SlideShare a Scribd company logo
WORKING OF STEAM TURBINE AND
ITS AUXILIARIES
JYOTHISHMATHI INSTITUTE OF
TECHNOLOGYAND SCIENCE
PRESENTED BY
G.SAI RAMANA (17275A0319)
V.GANESH (16271A0309)
S.MOUNIKA (17275A0302)
K.RAVI VARDHAN (16271A0321)
K.SHARAN (16271A0327)
CONTENTS
1.About Ntpc Ramagundam Rstps
2.Priniciple And Operation Of A Thermal Power Plant
3. Introduction To Steam Turbine & Steam Turbine Parts
4.Specifications of Steam Turbine
5.Turbine Auxiliaries
6. Lubrication Oil System
Conclusion
ABOUT NTPC RAMAGUNDAM – RSTPS
NTPC Ramagundam, a part of National Thermal Power Corporation, is a
2600 MW Power station
NTPC Ltd., Ramagundam has two TG Halls one for STAGE - I and the
other common for STAGE-II and STAGE-III.
Unit-wise power generation:
The whole plant is divided into 3 stages, each stage being planned at
one time.
STAGE 1 (3 * 200MW):
This stage consists of three units (Unit-1, Unit-2, Unit-3) each with a
generation capacity of 200MW
STAGE 2 (3 * 500MW):
This stage again consists of three units (Unit-4, Unit-5, Unit-6) each with
a generation capacity of 500MW.
STAGE 3 (1 * 500MW):
This stage comprises only one unit (Unit - 7). This is a first of its kind in
South India being a computer operated unit.
Principle and Operation of a Thermal
Power Plant
Principle:
Any Steam Power Plant operates under the Simple Ranki ne Cycle.
Hence the Rankine cycle is often termed as Basic Power Plant Cycle.
Block diagram of plant operating cycle
Mechanical Maintenance:
This dept. has the following sections
Boiler Maintenance:
Boiler feeders
Primary and secondary air pumps
Boiler feed pumps
Boiler core parts
Turbine Maintenance:
Turbine core parts
Turbine governing system
Introduction To Steam Turbine &
Steam Turbine Parts
A steam turbine is a mechanical device that extracts thermal energy from
pressurized steam, and converts it into rotary motion. Its modern
manifestation was invented by Sir Charles Parsons in 1884.
Classifications of steam turbines
1.Impulse Turbine
2.Reaction Turbine
HP TURBINE, BARREL TYPE CASING:
1.The outer casing of the HP turbine is of the barrel type and has
neither an axial nor a radial flange.
2.This prevents mass accumulation with high thermal stresses. The
almost perfect rotational symmetry permits moderate wall thickness of
nearly equal strength at all sections.
3.The guide blade carrier is axially split and kinematically supported. As
only slight pressure differences are effective, the horizontal flange and
connection bolts can be kept small.
4.The barrel type casing permits flexibility of operation in the form of
short startup times and a high rate of change of load even at high initial
steam conditions.
SECTIONAL VIEW OF HP TURBINE
IP TURBINE:
1.The IP turbine part is double flow construction. Attached in
the axially split casing is an inner casing supported
kinematically and taking the guide blades.
2.The reheated steam is admitted to the inner casing through
the top and bottom center of the casing.
3.The arrangement of an inner casing confines the high steam
inlet conditions to the admission branch of the casing, while
the joint of the outer casing is only subjected to the lower
pressure and lower temperature at theexhaust of the inner
casing.
IP TURBINE
LP TURBINE:
1.The casing of the double flow IP cylinder is of three shell
design. The shells are axially split and have rigid welded
construction.
2.The inner shell taking the first rows of the guide blades is
attached kinematically in the middle shelf.
3. Independent of the outer shell, the middle shell issupported
at four points on longitudinal beams. Two rings carrying them
last guide blade rows are also attached to the middle shelf.
LP TURBINE WITH SHAFT
Turbine Auxiliaries
TURBINE GOVERNING SYSTEM
Power station turbines are constant speed machines and they are rotated
at a speed of 3000rpm to enable the coupled generator to produce
electricity at 50 Hz frequency.
The main purpose of the governor is to maintain the desired speed of
turbine during fluctuation of load on generator by varying steam input
into the turbine as required.
TYPES OF GOVERNING SYSTEMS:
1. Throttle Governing.
2. Nozzle Governing.
3. Bypass Governing.
Throttle Governing Nozzle Governing
Bypass Governing
VACUUM SYSTEM:
As we begin the recirculating processes, the first system, which comes
into focus, is the vacuum system. The equipments under this system, as
described in this chapter, strive to maximize the work done of turbine by
maintaining the rated vacuum limits.
Condenser
CONDENSATE SYSTEM
The steam after condensing in the condensing in the condenser known as
condensate, is extracted out of the condenser hot well by condensate
pump and taken to the deaerator through ejectors, gland steam cooler
and series of LP heaters
Condensate Pumps:
The function of these pumps is to pump out the condensate to the
deaerator through’ injector, gland steam cooler and LP heaters. These
pumps have four stages and since the suction is at a negative pressure,
special arrangements have been made for providing sealing.
Gland Steam Cooler:
Steam from deaerator or from Auxillary steam header is
supplied to the end seals of the HP rotor and LP rotor
generally at a pressure of 0.01 to 1.03 ata. So as to prevent
ingress of atmosphere air into the turbine thru’ the end
clearances. This steam supplied to the end seals is
extracted by the gland steam cooler by the auction of
single stage steam ejector.
FEED WATER SYSTEM
This system plays an important role in the supply of feed water to the
boiler at requisite pressure and steam water ratio. This chapter describes
the various auxiliaries under this system starting from Boiler Feed Pump
to Feed regulating station via HP heaters.
Boiler Feed Pump:
This pump is horizontal and of barrel design driven by an Electric motor
through a hydraulic coupling. All the bearings of pump and motor are
forced lubricated by a suitable oil lubricating system with adequate
protection to trip the pump if the lubrication oil pressure fails below a
preset valve.
Turbine Driven Boiler Feed Pump:
The single cylinder turbine is of the axial flow type.The live steam flows
through emergency stop valve and then through the main control
valves.The valves regulate the steam supply through the turbine.There
are 14 stages of reaction blading.The turbine is provided with the electro
hydraulic governing system.The steam exhausted from the BFP turbine is
directly connected to the main condenser and the turbine glands are
gland steam.There are 2 TDBFP’s for each 500MW unit at ramagundam
of capacity 1080.3m3/hr at 204.32 bar.
High Pressure Heaters:
These are regenerative feed water heaters operating at high pressure and
located by the side of turbine. These are generally vertical type and
turbine bled steam pipes are connected to them.
HP heaters are connected in series on feed water side and by such
arrangement, the fed water, after feed pump enters the HP Heaters. The
steam is supplied to these heaters from the bled point of the turbine
through motor operated valves. These heaters have a group bypass
protection on the feed water side. In the event of tube rupture in any of
the HPH and the level of the condensate rising to dangerous level, the
group protection device diverts automatically the feed water directly to
boiler, thus bypassing all the 3 HP heaters.
COOLING WATER SYSTEM:
Equipment cooling water (ECW) system: This water is used to cool the heated
lubricating oil coming from the lube oil coolers of boiler and turbine side. This is
demineralised water and is supplied through ECW pumps.
Auxiliary cooling water (ACW) system: This is raw water, taken a taping from CW
pumps discharge side, pressurized and circulated in a Plate Heat Exchanger to cool
the heated ECW water.
COOLING TOWERS (CTs):
A closed circuit cooling system is used for heat rejection that consists of cooling
pond and two cooling towers, ponds and towers are connected in a parallel
arrangement to study the behavior of the cooling system.
The cooling tower models based on the analogy approach of a cooling tower and an
heat exchanger. An effectiveness-NTU method is employed to predict the cooling
tower performance with respect to ambient and load conditions.
LUBRICATION OIL SYSTEM
Introduction: same oil is used for governing & lubrication. The oil is kept in the main
oil tank. The governing is designed for operation at the oil pressure of 14kg/cmsq while
lubrication of bearings is designed to work at 2kg/cmsq.The following equipment is
available in the lubricating system.
1. Auxiliary oil pump
2. A.C lube oil pump
3. D.C emergency oil pump
4. main oil pump
5. booster pump
6. oil tank
7. oil coolers
8. vent fans
Turbine Lube Oil System
Conclusion
The working of Steam Turbine 500MW was studied, the
process of Conversion of Kinetic head of Steam into
Mechanical Energy was observed. The Auxiliaries of
Steam Turbine and their importance in power generation
were studied and observed the various components involved
in the working of Steam Turbine.

More Related Content

What's hot

steam turbines presentation
steam turbines presentationsteam turbines presentation
steam turbines presentation
Viswanath Raju Indukuri
 
Stator water system chemistry
Stator water system chemistryStator water system chemistry
Stator water system chemistry
Sudhanshu Sekhar Dash
 
Impulse and reaction steam turbines
Impulse and reaction steam turbinesImpulse and reaction steam turbines
Impulse and reaction steam turbines
Sushil Chapagain
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnostic
Pichai Chaibamrung
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Anish Kumar Gupta
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
Mohammed Sameer
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
Ashvani Shukla
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
Gaurav Kaushik
 
condensate system
condensate systemcondensate system
condensate system
vikrantdesh
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
Vaibhav Paydelwar
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to Knowledge
Anshuman Tyagi
 
Steam Turbines Basics
Steam Turbines BasicsSteam Turbines Basics
Steam Turbines Basics
Prasad Vejendla
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plantsSHIVAJI CHOUDHURY
 
A Report on Steam Turbine
A Report on Steam TurbineA Report on Steam Turbine
A Report on Steam Turbine
Rajput Chauhan
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheater
HOANG VAN DUC
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines
Amir Ayad
 
660 mw turbo generator & its auxiliaries
660 mw turbo generator & its auxiliaries660 mw turbo generator & its auxiliaries
660 mw turbo generator & its auxiliaries
Ashvani Shukla
 
Evaluation of a Boiler performance
Evaluation of a Boiler performanceEvaluation of a Boiler performance
Evaluation of a Boiler performance
Hashim Hasnain Hadi
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
Vaibhav Paydelwar
 
BASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINEBASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINE
SONAM PALJOR
 

What's hot (20)

steam turbines presentation
steam turbines presentationsteam turbines presentation
steam turbines presentation
 
Stator water system chemistry
Stator water system chemistryStator water system chemistry
Stator water system chemistry
 
Impulse and reaction steam turbines
Impulse and reaction steam turbinesImpulse and reaction steam turbines
Impulse and reaction steam turbines
 
Steam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnosticSteam Condenser performance and loss diagnostic
Steam Condenser performance and loss diagnostic
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
 
condensate system
condensate systemcondensate system
condensate system
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to Knowledge
 
Steam Turbines Basics
Steam Turbines BasicsSteam Turbines Basics
Steam Turbines Basics
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
 
A Report on Steam Turbine
A Report on Steam TurbineA Report on Steam Turbine
A Report on Steam Turbine
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheater
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines
 
660 mw turbo generator & its auxiliaries
660 mw turbo generator & its auxiliaries660 mw turbo generator & its auxiliaries
660 mw turbo generator & its auxiliaries
 
Evaluation of a Boiler performance
Evaluation of a Boiler performanceEvaluation of a Boiler performance
Evaluation of a Boiler performance
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
BASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINEBASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINE
 

Similar to Mini project ppt on working of steam turbine and its auxiliaries

kstps training report
kstps training reportkstps training report
kstps training report
Omprakash Choudhary
 
thermal power plant suratgarh ppt
thermal power plant suratgarh ppt thermal power plant suratgarh ppt
thermal power plant suratgarh ppt
Yogesh Singh Takhar
 
Gas Turbine Power Plant.pdf
Gas Turbine Power Plant.pdfGas Turbine Power Plant.pdf
Gas Turbine Power Plant.pdf
KIET Group of Institutions
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
DurgSingh
 
Gas turbines
Gas turbinesGas turbines
Gas turbines
Pampannagowda Patil
 
Ppt
PptPpt
thermal power plant
thermal power plantthermal power plant
thermal power plant
Sahil arora
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.
Ankit Kumar
 
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST MERCIFUL
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST  MERCIFULIN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST  MERCIFUL
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST MERCIFULHafiz M .Hamid
 
PANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANTPANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANT
Sahil arora
 
Internship report RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. Kayamkulam
Internship report  RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. KayamkulamInternship report  RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. Kayamkulam
Internship report RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. Kayamkulam
Sreesankar Jayasingrajan
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadav
mukesh yadav
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
CHANDAN JAISWAL
 
UNIT 2 PPE.ppt
UNIT 2 PPE.pptUNIT 2 PPE.ppt
UNIT 2 PPE.ppt
Rajeswarijana
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
Amit Gupta
 
Turbines
TurbinesTurbines
steam turbine[1] (3).pptxshshshhhshshshh
steam turbine[1] (3).pptxshshshhhshshshhsteam turbine[1] (3).pptxshshshhhshshshh
steam turbine[1] (3).pptxshshshhhshshshh
AzizAlabad
 
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1Prashant kumar
 

Similar to Mini project ppt on working of steam turbine and its auxiliaries (20)

KTPS
KTPSKTPS
KTPS
 
kstps training report
kstps training reportkstps training report
kstps training report
 
thermal power plant suratgarh ppt
thermal power plant suratgarh ppt thermal power plant suratgarh ppt
thermal power plant suratgarh ppt
 
Gas Turbine Power Plant.pdf
Gas Turbine Power Plant.pdfGas Turbine Power Plant.pdf
Gas Turbine Power Plant.pdf
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 
Gas turbines
Gas turbinesGas turbines
Gas turbines
 
Ppt
PptPpt
Ppt
 
thermal power plant
thermal power plantthermal power plant
thermal power plant
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.
 
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST MERCIFUL
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST  MERCIFULIN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST  MERCIFUL
IN THE NAME OF ALLAH THE MOST BENIFICIENT AND MOST MERCIFUL
 
PANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANTPANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANT
 
Internship report RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. Kayamkulam
Internship report  RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. KayamkulamInternship report  RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. Kayamkulam
Internship report RAJIV GANDHI COMBINED CYCLE POWER PLANT-NTPC LTD. Kayamkulam
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadav
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
UNIT 2 PPE.ppt
UNIT 2 PPE.pptUNIT 2 PPE.ppt
UNIT 2 PPE.ppt
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
 
Turbines
TurbinesTurbines
Turbines
 
bhel_report_STM
bhel_report_STMbhel_report_STM
bhel_report_STM
 
steam turbine[1] (3).pptxshshshhhshshshh
steam turbine[1] (3).pptxshshshhhshshshhsteam turbine[1] (3).pptxshshshhhshshshh
steam turbine[1] (3).pptxshshshhhshshshh
 
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
 

Recently uploaded

road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

Mini project ppt on working of steam turbine and its auxiliaries

  • 1. WORKING OF STEAM TURBINE AND ITS AUXILIARIES
  • 2. JYOTHISHMATHI INSTITUTE OF TECHNOLOGYAND SCIENCE PRESENTED BY G.SAI RAMANA (17275A0319) V.GANESH (16271A0309) S.MOUNIKA (17275A0302) K.RAVI VARDHAN (16271A0321) K.SHARAN (16271A0327)
  • 3. CONTENTS 1.About Ntpc Ramagundam Rstps 2.Priniciple And Operation Of A Thermal Power Plant 3. Introduction To Steam Turbine & Steam Turbine Parts 4.Specifications of Steam Turbine 5.Turbine Auxiliaries 6. Lubrication Oil System Conclusion
  • 4. ABOUT NTPC RAMAGUNDAM – RSTPS NTPC Ramagundam, a part of National Thermal Power Corporation, is a 2600 MW Power station
  • 5. NTPC Ltd., Ramagundam has two TG Halls one for STAGE - I and the other common for STAGE-II and STAGE-III. Unit-wise power generation: The whole plant is divided into 3 stages, each stage being planned at one time. STAGE 1 (3 * 200MW): This stage consists of three units (Unit-1, Unit-2, Unit-3) each with a generation capacity of 200MW STAGE 2 (3 * 500MW): This stage again consists of three units (Unit-4, Unit-5, Unit-6) each with a generation capacity of 500MW. STAGE 3 (1 * 500MW): This stage comprises only one unit (Unit - 7). This is a first of its kind in South India being a computer operated unit.
  • 6. Principle and Operation of a Thermal Power Plant Principle: Any Steam Power Plant operates under the Simple Ranki ne Cycle. Hence the Rankine cycle is often termed as Basic Power Plant Cycle.
  • 7. Block diagram of plant operating cycle
  • 8. Mechanical Maintenance: This dept. has the following sections Boiler Maintenance: Boiler feeders Primary and secondary air pumps Boiler feed pumps Boiler core parts Turbine Maintenance: Turbine core parts Turbine governing system
  • 9. Introduction To Steam Turbine & Steam Turbine Parts A steam turbine is a mechanical device that extracts thermal energy from pressurized steam, and converts it into rotary motion. Its modern manifestation was invented by Sir Charles Parsons in 1884.
  • 10. Classifications of steam turbines 1.Impulse Turbine 2.Reaction Turbine
  • 11. HP TURBINE, BARREL TYPE CASING: 1.The outer casing of the HP turbine is of the barrel type and has neither an axial nor a radial flange. 2.This prevents mass accumulation with high thermal stresses. The almost perfect rotational symmetry permits moderate wall thickness of nearly equal strength at all sections. 3.The guide blade carrier is axially split and kinematically supported. As only slight pressure differences are effective, the horizontal flange and connection bolts can be kept small. 4.The barrel type casing permits flexibility of operation in the form of short startup times and a high rate of change of load even at high initial steam conditions.
  • 12. SECTIONAL VIEW OF HP TURBINE
  • 13. IP TURBINE: 1.The IP turbine part is double flow construction. Attached in the axially split casing is an inner casing supported kinematically and taking the guide blades. 2.The reheated steam is admitted to the inner casing through the top and bottom center of the casing. 3.The arrangement of an inner casing confines the high steam inlet conditions to the admission branch of the casing, while the joint of the outer casing is only subjected to the lower pressure and lower temperature at theexhaust of the inner casing.
  • 15. LP TURBINE: 1.The casing of the double flow IP cylinder is of three shell design. The shells are axially split and have rigid welded construction. 2.The inner shell taking the first rows of the guide blades is attached kinematically in the middle shelf. 3. Independent of the outer shell, the middle shell issupported at four points on longitudinal beams. Two rings carrying them last guide blade rows are also attached to the middle shelf.
  • 17.
  • 18. Turbine Auxiliaries TURBINE GOVERNING SYSTEM Power station turbines are constant speed machines and they are rotated at a speed of 3000rpm to enable the coupled generator to produce electricity at 50 Hz frequency. The main purpose of the governor is to maintain the desired speed of turbine during fluctuation of load on generator by varying steam input into the turbine as required. TYPES OF GOVERNING SYSTEMS: 1. Throttle Governing. 2. Nozzle Governing. 3. Bypass Governing.
  • 21. VACUUM SYSTEM: As we begin the recirculating processes, the first system, which comes into focus, is the vacuum system. The equipments under this system, as described in this chapter, strive to maximize the work done of turbine by maintaining the rated vacuum limits. Condenser
  • 22. CONDENSATE SYSTEM The steam after condensing in the condensing in the condenser known as condensate, is extracted out of the condenser hot well by condensate pump and taken to the deaerator through ejectors, gland steam cooler and series of LP heaters Condensate Pumps: The function of these pumps is to pump out the condensate to the deaerator through’ injector, gland steam cooler and LP heaters. These pumps have four stages and since the suction is at a negative pressure, special arrangements have been made for providing sealing.
  • 23. Gland Steam Cooler: Steam from deaerator or from Auxillary steam header is supplied to the end seals of the HP rotor and LP rotor generally at a pressure of 0.01 to 1.03 ata. So as to prevent ingress of atmosphere air into the turbine thru’ the end clearances. This steam supplied to the end seals is extracted by the gland steam cooler by the auction of single stage steam ejector.
  • 24. FEED WATER SYSTEM This system plays an important role in the supply of feed water to the boiler at requisite pressure and steam water ratio. This chapter describes the various auxiliaries under this system starting from Boiler Feed Pump to Feed regulating station via HP heaters. Boiler Feed Pump: This pump is horizontal and of barrel design driven by an Electric motor through a hydraulic coupling. All the bearings of pump and motor are forced lubricated by a suitable oil lubricating system with adequate protection to trip the pump if the lubrication oil pressure fails below a preset valve.
  • 25. Turbine Driven Boiler Feed Pump: The single cylinder turbine is of the axial flow type.The live steam flows through emergency stop valve and then through the main control valves.The valves regulate the steam supply through the turbine.There are 14 stages of reaction blading.The turbine is provided with the electro hydraulic governing system.The steam exhausted from the BFP turbine is directly connected to the main condenser and the turbine glands are gland steam.There are 2 TDBFP’s for each 500MW unit at ramagundam of capacity 1080.3m3/hr at 204.32 bar.
  • 26. High Pressure Heaters: These are regenerative feed water heaters operating at high pressure and located by the side of turbine. These are generally vertical type and turbine bled steam pipes are connected to them. HP heaters are connected in series on feed water side and by such arrangement, the fed water, after feed pump enters the HP Heaters. The steam is supplied to these heaters from the bled point of the turbine through motor operated valves. These heaters have a group bypass protection on the feed water side. In the event of tube rupture in any of the HPH and the level of the condensate rising to dangerous level, the group protection device diverts automatically the feed water directly to boiler, thus bypassing all the 3 HP heaters.
  • 27. COOLING WATER SYSTEM: Equipment cooling water (ECW) system: This water is used to cool the heated lubricating oil coming from the lube oil coolers of boiler and turbine side. This is demineralised water and is supplied through ECW pumps. Auxiliary cooling water (ACW) system: This is raw water, taken a taping from CW pumps discharge side, pressurized and circulated in a Plate Heat Exchanger to cool the heated ECW water. COOLING TOWERS (CTs): A closed circuit cooling system is used for heat rejection that consists of cooling pond and two cooling towers, ponds and towers are connected in a parallel arrangement to study the behavior of the cooling system. The cooling tower models based on the analogy approach of a cooling tower and an heat exchanger. An effectiveness-NTU method is employed to predict the cooling tower performance with respect to ambient and load conditions.
  • 28. LUBRICATION OIL SYSTEM Introduction: same oil is used for governing & lubrication. The oil is kept in the main oil tank. The governing is designed for operation at the oil pressure of 14kg/cmsq while lubrication of bearings is designed to work at 2kg/cmsq.The following equipment is available in the lubricating system. 1. Auxiliary oil pump 2. A.C lube oil pump 3. D.C emergency oil pump 4. main oil pump 5. booster pump 6. oil tank 7. oil coolers 8. vent fans
  • 30. Conclusion The working of Steam Turbine 500MW was studied, the process of Conversion of Kinetic head of Steam into Mechanical Energy was observed. The Auxiliaries of Steam Turbine and their importance in power generation were studied and observed the various components involved in the working of Steam Turbine.