Generation from Speed-Breakers of ...
IRJET Journal
 
Capability Statement
Capability StatementCapability Statement
Capability Statement
Phil Styles
 
Amiya Resume - Apr 2016
Amiya Resume - Apr 2016Amiya Resume - Apr 2016
Amiya Resume - Apr 2016
AMIYA KUMAR GHOSH
 
Styles_Phil_Geotech (long) 20151222
Styles_Phil_Geotech (long) 20151222Styles_Phil_Geotech (long) 20151222
Styles_Phil_Geotech (long) 20151222
Phil Styles
 
35
3535

What's hot (17)

GSG Project Experience
GSG Project ExperienceGSG Project Experience
GSG Project Experience
 
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...
 
Jason Abendroth Resume_10_2015
Jason Abendroth Resume_10_2015Jason Abendroth Resume_10_2015
Jason Abendroth Resume_10_2015
 
SOFE Poster 2013
SOFE Poster 2013SOFE Poster 2013
SOFE Poster 2013
 
Max Sommers CV 2017
Max Sommers CV 2017Max Sommers CV 2017
Max Sommers CV 2017
 
Zupt Inertial Metrology - SUT / THS Subsea Metrology Seminar
Zupt Inertial Metrology - SUT / THS Subsea Metrology SeminarZupt Inertial Metrology - SUT / THS Subsea Metrology Seminar
Zupt Inertial Metrology - SUT / THS Subsea Metrology Seminar
 
Geotechnical Engineering - Dams
Geotechnical Engineering - DamsGeotechnical Engineering - Dams
Geotechnical Engineering - Dams
 
Resume Dwyer 9-16
Resume Dwyer 9-16Resume Dwyer 9-16
Resume Dwyer 9-16
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002
 
CV ASIF MAHMOOD
CV ASIF MAHMOODCV ASIF MAHMOOD
CV ASIF MAHMOOD
 
Cv asif mahmood
Cv asif mahmoodCv asif mahmood
Cv asif mahmood
 
IRJET- An Innovative Method of Electricity Generation from Speed-Breakers of ...
IRJET- An Innovative Method of Electricity Generation from Speed-Breakers of ...IRJET- An Innovative Method of Electricity Generation from Speed-Breakers of ...
IRJET- An Innovative Method of Electricity Generation from Speed-Breakers of ...
 
Capability Statement
Capability StatementCapability Statement
Capability Statement
 
Amiya Resume - Apr 2016
Amiya Resume - Apr 2016Amiya Resume - Apr 2016
Amiya Resume - Apr 2016
 
Styles_Phil_Geotech (long) 20151222
Styles_Phil_Geotech (long) 20151222Styles_Phil_Geotech (long) 20151222
Styles_Phil_Geotech (long) 20151222
 
35
3535
35
 

Similar to GeoSS,18SEAGS, 2013, Singapore

Resume Principal Consultant Soilsrock
Resume Principal Consultant SoilsrockResume Principal Consultant Soilsrock
Resume Principal Consultant Soilsrock
Jorge Cabaco
 
LECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdfLECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdf
DRJULAIDAKALIWON
 
Building technology.pptx
Building technology.pptxBuilding technology.pptx
Building technology.pptx
Neha569445
 
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
Appalachian Research Initiative for Environmental Science
 
Underground rock reinforcement and support
Underground rock reinforcement and supportUnderground rock reinforcement and support
Underground rock reinforcement and support
Balraj Joshi
 
Dam engineering i 3
Dam engineering i 3Dam engineering i 3
Dam engineering i 3
FeteneBefekadu
 
Introduction to Site Investigation Methods
Introduction to Site Investigation MethodsIntroduction to Site Investigation Methods
Introduction to Site Investigation Methods
MohdBilal430488
 
Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over view
R K DHIMAN
 
Soil.pptx
Soil.pptxSoil.pptx
Soil.pptx
Parthanajwala1
 
Applicatio of Soil Structure Interaction in the analysis of flexible retainin...
Applicatio of Soil Structure Interaction in the analysis of flexible retainin...Applicatio of Soil Structure Interaction in the analysis of flexible retainin...
Applicatio of Soil Structure Interaction in the analysis of flexible retainin...
NikhilGautam68
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Mohit Shukla
 
Dirnberger Kiewit Resume
Dirnberger Kiewit ResumeDirnberger Kiewit Resume
Dirnberger Kiewit Resume
Moe Dirnberger, PhD, PE, RG, D. GE
 
2006 AEG Godwin presentation
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentation
William Godwin
 
Geotech site investigation
Geotech site investigationGeotech site investigation
Geotech site investigation
SHWETABH SINHA
 
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
Mohd Murtaza
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
Dr Mazin Alhamrany
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnelling
Prof. A.Balasubramanian
 
3.0 soil exploration
3.0 soil exploration3.0 soil exploration
3.0 soil exploration
Rakesh Reddy
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
IRJET Journal
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
IRJET Journal
 

Similar to GeoSS,18SEAGS, 2013, Singapore (20)

Resume Principal Consultant Soilsrock
Resume Principal Consultant SoilsrockResume Principal Consultant Soilsrock
Resume Principal Consultant Soilsrock
 
LECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdfLECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdf
 
Building technology.pptx
Building technology.pptxBuilding technology.pptx
Building technology.pptx
 
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
 
Underground rock reinforcement and support
Underground rock reinforcement and supportUnderground rock reinforcement and support
Underground rock reinforcement and support
 
Dam engineering i 3
Dam engineering i 3Dam engineering i 3
Dam engineering i 3
 
Introduction to Site Investigation Methods
Introduction to Site Investigation MethodsIntroduction to Site Investigation Methods
Introduction to Site Investigation Methods
 
Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over view
 
Soil.pptx
Soil.pptxSoil.pptx
Soil.pptx
 
Applicatio of Soil Structure Interaction in the analysis of flexible retainin...
Applicatio of Soil Structure Interaction in the analysis of flexible retainin...Applicatio of Soil Structure Interaction in the analysis of flexible retainin...
Applicatio of Soil Structure Interaction in the analysis of flexible retainin...
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
Dirnberger Kiewit Resume
Dirnberger Kiewit ResumeDirnberger Kiewit Resume
Dirnberger Kiewit Resume
 
2006 AEG Godwin presentation
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentation
 
Geotech site investigation
Geotech site investigationGeotech site investigation
Geotech site investigation
 
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnelling
 
3.0 soil exploration
3.0 soil exploration3.0 soil exploration
3.0 soil exploration
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
 

GeoSS,18SEAGS, 2013, Singapore

  • 1. CHANGES IN GEOTECHNICAL ENGINEERING Chua Tong Seng Managing Director, Kiso-Jiban Singapore Pte Ltd GeoSS
  • 2. CHANGES IN SINGAPORE 6000 year ago Pre-Jurassic age 2013 - Future1960
  • 3. Root of Trees: Geotechnical Engineering
  • 4. CHANGES IN CAREER PATH Knowledge & Happiness
  • 5. Specialist Contractor Soil Nails & Ground anchors Ground anchor and soil nails
  • 6. Deep Excavation in Built-up Area
  • 7. Geotechnical Consultant Supervision & Analysis of KPE, Kallang Paya Lebar Expressway Longest road tunnel in Singapore & South East Asia
  • 8. KPE, Kallang Paya Lebar Expressway One of the toughest projects in the world, The Straits Times, 2004
  • 9. KPE Tunnel & Pelton Canal 36 ~ 55 m 10 m 5 m ~ 6 m Song,2006 South Bound North Bound 18 – 27m canal
  • 11. HDB Blk HDB Blk Soft Soil Old Alluvium 1m thick D/ Walls South BoundNorth Bound 1m thick Cross-Wall using Diaphragm Panel (7m c/c)0.8m thick Center D/ Wall Sheet Pile + soldier piles 1.4m thick D/ Walls Bored Pile Soft Soil Chan,2006 Cross Section ~RL70 ~RL103
  • 12. Blk 122 Blk 125 Construction of Southbound Tunnel Half Box Construction First Stage Song,2006 Cross-Wall @7m c/c
  • 13. Blk 122 Blk 125 Excavation up to formation level (with Strutting System) Half Box Construction Second Stage Song,2006 Completed tunnel
  • 14. 2- Stage Construction (Half-box) First Stage excavation: SB Second stage excavation: NB SB SB NBSB
  • 15. Construction is Imperfect (No Change) • need to factor construction imperfection in design • close supervision together with finer understanding of the geotechnical behaviour through Analysis is important
  • 16. Geotechnical Consultant LTA, Circle Line Project, PPJ Station North D-wall Construction Top Deck Slab Construction P24
  • 18. Layout Plan P20 P25P21 P22 P23 P24
  • 19. Site Inspection of Cross-wall
  • 21. Across the Causeway: JB,Malaysia
  • 22. Further North: Kuala Lumpur Limestone
  • 24. Middle East Project: Saudi Arabia
  • 26. MEETING PEOPLE Kepple Land International Limited Keppel AlNumu Development Ltd (A Keppel Land – SEDCO Joint Venture) Saudi Diyar Consultants Kiso-Jiban Consultants Co Ltd
  • 27. CHANGES IN TECHNOLOGY Some Observed Trends
  • 29. Reclamation Method of Placing and Type of Materials
  • 30. Shore Protection Shallow: Armour Rocks Deeper: Caisson
  • 31. Pile Load Testing Anchors, Kentledge, Reaction Frame, Rapid Load Test, Proof Coring
  • 32. SOIL INVESTIGATION Borehole Image Processor, BIP interesting and game changing
  • 33. CHANGES IN METHOD OF ANALYSIS Trends toward “finding the full picture myself” 2-D 3-DEmpirical • i.e. Terzaghi & Peck, 1967 • Based on “what others tell you”
  • 34. Building Information Modeling, BIM in Geotechnical Works BIM, 4-D (time dimension) Holistic Approach including Analysis & Design
  • 35. CHANGES IN LAWS & PUBLIC EXPECTATION Intersecting Trends
  • 36. Impact of Nicoll Highway Collapse Site photo KY Yong & SL Lee, 2008
  • 37. Changes in Building Control (Amendment) Act 2007 • Any projects that involved: • Deep excavation for depth >6m • Foundations for buildings more than 30 storey • Bored tunnel with diameter more than 2m • Slope with height more than 6m Require specialist PE(Geo) and specialist AC(Geo) • New definition of Temporary buildings • Does not include any earth retaining structure • Temporary Works and Permanent Works are treated with the same level of importance
  • 38. Role of Specialist PE(Geo) and AC(Geo) Building Control (Amendment No.2) Regulations 2008 • Specialist Professional Engineer (Geo) – Determine the SI, namely type, extent (which shall include quantity, layout, and depth) method of sampling, coring and laboratory test results for the design and construction of earth retaining structure including earth slope; – Analyse the SI results and determine the geotechnical parameters for the design of the earth retaining structure including consideration of onerous water conditions, seepage pressures and surcharge, earth, water, construction and accidental loadings; – Determine and adopt appropriate method or model for the analysis and design including the consideration of drained, undrained and consolidation analyses, and appropriate drainage conditions; – Determine suitability of earth retaining structure types and scheme, and the method and sequence of construction; – Analyse the stability of the excavation work, taking into consideration ground water, drainage and seepage conditions, basal heave, hydraulic uplift and piping, and determine the ground stabilisation or improvement works as appropriate; – Determine allowable limits of ground deformation and changes in ground water and piezometric levels, and measures to control groundwater where required; – Design tie-backs, soil or rock reinforcement, where applicable, including the consideration of the structural and geotechnical capacity; – Ensure that drawings of the earth retaining structure, including earth slope, are consist with the calculation relating to the geotechnical aspects; – Determine the instrumentation and monitoring of geotechnical engineering parameters such as pore pressure, water table levels, ground deformation and stresses including the consideration of location, type and number of instruments, and frequency of monitoring and reporting; and – Assess monitoring results and sit condition to ensure that the geotechnical aspects during construction are within design assumptions and parameters at every critical stage of construction and review or modify the design so as to ensure its adequacy as appropriate. • Specialist Accredited Checker AC (Geo) – Review the adequacy of the SI, namely type, extent (which shall include quantity, location and depth) and laboratory tests results relating to the design and construction of the earth retaining structure (inc earth slopes); – Review SI results and the geotechnical parameters for the design of the earth retaining structures, including consideration of onerous water conditions, seepage pressures, surcharge, earth, water, construction and accidental loadings; – Review the method or model adopted for analysis and design, including the consideration of drained, undrained and consolidation analyses, and appropriate drainage conditions; – Review suitability of earth retaining structure types and scheme, and the method and sequence of construction to be applied; – Review the stability of the excavation work, taking into consideration groundwater, drainage and seepage conditions, basal heave, hydraulic uplift and piping, and any ground stabilisation or improvement works as appropriate; – Review allowable limit of ground deformation and changes in groundwater and piezometric levels, and measures to control groundwater where required; – Review the design of tie-backs, soil or rock reinforcement, where applicable, including the consideration of the structural and geotechnical capacity; – Review the instrumentation and monitoring of geotechnical engineering parameters (such as pore pressure, water table levels, ground deformation and stresses) including the consideration of location, type and number of instruments, and frequency of monitoring and reporting; – Review instrumentation and monitoring results and performance of the earth retaining structure (including any earth slope), and ground condition at the site to ensure tat there is no inadequacy in the geotechnical aspects during the construction if carried out in accordance with the plans of the underground buildings works; and – Review the adequacy of the founding or penetration depth of any embedded earth retaining wall
  • 39. WHAT LIES AHEAD OF US? Inspirations to keep Spirit Up
  • 40. Public Housing Project 12 &25 storey More than 40 storey
  • 41. “Interaction and Iteration” to Integration Plaxis 3D Foundation V2 ETABS V9.7 Initial spring constant Loadings Springs
  • 42. Infrastructure Projects more Complex Typical depth = 20-25m Deeper Wen,2012
  • 44. CHANGES IN HABITS Plaxis Colour Coding to Improve Productivity and Efficiency (QP,AC & BCA)
  • 45. CHANGES IN PILING PRACTICES Large Diameter Piles with Bell-out
  • 46. HOW DO WE COPE WITH CHANGES? Learn from Others
  • 47. LEARN FROM MISTAKE “Engineers shall hold paramount the safety, health and welfare of the Public”, … Prof R. Gilbert, USA
  • 48. GeoSS-BCA Hong Kong Educational Visit 18-21 March 2012 • GeoSS • BCA • HDB • Consultants • Piling Specialists
  • 49. GeoSS-BCA Taiwan Industry Learning Trip 17-20 March 2013
  • 51. Passionate about your Profession / Society GeoSS-BCA-TGS, Taiwan, 2013 5YGEC, Japan, 2012
  • 52. Empowering the Youth, SYGeoSS • Founded on 25 May 2012 – Cham Wee Meng (Chairman) – Lim Shiyi (Vice Chairman) – Michelle Lew (Secretary) – Dr. Yang Haibo (Treasurer) – Goh Kok Hun – Edward Koh Cho Meng – Zhang Yunho – Tran Vu Quoc
  • 53. FACE THE CHANGES TOGETHER Thank you SYGeoSS Alumni Industry GeoSS GeoSS