Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Construction of Piping Works at Dabbiya Clusters
Method Statement
For
Piping Works at Site – for New Piping at Dabbiya
Clusters 14P-9J-7G-5E-1A
Revision Status:
Second Issue CM CM CM
First Issue CM CM CM
REV DATE STATUS PREP.BY CHKD. BY APPD.BY
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 2 of 12
TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
6. SEQUNCE OF WORKS
7. QA/QC
8. RESOURCE
9. HSE REQUIMENTS
10. EMERANCY CONTACTS
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 3 of 12
1.0 Purpose:
The purpose of this methodology is to provide a systematic control and direction for the activity
for the installation of piping at site. This method statement provides the expectation to execute
work in safe, eco-friendly manner and in compliance to the ADCO HSE and Quality
requirements.
2.0 Scope:
As part of the scope of work for the Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
project Matrix is to carry out the installation of piping at site and other associated works. This
installation will be comprised of welding of field joints and the assembly of completed pipe
spools which were prefabricated at Matrix’s workshop.
As it stands there are five clusters in Dabbiya under this scope, all of the clusters will require the
installation of new piping. The piping will vary in terms of pipe class, where some wells will
have 1500# piping for the water injection wells and others have KG10 piping for gas injection.
The following clusters will be covered under this scope:
Cluster 14P – Water Injection
Cluster 9J – Gas Injection
Cluster 7G – WAG
Cluster 5E – Dual Water Injection and WAG injection
Cluster 1A – Gas injection
3.0 References
 ADCO Contract No: 15410.01/EC 10825-Contracts Specification and Documents
 ADCO Doc No:31.38.01.31A- Shop and Field Fabrication of Piping
 ADCO Doc No: 30.99.12.0610-Rev3- Technical specification for piping system
 ADCO HSE Manual Volume-10
 ASME B 31.3- Process piping
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 4 of 12
 ADCO WS-1 Rev2-Specification for welding and inspection of shop and field fabricated
carbon steel process and utility.
 DOC No P12169 REV1- Project Quality Plan
 AWS D1.1 -Structural welding code
 DEP 34.28.00.31A -Structural steel works
4.0 Definitions
 Client - Abu Dhabi Company for Onshore Oil Operations ( ADCO)
 QHSE - Quality, Health, Safety & Environment
 QCI - Quality Control Inspector
 ITP - Inspection and Test Plan
 WPS - Welding Procedure Specification
 NDT - Non Destructive Testing
 PWHT - Post Weld Heat Treatment
5.0 Responsibilities
Matrix shall arrange all the resources deemed necessary for carrying out the works related to
the piping installations. In addition to the above Matrix will also ensure that adequate safety
precautions are put in place in order to carry out the job in a safe manner.
Construction Manager:
The Construction Manager is responsible in executing the works as per ADCO procedure
and approved method statement.
Supervisor/ Foreman:
 Ensure that welding equipment, baking oven, quiver are in good condition.
 Ensure welding is done as per the approved WPS and approved for construction
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 5 of 12
drawings and in line with ADCO HSE requirements.
 Ensure that weld maps / spool drawings are available.
 Coordinate with QC personnel to study the cause of any reported weld defects and
arrange to take corrective and preventive action.
 Adhere to the ADCO HSE requirements.
 Comply with ADCO PTW requirements.
QC Inspector:
 Carry out the inspection as per the Inspection and test plan.
 Approving/ rejecting the item based on inspection.
 Submitting the quality records to the client and getting their approval.
 Responsible to keep records of all inspection related activities & Material traceability.
 Adhere to the HSE requirements.
HSE Officer:
 Advise the construction crew on HSE aspects and ensure their safety.
 Arrange through Job performer for tool box talk covering risk assessment in language
understandable by workers.
 Cross checking certified material devices and equipments are used.
 Do weekly, monthly HSE audit.
 Ensure appropriate safety measures are taken as per the risk assessment and
controlled documents.
 Ensure that all staff adhere to the HSE plan and HSE requirements.
6.0 Sequence of Works
6.1 PTW Issuance
 A Hot Work permit will be issued to carry out the works, along with the permit will
be the attached crane certificate, approved method statement, risk assessment, and
approved drawings shall also be attached.
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 6 of 12
6.2 Safety Setup
 Arrange the required safety signs, barricades and other related safety precautions
highlighted in the risk assessment and permit prior to commencing the works.
 The works shall only commence after the job performer has checked and ensured that
all safety precautions and safety requirements are in place.
 Ensure employees understand the hazards and control measures related to the critical
activities, i.e. lifting, welding.
 Ensure personnel stay away from lifting zone and do not enter under the suspended
loads.
 Qualified First Aider must be on site and identified by a sticker on his helmet.
 Display Emergency Contact number on site.
6.3 Site Works-Field Joints
 Prefabricated pipe spools shall be carefully loaded and transported to site. The
transported spools will be tied down with ample support to prevent any damage.
Spools will be tied down using nylon straps/belts. Under no circumstances will the
pipes be tied down using chains or cables to prevent any scratches or damage.
 Upon receiving the pipes at site, they shall be offloaded and placed either in position
on the pipe supports or placed on the ground on top of wooden supports. All flanged
ends or open ends will remain sealed to prevent any sand or debris from entering.
 Lifting of the pipe spools shall be done by using either a HIAB or Crane. Third Party
certified slings and riggers shall be used during the lifting operations. All lifting tools
and tackles shall be color coded based on the current color code.
 Once the spools are lifted into position, the fabricator/pipe fitter shall ensure that
proper alignment is achieved, lengths of spools are correct as per the piping layout
and isometric sheet prior to either bolting the spools together or welding any field
joints.
 Welding and grinding of field joints shall be carried out inside a closed habitat made
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 7 of 12
of fire retardant material. Any live facilities will be covered with the fire retardant
blanket as an additional precaution.
 Welding shall be done as per the approved procedure, specification and approved for
construction drawings.
 Approved welders for the specific WPS shall be used for welding.
 Welded surfaces shall be clean and free from grease, oil, paint or other foreign
material which are detrimental to welding.
 When the weather does not permit satisfactory workmanship welding shall not be
done, on site in windy condition the pipe ends shall be closed to prevent through
draughts during welding. Suitable covering using tarpaulin (fire retardant) shall be
provided. Welding shall not be done when the weld surface is wet or when the area is
exposed to rain and strong windy conditions. Preheating to be done properly during
cold weather.
6.4 Site Works - Welding of Pipe Supports
 As required some structural steel pipe supports are to be welded to the base plates
inserted into the precast foundations. Other pipe supports are to be welded to the
existing pipe support structural steel racks.
 Locations to be welded will be covered as required with a fire proof tarpaulin.
 The base plate or support shall be cleaned by grinding to remove any surface debris,
or paint.
 The support will then be placed in position, aligned, and tack welded. Once tack
welding is completed, the alignment will be rechecked and final welding will be
carried out.
 Welding shall be done based on the approved welding procedure for structural steel.
6.5 Site-Works-Valve Installation
 Where ever valves are to be installed, the installation/orientation of valve handles and
flow direction shall be according to the piping layout.
 All valves to be installed will be cross checked according to the mesc number to
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 8 of 12
ensure that the proper valves are installed in the proper location.
 Valves shall be installed in the closed position except for ball valves and plug valves.
 New gaskets will be installed between the valve flange and pipe flange. Final
tightening of all nuts shall be done once proper alignment is achieved.
 Bolting of flanges will be done in a cross pattern.
 All bolts, gaskets and valves shall be properly stored to avoid contamination with the
environment. Valve ends will be sealed until installation and gaskets and bolts shall
be kept clean of any debris such as sand.
6.6 Scaffolding
 Scaffolding if required shall be erected by qualified personnel in a safe and suitable
manner.
 Scaffolding above 2 m in height shall be inspected by a scaffolding inspector and a
scaff-tag shall be signed and provided on the scaffolding near the ladder. No one shall
use the scaffolding without the scaff-tag being approved.
 Scaffolding material to be used shall be in good conditions, brass hammer shall be
used to assemble and tighten the scaffolding locks.
7.0 QA/QC
7.1 Weld Identification
 Each weld shall be uniquely identified with the joint number and welder number.
 After completing the weld the welder shall mark the joint no: & welder no: near the
weld using paint or indelible crayon.
 After welding each spool the line no, spool no & etc shall be marked / tagged on the
spool and stocked over wooden sleepers or other suitable material above ground.
7.2 Non Destructive Testing
 Non destructive testing shall be done as per the approved procedure using approved
sub contractor.
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 9 of 12
7.3 Alignment Circumferential Welds
 Butt weld alignment shall satisfy the requirement of ANSI B 31.3 and conditions
stated below.
 Internal misalignment of pipe work shall not exceed 1.6 mm in order to facilitate
welding of the root pass. When a GTAW process is to be used maximum misalignment
shall not exceed 0.8 mm. If there is excess misalignment tapering of the internal diameter
of the thicker member to a taper of 1:4 shall be done. Ensure minimum wall thickness is
maintained.
 If misalignment up to 3.2 mm exists, internal grinding or machining may be
conducted to improve root alignment, provided the taper does not exceed 1 in 4
maximum and the minimum required wall thickness is maintained.
 External or internal clamps shall be used not only for misalignment correction but
also for alignment in general. Misalignment correction using heavy hammering or
heating of the pipe shall not be done.
7.4 Weld Separation
 Circumferential welds (Girth welds):
Distance between weld shall be measured between the adjacent edges of the cap passes.
Circumferential butt welds (Girth welds) shall be separated by maximum possible
distance. However between fittings, short pipe lengths may be required. In this case, butt
welds shall not be within 75 mm of adjacent girth weld for nominal pipe sizes of 75 mm
and above. For pipe sizes less than 75mm nominal, girth weld shall not be within the
greater of 4 times the wall thickness or one pipe diameter of adjacent girth welds. Girth
welds closer than the above limit shall require approval of the client and may require
PWHT solely at the discretion of the company.
 Branch / Nozzle / attachment welds.
Branch / nozzle and other pressure attachment welds shall have minimum 3” distance to
adjacent pressure welds. Non pressure containing attachment welds shall be separated by
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 10 of 12
2” from adjacent pressure containing welds.
 Longitudinal seams of adjacent pipes shall be separated by at least 4”.
7.5 Repair Welding
 Any defects which require repair shall be entirely removed to sound metal. Metal
shall be removed 1” on both side of the defect without substantial removal of the
Base metal.
 By grinding, the metal shall be removed and the groove shall be smooth without any
undercut. Visual examination and magnetic/dye penetrant test shall be done on the
grove.
 If repairs are done after hydro test / PWHT, the same will be repeated after repair.
Welding repair shall be done only twice. After second repair if the weld is not
acceptable the weld shall be removed, re beveled and re welded.
 Same NDT technique & acceptance criteria for the original weld shall be done after
repair welding.
 Proper cutting disc shall be used. Grinding disc shall not be used for cutting purposes.
8.0 Resources
 Welding machine
 Grinding machine
 Preheating torches with propane gas cylinders
 Holding ovens/baking ovens
 PWHT equipment
 Hiab, Crane, trailer
 Cutting tools
 Generator
Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins
Contract No. 15410.01/EC10825; Matrix Project No- P12169
Method Statement for Piping Works at Dabbiya Clusters
Page 11 of 12
9.0 HSE Requirements
9.1 Risk Rating
 Risk Rating is Medium: Job will have to be closely supervised by Job Performer, Safety
officer and Supervisor.
9.2 HSE Requirements
 Basic PPE, such as coverall, helmet, safety shoes, gloves, goggles and face mask (during
windy days).
 Appropriate approved PTW and certificate shall be obtained prior to commencing the
job.
 Standby vehicle will be present for emergency purposes.
 Daily TBT
 Approved and valid fire extinguishers (dry powder) shall be available.
 Sufficient cold drinking water to be available at all times.
 Third party certificates of all riggers and cranes
 Proper color coding of all lifting tools, tackles
10.0 Emergency contacts
The following shall be the contact number in case of any emergency.
1. ADCO Control Room - - 02 6046999
2. Mr. Chafic Mansour - Project Manager - 050 6670376
3. Mr. Zakir Ali-Safety Officer - 050 6112845

More Related Content

What's hot

Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
Patsifit Construction Sdn.Bhd
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workthanhuce
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
Dwarika Bhushan Sharma
 
Lifting plan
Lifting planLifting plan
Lifting plan
tnsv22
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
Sergio Augusto Esteves
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
Muhammad Shahid
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
DusanJankovic8
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
MohPhoolay
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
Sharad Naik
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
Al-Amin Ahmed Nabin
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
HaGun Gunawan
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Emeka Ngwobia
 
Aramco inspection handbook
Aramco inspection handbookAramco inspection handbook
Aramco inspection handbookram111eg
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
MOHAMMAD ATIF ALI
 
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURESSAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
HASNIZAM BIN MD SAAD
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
RA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksRA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksSajid Ali
 

What's hot (20)

Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-work
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.
 
Aramco inspection handbook
Aramco inspection handbookAramco inspection handbook
Aramco inspection handbook
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURESSAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
SAFETY REQUIREMENTS FOR FORMWORK STRUCTURES
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
RA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksRA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe Works
 

Viewers also liked

Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002Minh Bui Si
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW TW Carl
 
5 essential keys to webdesign success
5 essential keys to webdesign success5 essential keys to webdesign success
5 essential keys to webdesign successPaul Adedoyin
 
574An Integrated Framework for IT Infrastructure Management by Work Flow Mana...
574An Integrated Framework for IT Infrastructure Management by Work Flow Mana...574An Integrated Framework for IT Infrastructure Management by Work Flow Mana...
574An Integrated Framework for IT Infrastructure Management by Work Flow Mana...
idescitation
 
Trainer-Skills-Matrix Rory Prosser
Trainer-Skills-Matrix Rory ProsserTrainer-Skills-Matrix Rory Prosser
Trainer-Skills-Matrix Rory ProsserRory Prosser
 
Presentasi Media Gathering dari Rekind
Presentasi Media Gathering dari RekindPresentasi Media Gathering dari Rekind
Presentasi Media Gathering dari Rekind
Ruslan Chandra
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
Joe Kalchbrenner
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
Stephanus Roux C Eng , IntPE(uk) , FIET
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
NECB
 
Pipe and-fittings
Pipe and-fittingsPipe and-fittings
Pipe and-fittingsthanhuce
 
6 key learnings for responsive webdesign
6 key learnings for responsive webdesign6 key learnings for responsive webdesign
6 key learnings for responsive webdesign
Bart De Waele
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Minh Bui Si
 
Welding visual inspection
Welding visual inspectionWelding visual inspection
Welding visual inspectionbusinespartner
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
bernard347
 
Method statement painting
Method statement painting Method statement painting
Method statement painting
Daniel SLSA CLA
 
Introduction to Storage Tanks
Introduction to Storage TanksIntroduction to Storage Tanks
Introduction to Storage Tanks
Ankur Sharma
 

Viewers also liked (16)

Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
5 essential keys to webdesign success
5 essential keys to webdesign success5 essential keys to webdesign success
5 essential keys to webdesign success
 
574An Integrated Framework for IT Infrastructure Management by Work Flow Mana...
574An Integrated Framework for IT Infrastructure Management by Work Flow Mana...574An Integrated Framework for IT Infrastructure Management by Work Flow Mana...
574An Integrated Framework for IT Infrastructure Management by Work Flow Mana...
 
Trainer-Skills-Matrix Rory Prosser
Trainer-Skills-Matrix Rory ProsserTrainer-Skills-Matrix Rory Prosser
Trainer-Skills-Matrix Rory Prosser
 
Presentasi Media Gathering dari Rekind
Presentasi Media Gathering dari RekindPresentasi Media Gathering dari Rekind
Presentasi Media Gathering dari Rekind
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
 
Pipe and-fittings
Pipe and-fittingsPipe and-fittings
Pipe and-fittings
 
6 key learnings for responsive webdesign
6 key learnings for responsive webdesign6 key learnings for responsive webdesign
6 key learnings for responsive webdesign
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0
 
Welding visual inspection
Welding visual inspectionWelding visual inspection
Welding visual inspection
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
 
Method statement painting
Method statement painting Method statement painting
Method statement painting
 
Introduction to Storage Tanks
Introduction to Storage TanksIntroduction to Storage Tanks
Introduction to Storage Tanks
 

Similar to Method of statement piping works

DW143-Ductwork-Leakage-Testing.pdf
DW143-Ductwork-Leakage-Testing.pdfDW143-Ductwork-Leakage-Testing.pdf
DW143-Ductwork-Leakage-Testing.pdf
wrsconsultoria1
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalIan Kelly
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 
Aramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector ResumeAramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector Resume
Robin Parayil
 
Resume - Sr.QC Inspector-Mech.welding-painting-piping-pipeline
Resume -   Sr.QC Inspector-Mech.welding-painting-piping-pipelineResume -   Sr.QC Inspector-Mech.welding-painting-piping-pipeline
Resume - Sr.QC Inspector-Mech.welding-painting-piping-pipelineUDAYAKUMAR P C PANICKER
 
Rengaraj n c vdone
Rengaraj  n c vdoneRengaraj  n c vdone
Rengaraj n c vdone
Assignment Help
 
Awareness of RIG high pressure piping activities
Awareness of RIG high pressure piping activitiesAwareness of RIG high pressure piping activities
Awareness of RIG high pressure piping activities
Abdul Sayeed Mohammed
 
Rengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15doneRengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15done
Assignment Help
 
BR08 Proposed Section B - B
BR08 Proposed Section B - BBR08 Proposed Section B - B
BR08 Proposed Section B - Bsarah ralphs
 
MD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalMD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalM.Nafis Haque
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
Bharatha Rathnayke
 
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
JOBY Joby.Stephan
 
Root Cause Of Piping Failures | COMPRESSORtech2
Root Cause Of Piping Failures | COMPRESSORtech2 Root Cause Of Piping Failures | COMPRESSORtech2
Root Cause Of Piping Failures | COMPRESSORtech2
dieselpub
 
Sathish_CV Quality Control Engineer
Sathish_CV Quality Control EngineerSathish_CV Quality Control Engineer
Sathish_CV Quality Control EngineerSathish Murugesan
 
Stuart Cooper C.V. NEW 2014
Stuart Cooper C.V. NEW 2014Stuart Cooper C.V. NEW 2014
Stuart Cooper C.V. NEW 2014Stuart Cooper
 

Similar to Method of statement piping works (20)

DW143-Ductwork-Leakage-Testing.pdf
DW143-Ductwork-Leakage-Testing.pdfDW143-Ductwork-Leakage-Testing.pdf
DW143-Ductwork-Leakage-Testing.pdf
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_final
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
Waseem CV
Waseem CVWaseem CV
Waseem CV
 
Report
ReportReport
Report
 
Aramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector ResumeAramco Approved Welding Inspector Resume
Aramco Approved Welding Inspector Resume
 
03 Mohamed_fathi
03 Mohamed_fathi03 Mohamed_fathi
03 Mohamed_fathi
 
CV - Prasath.V.R
CV - Prasath.V.RCV - Prasath.V.R
CV - Prasath.V.R
 
Resume - Sr.QC Inspector-Mech.welding-painting-piping-pipeline
Resume -   Sr.QC Inspector-Mech.welding-painting-piping-pipelineResume -   Sr.QC Inspector-Mech.welding-painting-piping-pipeline
Resume - Sr.QC Inspector-Mech.welding-painting-piping-pipeline
 
Rengaraj n c vdone
Rengaraj  n c vdoneRengaraj  n c vdone
Rengaraj n c vdone
 
Awareness of RIG high pressure piping activities
Awareness of RIG high pressure piping activitiesAwareness of RIG high pressure piping activities
Awareness of RIG high pressure piping activities
 
Rengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15doneRengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15done
 
BR08 Proposed Section B - B
BR08 Proposed Section B - BBR08 Proposed Section B - B
BR08 Proposed Section B - B
 
MD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalMD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_original
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
 
Root Cause Of Piping Failures | COMPRESSORtech2
Root Cause Of Piping Failures | COMPRESSORtech2 Root Cause Of Piping Failures | COMPRESSORtech2
Root Cause Of Piping Failures | COMPRESSORtech2
 
Sathish_CV Quality Control Engineer
Sathish_CV Quality Control EngineerSathish_CV Quality Control Engineer
Sathish_CV Quality Control Engineer
 
Siddharth_resume_Engg.
Siddharth_resume_Engg.Siddharth_resume_Engg.
Siddharth_resume_Engg.
 
Stuart Cooper C.V. NEW 2014
Stuart Cooper C.V. NEW 2014Stuart Cooper C.V. NEW 2014
Stuart Cooper C.V. NEW 2014
 

Recently uploaded

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 

Recently uploaded (20)

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 

Method of statement piping works

  • 1. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Construction of Piping Works at Dabbiya Clusters Method Statement For Piping Works at Site – for New Piping at Dabbiya Clusters 14P-9J-7G-5E-1A Revision Status: Second Issue CM CM CM First Issue CM CM CM REV DATE STATUS PREP.BY CHKD. BY APPD.BY
  • 2. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 2 of 12 TABLE OF CONTENTS 1. PURPOSE 2. SCOPE 3. REFERENCES 4. DEFINITIONS 5. RESPONSIBILITIES 6. SEQUNCE OF WORKS 7. QA/QC 8. RESOURCE 9. HSE REQUIMENTS 10. EMERANCY CONTACTS
  • 3. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 3 of 12 1.0 Purpose: The purpose of this methodology is to provide a systematic control and direction for the activity for the installation of piping at site. This method statement provides the expectation to execute work in safe, eco-friendly manner and in compliance to the ADCO HSE and Quality requirements. 2.0 Scope: As part of the scope of work for the Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins project Matrix is to carry out the installation of piping at site and other associated works. This installation will be comprised of welding of field joints and the assembly of completed pipe spools which were prefabricated at Matrix’s workshop. As it stands there are five clusters in Dabbiya under this scope, all of the clusters will require the installation of new piping. The piping will vary in terms of pipe class, where some wells will have 1500# piping for the water injection wells and others have KG10 piping for gas injection. The following clusters will be covered under this scope: Cluster 14P – Water Injection Cluster 9J – Gas Injection Cluster 7G – WAG Cluster 5E – Dual Water Injection and WAG injection Cluster 1A – Gas injection 3.0 References  ADCO Contract No: 15410.01/EC 10825-Contracts Specification and Documents  ADCO Doc No:31.38.01.31A- Shop and Field Fabrication of Piping  ADCO Doc No: 30.99.12.0610-Rev3- Technical specification for piping system  ADCO HSE Manual Volume-10  ASME B 31.3- Process piping
  • 4. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 4 of 12  ADCO WS-1 Rev2-Specification for welding and inspection of shop and field fabricated carbon steel process and utility.  DOC No P12169 REV1- Project Quality Plan  AWS D1.1 -Structural welding code  DEP 34.28.00.31A -Structural steel works 4.0 Definitions  Client - Abu Dhabi Company for Onshore Oil Operations ( ADCO)  QHSE - Quality, Health, Safety & Environment  QCI - Quality Control Inspector  ITP - Inspection and Test Plan  WPS - Welding Procedure Specification  NDT - Non Destructive Testing  PWHT - Post Weld Heat Treatment 5.0 Responsibilities Matrix shall arrange all the resources deemed necessary for carrying out the works related to the piping installations. In addition to the above Matrix will also ensure that adequate safety precautions are put in place in order to carry out the job in a safe manner. Construction Manager: The Construction Manager is responsible in executing the works as per ADCO procedure and approved method statement. Supervisor/ Foreman:  Ensure that welding equipment, baking oven, quiver are in good condition.  Ensure welding is done as per the approved WPS and approved for construction
  • 5. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 5 of 12 drawings and in line with ADCO HSE requirements.  Ensure that weld maps / spool drawings are available.  Coordinate with QC personnel to study the cause of any reported weld defects and arrange to take corrective and preventive action.  Adhere to the ADCO HSE requirements.  Comply with ADCO PTW requirements. QC Inspector:  Carry out the inspection as per the Inspection and test plan.  Approving/ rejecting the item based on inspection.  Submitting the quality records to the client and getting their approval.  Responsible to keep records of all inspection related activities & Material traceability.  Adhere to the HSE requirements. HSE Officer:  Advise the construction crew on HSE aspects and ensure their safety.  Arrange through Job performer for tool box talk covering risk assessment in language understandable by workers.  Cross checking certified material devices and equipments are used.  Do weekly, monthly HSE audit.  Ensure appropriate safety measures are taken as per the risk assessment and controlled documents.  Ensure that all staff adhere to the HSE plan and HSE requirements. 6.0 Sequence of Works 6.1 PTW Issuance  A Hot Work permit will be issued to carry out the works, along with the permit will be the attached crane certificate, approved method statement, risk assessment, and approved drawings shall also be attached.
  • 6. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 6 of 12 6.2 Safety Setup  Arrange the required safety signs, barricades and other related safety precautions highlighted in the risk assessment and permit prior to commencing the works.  The works shall only commence after the job performer has checked and ensured that all safety precautions and safety requirements are in place.  Ensure employees understand the hazards and control measures related to the critical activities, i.e. lifting, welding.  Ensure personnel stay away from lifting zone and do not enter under the suspended loads.  Qualified First Aider must be on site and identified by a sticker on his helmet.  Display Emergency Contact number on site. 6.3 Site Works-Field Joints  Prefabricated pipe spools shall be carefully loaded and transported to site. The transported spools will be tied down with ample support to prevent any damage. Spools will be tied down using nylon straps/belts. Under no circumstances will the pipes be tied down using chains or cables to prevent any scratches or damage.  Upon receiving the pipes at site, they shall be offloaded and placed either in position on the pipe supports or placed on the ground on top of wooden supports. All flanged ends or open ends will remain sealed to prevent any sand or debris from entering.  Lifting of the pipe spools shall be done by using either a HIAB or Crane. Third Party certified slings and riggers shall be used during the lifting operations. All lifting tools and tackles shall be color coded based on the current color code.  Once the spools are lifted into position, the fabricator/pipe fitter shall ensure that proper alignment is achieved, lengths of spools are correct as per the piping layout and isometric sheet prior to either bolting the spools together or welding any field joints.  Welding and grinding of field joints shall be carried out inside a closed habitat made
  • 7. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 7 of 12 of fire retardant material. Any live facilities will be covered with the fire retardant blanket as an additional precaution.  Welding shall be done as per the approved procedure, specification and approved for construction drawings.  Approved welders for the specific WPS shall be used for welding.  Welded surfaces shall be clean and free from grease, oil, paint or other foreign material which are detrimental to welding.  When the weather does not permit satisfactory workmanship welding shall not be done, on site in windy condition the pipe ends shall be closed to prevent through draughts during welding. Suitable covering using tarpaulin (fire retardant) shall be provided. Welding shall not be done when the weld surface is wet or when the area is exposed to rain and strong windy conditions. Preheating to be done properly during cold weather. 6.4 Site Works - Welding of Pipe Supports  As required some structural steel pipe supports are to be welded to the base plates inserted into the precast foundations. Other pipe supports are to be welded to the existing pipe support structural steel racks.  Locations to be welded will be covered as required with a fire proof tarpaulin.  The base plate or support shall be cleaned by grinding to remove any surface debris, or paint.  The support will then be placed in position, aligned, and tack welded. Once tack welding is completed, the alignment will be rechecked and final welding will be carried out.  Welding shall be done based on the approved welding procedure for structural steel. 6.5 Site-Works-Valve Installation  Where ever valves are to be installed, the installation/orientation of valve handles and flow direction shall be according to the piping layout.  All valves to be installed will be cross checked according to the mesc number to
  • 8. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 8 of 12 ensure that the proper valves are installed in the proper location.  Valves shall be installed in the closed position except for ball valves and plug valves.  New gaskets will be installed between the valve flange and pipe flange. Final tightening of all nuts shall be done once proper alignment is achieved.  Bolting of flanges will be done in a cross pattern.  All bolts, gaskets and valves shall be properly stored to avoid contamination with the environment. Valve ends will be sealed until installation and gaskets and bolts shall be kept clean of any debris such as sand. 6.6 Scaffolding  Scaffolding if required shall be erected by qualified personnel in a safe and suitable manner.  Scaffolding above 2 m in height shall be inspected by a scaffolding inspector and a scaff-tag shall be signed and provided on the scaffolding near the ladder. No one shall use the scaffolding without the scaff-tag being approved.  Scaffolding material to be used shall be in good conditions, brass hammer shall be used to assemble and tighten the scaffolding locks. 7.0 QA/QC 7.1 Weld Identification  Each weld shall be uniquely identified with the joint number and welder number.  After completing the weld the welder shall mark the joint no: & welder no: near the weld using paint or indelible crayon.  After welding each spool the line no, spool no & etc shall be marked / tagged on the spool and stocked over wooden sleepers or other suitable material above ground. 7.2 Non Destructive Testing  Non destructive testing shall be done as per the approved procedure using approved sub contractor.
  • 9. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 9 of 12 7.3 Alignment Circumferential Welds  Butt weld alignment shall satisfy the requirement of ANSI B 31.3 and conditions stated below.  Internal misalignment of pipe work shall not exceed 1.6 mm in order to facilitate welding of the root pass. When a GTAW process is to be used maximum misalignment shall not exceed 0.8 mm. If there is excess misalignment tapering of the internal diameter of the thicker member to a taper of 1:4 shall be done. Ensure minimum wall thickness is maintained.  If misalignment up to 3.2 mm exists, internal grinding or machining may be conducted to improve root alignment, provided the taper does not exceed 1 in 4 maximum and the minimum required wall thickness is maintained.  External or internal clamps shall be used not only for misalignment correction but also for alignment in general. Misalignment correction using heavy hammering or heating of the pipe shall not be done. 7.4 Weld Separation  Circumferential welds (Girth welds): Distance between weld shall be measured between the adjacent edges of the cap passes. Circumferential butt welds (Girth welds) shall be separated by maximum possible distance. However between fittings, short pipe lengths may be required. In this case, butt welds shall not be within 75 mm of adjacent girth weld for nominal pipe sizes of 75 mm and above. For pipe sizes less than 75mm nominal, girth weld shall not be within the greater of 4 times the wall thickness or one pipe diameter of adjacent girth welds. Girth welds closer than the above limit shall require approval of the client and may require PWHT solely at the discretion of the company.  Branch / Nozzle / attachment welds. Branch / nozzle and other pressure attachment welds shall have minimum 3” distance to adjacent pressure welds. Non pressure containing attachment welds shall be separated by
  • 10. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 10 of 12 2” from adjacent pressure containing welds.  Longitudinal seams of adjacent pipes shall be separated by at least 4”. 7.5 Repair Welding  Any defects which require repair shall be entirely removed to sound metal. Metal shall be removed 1” on both side of the defect without substantial removal of the Base metal.  By grinding, the metal shall be removed and the groove shall be smooth without any undercut. Visual examination and magnetic/dye penetrant test shall be done on the grove.  If repairs are done after hydro test / PWHT, the same will be repeated after repair. Welding repair shall be done only twice. After second repair if the weld is not acceptable the weld shall be removed, re beveled and re welded.  Same NDT technique & acceptance criteria for the original weld shall be done after repair welding.  Proper cutting disc shall be used. Grinding disc shall not be used for cutting purposes. 8.0 Resources  Welding machine  Grinding machine  Preheating torches with propane gas cylinders  Holding ovens/baking ovens  PWHT equipment  Hiab, Crane, trailer  Cutting tools  Generator
  • 11. Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins Contract No. 15410.01/EC10825; Matrix Project No- P12169 Method Statement for Piping Works at Dabbiya Clusters Page 11 of 12 9.0 HSE Requirements 9.1 Risk Rating  Risk Rating is Medium: Job will have to be closely supervised by Job Performer, Safety officer and Supervisor. 9.2 HSE Requirements  Basic PPE, such as coverall, helmet, safety shoes, gloves, goggles and face mask (during windy days).  Appropriate approved PTW and certificate shall be obtained prior to commencing the job.  Standby vehicle will be present for emergency purposes.  Daily TBT  Approved and valid fire extinguishers (dry powder) shall be available.  Sufficient cold drinking water to be available at all times.  Third party certificates of all riggers and cranes  Proper color coding of all lifting tools, tackles 10.0 Emergency contacts The following shall be the contact number in case of any emergency. 1. ADCO Control Room - - 02 6046999 2. Mr. Chafic Mansour - Project Manager - 050 6670376 3. Mr. Zakir Ali-Safety Officer - 050 6112845