SlideShare a Scribd company logo
SCAFFOLD SAFE WORK
METHOD STATEMENT
PROJECT TITLE – ABC
CADANGAN MEMBAIKPULIH 5 RUMAH KEDIA SEDIA ADA 2 TINGKAT NO 191,
193,195,197 & 199 ( FASA 1 ), MENDIRIKAN 1 BLOK BANGUNAN PEJABAT 23
TINGKAT ( FASA 2 ) YANG TERDIRI DARIPADA: LOBI & RUANG M&E,CAR PARK
DAN TOWER 23 TINGKAT DI ATAS LOT 5 JALAN MEGAZINE,SEKSYEN 11W,
BANDAR GEORGETOWN, DTL, PULAU PINANG.
Company ABC Department Safety & Health
Title Scaffold Safe Work Method
Statement.
Rev.No 00
Originator Approver ABC
Position C & S Engineer Position Project Manager
Date Date
1 | P a g e
CONTENTS PAGE
1. INTRODUCTION 1
2. PURPOSE 2
3. SCOPE 2
4. DEFINITIONS 3
5. CONTROL MEASURES FOR WORKING PLATFORMS 5
6. ERECTING, ALTERING OR DISMANTLING 5
6.1 DESIGN CRITERIA FOR ERECTION PLATFORMS 6
6.2 DESIGN CRITERIA FOR TEMPORARY EDGE PROTECTION 7
6.3 GENERIC WORK SEQUENCE – SCAFFOLD ERECTING AND DISMANTLING 7
APPENDIX A – SCAFFOLD DESIGN 8
APPENDIX B – SCAFFOLD CALCULATION 9
APPENDIX C – SCAFFOLD INSPECTION CHECKLIST 10
2 | P a g e
1. INTRODUCTION
This Safe Work Method Statement provides information on how to manage risks associated with
scaffolds and scaffolding work at a workplace. It is supported by guidance for scaffold installation,
scaffold dismantling, scaffold inspection and maintenance, and advice for contractor and workers on
managing the risks associated with scaffolds and related scaffolding work.
A scaffold is a temporary structure erected to support access or working platforms. Scaffolds are
commonly used in construction work so workers have a safe, stable work platform when work
cannot be done at ground level or on a finished floor.
Scaffolding work is erecting, altering or dismantling a temporary structure erected to support a
platform and from which a person or object could fall more than 4 metres from the platform or the
structure. Scaffolding work must be undertaken under supervision of scaffold supervisor, which by a
person holding the appropriate licence.
Every metal tube scaffold exceeding 40 meter in height and every other scaffold exceeding 15
metres in height shall be constructed in accordance with the design and drawings of a Professional
Engineer.
3 | P a g e
2. PURPOSE
The following method statement is written to provide a safe and efficient system of work for the
installation of general working scaffold to all areas of construction sites both internal and external. It
will also cover all scaffold adaption’s to general scaffold and any safety and maintenance checks to
be held under current safety legislation within the construction industry. It will cover such areas as;
first installation scaffold, basic lifts (internal and external), adaption’s as work progresses during the
duration of project to basic scaffolding and general working guidelines . Any deviation which is
necessary for Safe Work Method Statement must first be notified to Project Manager and P.E who
will agree the best approach to Safe Work Method Statement with principle contractors approval.
3. SCOPE
This guide covers the erecting, altering and dismantling of prefabricated frame modular
scaffolding founded on the ground or another solid surface.
Fully decked scaffolds over 15 m in height may exceed the design strength of the system and the
design should be verified by an engineer competent in scaffold design.
There may be prefabricated modular steel scaffolding designs (component or site-specific
configuration) that require specific erection methods. For example:
• scaffolds that require specific engineering designs, such as hung scaffolds, cantilevered
scaffolds, loading platforms, birdcage scaffolds or scaffolds where the loads from
one bay are transferred to the adjoining standards, eg spur scaffolds or scaffolds
incorporating an access opening
4 | P a g e
4. DEFINITIONS
For the purpose of this guide, the following definitions apply:
BASE LIFT the first level of transoms and ledgers above the jacks.
CLOSED PLATFORM a platform that is constructed and that is capable of
functioning as a working platform, but is temporarily closed to
any loading or access.
ERECTION PLATFORM a temporary platform that is placed on the scaffold or
temporarily constructed as part of the scaffold to assist with
the installation (or removal) of the standards, transoms,
ledgers, guardrails and mid-rails for the platform above.
HOP-UP BRACKET
(PLATFORM a bracket that is attached to a scaffold to enable a platform to
BRACKET) be placed adjacent to a bay of an independent scaffold.
MUST indicates that the requirements are mandatory under the
occupational health and safety legislation.
PRINCIPAL
CONTRACTOR
a person who is appointed or taken to be the principal
contractor for the construction work.
SAFE WORK METHOD • describes how work is to be carried out
STATEMENT • identifies the work activities assessed as having safety risks
• identifies the safety risks
• describes the control measures that will be applied to the
work activities
• includes a description of the equipment used in the
work, the standards and codes to be complied with, the
qualifications of the personnel doing the work and the
training required to do the work.
SHOULD indicates a recommendation to do something that is not a
mandatory requirement under the occupational health and
safety legislation.
SOLID SURFACE a surface with adequate stiffness and strength to sustain
imposed loads from the scaffold.
TEMPORARY EDGE
PROTECTION a guardrail and midrail or proprietary system installed
to provide fall protection for scaffolders in advance of
the placement (or after removal) of the permanent edge
protection.
5 | P a g e
TIE BAR a member fixed to the cantilevered end of a pair of hop-up
brackets to prevent the brackets from spreading and the
planks from becoming dislodged.
TOE BOARD a scaffold plank or purpose-designed component fixed at the
edge of a platform to prevent material from falling off the
platform.
WORKING FACE the face of a building or structure at which the scaffold has
been erected to enable work to be carried out at some stage
of the project.
WORKING PLATFORM a platform on a scaffold, positioned at a work location for
supporting personnel, equipment and materials, and used to
provide a working area.
6 | P a g e
5. CONTROL MEASURES FOR WORKING PLATFORMS
There should be a system in place to limit the number of platforms permitted as working
platforms, and to limit the respective platform ratings, to prevent the scaffold being overloaded.
Possible systems include:
• closing off platforms at the access points by physical means
• placing signs at the access points to each platform, advising if closed or indicating the duty
rating of a working platform
• assigning an on-site scaffold coordinator to the relevant contractors, to control the use of various
platforms, or sections of platform.
Principal contractors must clearly identify in their site-specific occupational health and safety (OHS)
management plan those responsible for implementing the control measures.
The system should also:
• include in the site induction the control measures and the names of those persons
responsible for implementing the controls
• have means to identify working platforms that are closed – this can be discussed at regular
toolbox meetings
• have means to monitor and review the control measures regularly – if the control measures are
not effective, they should be modified, and records of the monitoring and modifications should
be kept.
6. ERECTING, ALTERING OR DISMANTLING
Risk assessments and safe work method statements are the joint responsibility of the principal
contractor and scaffolding employer. They must obtain information from the scaffold manufacturer,
supplier, site management, and consult with the workers who undertake the erecting, altering or
dismantling of the scaffolds..
For safe completion of the work, consider the following:
• Pass scaffold items – do not throw them.
• The scaffolder must work from a safe position when installing edge protection for the platform
above, eg by:
• The scaffolder should be supported on a fully planked platform when installing the platform
immediately above.
• The fully planked platforms should be nominally 2 m apart, vertically, and remain in place
until the scaffold is dismantled.
• The first platform can be up to 3 m above the ground or supporting surface, except for the
access bay.
• Safe access must be provided up to the first platform and between platforms on the scaffold.
• Risks from overhead power lines must be assessed and controlled.
7 | P a g e
6.1 DESIGN CRITERIA FOR ERECTION PLATFORMS
Erection platforms should comply with the criteria given below.
Type of erection platform Criteria
Ladder-based erection Load rating: minimum 120 kg.
platforms
Stiles: minimum spacing 350 mm.
(for scaffolding platform
Platform area: minimum 350 mm wide x 300 mm deep,
including the ladder rung if it is at the same level as the
platform.erection platform max 2 m
in heights )
For erection platforms up to 1.2 m in height, incorporate a
built-in mid-rail on the three non-access sides. For single
ladder types the continuing stiles are considered as mid-rails.
For erection platforms between 1.2 m and 2 m in height,
incorporate guardrails on the three non-access sides.
Erection platforms Load rating: minimum 120 kg.
supported on ledgers/
Erection platform area: minimum 500 mm x 600 mm.
guardrails (suitable for
On scaffolding edge sides, incorporate a built-in mid-rail.
scaffolding platform
spacing of up to 2 m)
Scaffold planks supported Platform area: minimum 2 x 225 mm wide scaffold planks.
on temporary transoms
(suitable for scaffolding
platform spacing of up to
2 m)
8 | P a g e
6.2 DESIGN CRITERIA FOR TEMPORARY EDGE PROTECTION
Temporary edge protection must meet the strength requirements for guardrails and mid-rails
specified in BOWEC General requirements and should be designed to allow the installation and
removal of the permanent guardrails whilst it is in position.
6.3 GENERIC WORK SEQUENCE – SCAFFOLD ERECTING AND DISMANTLING
Where work methods differ from the generic work sequence below alternative methods must
provide an equivalent level of safety to those specified in this guide.
Task Activity – Erection of Scaffold
Break the job
down into steps
Base out scaffold • Prevent unauthorised access to scaffold area.
and erect base lift • One scaffolder holds standards, while another places transoms and
and first lift ledgers.
• Adjust screw jacks to level the scaffold.
• Erect transoms and ledgers for the first lift.
• Erect planks from below for the first lift.
Complete first lift • Install access stairway or ladder to platform for the first lift.
• If access is by stairway, ensure the stair access bay is erected with
the run of the scaffold.
• Install edge protection comprising guardrail, mid-rail and toeboard
or mesh panels to first lift.
Erect next lift Working from a fully planked platform on the first lift, install standards
from a platform (where the standard joint is 1 to 1.5 m above the platform level),
transoms, ledgers and hop-ups for the next lift above.
Where using erection platforms
− Place an erection platform on the scaffold
− Working from the erection platform, erect standards (where the
standard joint is 1 to 1.5 m above the erection platform level),
mid-rails and guardrails for the lift above.
− Standing on the working platform (or an erection platform for
lifts of 2.5 to 3 m), place planks within the transoms to form the
above working platform.
− Install ladder or stairway access to working platform above.
− Access the above working platform.
− Install toeboards (or other systems to prevent objects falling).
9 | P a g e
Break the job down
into steps
Where using temporary edge protection
− Install temporary edge protection for platform above.
− Install transoms and ledgers for platform above.
− Standing on the working platform (or an erection platform for
lifts of 2.5 to 3 m), place planks within the transoms to form the
above working platform.
− Install ladder or stairway access to working platform above.
− Access the above working platform.
− Install next standards, guardrails and mid-rails.
− Install toeboards (or other systems to prevent objects falling).
• Scaffold should be erected as close as practicable to the working
face. Where the scaffold is greater than 225 mm from the working
face, install guardrails and mid-rails to the inner face standards.
Erect next lifts • Unless a specific engineering design is provided, fix the first row of
ties no more than 4 m above the ground. Do not allow a scaffold
to free stand more than 4 m above the ground or a row of ties.
• Secure objects or remove unsecured objects from the scaffold.
• Repeat erection sequence as per previous task.
Dismantle scaffold General precautions
• Access the scaffold platform from a ladder or stair access – do not
climb the standards, ledgers and transoms.
• Maintain a tidy work area.
• Do not overload the scaffold bays – progressively remove scaffolding
equipment from platforms and stack it neatly on the ground.
• Do not leave loose materials on platforms.
• Do not throw down any materials or scaffolding equipment.
• Remove chain wire mesh and shade cloth while working from a
fully planked platform.
• Work with a guardrail in place when removing and passing mesh
Panels down.
• Work from a fully planked platform below when dismantling hop-up
brackets, tie bars and planks.
• Do not allow an unsheeted scaffold to free stand more than4 m or
a sheeted scaffold more than 2 m above the highest tie remaining
in place.
• Before lifting a toeboard, ensure the adjacent plank is held in place.
Task Activity
10 | P a g e
Task
Break the job
down into steps
Activity
Dismantling sequence
Note: Follow the below dismantling sequence if you are using
erection platforms. If you are using a temporary edge protection
system, modify the dismantling sequence to suit.
• Access the top platform by stairway or ladder.
• Start dismantling from an end bay.
• Remove chain wire mesh and shade cloth, or mesh panels,
from the level to be dismantled or from the whole scaffold if
not required during the dismantling process.
• Move down to the platform below.
• Dismantle top platform planks.
• Working from an erection platform on the fully planked
platform, dismantle guardrails, mid-rails, ledgers, transoms
and standards from the level above.
• Step off the erection platform.
• Dismantle the hop-up platform above, if in place.
• Remove not more than three planks (ensure at least two
planks remain) to enable the dismantled materials to be
passed down to the next level (where they are to be
temporarily stacked or removed from the scaffold).
• If removing dismantled materials progressively down through
the scaffold, ensure that the gaps created are not directly
below each other and that planks are replaced when a gap is
not being used to lower materials.
• Remove ties progressively as the scaffold is dismantled.
Progressively repeat this procedure until dismantling can be
completed from the ground

More Related Content

What's hot

Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
Muhammad Shahid
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
hafiz abdul majid
 
Mobile crane legal requirements
Mobile crane  legal requirementsMobile crane  legal requirements
Mobile crane legal requirements
Hamat, Mohd Kudzi
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety Training
William York
 
Erection of scaffolding
Erection of scaffoldingErection of scaffolding
Erection of scaffolding
SAKET AGRAWAL
 
Scaffold classes and duties (cals)
Scaffold classes and duties (cals)Scaffold classes and duties (cals)
Scaffold classes and duties (cals)
robadet
 
Lifting plan
Lifting planLifting plan
Lifting plan
tnsv22
 
Scaffolding checklist
Scaffolding checklistScaffolding checklist
Scaffolding checklist
HASNIZAM BIN MD SAAD
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
DusanJankovic8
 
Scaffolding2. CO3.ppt
Scaffolding2. CO3.pptScaffolding2. CO3.ppt
Scaffolding2. CO3.ppt
Amelita Mangayan
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
VasudevaRajuDantulur1
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
Azmeel Contracting Company
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
Osho Shemil Baba
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
Mohammed Mubasheeruddin
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
FAIZ FAREED
 
Mounted Boom Concrete Pump Safety
Mounted Boom Concrete Pump SafetyMounted Boom Concrete Pump Safety
Mounted Boom Concrete Pump Safety
Ali Kamal Mostofa Rubel
 
BANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptBANKSMAN TRAINING.ppt
BANKSMAN TRAINING.ppt
Kamran Zafar
 
bar bending safety precautions.pdf
bar bending safety precautions.pdfbar bending safety precautions.pdf
bar bending safety precautions.pdf
construction
 
Basic rigging training manual
Basic rigging training manualBasic rigging training manual
Basic rigging training manual
Syam Tawakkal
 

What's hot (20)

Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Mobile crane legal requirements
Mobile crane  legal requirementsMobile crane  legal requirements
Mobile crane legal requirements
 
SCAFFOLDING Safety Training
SCAFFOLDING Safety TrainingSCAFFOLDING Safety Training
SCAFFOLDING Safety Training
 
Erection of scaffolding
Erection of scaffoldingErection of scaffolding
Erection of scaffolding
 
Scaffold classes and duties (cals)
Scaffold classes and duties (cals)Scaffold classes and duties (cals)
Scaffold classes and duties (cals)
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Scaffolding checklist
Scaffolding checklistScaffolding checklist
Scaffolding checklist
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
 
Scaffolding2. CO3.ppt
Scaffolding2. CO3.pptScaffolding2. CO3.ppt
Scaffolding2. CO3.ppt
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
Mounted Boom Concrete Pump Safety
Mounted Boom Concrete Pump SafetyMounted Boom Concrete Pump Safety
Mounted Boom Concrete Pump Safety
 
BANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptBANKSMAN TRAINING.ppt
BANKSMAN TRAINING.ppt
 
bar bending safety precautions.pdf
bar bending safety precautions.pdfbar bending safety precautions.pdf
bar bending safety precautions.pdf
 
Basic rigging training manual
Basic rigging training manualBasic rigging training manual
Basic rigging training manual
 

Viewers also liked

Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
Minh Bui Si
 
072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
Dr Fereidoun Dejahang
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
Minh Bui Si
 
Method statement painting
Method statement painting Method statement painting
Method statement painting
Daniel SLSA CLA
 
Stainless Steel Railing
Stainless Steel RailingStainless Steel Railing
Stainless Steel Railing
John Mike
 
Method Statement Cleaning and Treating New Commercial Systems
Method Statement Cleaning and Treating New Commercial SystemsMethod Statement Cleaning and Treating New Commercial Systems
Method Statement Cleaning and Treating New Commercial Systems
Fernox
 
Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)
Devinder Chawla
 
Stainless steel fabrication
Stainless steel fabricationStainless steel fabrication
Stainless steel fabrication
Absolute Metal Fabrications
 
Stainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
Stainless Steel Fabrication Works by Global Glass & Glazing System MumbaiStainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
Stainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
IndiaMART InterMESH Limited
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement welding
Aanand Subi
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
Minh Bui Si
 
Method of Statement - Painting works
Method of Statement - Painting worksMethod of Statement - Painting works
Method of Statement - Painting works
Mohd Nizam Mohd Zan
 
Method of Statement - Road furniture works
Method of Statement - Road furniture worksMethod of Statement - Road furniture works
Method of Statement - Road furniture works
Mohd Nizam Mohd Zan
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
NECB
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
Mohd Nizam Mohd Zan
 
Pipe and-fittings
Pipe and-fittingsPipe and-fittings
Pipe and-fittings
thanhuce
 
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
pierdole
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
Minh Bui Si
 
Method stm lean concrete
Method stm lean concreteMethod stm lean concrete
Method stm lean concrete
Minh Bui Si
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
Tong Seng Chua
 

Viewers also liked (20)

Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
072 Method Statement
072 Method Statement072 Method Statement
072 Method Statement
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Method statement painting
Method statement painting Method statement painting
Method statement painting
 
Stainless Steel Railing
Stainless Steel RailingStainless Steel Railing
Stainless Steel Railing
 
Method Statement Cleaning and Treating New Commercial Systems
Method Statement Cleaning and Treating New Commercial SystemsMethod Statement Cleaning and Treating New Commercial Systems
Method Statement Cleaning and Treating New Commercial Systems
 
Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)
 
Stainless steel fabrication
Stainless steel fabricationStainless steel fabrication
Stainless steel fabrication
 
Stainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
Stainless Steel Fabrication Works by Global Glass & Glazing System MumbaiStainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
Stainless Steel Fabrication Works by Global Glass & Glazing System Mumbai
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement welding
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 
Method of Statement - Painting works
Method of Statement - Painting worksMethod of Statement - Painting works
Method of Statement - Painting works
 
Method of Statement - Road furniture works
Method of Statement - Road furniture worksMethod of Statement - Road furniture works
Method of Statement - Road furniture works
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
 
Pipe and-fittings
Pipe and-fittingsPipe and-fittings
Pipe and-fittings
 
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Method stm lean concrete
Method stm lean concreteMethod stm lean concrete
Method stm lean concrete
 
Supervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, SingaporeSupervision of piling works, ACES, 2011, Singapore
Supervision of piling works, ACES, 2011, Singapore
 

Similar to Scaffold safe work method statement

Scaffolding safety procedures and its types
Scaffolding safety procedures and its typesScaffolding safety procedures and its types
Scaffolding safety procedures and its types
abhisheksharma12001
 
SCAFFOLDING
SCAFFOLDINGSCAFFOLDING
SCAFFOLDING
Akhilesh A
 
UNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfUNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdf
PinakRay1
 
Safety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of ConstructionSafety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of Construction
Sandeep Jain
 
4.6 working at heights and fall protection plan
4.6 working at heights and fall protection plan4.6 working at heights and fall protection plan
4.6 working at heights and fall protection plan
Dwarika Bhushan Sharma
 
Scaffold 0c8be2a1 9996-490a-99c0-6ef40baed98a
Scaffold 0c8be2a1 9996-490a-99c0-6ef40baed98aScaffold 0c8be2a1 9996-490a-99c0-6ef40baed98a
Scaffold 0c8be2a1 9996-490a-99c0-6ef40baed98a
uniqcogroup
 
Guide to Spider Lifts, Spider Cranes.pptx
Guide to Spider Lifts, Spider Cranes.pptxGuide to Spider Lifts, Spider Cranes.pptx
Guide to Spider Lifts, Spider Cranes.pptx
Muhammad Luqman
 
CS S3
CS S3CS S3
Safety-engineering-report-gr.6.pptx
Safety-engineering-report-gr.6.pptxSafety-engineering-report-gr.6.pptx
Safety-engineering-report-gr.6.pptx
JessadelCadalin1
 
Scaffolding by chakamba j
Scaffolding by chakamba jScaffolding by chakamba j
Scaffolding by chakamba j
John Chakamba
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017
John Newquist
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
ssuseref23d3
 
Principles of Scaffolding.pdf
Principles of Scaffolding.pdfPrinciples of Scaffolding.pdf
Principles of Scaffolding.pdf
alad8
 
Erection Methodology (KG Marg) MLCP.pptx
Erection Methodology (KG Marg) MLCP.pptxErection Methodology (KG Marg) MLCP.pptx
Erection Methodology (KG Marg) MLCP.pptx
zrahman0161
 
Personnel liftingad
Personnel liftingadPersonnel liftingad
Personnel liftingad
Roberth Rodriguez Giraldo
 
Jump Formwork
Jump FormworkJump Formwork
Working at Heights
Working at Heights Working at Heights
Working at Heights
FTERIESW
 
Application of Standards and guidelines for access systems to manage fall fro...
Application of Standards and guidelines for access systems to manage fall fro...Application of Standards and guidelines for access systems to manage fall fro...
Application of Standards and guidelines for access systems to manage fall fro...
NSW Environment and Planning
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
Katy A. Beitia G.
 
Erection of structural components in precast constructions
Erection of structural components in precast constructionsErection of structural components in precast constructions
Erection of structural components in precast constructions
ParamaAthmeka
 

Similar to Scaffold safe work method statement (20)

Scaffolding safety procedures and its types
Scaffolding safety procedures and its typesScaffolding safety procedures and its types
Scaffolding safety procedures and its types
 
SCAFFOLDING
SCAFFOLDINGSCAFFOLDING
SCAFFOLDING
 
UNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfUNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdf
 
Safety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of ConstructionSafety & Quality Aspects in '3-S' System of Construction
Safety & Quality Aspects in '3-S' System of Construction
 
4.6 working at heights and fall protection plan
4.6 working at heights and fall protection plan4.6 working at heights and fall protection plan
4.6 working at heights and fall protection plan
 
Scaffold 0c8be2a1 9996-490a-99c0-6ef40baed98a
Scaffold 0c8be2a1 9996-490a-99c0-6ef40baed98aScaffold 0c8be2a1 9996-490a-99c0-6ef40baed98a
Scaffold 0c8be2a1 9996-490a-99c0-6ef40baed98a
 
Guide to Spider Lifts, Spider Cranes.pptx
Guide to Spider Lifts, Spider Cranes.pptxGuide to Spider Lifts, Spider Cranes.pptx
Guide to Spider Lifts, Spider Cranes.pptx
 
CS S3
CS S3CS S3
CS S3
 
Safety-engineering-report-gr.6.pptx
Safety-engineering-report-gr.6.pptxSafety-engineering-report-gr.6.pptx
Safety-engineering-report-gr.6.pptx
 
Scaffolding by chakamba j
Scaffolding by chakamba jScaffolding by chakamba j
Scaffolding by chakamba j
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
Principles of Scaffolding.pdf
Principles of Scaffolding.pdfPrinciples of Scaffolding.pdf
Principles of Scaffolding.pdf
 
Erection Methodology (KG Marg) MLCP.pptx
Erection Methodology (KG Marg) MLCP.pptxErection Methodology (KG Marg) MLCP.pptx
Erection Methodology (KG Marg) MLCP.pptx
 
Personnel liftingad
Personnel liftingadPersonnel liftingad
Personnel liftingad
 
Jump Formwork
Jump FormworkJump Formwork
Jump Formwork
 
Working at Heights
Working at Heights Working at Heights
Working at Heights
 
Application of Standards and guidelines for access systems to manage fall fro...
Application of Standards and guidelines for access systems to manage fall fro...Application of Standards and guidelines for access systems to manage fall fro...
Application of Standards and guidelines for access systems to manage fall fro...
 
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
0-GG010-MZ711-00020 Scaffolding Procedure rev.1 .docx
 
Erection of structural components in precast constructions
Erection of structural components in precast constructionsErection of structural components in precast constructions
Erection of structural components in precast constructions
 

Recently uploaded

The Significance of Flowers in Our Lives
The Significance of Flowers in Our LivesThe Significance of Flowers in Our Lives
The Significance of Flowers in Our Lives
BISOU Flowers
 
Siddhivinayak temple timings Houston, TX
Siddhivinayak temple timings Houston, TXSiddhivinayak temple timings Houston, TX
Siddhivinayak temple timings Houston, TX
gaurisiddhivinayakte
 
Copy Trading Forex Brokers 2024 ptx
Copy Trading Forex Brokers 2024      ptxCopy Trading Forex Brokers 2024      ptx
Copy Trading Forex Brokers 2024 ptx
Brokerreviewfx
 
Expert Tips for Pruning Your Plants.pdf.
Expert Tips for Pruning Your Plants.pdf.Expert Tips for Pruning Your Plants.pdf.
Expert Tips for Pruning Your Plants.pdf.
Local Gardeners
 
x ray baggage scanner manufacturers in India
x ray baggage scanner manufacturers in Indiax ray baggage scanner manufacturers in India
x ray baggage scanner manufacturers in India
Gujar Industries India Pvt. Ltd
 
Electrical Testing Lab Services in Dubai.pdf
Electrical Testing Lab Services in Dubai.pdfElectrical Testing Lab Services in Dubai.pdf
Electrical Testing Lab Services in Dubai.pdf
sandeepmetsuae
 
Greeting powerpoint slide for kids( 4-6 years old)
Greeting powerpoint slide for kids( 4-6 years old)Greeting powerpoint slide for kids( 4-6 years old)
Greeting powerpoint slide for kids( 4-6 years old)
lenguyenthaotrang663
 
eBrand Promotion Full Service Digital Agency Company Profile
eBrand Promotion Full Service Digital Agency Company ProfileeBrand Promotion Full Service Digital Agency Company Profile
eBrand Promotion Full Service Digital Agency Company Profile
ChimaOrjiOkpi
 
WORK PERMIT IN NORWAY | WORK VISA SERVICE
WORK  PERMIT  IN  NORWAY | WORK VISA SERVICEWORK  PERMIT  IN  NORWAY | WORK VISA SERVICE
WORK PERMIT IN NORWAY | WORK VISA SERVICE
RKIMT
 
Best Immigration Consultants in Amritsar- SAGA Studies
Best Immigration Consultants in Amritsar- SAGA StudiesBest Immigration Consultants in Amritsar- SAGA Studies
Best Immigration Consultants in Amritsar- SAGA Studies
SAGA Studies
 
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Summerland Environmental
 
Emmanuel Katto Uganda - A Philanthropist
Emmanuel Katto Uganda - A PhilanthropistEmmanuel Katto Uganda - A Philanthropist
Emmanuel Katto Uganda - A Philanthropist
Marina Costa
 
Best Web Development Frameworks in 2024
Best Web Development Frameworks in 2024Best Web Development Frameworks in 2024
Best Web Development Frameworks in 2024
growthgrids
 
Bridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Bridging the Language Gap The Power of Simultaneous Interpretation in RwandaBridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Bridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Kasuku Translation Ltd
 
antivirus and security software | basics
antivirus and security software | basicsantivirus and security software | basics
antivirus and security software | basics
basicsprotection
 
Biomass Briquettes A Sustainable Solution for Energy and Waste Management..pptx
Biomass Briquettes A Sustainable Solution for Energy and Waste Management..pptxBiomass Briquettes A Sustainable Solution for Energy and Waste Management..pptx
Biomass Briquettes A Sustainable Solution for Energy and Waste Management..pptx
ECOSTAN Biofuel Pvt Ltd
 
Top 10 Challenges That Every Web Designer Face on A Daily Basis.pptx
Top 10 Challenges That Every Web Designer Face on A Daily Basis.pptxTop 10 Challenges That Every Web Designer Face on A Daily Basis.pptx
Top 10 Challenges That Every Web Designer Face on A Daily Basis.pptx
e-Definers Technology
 
The Fraud Examiner’s Report – What the Certified Fraud Examiner Should Know
The Fraud Examiner’s Report –  What the Certified Fraud Examiner Should KnowThe Fraud Examiner’s Report –  What the Certified Fraud Examiner Should Know
The Fraud Examiner’s Report – What the Certified Fraud Examiner Should Know
Godwin Emmanuel Oyedokun MBA MSc PhD FCA FCTI FCNA CFE FFAR
 
Understanding Love Compatibility or Synastry: Why It Matters
Understanding Love Compatibility or Synastry: Why It MattersUnderstanding Love Compatibility or Synastry: Why It Matters
Understanding Love Compatibility or Synastry: Why It Matters
AstroForYou
 
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptxTop Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Merchantech - Payment Processing Services
 

Recently uploaded (20)

The Significance of Flowers in Our Lives
The Significance of Flowers in Our LivesThe Significance of Flowers in Our Lives
The Significance of Flowers in Our Lives
 
Siddhivinayak temple timings Houston, TX
Siddhivinayak temple timings Houston, TXSiddhivinayak temple timings Houston, TX
Siddhivinayak temple timings Houston, TX
 
Copy Trading Forex Brokers 2024 ptx
Copy Trading Forex Brokers 2024      ptxCopy Trading Forex Brokers 2024      ptx
Copy Trading Forex Brokers 2024 ptx
 
Expert Tips for Pruning Your Plants.pdf.
Expert Tips for Pruning Your Plants.pdf.Expert Tips for Pruning Your Plants.pdf.
Expert Tips for Pruning Your Plants.pdf.
 
x ray baggage scanner manufacturers in India
x ray baggage scanner manufacturers in Indiax ray baggage scanner manufacturers in India
x ray baggage scanner manufacturers in India
 
Electrical Testing Lab Services in Dubai.pdf
Electrical Testing Lab Services in Dubai.pdfElectrical Testing Lab Services in Dubai.pdf
Electrical Testing Lab Services in Dubai.pdf
 
Greeting powerpoint slide for kids( 4-6 years old)
Greeting powerpoint slide for kids( 4-6 years old)Greeting powerpoint slide for kids( 4-6 years old)
Greeting powerpoint slide for kids( 4-6 years old)
 
eBrand Promotion Full Service Digital Agency Company Profile
eBrand Promotion Full Service Digital Agency Company ProfileeBrand Promotion Full Service Digital Agency Company Profile
eBrand Promotion Full Service Digital Agency Company Profile
 
WORK PERMIT IN NORWAY | WORK VISA SERVICE
WORK  PERMIT  IN  NORWAY | WORK VISA SERVICEWORK  PERMIT  IN  NORWAY | WORK VISA SERVICE
WORK PERMIT IN NORWAY | WORK VISA SERVICE
 
Best Immigration Consultants in Amritsar- SAGA Studies
Best Immigration Consultants in Amritsar- SAGA StudiesBest Immigration Consultants in Amritsar- SAGA Studies
Best Immigration Consultants in Amritsar- SAGA Studies
 
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
Sustainable Solutions for Chemical Waste Disposal by Summerland Environmental...
 
Emmanuel Katto Uganda - A Philanthropist
Emmanuel Katto Uganda - A PhilanthropistEmmanuel Katto Uganda - A Philanthropist
Emmanuel Katto Uganda - A Philanthropist
 
Best Web Development Frameworks in 2024
Best Web Development Frameworks in 2024Best Web Development Frameworks in 2024
Best Web Development Frameworks in 2024
 
Bridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Bridging the Language Gap The Power of Simultaneous Interpretation in RwandaBridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
Bridging the Language Gap The Power of Simultaneous Interpretation in Rwanda
 
antivirus and security software | basics
antivirus and security software | basicsantivirus and security software | basics
antivirus and security software | basics
 
Biomass Briquettes A Sustainable Solution for Energy and Waste Management..pptx
Biomass Briquettes A Sustainable Solution for Energy and Waste Management..pptxBiomass Briquettes A Sustainable Solution for Energy and Waste Management..pptx
Biomass Briquettes A Sustainable Solution for Energy and Waste Management..pptx
 
Top 10 Challenges That Every Web Designer Face on A Daily Basis.pptx
Top 10 Challenges That Every Web Designer Face on A Daily Basis.pptxTop 10 Challenges That Every Web Designer Face on A Daily Basis.pptx
Top 10 Challenges That Every Web Designer Face on A Daily Basis.pptx
 
The Fraud Examiner’s Report – What the Certified Fraud Examiner Should Know
The Fraud Examiner’s Report –  What the Certified Fraud Examiner Should KnowThe Fraud Examiner’s Report –  What the Certified Fraud Examiner Should Know
The Fraud Examiner’s Report – What the Certified Fraud Examiner Should Know
 
Understanding Love Compatibility or Synastry: Why It Matters
Understanding Love Compatibility or Synastry: Why It MattersUnderstanding Love Compatibility or Synastry: Why It Matters
Understanding Love Compatibility or Synastry: Why It Matters
 
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptxTop Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
Top Challenges Faced by High-Risk Merchants and How to Overcome Them.pptx
 

Scaffold safe work method statement

  • 1. SCAFFOLD SAFE WORK METHOD STATEMENT PROJECT TITLE – ABC CADANGAN MEMBAIKPULIH 5 RUMAH KEDIA SEDIA ADA 2 TINGKAT NO 191, 193,195,197 & 199 ( FASA 1 ), MENDIRIKAN 1 BLOK BANGUNAN PEJABAT 23 TINGKAT ( FASA 2 ) YANG TERDIRI DARIPADA: LOBI & RUANG M&E,CAR PARK DAN TOWER 23 TINGKAT DI ATAS LOT 5 JALAN MEGAZINE,SEKSYEN 11W, BANDAR GEORGETOWN, DTL, PULAU PINANG. Company ABC Department Safety & Health Title Scaffold Safe Work Method Statement. Rev.No 00 Originator Approver ABC Position C & S Engineer Position Project Manager Date Date
  • 2. 1 | P a g e CONTENTS PAGE 1. INTRODUCTION 1 2. PURPOSE 2 3. SCOPE 2 4. DEFINITIONS 3 5. CONTROL MEASURES FOR WORKING PLATFORMS 5 6. ERECTING, ALTERING OR DISMANTLING 5 6.1 DESIGN CRITERIA FOR ERECTION PLATFORMS 6 6.2 DESIGN CRITERIA FOR TEMPORARY EDGE PROTECTION 7 6.3 GENERIC WORK SEQUENCE – SCAFFOLD ERECTING AND DISMANTLING 7 APPENDIX A – SCAFFOLD DESIGN 8 APPENDIX B – SCAFFOLD CALCULATION 9 APPENDIX C – SCAFFOLD INSPECTION CHECKLIST 10
  • 3. 2 | P a g e 1. INTRODUCTION This Safe Work Method Statement provides information on how to manage risks associated with scaffolds and scaffolding work at a workplace. It is supported by guidance for scaffold installation, scaffold dismantling, scaffold inspection and maintenance, and advice for contractor and workers on managing the risks associated with scaffolds and related scaffolding work. A scaffold is a temporary structure erected to support access or working platforms. Scaffolds are commonly used in construction work so workers have a safe, stable work platform when work cannot be done at ground level or on a finished floor. Scaffolding work is erecting, altering or dismantling a temporary structure erected to support a platform and from which a person or object could fall more than 4 metres from the platform or the structure. Scaffolding work must be undertaken under supervision of scaffold supervisor, which by a person holding the appropriate licence. Every metal tube scaffold exceeding 40 meter in height and every other scaffold exceeding 15 metres in height shall be constructed in accordance with the design and drawings of a Professional Engineer.
  • 4. 3 | P a g e 2. PURPOSE The following method statement is written to provide a safe and efficient system of work for the installation of general working scaffold to all areas of construction sites both internal and external. It will also cover all scaffold adaption’s to general scaffold and any safety and maintenance checks to be held under current safety legislation within the construction industry. It will cover such areas as; first installation scaffold, basic lifts (internal and external), adaption’s as work progresses during the duration of project to basic scaffolding and general working guidelines . Any deviation which is necessary for Safe Work Method Statement must first be notified to Project Manager and P.E who will agree the best approach to Safe Work Method Statement with principle contractors approval. 3. SCOPE This guide covers the erecting, altering and dismantling of prefabricated frame modular scaffolding founded on the ground or another solid surface. Fully decked scaffolds over 15 m in height may exceed the design strength of the system and the design should be verified by an engineer competent in scaffold design. There may be prefabricated modular steel scaffolding designs (component or site-specific configuration) that require specific erection methods. For example: • scaffolds that require specific engineering designs, such as hung scaffolds, cantilevered scaffolds, loading platforms, birdcage scaffolds or scaffolds where the loads from one bay are transferred to the adjoining standards, eg spur scaffolds or scaffolds incorporating an access opening
  • 5. 4 | P a g e 4. DEFINITIONS For the purpose of this guide, the following definitions apply: BASE LIFT the first level of transoms and ledgers above the jacks. CLOSED PLATFORM a platform that is constructed and that is capable of functioning as a working platform, but is temporarily closed to any loading or access. ERECTION PLATFORM a temporary platform that is placed on the scaffold or temporarily constructed as part of the scaffold to assist with the installation (or removal) of the standards, transoms, ledgers, guardrails and mid-rails for the platform above. HOP-UP BRACKET (PLATFORM a bracket that is attached to a scaffold to enable a platform to BRACKET) be placed adjacent to a bay of an independent scaffold. MUST indicates that the requirements are mandatory under the occupational health and safety legislation. PRINCIPAL CONTRACTOR a person who is appointed or taken to be the principal contractor for the construction work. SAFE WORK METHOD • describes how work is to be carried out STATEMENT • identifies the work activities assessed as having safety risks • identifies the safety risks • describes the control measures that will be applied to the work activities • includes a description of the equipment used in the work, the standards and codes to be complied with, the qualifications of the personnel doing the work and the training required to do the work. SHOULD indicates a recommendation to do something that is not a mandatory requirement under the occupational health and safety legislation. SOLID SURFACE a surface with adequate stiffness and strength to sustain imposed loads from the scaffold. TEMPORARY EDGE PROTECTION a guardrail and midrail or proprietary system installed to provide fall protection for scaffolders in advance of the placement (or after removal) of the permanent edge protection.
  • 6. 5 | P a g e TIE BAR a member fixed to the cantilevered end of a pair of hop-up brackets to prevent the brackets from spreading and the planks from becoming dislodged. TOE BOARD a scaffold plank or purpose-designed component fixed at the edge of a platform to prevent material from falling off the platform. WORKING FACE the face of a building or structure at which the scaffold has been erected to enable work to be carried out at some stage of the project. WORKING PLATFORM a platform on a scaffold, positioned at a work location for supporting personnel, equipment and materials, and used to provide a working area.
  • 7. 6 | P a g e 5. CONTROL MEASURES FOR WORKING PLATFORMS There should be a system in place to limit the number of platforms permitted as working platforms, and to limit the respective platform ratings, to prevent the scaffold being overloaded. Possible systems include: • closing off platforms at the access points by physical means • placing signs at the access points to each platform, advising if closed or indicating the duty rating of a working platform • assigning an on-site scaffold coordinator to the relevant contractors, to control the use of various platforms, or sections of platform. Principal contractors must clearly identify in their site-specific occupational health and safety (OHS) management plan those responsible for implementing the control measures. The system should also: • include in the site induction the control measures and the names of those persons responsible for implementing the controls • have means to identify working platforms that are closed – this can be discussed at regular toolbox meetings • have means to monitor and review the control measures regularly – if the control measures are not effective, they should be modified, and records of the monitoring and modifications should be kept. 6. ERECTING, ALTERING OR DISMANTLING Risk assessments and safe work method statements are the joint responsibility of the principal contractor and scaffolding employer. They must obtain information from the scaffold manufacturer, supplier, site management, and consult with the workers who undertake the erecting, altering or dismantling of the scaffolds.. For safe completion of the work, consider the following: • Pass scaffold items – do not throw them. • The scaffolder must work from a safe position when installing edge protection for the platform above, eg by: • The scaffolder should be supported on a fully planked platform when installing the platform immediately above. • The fully planked platforms should be nominally 2 m apart, vertically, and remain in place until the scaffold is dismantled. • The first platform can be up to 3 m above the ground or supporting surface, except for the access bay. • Safe access must be provided up to the first platform and between platforms on the scaffold. • Risks from overhead power lines must be assessed and controlled.
  • 8. 7 | P a g e 6.1 DESIGN CRITERIA FOR ERECTION PLATFORMS Erection platforms should comply with the criteria given below. Type of erection platform Criteria Ladder-based erection Load rating: minimum 120 kg. platforms Stiles: minimum spacing 350 mm. (for scaffolding platform Platform area: minimum 350 mm wide x 300 mm deep, including the ladder rung if it is at the same level as the platform.erection platform max 2 m in heights ) For erection platforms up to 1.2 m in height, incorporate a built-in mid-rail on the three non-access sides. For single ladder types the continuing stiles are considered as mid-rails. For erection platforms between 1.2 m and 2 m in height, incorporate guardrails on the three non-access sides. Erection platforms Load rating: minimum 120 kg. supported on ledgers/ Erection platform area: minimum 500 mm x 600 mm. guardrails (suitable for On scaffolding edge sides, incorporate a built-in mid-rail. scaffolding platform spacing of up to 2 m) Scaffold planks supported Platform area: minimum 2 x 225 mm wide scaffold planks. on temporary transoms (suitable for scaffolding platform spacing of up to 2 m)
  • 9. 8 | P a g e 6.2 DESIGN CRITERIA FOR TEMPORARY EDGE PROTECTION Temporary edge protection must meet the strength requirements for guardrails and mid-rails specified in BOWEC General requirements and should be designed to allow the installation and removal of the permanent guardrails whilst it is in position. 6.3 GENERIC WORK SEQUENCE – SCAFFOLD ERECTING AND DISMANTLING Where work methods differ from the generic work sequence below alternative methods must provide an equivalent level of safety to those specified in this guide. Task Activity – Erection of Scaffold Break the job down into steps Base out scaffold • Prevent unauthorised access to scaffold area. and erect base lift • One scaffolder holds standards, while another places transoms and and first lift ledgers. • Adjust screw jacks to level the scaffold. • Erect transoms and ledgers for the first lift. • Erect planks from below for the first lift. Complete first lift • Install access stairway or ladder to platform for the first lift. • If access is by stairway, ensure the stair access bay is erected with the run of the scaffold. • Install edge protection comprising guardrail, mid-rail and toeboard or mesh panels to first lift. Erect next lift Working from a fully planked platform on the first lift, install standards from a platform (where the standard joint is 1 to 1.5 m above the platform level), transoms, ledgers and hop-ups for the next lift above. Where using erection platforms − Place an erection platform on the scaffold − Working from the erection platform, erect standards (where the standard joint is 1 to 1.5 m above the erection platform level), mid-rails and guardrails for the lift above. − Standing on the working platform (or an erection platform for lifts of 2.5 to 3 m), place planks within the transoms to form the above working platform. − Install ladder or stairway access to working platform above. − Access the above working platform. − Install toeboards (or other systems to prevent objects falling).
  • 10. 9 | P a g e Break the job down into steps Where using temporary edge protection − Install temporary edge protection for platform above. − Install transoms and ledgers for platform above. − Standing on the working platform (or an erection platform for lifts of 2.5 to 3 m), place planks within the transoms to form the above working platform. − Install ladder or stairway access to working platform above. − Access the above working platform. − Install next standards, guardrails and mid-rails. − Install toeboards (or other systems to prevent objects falling). • Scaffold should be erected as close as practicable to the working face. Where the scaffold is greater than 225 mm from the working face, install guardrails and mid-rails to the inner face standards. Erect next lifts • Unless a specific engineering design is provided, fix the first row of ties no more than 4 m above the ground. Do not allow a scaffold to free stand more than 4 m above the ground or a row of ties. • Secure objects or remove unsecured objects from the scaffold. • Repeat erection sequence as per previous task. Dismantle scaffold General precautions • Access the scaffold platform from a ladder or stair access – do not climb the standards, ledgers and transoms. • Maintain a tidy work area. • Do not overload the scaffold bays – progressively remove scaffolding equipment from platforms and stack it neatly on the ground. • Do not leave loose materials on platforms. • Do not throw down any materials or scaffolding equipment. • Remove chain wire mesh and shade cloth while working from a fully planked platform. • Work with a guardrail in place when removing and passing mesh Panels down. • Work from a fully planked platform below when dismantling hop-up brackets, tie bars and planks. • Do not allow an unsheeted scaffold to free stand more than4 m or a sheeted scaffold more than 2 m above the highest tie remaining in place. • Before lifting a toeboard, ensure the adjacent plank is held in place. Task Activity
  • 11. 10 | P a g e Task Break the job down into steps Activity Dismantling sequence Note: Follow the below dismantling sequence if you are using erection platforms. If you are using a temporary edge protection system, modify the dismantling sequence to suit. • Access the top platform by stairway or ladder. • Start dismantling from an end bay. • Remove chain wire mesh and shade cloth, or mesh panels, from the level to be dismantled or from the whole scaffold if not required during the dismantling process. • Move down to the platform below. • Dismantle top platform planks. • Working from an erection platform on the fully planked platform, dismantle guardrails, mid-rails, ledgers, transoms and standards from the level above. • Step off the erection platform. • Dismantle the hop-up platform above, if in place. • Remove not more than three planks (ensure at least two planks remain) to enable the dismantled materials to be passed down to the next level (where they are to be temporarily stacked or removed from the scaffold). • If removing dismantled materials progressively down through the scaffold, ensure that the gaps created are not directly below each other and that planks are replaced when a gap is not being used to lower materials. • Remove ties progressively as the scaffold is dismantled. Progressively repeat this procedure until dismantling can be completed from the ground