SlideShare a Scribd company logo
METHOD STATEMENT
Page 1 of 9
Description of
Task/ Activity: METHOD STATEMENT FOR PIPE WELDING AT POWER GENERATION
BUILDING.
Project Name: Al Ba’itha Mine Infrastructure and Utilities
Company: Ma’ameer General Contracting, MGC
Prepared By: Anand Subi
Position: Qc inspector Date:
Contractor Project
Manager Review:
Sumesh.G.P
Position: Site Manager Date:
DL Discipline
Engineer/Manager Review:
Position: Construction Manager Date:
DL HSE Manager Review: George Kennedy
Position: HSE Manager Date:
WPF Review: HENRY
Position: HSE Manager Date:
Document Reference:
Associated JSA
Reference Number Attached
Yes No
METHOD STATEMENT
Page 2 of 9
Key Plant and Tools
Required:
Chainblock,welding machines etc.
Key Materials
Required:
N/A
Other Essential
Equipment:
(i.e.: access platforms, Lifting Ropes,Barricade,Signage,Flags,
Winches, Chain block)
Specific Identified
Residual Hazards:
(or refer to the task
specific risk
assessment(s))
N/A
Specific Staff Training
Requirements:
(i.e.: Confined Spaces/Abrasive Wheels/Working at Height/Plant Operators etc)
, crane operator, riggers
Temporary Supports
and Props needed to
facilitate the works:
(If none, state none.)
None
Method of Access and
Egress to the work
area:
N/A
Fall Protection
Measures:
(Where work at height cannot
be eliminated - consider both
Personnel & Materials)
(i.e.: Guard Rails/Toe Boards/Brick Guards/Safety Harnesses/Exclusion Zones etc)
Exclusion zone with barricade , signage and flag man.
Hazardous
Substances:
(Attach COSHH Assessments
and MSDS)
(i.e.: Lubricants/Solvents/Flammable Materials/Refrigerants/Welding Gases etc)
Very Toxic Harmful/
Irritant
Corrosive Dangerous
for the
environment
Oxidising Highly
flammable
Explosive
Applicable: No No No No No No No
METHOD STATEMENT
Page 3 of 9
SWL's:
(Detail any limits on the loadings applicable to temporary plant/equipment or fixed elements of the structure
where the work is taking place.)
Required Personnel
Protective Equip.:
Yes Yes Yes Yes No Yes
OTHER:
1: Coveralls
:
Safety
Boots
Hard Hats Safety
Gloves
Hearing
Protection
Respiratory
Protection
Eye
Protection
Yes Yes Yes
Yes
Yes Yes
High
Visibility
Welder
Shield
Face Shield Fall Arrest Disposable
Mask
Goggles
Emergency
Procedures:
The duties, responsibilities, and names of employees assigned with rescue
and medical tasks.
First Aid Facilities:
Name of On-Site First Aider: Umer
First Aid Box Location: Power Generation biulding
Location of Nearest Hospital: Qiba Hospital
Other Information &
Comments:
Mechanical Engineer – Hamayoun Nawaz
Communication methods : Face to Face - team briefings, meetings
and presentations.
METHOD STATEMENT
Page 4 of 9
RESPONSIBILITIES
1) All work will be undertaken by qualified competent persons with
experience of the type of work described above, and in all
cases in full accordance with safety procedures specified.
2) It is the responsibility of the supervisor to ensure prior to giving
any personnel the job of installation that they are fully aware of
the hazards involved and are competent to carry out the work
safely.
3) The supervisor must ensure that this procedure is fully
complied with.
3.1) All mechanical workers must check by a mechanical supervisor
before starting of any work.
3.2)All workers must also sign in on each piece of equipment before
doing any work on it. All required information must be entered legibly.
Users should request a replacement for full sign in sheets.
4) Site In Charge(Sumesh G.P) – has an ultimate responsibility of
compliance of work to, relevant methodologies, standards,
specifications listed, while assuring adequate organization
resources.
5) HSE Supervisor(Saiuj) – shall be responsible to implement
HSE Plan.
6) QA/QC Inspector(Anand) – responsible for the Inspection
Request (IR) preparation, 100% inspection activities and
ensure compliance with quality requirements and
specifications.
7) Field Engineer(H.Nawas) – ensure that all related works are
carried out in accordance with approved released for
construction drawings, specifications, schedule, quality and
safety. Reports to Site Manager
8) Fabricators– will do all the fabrication work as per approved
drawings and standards
9) Helpers- These are to assist the technicians for the technical
works ,cleaning etc.
10)Supervisor / Foreman(Umar,Afsal) – Supervise all field
installations and reports to Field Engineer.
METHOD STATEMENT
Page 5 of 9
11)Welders- the qualified welders will give production joints as per
approved welding procedure specification.
12)Ensure that Hoisting and Rigging accessories are free from
damage.
13 ) Provide third party inspection certificates for the welding
accessories.
14) Surveyors report is required for the level of foundation, centre
line etc.
15) All personnel must have competency certification cards to be
in date.
16) Users are required to clean up all chips, dirt, oil, etc.
produced during the use of any piece of equipment.
Compressed air shall not to be used to clean the machines.
17) Cleanup starts 15 minutes before the posted closing time.
SAFETY:
1. Every employee should be trained in work place safety.
2. To prevent accident sharpedges of materials, wooden or
metal lining should be properly handled.
3 Clamps to be used for piping welding must be suitable,
sufficient and fit for purpose.
4. When welding the all mechanical equipment must be
protected with flags, watch man barriers etc.
6. Concerned persons are allowed during welding..
7 The technicians working on top, must handle the parts
andtools
Carefully so as to prevent them to fall down.
8. All tools and equipment are to be returned to their proper location
before the user leaves the area.
9. No equipment is to be left running while physically or
mentally unattended
METHOD STATEMENT
Page 6 of 9
10. Any personal injuries are to be reported immediately. Those
giving first aid to others should use the gloves provided to protect
themselves from blood borne disease. All injuries must be reported
immediately. Depleted first aid supplies should also be reported
immediately.
11. No food or drink is permitted in the site. No audio equipment,
either with or without headsets may be operated in the lab.
12. Users must receive proper instruction on each piece of equipment
prior to using it for the first time. Typically, this will occur in during
a regularly scheduled training program.
13. Users must not undertake any actions that may injure or distract
other users or result in damage to equipment or the work of others
CUTTING AND WELDING PROCEDURES:
 All cutting and welding operations performed at tuft by tuft
personnel or contractors must be carried out in accordance
with standards set forth by the American Welding Society and
the appropriate American National Standard institute standard
concerning cutting and welding.
 Designated Areas should be barricaded.
 Cutting and welding is only permitted by designated areas.
 FIRE PRECAUTIONS
 When cutting or welding outside a designated area, remove
the work to a safe location free of combustible materials if
possible.
 If the work cannot be moved ,clear flammable materials and
rubbish from the area for about a 35 feet radius.
 If these precautions are not feasible, shield or cover such
materials with fire resistive materials to protect them for
combustion.
 Holes in the floor and walls must be covered to prevent sparks
from falling through unnoticed onto people or combustible
materials below.
 Maintain a fire watch when doing this kind of work and have
METHOD STATEMENT
Page 7 of 9
a charged fire extinguisher readily available.
 Do not cut or weld any closed vessel that has contained or has
suspected to have contained flammable or toxic materials until
it has been tested, thoroughly cleaned , purged and vented.
 Traces of the material may still be in the vessel and result in a
fire or explosion ,or create a toxic exposure.
 Accident Prevention
 Common sense and safe working practice is the key to
accident prevention. If you are unsure about an operation,
request assistance.
SEQUENCE OF WORK
The following working sequences are to be followed in site.
1. Identify the materials and equipments in site.
2. Refer the drawings and ensure the proper locations and dimensions
by concerned engineer.
3. Arrange all tools,materials and equipments orderly near to the work
area.The following tools and equipments to be used
a)welding machine
b)electrodes
c)grinder
d)pipe supports
e)spirit level
f)right angle
g)measuring tape
h)permanent marker
i)argon cylinder etc.
4. Prepare the pipes and other fittings as per approved drawings and
standards.
5. Start to fitup process as per approved welding procedure
specifications by qualified fabricators ,fitters and welders.
6. Check and ensure all welders and other technicians are qualified.
7. Monitor all welding and related works by approved supervisors and
qc inspector
8. Prepare all quality and related documents by qc inspector.
9. Coordinate with the owner and client inspectors or engineers for final
METHOD STATEMENT
Page 8 of 9
inspection and keep all records as per client procedures.
INSTALLATION AND INSPECTION
Prior to final installation, the mechanical discipline shall release the and
verifying the activities of bolting, chipping work and other cleaning.
Each installation procedure shall follow the Inspection plan as per QC
document.The qc inspector is responsible for all qc documents to submit
and keep updated records.
METHOD STATEMENT
Page 9 of 9
DATE TRADE
NAME
PRINT SIGNATURE
RESPONSIBLE ENGINEER / SUPERVISOR
I HAVE READ AND UNDERSTOOD THE METHOD STATEMENT
FOR THE WORK ACTIVITIES ABOVE

More Related Content

What's hot

Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
MohammedAliQazi
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
Jsa heat-treatment
Jsa  heat-treatmentJsa  heat-treatment
Jsa heat-treatment
Fãrük Ñäzmî
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
Simba Zhao
 
bar bending safety precautions.pdf
bar bending safety precautions.pdfbar bending safety precautions.pdf
bar bending safety precautions.pdf
construction
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
DusanJankovic8
 
Weekly excavation checklist
Weekly excavation checklistWeekly excavation checklist
Weekly excavation checklist
Azmeel Contracting Company
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
MohPhoolay
 
Welding safety
Welding safetyWelding safety
Welding safety
garfield Tulloch
 
Offshore shift supervisor cum Offshore Construction Superintendent
Offshore shift supervisor cum Offshore Construction SuperintendentOffshore shift supervisor cum Offshore Construction Superintendent
Offshore shift supervisor cum Offshore Construction Superintendent
Muhammad MuhdKhairul
 
DOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work ProcedureDOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work Procedure
HENRY EROMOSELE OIGIANGBE
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
Dwarika Bhushan Sharma
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work training
Karnav Rana
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet
Phạm Thành
 
30 workplace temporary electrical supply risk assessment templates
30 workplace temporary electrical supply risk assessment templates30 workplace temporary electrical supply risk assessment templates
30 workplace temporary electrical supply risk assessment templates
Dwarika Bhushan Sharma
 
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docxWORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
Dwarika Bhushan Sharma
 
HEIGHT WORK SAFETY REPORT
HEIGHT WORK SAFETY REPORTHEIGHT WORK SAFETY REPORT
HEIGHT WORK SAFETY REPORT
Er Abhishek Kumar
 

What's hot (20)

Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Jsa heat-treatment
Jsa  heat-treatmentJsa  heat-treatment
Jsa heat-treatment
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
bar bending safety precautions.pdf
bar bending safety precautions.pdfbar bending safety precautions.pdf
bar bending safety precautions.pdf
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
 
Weekly excavation checklist
Weekly excavation checklistWeekly excavation checklist
Weekly excavation checklist
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
 
Welding safety
Welding safetyWelding safety
Welding safety
 
Offshore shift supervisor cum Offshore Construction Superintendent
Offshore shift supervisor cum Offshore Construction SuperintendentOffshore shift supervisor cum Offshore Construction Superintendent
Offshore shift supervisor cum Offshore Construction Superintendent
 
DOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work ProcedureDOC-20220402-WA0048..ppt- Permit To Work Procedure
DOC-20220402-WA0048..ppt- Permit To Work Procedure
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work training
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet
 
30 workplace temporary electrical supply risk assessment templates
30 workplace temporary electrical supply risk assessment templates30 workplace temporary electrical supply risk assessment templates
30 workplace temporary electrical supply risk assessment templates
 
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
 
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docxWORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
 
HEIGHT WORK SAFETY REPORT
HEIGHT WORK SAFETY REPORTHEIGHT WORK SAFETY REPORT
HEIGHT WORK SAFETY REPORT
 

Viewers also liked

Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & windowMinh Bui Si
 
Stainless Steel Railing
Stainless Steel RailingStainless Steel Railing
Stainless Steel Railing
John Mike
 
Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)
Devinder Chawla
 
Stainless steel fabrication
Stainless steel fabricationStainless steel fabrication
Stainless steel fabrication
Absolute Metal Fabrications
 
Stainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
Stainless Steel Fabrication Works by Global Glass & Glazing System MumbaiStainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
Stainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
IndiaMART InterMESH Limited
 
13 managinghse standardsinpetronascarigali
13 managinghse standardsinpetronascarigali13 managinghse standardsinpetronascarigali
13 managinghse standardsinpetronascarigali
innobun
 
Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
Patsifit Construction Sdn.Bhd
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)Mohd Zaini Baharum
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003Minh Bui Si
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
NECB
 
Pipe and-fittings
Pipe and-fittingsPipe and-fittings
Pipe and-fittingsthanhuce
 
General Welding Safety Practices.138344336521672.OS
General Welding Safety Practices.138344336521672.OSGeneral Welding Safety Practices.138344336521672.OS
General Welding Safety Practices.138344336521672.OS
Eiyla Hamdan
 
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
pierdole
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010Minh Bui Si
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeTong Seng Chua
 
072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
Dr Fereidoun Dejahang
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workthanhuce
 
61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud
Jithu John
 
Welding Safety 2014
Welding Safety 2014Welding Safety 2014
Welding Safety 2014vtsiri
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surfaceMinh Bui Si
 

Viewers also liked (20)

Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & window
 
Stainless Steel Railing
Stainless Steel RailingStainless Steel Railing
Stainless Steel Railing
 
Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)
 
Stainless steel fabrication
Stainless steel fabricationStainless steel fabrication
Stainless steel fabrication
 
Stainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
Stainless Steel Fabrication Works by Global Glass & Glazing System MumbaiStainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
Stainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
 
13 managinghse standardsinpetronascarigali
13 managinghse standardsinpetronascarigali13 managinghse standardsinpetronascarigali
13 managinghse standardsinpetronascarigali
 
Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
 
Pipe and-fittings
Pipe and-fittingsPipe and-fittings
Pipe and-fittings
 
General Welding Safety Practices.138344336521672.OS
General Welding Safety Practices.138344336521672.OSGeneral Welding Safety Practices.138344336521672.OS
General Welding Safety Practices.138344336521672.OS
 
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
 
072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-work
 
61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud
 
Welding Safety 2014
Welding Safety 2014Welding Safety 2014
Welding Safety 2014
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 

Similar to Methodstatement welding

Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)
Iqbal Mohammad
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
Atif767782
 
Safety clearance for contractor before start of job
Safety clearance for contractor before start of jobSafety clearance for contractor before start of job
Safety clearance for contractor before start of job
Bimal Chandra Das
 
MS False Ceiling Rolling shutter & Door,Window Fixing_RA.doc
MS False Ceiling Rolling shutter & Door,Window Fixing_RA.docMS False Ceiling Rolling shutter & Door,Window Fixing_RA.doc
MS False Ceiling Rolling shutter & Door,Window Fixing_RA.doc
RajuBiswas41
 
cpwd training
cpwd trainingcpwd training
cpwd training
akash kumar
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
FESTUS RICHARD SIAME
 
Health/Safety and facilities for contractor personnel under FIDIC
Health/Safety and facilities for contractor personnel under FIDICHealth/Safety and facilities for contractor personnel under FIDIC
Health/Safety and facilities for contractor personnel under FIDIC
naeem khan
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
Personal Secret
 
JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building
Alvin160771
 
Safety plan
Safety planSafety plan
Safety plan
Shyam Krishna Karki
 
SUPERVISOR CV for ONSHORE and OFFSHORE MECHANICAL, MANTENANCE, CONSTRUCTION ...
SUPERVISOR CV  for ONSHORE and OFFSHORE MECHANICAL, MANTENANCE, CONSTRUCTION ...SUPERVISOR CV  for ONSHORE and OFFSHORE MECHANICAL, MANTENANCE, CONSTRUCTION ...
SUPERVISOR CV for ONSHORE and OFFSHORE MECHANICAL, MANTENANCE, CONSTRUCTION ...Saleem P.P
 
HSE Management Plan
HSE Management PlanHSE Management Plan
HSE Management Plan
Philip Hà
 
CV-Saddamulla HSE Officer
CV-Saddamulla HSE OfficerCV-Saddamulla HSE Officer
CV-Saddamulla HSE OfficerMohd Saddamulla
 
Site_Safety_Induction on Health, Safety and Environment .pdf
Site_Safety_Induction on Health, Safety and Environment .pdfSite_Safety_Induction on Health, Safety and Environment .pdf
Site_Safety_Induction on Health, Safety and Environment .pdf
ObijiakuIjeoma
 
Core Risk Assessment for Office work.docx
Core  Risk Assessment for Office work.docxCore  Risk Assessment for Office work.docx
Core Risk Assessment for Office work.docx
IbrahimEsmat
 
Fire Suppression System Risk assessment file
Fire Suppression System Risk assessment fileFire Suppression System Risk assessment file
Fire Suppression System Risk assessment file
chopriroti
 

Similar to Methodstatement welding (20)

Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)
 
AHU.pdf
AHU.pdfAHU.pdf
AHU.pdf
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
Safety clearance for contractor before start of job
Safety clearance for contractor before start of jobSafety clearance for contractor before start of job
Safety clearance for contractor before start of job
 
MS False Ceiling Rolling shutter & Door,Window Fixing_RA.doc
MS False Ceiling Rolling shutter & Door,Window Fixing_RA.docMS False Ceiling Rolling shutter & Door,Window Fixing_RA.doc
MS False Ceiling Rolling shutter & Door,Window Fixing_RA.doc
 
cpwd training
cpwd trainingcpwd training
cpwd training
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
 
ehs
ehsehs
ehs
 
Health/Safety and facilities for contractor personnel under FIDIC
Health/Safety and facilities for contractor personnel under FIDICHealth/Safety and facilities for contractor personnel under FIDIC
Health/Safety and facilities for contractor personnel under FIDIC
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building
 
Safety plan
Safety planSafety plan
Safety plan
 
SUPERVISOR CV for ONSHORE and OFFSHORE MECHANICAL, MANTENANCE, CONSTRUCTION ...
SUPERVISOR CV  for ONSHORE and OFFSHORE MECHANICAL, MANTENANCE, CONSTRUCTION ...SUPERVISOR CV  for ONSHORE and OFFSHORE MECHANICAL, MANTENANCE, CONSTRUCTION ...
SUPERVISOR CV for ONSHORE and OFFSHORE MECHANICAL, MANTENANCE, CONSTRUCTION ...
 
A.hegazy c.v
A.hegazy c.vA.hegazy c.v
A.hegazy c.v
 
HSE Management Plan
HSE Management PlanHSE Management Plan
HSE Management Plan
 
CV-Saddamulla HSE Officer
CV-Saddamulla HSE OfficerCV-Saddamulla HSE Officer
CV-Saddamulla HSE Officer
 
Site_Safety_Induction on Health, Safety and Environment .pdf
Site_Safety_Induction on Health, Safety and Environment .pdfSite_Safety_Induction on Health, Safety and Environment .pdf
Site_Safety_Induction on Health, Safety and Environment .pdf
 
Core Risk Assessment for Office work.docx
Core  Risk Assessment for Office work.docxCore  Risk Assessment for Office work.docx
Core Risk Assessment for Office work.docx
 
Project
ProjectProject
Project
 
Fire Suppression System Risk assessment file
Fire Suppression System Risk assessment fileFire Suppression System Risk assessment file
Fire Suppression System Risk assessment file
 

Recently uploaded

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 

Recently uploaded (20)

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 

Methodstatement welding

  • 1. METHOD STATEMENT Page 1 of 9 Description of Task/ Activity: METHOD STATEMENT FOR PIPE WELDING AT POWER GENERATION BUILDING. Project Name: Al Ba’itha Mine Infrastructure and Utilities Company: Ma’ameer General Contracting, MGC Prepared By: Anand Subi Position: Qc inspector Date: Contractor Project Manager Review: Sumesh.G.P Position: Site Manager Date: DL Discipline Engineer/Manager Review: Position: Construction Manager Date: DL HSE Manager Review: George Kennedy Position: HSE Manager Date: WPF Review: HENRY Position: HSE Manager Date: Document Reference: Associated JSA Reference Number Attached Yes No
  • 2. METHOD STATEMENT Page 2 of 9 Key Plant and Tools Required: Chainblock,welding machines etc. Key Materials Required: N/A Other Essential Equipment: (i.e.: access platforms, Lifting Ropes,Barricade,Signage,Flags, Winches, Chain block) Specific Identified Residual Hazards: (or refer to the task specific risk assessment(s)) N/A Specific Staff Training Requirements: (i.e.: Confined Spaces/Abrasive Wheels/Working at Height/Plant Operators etc) , crane operator, riggers Temporary Supports and Props needed to facilitate the works: (If none, state none.) None Method of Access and Egress to the work area: N/A Fall Protection Measures: (Where work at height cannot be eliminated - consider both Personnel & Materials) (i.e.: Guard Rails/Toe Boards/Brick Guards/Safety Harnesses/Exclusion Zones etc) Exclusion zone with barricade , signage and flag man. Hazardous Substances: (Attach COSHH Assessments and MSDS) (i.e.: Lubricants/Solvents/Flammable Materials/Refrigerants/Welding Gases etc) Very Toxic Harmful/ Irritant Corrosive Dangerous for the environment Oxidising Highly flammable Explosive Applicable: No No No No No No No
  • 3. METHOD STATEMENT Page 3 of 9 SWL's: (Detail any limits on the loadings applicable to temporary plant/equipment or fixed elements of the structure where the work is taking place.) Required Personnel Protective Equip.: Yes Yes Yes Yes No Yes OTHER: 1: Coveralls : Safety Boots Hard Hats Safety Gloves Hearing Protection Respiratory Protection Eye Protection Yes Yes Yes Yes Yes Yes High Visibility Welder Shield Face Shield Fall Arrest Disposable Mask Goggles Emergency Procedures: The duties, responsibilities, and names of employees assigned with rescue and medical tasks. First Aid Facilities: Name of On-Site First Aider: Umer First Aid Box Location: Power Generation biulding Location of Nearest Hospital: Qiba Hospital Other Information & Comments: Mechanical Engineer – Hamayoun Nawaz Communication methods : Face to Face - team briefings, meetings and presentations.
  • 4. METHOD STATEMENT Page 4 of 9 RESPONSIBILITIES 1) All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified. 2) It is the responsibility of the supervisor to ensure prior to giving any personnel the job of installation that they are fully aware of the hazards involved and are competent to carry out the work safely. 3) The supervisor must ensure that this procedure is fully complied with. 3.1) All mechanical workers must check by a mechanical supervisor before starting of any work. 3.2)All workers must also sign in on each piece of equipment before doing any work on it. All required information must be entered legibly. Users should request a replacement for full sign in sheets. 4) Site In Charge(Sumesh G.P) – has an ultimate responsibility of compliance of work to, relevant methodologies, standards, specifications listed, while assuring adequate organization resources. 5) HSE Supervisor(Saiuj) – shall be responsible to implement HSE Plan. 6) QA/QC Inspector(Anand) – responsible for the Inspection Request (IR) preparation, 100% inspection activities and ensure compliance with quality requirements and specifications. 7) Field Engineer(H.Nawas) – ensure that all related works are carried out in accordance with approved released for construction drawings, specifications, schedule, quality and safety. Reports to Site Manager 8) Fabricators– will do all the fabrication work as per approved drawings and standards 9) Helpers- These are to assist the technicians for the technical works ,cleaning etc. 10)Supervisor / Foreman(Umar,Afsal) – Supervise all field installations and reports to Field Engineer.
  • 5. METHOD STATEMENT Page 5 of 9 11)Welders- the qualified welders will give production joints as per approved welding procedure specification. 12)Ensure that Hoisting and Rigging accessories are free from damage. 13 ) Provide third party inspection certificates for the welding accessories. 14) Surveyors report is required for the level of foundation, centre line etc. 15) All personnel must have competency certification cards to be in date. 16) Users are required to clean up all chips, dirt, oil, etc. produced during the use of any piece of equipment. Compressed air shall not to be used to clean the machines. 17) Cleanup starts 15 minutes before the posted closing time. SAFETY: 1. Every employee should be trained in work place safety. 2. To prevent accident sharpedges of materials, wooden or metal lining should be properly handled. 3 Clamps to be used for piping welding must be suitable, sufficient and fit for purpose. 4. When welding the all mechanical equipment must be protected with flags, watch man barriers etc. 6. Concerned persons are allowed during welding.. 7 The technicians working on top, must handle the parts andtools Carefully so as to prevent them to fall down. 8. All tools and equipment are to be returned to their proper location before the user leaves the area. 9. No equipment is to be left running while physically or mentally unattended
  • 6. METHOD STATEMENT Page 6 of 9 10. Any personal injuries are to be reported immediately. Those giving first aid to others should use the gloves provided to protect themselves from blood borne disease. All injuries must be reported immediately. Depleted first aid supplies should also be reported immediately. 11. No food or drink is permitted in the site. No audio equipment, either with or without headsets may be operated in the lab. 12. Users must receive proper instruction on each piece of equipment prior to using it for the first time. Typically, this will occur in during a regularly scheduled training program. 13. Users must not undertake any actions that may injure or distract other users or result in damage to equipment or the work of others CUTTING AND WELDING PROCEDURES:  All cutting and welding operations performed at tuft by tuft personnel or contractors must be carried out in accordance with standards set forth by the American Welding Society and the appropriate American National Standard institute standard concerning cutting and welding.  Designated Areas should be barricaded.  Cutting and welding is only permitted by designated areas.  FIRE PRECAUTIONS  When cutting or welding outside a designated area, remove the work to a safe location free of combustible materials if possible.  If the work cannot be moved ,clear flammable materials and rubbish from the area for about a 35 feet radius.  If these precautions are not feasible, shield or cover such materials with fire resistive materials to protect them for combustion.  Holes in the floor and walls must be covered to prevent sparks from falling through unnoticed onto people or combustible materials below.  Maintain a fire watch when doing this kind of work and have
  • 7. METHOD STATEMENT Page 7 of 9 a charged fire extinguisher readily available.  Do not cut or weld any closed vessel that has contained or has suspected to have contained flammable or toxic materials until it has been tested, thoroughly cleaned , purged and vented.  Traces of the material may still be in the vessel and result in a fire or explosion ,or create a toxic exposure.  Accident Prevention  Common sense and safe working practice is the key to accident prevention. If you are unsure about an operation, request assistance. SEQUENCE OF WORK The following working sequences are to be followed in site. 1. Identify the materials and equipments in site. 2. Refer the drawings and ensure the proper locations and dimensions by concerned engineer. 3. Arrange all tools,materials and equipments orderly near to the work area.The following tools and equipments to be used a)welding machine b)electrodes c)grinder d)pipe supports e)spirit level f)right angle g)measuring tape h)permanent marker i)argon cylinder etc. 4. Prepare the pipes and other fittings as per approved drawings and standards. 5. Start to fitup process as per approved welding procedure specifications by qualified fabricators ,fitters and welders. 6. Check and ensure all welders and other technicians are qualified. 7. Monitor all welding and related works by approved supervisors and qc inspector 8. Prepare all quality and related documents by qc inspector. 9. Coordinate with the owner and client inspectors or engineers for final
  • 8. METHOD STATEMENT Page 8 of 9 inspection and keep all records as per client procedures. INSTALLATION AND INSPECTION Prior to final installation, the mechanical discipline shall release the and verifying the activities of bolting, chipping work and other cleaning. Each installation procedure shall follow the Inspection plan as per QC document.The qc inspector is responsible for all qc documents to submit and keep updated records.
  • 9. METHOD STATEMENT Page 9 of 9 DATE TRADE NAME PRINT SIGNATURE RESPONSIBLE ENGINEER / SUPERVISOR I HAVE READ AND UNDERSTOOD THE METHOD STATEMENT FOR THE WORK ACTIVITIES ABOVE