Block PM307,Bertam Field Development Project
Review of PTI Documentation
Department of Occupational Safety & Health (DOSH)
Ministry of Human Resources
LMBV jointly submitted with
SUBSURF Sdn.Bhd/DOF SUBSEA
26 November 2014
TABLE OF CONTENT
1. Objective of Presentation
2. Bertam Field Background
3. Bertam Development Concept
4. General Arrangement
5. Project Schedule
6. PTI Documentation Requirement
• DOSH Requirement vs Lundin’s Submission on 13 November 2014
7. Bertam Production Flow Plan/ Flow Path
8. Installation Procedure
9. QA/QC of Jumper Hoses and Accessories
1.0 OBJECTIVE OF PRESENTATION
To provide an overview of the project documentation submitted for
Bertam Field Development Project.
2.0 BERTAM FIELD BACKGROUND
Block PM307 Location Map
Forecast Production:
18,000 bpd Oil
2 MMscfd Gas
0-95% Water cut
14 wells
Bertam Field, 76m water
depth, offshore Peninsula
Malaysia, 175km East of
KSB.
Field life 8-10 years
Target first oil:
2nd Half 2014
BERTAM
FIELD
2.0 BERTAM FIELD BACKGROUND
• Partnership: Lundin Malaysia B.V (75%, Operator) and Petronas Carigali (25%)
• Water Depth: ~76 m
• Production Sharing Contract (PSC) Effective: 15th August 1996
• PSC Expiry: 14th August 2025
• Lundin Farm-in: 1st May 2011
• Lundin as nominated Operator
• Lundin Owner of FPSO.
• Previous name ‘Ikdam’ when in Tunisia. New name FPSO Bertam.
• Field Development Plan Approved by Petronas & Partner Petronas Carigali in September 2013.
• Planned First Oil: 1st Half 2015
3.0 BERTAM DEVELOPMENT CONCEPT
• Bertam field is located 175km off the east coast of Peninsular Malaysia in Block PM307, close
to the Indonesian border at a water depth of approximately 76 m.
• The nearby fields are Malong, Sotong and Belida (South Natuna Sea, Block B, Indonesia).
• Development concept identical to Petronas’ “Truong Song Development”, Vietnam
4.0 GENERAL ARRANGEMENT (1 of 2)
4.0 GENERAL ARRANGEMENT (2 of 2)
5.0 BERTAM DEVELOPMENT PROJECT SCHEDULE
1 General description and workscope of the project(s) √
2
A copy of Award Letter from the Project Owner to the appointed Contractor(s) registered
with Department Of Safety & Health:
√
2.1 Implementation & Execution Schedule for project activities √
2.2 Organisation Chart (in relation to the project execution) √
2.3 Design specifications, attached with pipeline details √
2.4 Design calculations e.g. Linepipe Wall Thickness Calculations √
3
One (1) copy of A1-sized plans (endorsed by project owner/contractor) :-
3.1 Piping & instrumentation diagram (P&ID) √
3.2 Location & arrangement plan √
3.3 Pipeline profile & flow plan √
3.4 Isometrics plan N/A
4 Copies of Welding Procedure Specifications (WPS) or Procedure Qualification Records √
5
Copies of Welder Qualification Test and Welding Verification Form (JKKP BP1) endorsed by
DOSH Officer and within the approved validity period
√
6
Technical specifications and petroleum equipment catalogues used for the project. All
equipment must be from the models which have been pre-approved by DOSH
√
7
Relevant procedures:
7.1 Corrosion control technique (internal/external coatings, cathodic protection etc) N/A
7.2 Quality Control Procedure √
7.3 Commissioning Procedure √
7.4 Repair and Modification Procedures (for pipeline modification works) √
8 List of unfired-pressure vessels (filter, scrapper trap etc.) installed, if available √
6.0 LUNDIN’S COMPLIANCE TO DOSH’S PTI DOCUMENTATION REQUIREMENT
6.0 DOSH’S REQUIREMENT vs LUNDIN’S SUBMISSION (Part 1 of 4)
No DOSH’S PTI DOCUMENTATION REQUIREMENT LUNDIN’S SUBMISSION ON 13 NOVEMBER 2014
1 General description and workscope of the project(s) Exhibit 3 - Scope of Works (ref: LSL/C/PRJ/14/008)
2
A copy of Award Letter from the Project Owner to the appointed
Contractor(s) registered with Department Of Safety & Health:
1. Letter of Award – See Attached.
2. Subsurf was waived off the requirement of registration with DOSH. Please refer
to letter ref. no: CRR/DOSH/MY/002.173-07.14 (see attached).
2.1 Implementation & Execution Schedule for project activities Please see attached ‘Bertam Summary Schedule 1st
Oil March 2015’
2.2 Organisation Chart (in relation to the project execution)
Please see attached organization chart for DOF Subsea' org chart.
2.3 Design specifications, attached with pipeline details
See item #6
2.4 Design calculations e.g. Wall Thickness Calculation
1. Line Sizing Report (ref: BWP-RP-F-003 Rev D1)
2. Index - Equipment Sizing Calculation Report (ref: BWP-RP-F-0004)
3 3.1 Piping & instrumentation diagram (P&ID)
1. WHP
a) PNID by Aker Solutions - (22 pages, Rev C2) AFC 9 October 2013
2. FPSO
a) PFD by Kavin Engineering - (8 pages, Rev C1 ) AFC 7 May 2014
b) PNID by Kavin Engineering - (35 pages, Rev C2) AFC 2 Aug 2014
6.0 DOSH’S REQUIREMENT vs LUNDIN’S Submission (Part 2 of 4)
No DOSH’S PTI DOCUMENTATION REQUIREMENT LUNDIN’S SUBMISSION ON 13 NOVEMBER 2014
3
3.2 Location & arrangement plan
List of project drawings for Location & arrangement plan:-
1. Hose & Umbilical Assembly General Arrangment - AML Consultants (ref: BMA-FPS-
DR-P-7001 Rev. 2, 14 Feb 2014)
2. Elevation Sheet 1 - Looking Platform North & East - AML Consultants (ref: BMA-
FPS-DR-P-7002 Rev. 2, 14 Feb 2014)
NOTE: The 2 Drawings above are contained in a single file (DRAWINGS AT Rev C1
13.11.14.pdf) attached to 3.2 folder in the documentation package.
3.3 Pipeline profile & flow plan
Description of Submission:
1. Flowlines carrying hydrocarbon (production & diesel) consist of:-
a) 6" Production Jumper Hose (70m, rubber/steel construction)
b) 4" Diesel Jumper Hose (70m, rubber/steel construction)
2. Tie-in flowline from Wellhead Platform to the FPSO is a flanged-connected flexible
jumper hose, therefore a pipeline profile is not applicable to this project.
3. Description of Production & Diesel flow path is depicted in the following list of
documents:-
a) WHP
Refer to PNID by Aker Solutions, see item #3.1
Drwg: WHP-FPSO Interface (ref: BMA-WHP-DR-F-108, Sht 1 of 1
b) FPSO
Ref. PNID by Kavin Engineering, see item #3.1
Drwg No.: Interface Diagram (ref: BMA-FPS-DR-F-00-0039, 2 sheets).
c) Jumper Hoses
• Manuli Hoses Drawings (6" Production Jumper Hose & 4" Diesel
Jumper Hose)
• Flexy Hose Drawings
• AML AFC drawings Rev C1/C2
6.0 DOSH’S REQUIREMENT vs LUNDIN’S Submission (Part 3 of 4)
No DOSH’S PTI DOCUMENTATION REQUIREMENT LUNDIN’S SUBMISSION ON 13 NOVEMBER 2014
3 3.4 Isometrics plan
Not Applicable since the flowline between WHP & FPSO consist of flexible
jumper hoses.
Note:
In place of isometric drawings, Lundin submits drawings as per item #3.3
4
Copies of Welding Procedure Specifications (WPS) or Procedure
Qualification Records
Not Applicable since jumper hose tie-in connection is flanged.
Lundin submits the FAT reports & NDT Reports for hoses & accessories as
of QAQC documentation.
5
Copies of Welder Qualification Test and Welding Verification Form
(JKKP BP1) endorsed by DOSH Officer and within the approved
validity period
Not Applicable since jumper hose tie-in connection is flanged.
Lundin submits the FAT reports & NDT Reports for hoses & accessories as
of QAQC documentation.
6
Technical specifications and petroleum equipment catalogues
used for the project. All equipments must be from the models
which have been pre-approved by DOSH
Specifications for Production & Diesel Jumper Hoses:-
1. Crude Transfer Hose Specifications (Ref: BMA-FPS-SP-P-7001 Rev1)
2. Diesel Hose Specification (Ref: BMA-FPS-SP-P-7003 Rev3)
General Arrangement Drawings for Production & Diesel Jumper Hoses
(Manuli):-
1. Jumper Long Length Crude Transfer Extra Cover Hose (ref: BMA-WHP-
MK-02-D01-001).
2. Jumper Longth Length Diesel Hose (ref: BMA-WHP-MK-02-D01-002).
6.0 DOSH’S REQUIREMENT vs LUNDIN’S Submission (Part 3 of 4)
No DOSH’S PTI DOCUMENTATION REQUIREMENT LUNDIN’S SUBMISSION ON 13 NOVEMBER 2014
7
Relevant procedures:
7.1 Corrosion control technique (internal/external coatings,
cathodic protection etc)
Not Applicable. Jumper Hoses's construction material consist of rubber
compound interlayed with steel wire reinforcements.
7.2 Quality Control Procedure See attached
7.3 Commissioning Procedure
See attached: Completion, Commissioning Strategy and Execution Plan
(ref: BMA-WHP-PR-C-00-0101)
7.4 Repair and Modification Procedures (for pipeline modification
works)
See attached: Project Quality Plan (ref: BMA-WHP-PR-Q-00-0100)
Note: Not Applicable since the flowline between WHP & FPSO consist of
flexible jumper hoses.
8
List of unfired-pressure vessels (filter, scrapper trap etc.)
installed, if available
On WHP, well stream shall flow through a test separator, V-1010 (ASME
Sect 8 Div 1).
On FPSO, the main process scheme involves the production undergoing 2
staged 3-phase separation via the following list of pressure vessels:-
1. 1st stage separator, V-1120 (ASME Sect 8 Div 1)
2. 2nd stage separator, V-1140 (ASME Sect 8 Div 1)
(Reference: PFD, Crude Separation and Stabilization System - ref: BMA-
FPS-DR-F-00-0019 Rev C1)
7.0 BERTAM PRODUCTION FLOW PLAN/PATH
1. Installation Procedure was jointly developed by AML & DOF based on installation analysis and
structural integrity checks on the hoses, umbilical, WHP & FPSO receiving facilities.
2. Lifting and hauling of hoses/umbilical shall be utilizing the WHP & FPSO deck cranes in tandem.
3. For load transfer purposes, Pad eyes & D-Rings were pre-installed on WHP Hose Balcony & FPSO
Hose Gallery according to static and dynamic loads analysis for hoses/umbilical.
8.0 INSTALLATION PROCEDURE
9.0 QUALITY ASSURANCE & QUALITY CONTROL OF JUMPER HOSES & ACCESSORIES
• FAT for 6” Production jumper hoses & 4” Diesel
jumper hoses was successfully completed in early
July 2014 in Rome, Italy. All FAT activities were
witnessed by Lundin & DNV.
• FAT consists of hydro-test & electrical continuity
tests for all hoses.
• QA/QC Documents for hoses & accessories (Test
Reports, Mill Certs, NDT Reports) are included in
Lundin’s submission to DOSH for review.
THANK YOU
Back-up Slides
BERTAM: KEY DATES
• Petronas Milestones Review #1 development feasibility endorsed May 2012
• Petronas Milestones Review # 2 endorsed in August 2012
• Petronas Milestones Review # 3 endorsed in November 2012
• Petronas Milestones Review # 4 endorsed in February 2013
• Petronas Milestones Review # 5 endorsed in April 2013
• Field Development Plan (FDP) approved by Petronas in September 2013
• FPSO ‘Ikdam’ Upgrades Works awarded to Keppel Singapore in September 2013
• Well Head Platform Fabrication contract awarded to THHE on November 2013
• FPSO ‘Ikdam’ was officially renamed FPSO BERTAM in June 2014
• Transportation & Installation (FPSO Scope ) contract awarded to Subsurf/DOF on July
2014
• Target MCD for WHP from THHE - OCTOBER 2014
• Target Sail-away from Keppel – OCTOBER 2014.
• 1st Oil targeted in 4Qtr 2014
Project has very strong support by Petronas & Partner
Petronas Carigali hence the Fast Approvals achieved to date.
CONTRACTING STRATEGY
Detailed Design & Engineering
WHP by Aker Engineering
FPSO by Longitude
Fabrication
WHP by THHE
FPSO upgrade works by Keppel Shipyard, Singapore
Transportation & Installation
WHP by TLO
FPSO by Subsurf/DOF
Hook-up & Commissioning of Topside Process kit
WHP by PBJV
FPSO by Lundin
TRANSPORTATION & INSTALLATION SCOPE OF WORKS – SUBSURF/DOF
1. Phase 1 – Installation of Mooring Piles and Mooring Chains
• Successfully completed on 2 August 2014
2. Phase 2 – Hook up of FPSO to Pre-laid Mooring Chains
• To commence on late October/November 2014
3. Phase 3 – Installation of Hoses and Umbilical
• To commence on November 2014
* Prior to start-up, full Nitrogen leak test will be done on the flexible hoses (production &
diesel lines).
CONTRACTING STRATEGY
Detailed Design & Engineering
WHP by Aker Engineering
FPSO by Longitude
Fabrication
WHP by THHE
FPSO upgrade works by Keppel Shipyard, Singapore
Transportation & Installation
WHP by TLO
FPSO by Subsurf/DOF
Hook-up & Commissioning of Topside Process
WHP by PBJV
FPSO by Lundin
Back-up Slides
Skandi Hawk
1. ISV is positioned on the south side of the
WHP – within the radius of the WHP &
FPSO crane
2. FPSO crane picks up FPSO end of the jumper
and is lifted off the deck of the ISV
A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
3. WHP crane picks up WHP end of the jumper
and is lifted off the deck of the ISV
4. Both cranes lift the jumpers simultaneously so
that the entire jumper length is off the ISV’s deck.
A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
5. Slew both cranes to bring jumper ends
closer to the FPSO hull & WHP
Balcony). Crane booms are then lowered
down to align the jumper ends to the tie-
in connection points.
6. At the FPSO, slew the crane to bring
the jumper near it’s respective tie-in
flanges of the FPSO hose gallery.
A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
7. Lift jumper end to FPSO deck level.
Connect hang-off rigging to soft slings
c/w lifting spool lugs on jumpers.
8. Transfer load from FPSO crane to hang-off rigging
and remove lifting flange..
A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
9. Lift jumper up to I-Tube flange and fasten
connection. Remove the hang-off rigging & store
A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
A. Installation Procedures - Jumper Hose to WHP Balcony
1. At WHP, haul in the jumper using the
hang-off rigging connected to the pad-
eyes on the mezzanine deck and bring
jumper end inboard over the lay-over
arch.
2. Haul in the jumper using hang-off rigging connected to
D-rings on the cellar deck & bring jumper end towards
cellar deck .
A. Installation Procedures - Jumper Hose to WHP Balcony
3. Using the rigging configuration connected
to pre-installed pad-eyes & D-rings on the
cellar deck & mezzanine deck, the
jumper’s flange is aligned close to the
anchor-pipe.
4. Lifting Flange is removed. Jumper flange is pulled-in
using through-hole rigging connected to jumper lifting
spool & anchor-pipe’s flange. Gasket, studbolts &
studbolts & nuts is inserted and flanges are made-up
& torqued to specifications.

More Related Content

What's hot

Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Vijay Sarathy
 
02 wireline
02 wireline02 wireline
02 wirelineJohan RC
 
Oil Production Facilities
Oil Production FacilitiesOil Production Facilities
Oil Production FacilitiesInGu Lee
 
Pressure Relief Valve Sizing for Single Phase Flow
Pressure Relief Valve Sizing for Single Phase FlowPressure Relief Valve Sizing for Single Phase Flow
Pressure Relief Valve Sizing for Single Phase FlowVikram Sharma
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchHaGun Gunawan
 
Ig system & equipment oil tankers
Ig system &  equipment oil tankersIg system &  equipment oil tankers
Ig system & equipment oil tankersjabbar2002pk200
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedureGerard B. Hawkins
 
0020 introduction to fpso design
0020 introduction to fpso design0020 introduction to fpso design
0020 introduction to fpso designChieu Nguyen
 
Training_Manual_MS_5002_BURLINGTON.pdf
Training_Manual_MS_5002_BURLINGTON.pdfTraining_Manual_MS_5002_BURLINGTON.pdf
Training_Manual_MS_5002_BURLINGTON.pdfMebarki Hassane
 
Drilling operation and components
Drilling operation and componentsDrilling operation and components
Drilling operation and componentsChoong KW
 
C3.2.1. Topside Separation_2020
C3.2.1. Topside Separation_2020C3.2.1. Topside Separation_2020
C3.2.1. Topside Separation_2020David Seow
 
Gas Compression Stages – Process Design & Optimization
Gas Compression Stages – Process Design & OptimizationGas Compression Stages – Process Design & Optimization
Gas Compression Stages – Process Design & OptimizationVijay Sarathy
 
Introduction To Pressure Surge In Liquid Systems
Introduction To Pressure Surge In Liquid SystemsIntroduction To Pressure Surge In Liquid Systems
Introduction To Pressure Surge In Liquid SystemsGerard B. Hawkins
 

What's hot (20)

Knock-Out drums
Knock-Out drumsKnock-Out drums
Knock-Out drums
 
flare system design.pdf
flare system design.pdfflare system design.pdf
flare system design.pdf
 
OISD STD-150
OISD STD-150OISD STD-150
OISD STD-150
 
Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526Pressure Safety Valve Sizing - API 520/521/526
Pressure Safety Valve Sizing - API 520/521/526
 
02 wireline
02 wireline02 wireline
02 wireline
 
Oil Production Facilities
Oil Production FacilitiesOil Production Facilities
Oil Production Facilities
 
Three Phase Separators
Three Phase SeparatorsThree Phase Separators
Three Phase Separators
 
Pressure Relief Valve Sizing for Single Phase Flow
Pressure Relief Valve Sizing for Single Phase FlowPressure Relief Valve Sizing for Single Phase Flow
Pressure Relief Valve Sizing for Single Phase Flow
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
Ig system & equipment oil tankers
Ig system &  equipment oil tankersIg system &  equipment oil tankers
Ig system & equipment oil tankers
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning Procedure
 
0020 introduction to fpso design
0020 introduction to fpso design0020 introduction to fpso design
0020 introduction to fpso design
 
Training_Manual_MS_5002_BURLINGTON.pdf
Training_Manual_MS_5002_BURLINGTON.pdfTraining_Manual_MS_5002_BURLINGTON.pdf
Training_Manual_MS_5002_BURLINGTON.pdf
 
Ppt
PptPpt
Ppt
 
Boiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singaporeBoiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singapore
 
Drilling operation and components
Drilling operation and componentsDrilling operation and components
Drilling operation and components
 
C3.2.1. Topside Separation_2020
C3.2.1. Topside Separation_2020C3.2.1. Topside Separation_2020
C3.2.1. Topside Separation_2020
 
Wellheads and Flow Lines.pdf
Wellheads and Flow Lines.pdfWellheads and Flow Lines.pdf
Wellheads and Flow Lines.pdf
 
Gas Compression Stages – Process Design & Optimization
Gas Compression Stages – Process Design & OptimizationGas Compression Stages – Process Design & Optimization
Gas Compression Stages – Process Design & Optimization
 
Introduction To Pressure Surge In Liquid Systems
Introduction To Pressure Surge In Liquid SystemsIntroduction To Pressure Surge In Liquid Systems
Introduction To Pressure Surge In Liquid Systems
 

Similar to DOSH PTI Presentation for FPSO BERTAM LMBV (1)

INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTNur Ain Samsudin
 
38878 nga hdd guidelines rev. p0
38878   nga hdd guidelines rev. p0 38878   nga hdd guidelines rev. p0
38878 nga hdd guidelines rev. p0 Tashtiot media
 
riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15Monica Riccio
 
Petronas exploration guidelines
Petronas exploration guidelinesPetronas exploration guidelines
Petronas exploration guidelinesEaswaran Kanason
 
Pipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT methodPipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT methodpaulus konda
 
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)MAHESH PANDIT
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works Shaik Mohsin
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
 
59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r chomeworkping4
 
2136-872A-X003-001-VER-A4000C (1).PDF
2136-872A-X003-001-VER-A4000C (1).PDF2136-872A-X003-001-VER-A4000C (1).PDF
2136-872A-X003-001-VER-A4000C (1).PDFWorldofAllLyrics
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 
Ankur Singh 7 years exp. oil & gas
Ankur Singh 7 years exp. oil & gasAnkur Singh 7 years exp. oil & gas
Ankur Singh 7 years exp. oil & gasAnkur Singh
 
Guidelines for NDT of GRP pipe systems and tanks
Guidelines for NDT of GRP pipe systems and tanksGuidelines for NDT of GRP pipe systems and tanks
Guidelines for NDT of GRP pipe systems and tanksOsama Lari
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalIan Kelly
 
Rengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15doneRengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15doneAssignment Help
 
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdfPROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdfhasan752746
 

Similar to DOSH PTI Presentation for FPSO BERTAM LMBV (1) (20)

INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 
38878 nga hdd guidelines rev. p0
38878   nga hdd guidelines rev. p0 38878   nga hdd guidelines rev. p0
38878 nga hdd guidelines rev. p0
 
riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15riopipeline2015_1094_ibp1094_15
riopipeline2015_1094_ibp1094_15
 
18rf 31170-ts-002 (flange)
18rf 31170-ts-002 (flange)18rf 31170-ts-002 (flange)
18rf 31170-ts-002 (flange)
 
Petronas exploration guidelines
Petronas exploration guidelinesPetronas exploration guidelines
Petronas exploration guidelines
 
Pipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT methodPipeline integrity assessment with LRUT method
Pipeline integrity assessment with LRUT method
 
Report
ReportReport
Report
 
Tandur_Poornima_CV
Tandur_Poornima_CVTandur_Poornima_CV
Tandur_Poornima_CV
 
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c59323623 1943-g-g-001-r c
59323623 1943-g-g-001-r c
 
2136-872A-X003-001-VER-A4000C (1).PDF
2136-872A-X003-001-VER-A4000C (1).PDF2136-872A-X003-001-VER-A4000C (1).PDF
2136-872A-X003-001-VER-A4000C (1).PDF
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Ankur Singh 7 years exp. oil & gas
Ankur Singh 7 years exp. oil & gasAnkur Singh 7 years exp. oil & gas
Ankur Singh 7 years exp. oil & gas
 
Guidelines for NDT of GRP pipe systems and tanks
Guidelines for NDT of GRP pipe systems and tanksGuidelines for NDT of GRP pipe systems and tanks
Guidelines for NDT of GRP pipe systems and tanks
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_final
 
Rengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15doneRengaraj nagappan cv aug 15done
Rengaraj nagappan cv aug 15done
 
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdfPROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
PROJECT DESIGN DELIVERABLES SEQUENCE (PDD).pdf
 

DOSH PTI Presentation for FPSO BERTAM LMBV (1)

  • 1. Block PM307,Bertam Field Development Project Review of PTI Documentation Department of Occupational Safety & Health (DOSH) Ministry of Human Resources LMBV jointly submitted with SUBSURF Sdn.Bhd/DOF SUBSEA 26 November 2014
  • 2. TABLE OF CONTENT 1. Objective of Presentation 2. Bertam Field Background 3. Bertam Development Concept 4. General Arrangement 5. Project Schedule 6. PTI Documentation Requirement • DOSH Requirement vs Lundin’s Submission on 13 November 2014 7. Bertam Production Flow Plan/ Flow Path 8. Installation Procedure 9. QA/QC of Jumper Hoses and Accessories
  • 3. 1.0 OBJECTIVE OF PRESENTATION To provide an overview of the project documentation submitted for Bertam Field Development Project.
  • 4. 2.0 BERTAM FIELD BACKGROUND Block PM307 Location Map Forecast Production: 18,000 bpd Oil 2 MMscfd Gas 0-95% Water cut 14 wells Bertam Field, 76m water depth, offshore Peninsula Malaysia, 175km East of KSB. Field life 8-10 years Target first oil: 2nd Half 2014 BERTAM FIELD
  • 5. 2.0 BERTAM FIELD BACKGROUND • Partnership: Lundin Malaysia B.V (75%, Operator) and Petronas Carigali (25%) • Water Depth: ~76 m • Production Sharing Contract (PSC) Effective: 15th August 1996 • PSC Expiry: 14th August 2025 • Lundin Farm-in: 1st May 2011 • Lundin as nominated Operator • Lundin Owner of FPSO. • Previous name ‘Ikdam’ when in Tunisia. New name FPSO Bertam. • Field Development Plan Approved by Petronas & Partner Petronas Carigali in September 2013. • Planned First Oil: 1st Half 2015
  • 6. 3.0 BERTAM DEVELOPMENT CONCEPT • Bertam field is located 175km off the east coast of Peninsular Malaysia in Block PM307, close to the Indonesian border at a water depth of approximately 76 m. • The nearby fields are Malong, Sotong and Belida (South Natuna Sea, Block B, Indonesia). • Development concept identical to Petronas’ “Truong Song Development”, Vietnam
  • 9. 5.0 BERTAM DEVELOPMENT PROJECT SCHEDULE
  • 10. 1 General description and workscope of the project(s) √ 2 A copy of Award Letter from the Project Owner to the appointed Contractor(s) registered with Department Of Safety & Health: √ 2.1 Implementation & Execution Schedule for project activities √ 2.2 Organisation Chart (in relation to the project execution) √ 2.3 Design specifications, attached with pipeline details √ 2.4 Design calculations e.g. Linepipe Wall Thickness Calculations √ 3 One (1) copy of A1-sized plans (endorsed by project owner/contractor) :- 3.1 Piping & instrumentation diagram (P&ID) √ 3.2 Location & arrangement plan √ 3.3 Pipeline profile & flow plan √ 3.4 Isometrics plan N/A 4 Copies of Welding Procedure Specifications (WPS) or Procedure Qualification Records √ 5 Copies of Welder Qualification Test and Welding Verification Form (JKKP BP1) endorsed by DOSH Officer and within the approved validity period √ 6 Technical specifications and petroleum equipment catalogues used for the project. All equipment must be from the models which have been pre-approved by DOSH √ 7 Relevant procedures: 7.1 Corrosion control technique (internal/external coatings, cathodic protection etc) N/A 7.2 Quality Control Procedure √ 7.3 Commissioning Procedure √ 7.4 Repair and Modification Procedures (for pipeline modification works) √ 8 List of unfired-pressure vessels (filter, scrapper trap etc.) installed, if available √ 6.0 LUNDIN’S COMPLIANCE TO DOSH’S PTI DOCUMENTATION REQUIREMENT
  • 11. 6.0 DOSH’S REQUIREMENT vs LUNDIN’S SUBMISSION (Part 1 of 4) No DOSH’S PTI DOCUMENTATION REQUIREMENT LUNDIN’S SUBMISSION ON 13 NOVEMBER 2014 1 General description and workscope of the project(s) Exhibit 3 - Scope of Works (ref: LSL/C/PRJ/14/008) 2 A copy of Award Letter from the Project Owner to the appointed Contractor(s) registered with Department Of Safety & Health: 1. Letter of Award – See Attached. 2. Subsurf was waived off the requirement of registration with DOSH. Please refer to letter ref. no: CRR/DOSH/MY/002.173-07.14 (see attached). 2.1 Implementation & Execution Schedule for project activities Please see attached ‘Bertam Summary Schedule 1st Oil March 2015’ 2.2 Organisation Chart (in relation to the project execution) Please see attached organization chart for DOF Subsea' org chart. 2.3 Design specifications, attached with pipeline details See item #6 2.4 Design calculations e.g. Wall Thickness Calculation 1. Line Sizing Report (ref: BWP-RP-F-003 Rev D1) 2. Index - Equipment Sizing Calculation Report (ref: BWP-RP-F-0004) 3 3.1 Piping & instrumentation diagram (P&ID) 1. WHP a) PNID by Aker Solutions - (22 pages, Rev C2) AFC 9 October 2013 2. FPSO a) PFD by Kavin Engineering - (8 pages, Rev C1 ) AFC 7 May 2014 b) PNID by Kavin Engineering - (35 pages, Rev C2) AFC 2 Aug 2014
  • 12. 6.0 DOSH’S REQUIREMENT vs LUNDIN’S Submission (Part 2 of 4) No DOSH’S PTI DOCUMENTATION REQUIREMENT LUNDIN’S SUBMISSION ON 13 NOVEMBER 2014 3 3.2 Location & arrangement plan List of project drawings for Location & arrangement plan:- 1. Hose & Umbilical Assembly General Arrangment - AML Consultants (ref: BMA-FPS- DR-P-7001 Rev. 2, 14 Feb 2014) 2. Elevation Sheet 1 - Looking Platform North & East - AML Consultants (ref: BMA- FPS-DR-P-7002 Rev. 2, 14 Feb 2014) NOTE: The 2 Drawings above are contained in a single file (DRAWINGS AT Rev C1 13.11.14.pdf) attached to 3.2 folder in the documentation package. 3.3 Pipeline profile & flow plan Description of Submission: 1. Flowlines carrying hydrocarbon (production & diesel) consist of:- a) 6" Production Jumper Hose (70m, rubber/steel construction) b) 4" Diesel Jumper Hose (70m, rubber/steel construction) 2. Tie-in flowline from Wellhead Platform to the FPSO is a flanged-connected flexible jumper hose, therefore a pipeline profile is not applicable to this project. 3. Description of Production & Diesel flow path is depicted in the following list of documents:- a) WHP Refer to PNID by Aker Solutions, see item #3.1 Drwg: WHP-FPSO Interface (ref: BMA-WHP-DR-F-108, Sht 1 of 1 b) FPSO Ref. PNID by Kavin Engineering, see item #3.1 Drwg No.: Interface Diagram (ref: BMA-FPS-DR-F-00-0039, 2 sheets). c) Jumper Hoses • Manuli Hoses Drawings (6" Production Jumper Hose & 4" Diesel Jumper Hose) • Flexy Hose Drawings • AML AFC drawings Rev C1/C2
  • 13. 6.0 DOSH’S REQUIREMENT vs LUNDIN’S Submission (Part 3 of 4) No DOSH’S PTI DOCUMENTATION REQUIREMENT LUNDIN’S SUBMISSION ON 13 NOVEMBER 2014 3 3.4 Isometrics plan Not Applicable since the flowline between WHP & FPSO consist of flexible jumper hoses. Note: In place of isometric drawings, Lundin submits drawings as per item #3.3 4 Copies of Welding Procedure Specifications (WPS) or Procedure Qualification Records Not Applicable since jumper hose tie-in connection is flanged. Lundin submits the FAT reports & NDT Reports for hoses & accessories as of QAQC documentation. 5 Copies of Welder Qualification Test and Welding Verification Form (JKKP BP1) endorsed by DOSH Officer and within the approved validity period Not Applicable since jumper hose tie-in connection is flanged. Lundin submits the FAT reports & NDT Reports for hoses & accessories as of QAQC documentation. 6 Technical specifications and petroleum equipment catalogues used for the project. All equipments must be from the models which have been pre-approved by DOSH Specifications for Production & Diesel Jumper Hoses:- 1. Crude Transfer Hose Specifications (Ref: BMA-FPS-SP-P-7001 Rev1) 2. Diesel Hose Specification (Ref: BMA-FPS-SP-P-7003 Rev3) General Arrangement Drawings for Production & Diesel Jumper Hoses (Manuli):- 1. Jumper Long Length Crude Transfer Extra Cover Hose (ref: BMA-WHP- MK-02-D01-001). 2. Jumper Longth Length Diesel Hose (ref: BMA-WHP-MK-02-D01-002).
  • 14. 6.0 DOSH’S REQUIREMENT vs LUNDIN’S Submission (Part 3 of 4) No DOSH’S PTI DOCUMENTATION REQUIREMENT LUNDIN’S SUBMISSION ON 13 NOVEMBER 2014 7 Relevant procedures: 7.1 Corrosion control technique (internal/external coatings, cathodic protection etc) Not Applicable. Jumper Hoses's construction material consist of rubber compound interlayed with steel wire reinforcements. 7.2 Quality Control Procedure See attached 7.3 Commissioning Procedure See attached: Completion, Commissioning Strategy and Execution Plan (ref: BMA-WHP-PR-C-00-0101) 7.4 Repair and Modification Procedures (for pipeline modification works) See attached: Project Quality Plan (ref: BMA-WHP-PR-Q-00-0100) Note: Not Applicable since the flowline between WHP & FPSO consist of flexible jumper hoses. 8 List of unfired-pressure vessels (filter, scrapper trap etc.) installed, if available On WHP, well stream shall flow through a test separator, V-1010 (ASME Sect 8 Div 1). On FPSO, the main process scheme involves the production undergoing 2 staged 3-phase separation via the following list of pressure vessels:- 1. 1st stage separator, V-1120 (ASME Sect 8 Div 1) 2. 2nd stage separator, V-1140 (ASME Sect 8 Div 1) (Reference: PFD, Crude Separation and Stabilization System - ref: BMA- FPS-DR-F-00-0019 Rev C1)
  • 15. 7.0 BERTAM PRODUCTION FLOW PLAN/PATH
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29. 1. Installation Procedure was jointly developed by AML & DOF based on installation analysis and structural integrity checks on the hoses, umbilical, WHP & FPSO receiving facilities. 2. Lifting and hauling of hoses/umbilical shall be utilizing the WHP & FPSO deck cranes in tandem. 3. For load transfer purposes, Pad eyes & D-Rings were pre-installed on WHP Hose Balcony & FPSO Hose Gallery according to static and dynamic loads analysis for hoses/umbilical. 8.0 INSTALLATION PROCEDURE
  • 30. 9.0 QUALITY ASSURANCE & QUALITY CONTROL OF JUMPER HOSES & ACCESSORIES • FAT for 6” Production jumper hoses & 4” Diesel jumper hoses was successfully completed in early July 2014 in Rome, Italy. All FAT activities were witnessed by Lundin & DNV. • FAT consists of hydro-test & electrical continuity tests for all hoses. • QA/QC Documents for hoses & accessories (Test Reports, Mill Certs, NDT Reports) are included in Lundin’s submission to DOSH for review.
  • 33. BERTAM: KEY DATES • Petronas Milestones Review #1 development feasibility endorsed May 2012 • Petronas Milestones Review # 2 endorsed in August 2012 • Petronas Milestones Review # 3 endorsed in November 2012 • Petronas Milestones Review # 4 endorsed in February 2013 • Petronas Milestones Review # 5 endorsed in April 2013 • Field Development Plan (FDP) approved by Petronas in September 2013 • FPSO ‘Ikdam’ Upgrades Works awarded to Keppel Singapore in September 2013 • Well Head Platform Fabrication contract awarded to THHE on November 2013 • FPSO ‘Ikdam’ was officially renamed FPSO BERTAM in June 2014 • Transportation & Installation (FPSO Scope ) contract awarded to Subsurf/DOF on July 2014 • Target MCD for WHP from THHE - OCTOBER 2014 • Target Sail-away from Keppel – OCTOBER 2014. • 1st Oil targeted in 4Qtr 2014 Project has very strong support by Petronas & Partner Petronas Carigali hence the Fast Approvals achieved to date.
  • 34. CONTRACTING STRATEGY Detailed Design & Engineering WHP by Aker Engineering FPSO by Longitude Fabrication WHP by THHE FPSO upgrade works by Keppel Shipyard, Singapore Transportation & Installation WHP by TLO FPSO by Subsurf/DOF Hook-up & Commissioning of Topside Process kit WHP by PBJV FPSO by Lundin
  • 35. TRANSPORTATION & INSTALLATION SCOPE OF WORKS – SUBSURF/DOF 1. Phase 1 – Installation of Mooring Piles and Mooring Chains • Successfully completed on 2 August 2014 2. Phase 2 – Hook up of FPSO to Pre-laid Mooring Chains • To commence on late October/November 2014 3. Phase 3 – Installation of Hoses and Umbilical • To commence on November 2014 * Prior to start-up, full Nitrogen leak test will be done on the flexible hoses (production & diesel lines).
  • 36. CONTRACTING STRATEGY Detailed Design & Engineering WHP by Aker Engineering FPSO by Longitude Fabrication WHP by THHE FPSO upgrade works by Keppel Shipyard, Singapore Transportation & Installation WHP by TLO FPSO by Subsurf/DOF Hook-up & Commissioning of Topside Process WHP by PBJV FPSO by Lundin
  • 38. 1. ISV is positioned on the south side of the WHP – within the radius of the WHP & FPSO crane 2. FPSO crane picks up FPSO end of the jumper and is lifted off the deck of the ISV A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
  • 39. 3. WHP crane picks up WHP end of the jumper and is lifted off the deck of the ISV 4. Both cranes lift the jumpers simultaneously so that the entire jumper length is off the ISV’s deck. A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
  • 40. 5. Slew both cranes to bring jumper ends closer to the FPSO hull & WHP Balcony). Crane booms are then lowered down to align the jumper ends to the tie- in connection points. 6. At the FPSO, slew the crane to bring the jumper near it’s respective tie-in flanges of the FPSO hose gallery. A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
  • 41. 7. Lift jumper end to FPSO deck level. Connect hang-off rigging to soft slings c/w lifting spool lugs on jumpers. 8. Transfer load from FPSO crane to hang-off rigging and remove lifting flange.. A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
  • 42. 9. Lift jumper up to I-Tube flange and fasten connection. Remove the hang-off rigging & store A. Installation Procedures - Jumper Hose to FPSO Hose Gallery
  • 43. A. Installation Procedures - Jumper Hose to WHP Balcony 1. At WHP, haul in the jumper using the hang-off rigging connected to the pad- eyes on the mezzanine deck and bring jumper end inboard over the lay-over arch. 2. Haul in the jumper using hang-off rigging connected to D-rings on the cellar deck & bring jumper end towards cellar deck .
  • 44. A. Installation Procedures - Jumper Hose to WHP Balcony 3. Using the rigging configuration connected to pre-installed pad-eyes & D-rings on the cellar deck & mezzanine deck, the jumper’s flange is aligned close to the anchor-pipe. 4. Lifting Flange is removed. Jumper flange is pulled-in using through-hole rigging connected to jumper lifting spool & anchor-pipe’s flange. Gasket, studbolts & studbolts & nuts is inserted and flanges are made-up & torqued to specifications.