SlideShare a Scribd company logo
1 of 10
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
CAI MEP INTERNATIONAL CONTAINER TERMINAL 
METHOD STATEMENT OF EXCAVATION WORK 
Page 1
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
CONTENT 
1. Purpose Page 3 
2. Scope of Work Page 3 
3. Reference Technical Specifications Page 4 
4 Reference Drawings Page 4 
5 Excavation Procedures Page 5 
6 Quantity Control Page 8 
7 Safety Control Page 8 
8 Appendix 1 Page 10 
Page 2
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
1. PURPOSE 
This Method Statement is prepared to ensure that construction of buildings for the project shall 
comply on plans specifications and all relevant standard and code requirements in the execution 
of different work activities to be performed in the construction of buildings and other relevant 
structures associated with the project in general. In addition, this will serve as a tool to guide all 
technical personnel and layman execute proper construction procedures complied with the 
quality and safety plans for the project. 
2. SCOPE OF WORK 
The scope of work for the construction of all Building and its utilities: 
· Expansion excavation: 
No. Building name Storey Structure 
1 Security Office 1 RC Structure 
2 Amenity Block 2 RC Structure 
3 Container Freight Station (CFS) 1 + M 
RC & Steel 
Structure 
4 Container Gate 1 
RC & Steel 
Structure 
5 PMB Branch Office 2 RC Structure 
6 Operation Building 4 RC Structure 
7 Maintenance Shop 1 + M 
RC & Steel 
Structure 
8 Sub Station 1 RC Structure 
9 Reefer Rack 1 
RC & Steel 
Structure 
10 Miscellaneous structures 1 
R C & Steel 
Structure 
· Excavation to be used sheet pile: 
Page 3
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
No. Building name Storey Structure 
1 Septic tank 1 RC Structure 
2 Fuel Station 1 RC Structure 
3. REFERENCE TECHNICAL SPECIFICATION 
Refer to Division 01 - Part 3 and Division 01 - Part 4B – Volume 2 of Technical Specification 
4. REFERENCE DRAWINGS 
Refer to attachment of Excavation Shop Drawing and Excavation Sequence Drawing. 
5. EXCAVATION PROCEDURE 
Page 4
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
5.1 Flowchart 
5.2 Manpower and Equipment 
Page 5 
Completion of pile 
Preparation and Survey work for 
positions of Excavation 
Start Excavation constructing the 
Drainage 
Discharge water by pump 
Excavate up to designed level, 
cutting piles (if required) 
Excavate by small bucket or 
manual between piles 
Compact the bottom and cut the 
pile at designed level 
Foundation works 
Sand backfilling 
Finish works
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
- Manpower shall be organized in accordance with table 1 
No Description Quantity Remarks 
1 Engineer 1 
2 Surveyor 1 
3 Foremen 1 
4 Worker 30 
5 Safety officer 1 
Table 1 
- Equipments to be used for the work in accordance with table 2 
No Description Quantity Remarks 
1 Backhoe 02 
2 Dump Truck 03 
3 Level Machine 02 
4 Water Pump 05 
Table 2 
- Certificate of operator and equipment shall be submitted by separated document to the 
Engineer for review and approval. 
5.3 Detail Procedure 
5.3.1 Preparation and Survey work 
- Prior to the commencement of excavating works, the surveyor will establish control points in 
suitable locations to control excavating area, confirming the construction drawings of excavation 
areas to be attached as addition to this method statement distribute details to all concerned 
parties as required. 
5.3.2 Excavation work 
- Excavation shall be done in a safe and sequential manner on the basis of the prepared plan 
drawings and in accordance with the instructions by the Engineer. 
- The excavation method is either machine, manual cut or both and take care it to not disturb the 
soil below. 
- During excavation, it is necessary to make drainage ditch slope to sump pit as precaution in 
case raining and ground water occurs during construction. 
- Ground water will be drained by water pump with hose line is allocated to sump pit then 
discharge to the river. Contractor shall monitor ground water level and continuously run the 
Page 6
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
dewatering pumps to maintain dry working platform when ground water is encountered. 
Additional pumps will be added if the pumping capacity is insufficient. 
- Excavated soil to be loaded to dump truck and transported to the stockpile. Unsuitable material 
and waste material shall be removed from site to the waste yard in accordance with the 
specification requirements. 
5.3.3 Excavation up to design level 
- During excavation, pile may be cut above the design cutoff level if necessary. Excavation shall 
be taken care between the piles using small bucket (< 0.5 m3) or manual shoveling. 
- After completion of excavation, dimensions and elevation of bottom area will be checked by 
surveyor. The bottom will be leveled and compacted. 
5.3.4 Sand back filling 
- After completion of foundation concrete work and other concrete work under the ground, sand 
back filling will be executed in uniform horizontal layers across the full area of the foundation 
without segregation. 
- Approved suitable material should be used for backfilling. Compaction standard shall be 
employed in the execution of this work. 
- Fill materials shall be distributed evenly to the backfill area to a specified thickness of 
compaction = 150mm thick and compacted by compactor to a specified compaction factor. 
Sprinkle water to the earth fill in compliance with the allowable moisture contents specified 
before start compaction. 
5.4 Termite work 
· Material 
Page 7 
Mat 
pm3 
Typical section of excavation area
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
- Termite material shall be submitted by the separated document to the Engineer for approval 
before start work. 
· Application 
- Application procedure shall be submitted by the separated document to Engineer for approval 
before start the work. 
6. QUALITY CONTROL 
· Compaction of Backfilling 
- After excavation, the bottom surface of pit shall be compacted to not less than 95% of 
maximum dry density by vibratory plate compactor and the slope shall be trimmed off to avoid 
collapse of pit wall. 
- The fill material shall be checked and accepted by the Engineer before carrying out the work. 
· Survey of excavated area 
- After completion of excavation, dimensions shall be checked and recorded as attachment 1. 
Tolerance of bottom elevation is ±10mm 
7. SAFETY CONTROL 
· Fundamental Policy 
- “Safety is the First Priority" 
· Key Activities 
- Implementation of Safety & Health Education 
- Prevention of Heavy Machinery Accidents 
· Development and implementation of Activity 
- Implementation of Safety & Health Education 
- Pick up hazardous factors of each work activity and always reflect them at the safety meetings. 
Point out them every day at the meetings in order to let individual worker to renovate his safety 
consciousness. 
- Prevention of Heavy Machinery Accidents 
- Be consistent with inspection at beginning of works (including working ground), regular 
maintenance of machineries, designation of working area and provision of a proper signalman. 
· Others. 
Page 8
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
- Safety signboards and barricades shall be installed around excavated area. Security guard 
should observe all passengers around the site. 
Page 9
Doc. Title Method Statement of Building Work 
– Earth Work TOA-TOYO JOINT VENTURE 
Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix – 1 
Excavation Shop Drawing 
Sequence Drawing 
Page 10

More Related Content

What's hot

Method statement painting
Method statement painting Method statement painting
Method statement painting Daniel SLSA CLA
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and faAl-Amin Ahmed Nabin
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)DusanJankovic8
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pagesDavid H Moloney
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouringBharatha Rathnayke
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works Shaik Mohsin
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002Minh Bui Si
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion jointakash yadav
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement worksMohd Nizam Mohd Zan
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pagesDavid H Moloney
 
Chk construction site_inspection-checklist
Chk construction site_inspection-checklistChk construction site_inspection-checklist
Chk construction site_inspection-checklistimaduddin91
 
Demolition of existing boiler house
Demolition of existing boiler houseDemolition of existing boiler house
Demolition of existing boiler houseAnatoliZ
 
construction site safety and management
construction site safety and managementconstruction site safety and management
construction site safety and managementAnchal Gupta
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairingBharatha Rathnayke
 
Erection method statement
Erection method statementErection method statement
Erection method statementkanalbiru
 

What's hot (20)

Method statement painting
Method statement painting Method statement painting
Method statement painting
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and fa
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pages
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Method statement
Method statementMethod statement
Method statement
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
 
Scaffolding checklist
Scaffolding checklistScaffolding checklist
Scaffolding checklist
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
 
Chk construction site_inspection-checklist
Chk construction site_inspection-checklistChk construction site_inspection-checklist
Chk construction site_inspection-checklist
 
Demolition of existing boiler house
Demolition of existing boiler houseDemolition of existing boiler house
Demolition of existing boiler house
 
construction site safety and management
construction site safety and managementconstruction site safety and management
construction site safety and management
 
Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairing
 
Erection method statement
Erection method statementErection method statement
Erection method statement
 

Similar to Excavation method rectified 13-11-2010

Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Krm Chari
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
C.V Momen.last update
C.V Momen.last updateC.V Momen.last update
C.V Momen.last updateMomen Mohamed
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalIan Kelly
 
Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & windowMinh Bui Si
 
Industrial training presentation
Industrial training presentationIndustrial training presentation
Industrial training presentationNursyafiqah Ismail
 
Project Management Report for Tank Farm
Project Management Report for Tank FarmProject Management Report for Tank Farm
Project Management Report for Tank FarmAbhik Tushar Das
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Khalid Abdel Naser Abdel Rahim
 
WELL COSTING
WELL COSTINGWELL COSTING
WELL COSTINGAFATous
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
Mohab Samoil_Resume
Mohab Samoil_ResumeMohab Samoil_Resume
Mohab Samoil_ResumeMohab Samoil
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)Mohd Zaini Baharum
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCCRakshita Raghunath
 
Construction manual chapter 2
Construction manual chapter 2Construction manual chapter 2
Construction manual chapter 2vps1968
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavationAl-Amin Ahmed Nabin
 

Similar to Excavation method rectified 13-11-2010 (20)

Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Column & beam
Column & beamColumn & beam
Column & beam
 
C.V Momen.last update
C.V Momen.last updateC.V Momen.last update
C.V Momen.last update
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_final
 
Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & window
 
CV - Ahmed Mounir
CV - Ahmed MounirCV - Ahmed Mounir
CV - Ahmed Mounir
 
Industrial training presentation
Industrial training presentationIndustrial training presentation
Industrial training presentation
 
Project Management Report for Tank Farm
Project Management Report for Tank FarmProject Management Report for Tank Farm
Project Management Report for Tank Farm
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...
 
WELL COSTING
WELL COSTINGWELL COSTING
WELL COSTING
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
Mohab Samoil_Resume
Mohab Samoil_ResumeMohab Samoil_Resume
Mohab Samoil_Resume
 
HUSSIEN CV 24-12-2012
HUSSIEN CV 24-12-2012HUSSIEN CV 24-12-2012
HUSSIEN CV 24-12-2012
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
 
Shib
ShibShib
Shib
 
Construction manual chapter 2
Construction manual chapter 2Construction manual chapter 2
Construction manual chapter 2
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 

Excavation method rectified 13-11-2010

  • 1. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal CAI MEP INTERNATIONAL CONTAINER TERMINAL METHOD STATEMENT OF EXCAVATION WORK Page 1
  • 2. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal CONTENT 1. Purpose Page 3 2. Scope of Work Page 3 3. Reference Technical Specifications Page 4 4 Reference Drawings Page 4 5 Excavation Procedures Page 5 6 Quantity Control Page 8 7 Safety Control Page 8 8 Appendix 1 Page 10 Page 2
  • 3. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 1. PURPOSE This Method Statement is prepared to ensure that construction of buildings for the project shall comply on plans specifications and all relevant standard and code requirements in the execution of different work activities to be performed in the construction of buildings and other relevant structures associated with the project in general. In addition, this will serve as a tool to guide all technical personnel and layman execute proper construction procedures complied with the quality and safety plans for the project. 2. SCOPE OF WORK The scope of work for the construction of all Building and its utilities: · Expansion excavation: No. Building name Storey Structure 1 Security Office 1 RC Structure 2 Amenity Block 2 RC Structure 3 Container Freight Station (CFS) 1 + M RC & Steel Structure 4 Container Gate 1 RC & Steel Structure 5 PMB Branch Office 2 RC Structure 6 Operation Building 4 RC Structure 7 Maintenance Shop 1 + M RC & Steel Structure 8 Sub Station 1 RC Structure 9 Reefer Rack 1 RC & Steel Structure 10 Miscellaneous structures 1 R C & Steel Structure · Excavation to be used sheet pile: Page 3
  • 4. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal No. Building name Storey Structure 1 Septic tank 1 RC Structure 2 Fuel Station 1 RC Structure 3. REFERENCE TECHNICAL SPECIFICATION Refer to Division 01 - Part 3 and Division 01 - Part 4B – Volume 2 of Technical Specification 4. REFERENCE DRAWINGS Refer to attachment of Excavation Shop Drawing and Excavation Sequence Drawing. 5. EXCAVATION PROCEDURE Page 4
  • 5. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 5.1 Flowchart 5.2 Manpower and Equipment Page 5 Completion of pile Preparation and Survey work for positions of Excavation Start Excavation constructing the Drainage Discharge water by pump Excavate up to designed level, cutting piles (if required) Excavate by small bucket or manual between piles Compact the bottom and cut the pile at designed level Foundation works Sand backfilling Finish works
  • 6. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal - Manpower shall be organized in accordance with table 1 No Description Quantity Remarks 1 Engineer 1 2 Surveyor 1 3 Foremen 1 4 Worker 30 5 Safety officer 1 Table 1 - Equipments to be used for the work in accordance with table 2 No Description Quantity Remarks 1 Backhoe 02 2 Dump Truck 03 3 Level Machine 02 4 Water Pump 05 Table 2 - Certificate of operator and equipment shall be submitted by separated document to the Engineer for review and approval. 5.3 Detail Procedure 5.3.1 Preparation and Survey work - Prior to the commencement of excavating works, the surveyor will establish control points in suitable locations to control excavating area, confirming the construction drawings of excavation areas to be attached as addition to this method statement distribute details to all concerned parties as required. 5.3.2 Excavation work - Excavation shall be done in a safe and sequential manner on the basis of the prepared plan drawings and in accordance with the instructions by the Engineer. - The excavation method is either machine, manual cut or both and take care it to not disturb the soil below. - During excavation, it is necessary to make drainage ditch slope to sump pit as precaution in case raining and ground water occurs during construction. - Ground water will be drained by water pump with hose line is allocated to sump pit then discharge to the river. Contractor shall monitor ground water level and continuously run the Page 6
  • 7. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal dewatering pumps to maintain dry working platform when ground water is encountered. Additional pumps will be added if the pumping capacity is insufficient. - Excavated soil to be loaded to dump truck and transported to the stockpile. Unsuitable material and waste material shall be removed from site to the waste yard in accordance with the specification requirements. 5.3.3 Excavation up to design level - During excavation, pile may be cut above the design cutoff level if necessary. Excavation shall be taken care between the piles using small bucket (< 0.5 m3) or manual shoveling. - After completion of excavation, dimensions and elevation of bottom area will be checked by surveyor. The bottom will be leveled and compacted. 5.3.4 Sand back filling - After completion of foundation concrete work and other concrete work under the ground, sand back filling will be executed in uniform horizontal layers across the full area of the foundation without segregation. - Approved suitable material should be used for backfilling. Compaction standard shall be employed in the execution of this work. - Fill materials shall be distributed evenly to the backfill area to a specified thickness of compaction = 150mm thick and compacted by compactor to a specified compaction factor. Sprinkle water to the earth fill in compliance with the allowable moisture contents specified before start compaction. 5.4 Termite work · Material Page 7 Mat pm3 Typical section of excavation area
  • 8. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal - Termite material shall be submitted by the separated document to the Engineer for approval before start work. · Application - Application procedure shall be submitted by the separated document to Engineer for approval before start the work. 6. QUALITY CONTROL · Compaction of Backfilling - After excavation, the bottom surface of pit shall be compacted to not less than 95% of maximum dry density by vibratory plate compactor and the slope shall be trimmed off to avoid collapse of pit wall. - The fill material shall be checked and accepted by the Engineer before carrying out the work. · Survey of excavated area - After completion of excavation, dimensions shall be checked and recorded as attachment 1. Tolerance of bottom elevation is ±10mm 7. SAFETY CONTROL · Fundamental Policy - “Safety is the First Priority" · Key Activities - Implementation of Safety & Health Education - Prevention of Heavy Machinery Accidents · Development and implementation of Activity - Implementation of Safety & Health Education - Pick up hazardous factors of each work activity and always reflect them at the safety meetings. Point out them every day at the meetings in order to let individual worker to renovate his safety consciousness. - Prevention of Heavy Machinery Accidents - Be consistent with inspection at beginning of works (including working ground), regular maintenance of machineries, designation of working area and provision of a proper signalman. · Others. Page 8
  • 9. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal - Safety signboards and barricades shall be installed around excavated area. Security guard should observe all passengers around the site. Page 9
  • 10. Doc. Title Method Statement of Building Work – Earth Work TOA-TOYO JOINT VENTURE Doc. No CM – MS – BW - 008 Rev. No. 0 Date Nov, 2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix – 1 Excavation Shop Drawing Sequence Drawing Page 10