SlideShare a Scribd company logo
Northern Technical University
Engineering Technical College of Mosul
Building & Construction
Technology Engineering Dept.
Estimation, Specifications and
Contracts
SECOND CLASS
Lecturer:
Dr. Muthanna Adil Najm ABBU
2017-2018
Estimation, Specifications
& Contracts Factors Lecture .2
1
Dr. Muthanna Adil Najm Northern Technical University
PROCEDURE OF ESTIMATING OR METHOD OF ESTIMATING.
Estimating involves the following operations
1. Preparing detailed Estimate.
2. Calculating the rate of each unit of work
3. Preparing abstract of estimate
DATA REQUIRED TO PREPARE AN ESTIMATE
1. Drawings i.e.plans, elevations, sections etc.
2. Specifications.
3. Rates.
DRAWINGS
If the drawings are not clear and without complete dimensions the preparation
of estimation become very difficult. So, It is very essential before preparing
an estimate.
SPECIFICATIONS
a) General Specifications:
This gives the nature, quality, class and work and materials in general terms to
be used in various parts of wok. It helps no form a general idea of building.
b) Detailed Specifications:
These gives the detailed description of the various items of work laying down
the Quantities and qualities of materials, their proportions, the method of
preparation workmanship and execution of work.
RATES:
For preparing the estimate the unit rates of each item of work are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labour, skilled or unskilled of masons, carpenters, Mazdoor,
etc.,
Estimation, Specifications
& Contracts Factors Lecture .2
2
Dr. Muthanna Adil Najm Northern Technical University
LUMPSUM:
While preparing an estimate, it is not possible to workout in detail in case of
petty items. Items other than civil engineering such items are called
lumpsum items or simply L.S.Items. The following are some of L.S. Items
in the estimate.
1. Water supply and sanitary arrangements.
2. Electrical installations like meter, motor, etc.,
3. Architectural features.
4. Contingencies and unforeseen items.
Ingeneral, certain percentage on the cost of estimation is alloted for the above
L.S.Items.
Even if subestimates prepared or at the end of execution of work, the actual
cost should not exceed the L.S.amounts provided in the main estimate.
Factors affecting cost estimation:
There are three further factors that have a significant influence on how an
estimator
goes about preparing a construction estimate:
1. The type of project to be built
2. The delivery system used to move from the developer’s project idea to
a finished structure
3. The nature of the contract(s) used in the delivery system
Estimation, Specifications
& Contracts Factors Lecture .2
3
Dr. Muthanna Adil Najm Northern Technical University
Types of estimation:
A. Detailed Estimate
The most accurate and most reliable type of estimate. It consists of the quantities
and the cost of everything required in the project. This includes:-
(1) report, (2) technical specifications, (3) detailed drawings, (4) design data and
calculations, (5) basis of the rated prices adopted in estimation.
B. Approximate (Rough/Order of magnitude/Preliminary) Estimate
This method is based on comparative Cost of Structure. It is readily adaptable to
virtually every type of structure, including bridges, stadiums, schools, hospitals, and
offices. Very little information is required about the planned structure except that
the following general characteristics should be known:
1. Use — school, office, hospital, and so on
Estimation, Specifications
& Contracts Factors Lecture .2
4
Dr. Muthanna Adil Najm Northern Technical University
2. Kind of construction — wood, steel, concrete, and so on
3. Quality of construction — cheap, moderate, top grade
4. Locality — labor and material supply market area
5. Time of construction — year
By identifying a similar completed structure with nearly the same characteristics,
an order-of-magnitude estimate can be determined by proportioning cost according
to the appropriate unit for the structure.
There are several techniques to prepare the approximate estimate:-
(1) Service Unit or cost per unit Method
These units might be as follows:
• Schools — pupils
• Stadium — seats
• Hospital — beds
• Warehouses — cubic feet
(2) Unit-Area or Floor-Area Or plinth area
In this technique the cost of unit area of an already constructed building is
adapted as the basis to estimate the cost of a new similar building.
In the case of multi-storey buildings either one of the methods below may be
used:
I- consider the cost of the construction unit of area equal to all floors.
II- taking into account the different construction cost of some floors in
comparison to others.
(3) Unit - Volume or Cubic Rate Method
This is more accurate than its predecessor as it takes into account the third
dimension (i.e., height of floors).
(4) Approximate Quantities
Estimation, Specifications
& Contracts Factors Lecture .2
5
Dr. Muthanna Adil Najm Northern Technical University
In this method approximate quantities of each item of the work are calculated
and priced then the approximate cost of the project is calculated.
Using approximate techniques of estimation one must consider the following
points: -
(1). Specification level & finishing requirements.
(2). Time & duration of construction and inflation effect.
(3). Site & location of the project.
(4). General & special requirements of project.
(5). The structural nature of the building.
(6). Shape & height of building compared to the prototype.
C- Quantity Survey or Quantity Estimate
This involves the calculation of the quantities of materials required to complete
the work in question.
D- Revised Estimate
This type of estimate is prepared during construction when the difference
between reality and prepared estimation exceeds 5% regardless the reason behind
this difference (except major structural changes).
E- Supplementary Estimate
Used for the additional works that may seem necessary during the construction
phase.
F- Complete Estimate
It is the cost estimation of each item of works related to the job. It includes:
1 - the cost of land or property including:
• the cost of purchasing the land or its monetary value.
Estimation, Specifications
& Contracts Factors Lecture .2
6
Dr. Muthanna Adil Najm Northern Technical University
• fees of surveyor and the delimitation of the property.
• the cost of testing and transfer of ownership of the property.
• real estate tax and making the required improvements, if any.
2 - necessary expenses for legal actions between the owner and the contractor.
3 - the basic amount of main contract ( materials, labor .... etc).
4 - Emergency and unexpected conditions: to be calculated as a percentage of
the work (≈ 5%) and added to the cost of the extra works and supervision.
5 - Engineering fees including:
• Preparation of plans, designs and estimation.
• supervising.
6 - water and electricity fees during the construction phase.
7 - others, if any.
G- Annual Maintenance or Repair Estimate
This type of estimate is pertinent to the repair works and maintenance works that
are necessary to keep the project usable.
Practical examples on approximate estimation:
Example 1: Assume that the current cost for a 120-pupil school constructed of wood
frame for a city is $1,800,000. We are asked to develop an order-of-magnitude
estimate for a 90-pupil school.
Solution:
The first step is to separate the per-pupil cost.
$1,800,000/ 120 = $15,000 pupil
Apply the unit cost to the new school.
$15,000 pupil x 90 pupils = $1,350,000
Estimation, Specifications
& Contracts Factors Lecture .2
7
Dr. Muthanna Adil Najm Northern Technical University
Example 2: The total cost of construction of a hospital with capacity of (50) beds
is150 million dinars.
Cost per bed (patient) = 150 ÷ 50 = 3 million dinars
We can use this number to estimate the cost of similar hospital but with 20 beds, as
follows:
20 x 3 = 60 million dinars.
Example 3: a 24x15 m building consisting of 6 floors including the basement,
ground and terrace. Calculate the cost of 1 m2
using both above-mentioned methods,
if the total cost of the building is (648) million dinars.
solution:
(1) first method:
Total construction area = 6x (24x15) = 2160 m2
Cost of 1 m2
= 648000000 ÷ 2160 = 300,000 ID
(2) second method: suppose the cost basement floor = 60% of the cost of any of the
other floors
The cost of terrace = 40% of the cost of any of the other floors (except for the
basement).
The equivalent area of the basement = 24x15x60% = 216 m2
The equivalent area of the terrace = 24x15x40% = 144 m2
Area of rest floors = 4x (24x15) = 1440 m2
Total area of construction =1800 m2
the cost of 1 m2
of construction for the (typical) floors
= 648000000 ÷ 1800 = 360000 dinars
The cost of 1 m2
of basement = 360000x60% = 216000 dinars
Finally, the cost of 1 m2
of the surface = 360000x40% = 144000 dinars
Estimation, Specifications
& Contracts Factors Lecture .2
8
Dr. Muthanna Adil Najm Northern Technical University
Example 4: A 60x40m building consists of basement (2.8 m high), three other
floors (each 3m high). The total cost of building 2250 million I. D.
Calculate the cost of unit volume of the building assuming: -
a- identical cost of 1m3
for all floors.
b- costs of basement & ground floor are 60% and 120% of the other floors
respectively.
Solution: a-
Vbasement = 40x60x2.8 = 6720 m3
Vothers = 40x60x3x3 = 21600 m3
__________
Total =28320 m3
 Cost of 1 m3
= 2250000000 / 28320 = 79450 I. D.
b- equivalent Vbas . = 40x60x208x0.6 = 4032 m3
equivalent VG. F. = 40x60x3x1.2 = 8640 m3
V others = 40x60x3x2 = 14400 m3
__________
Total = 27072 m3
 cost of 1m3
of typical floor = 2250000000 / 28320 = 83112 ID
cost of 1 m3
of basement = 83112x0.6 = 49867.2 I.D.
cost of 1 m3
ground floor = 83112x1.2 = 99734.4 I.D.

More Related Content

What's hot

Types of estimates
Types of estimatesTypes of estimates
Types of estimates
Simarpreet Singh
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
ArunRavi43
 
Basics of estimation
Basics of estimation Basics of estimation
Basics of estimation
ddscte
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
ila vamsi krishna
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
Ganesh Tatikonda
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
ila vamsi krishna
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)Waqas Aslam
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
Arpit Sethia
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
AyushHajare
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-project
hlksd
 
Costing_Actual spendings & pricing
Costing_Actual spendings & pricingCosting_Actual spendings & pricing
Costing_Actual spendings & pricing
Ajinkya Deshpande
 
2# types of estimate
2# types of estimate2# types of estimate
2# types of estimate
LIJI A
 
Ppv ppt
Ppv pptPpv ppt
Ppv ppt
Nagma Modi
 
Factors affeccting cost estimates of a project
Factors affeccting cost estimates of a projectFactors affeccting cost estimates of a project
Factors affeccting cost estimates of a project
Ar.Vijay Kumar
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ganesh Tatikonda
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
Felix Vong
 

What's hot (20)

Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Basics of estimation
Basics of estimation Basics of estimation
Basics of estimation
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-project
 
Costing_Actual spendings & pricing
Costing_Actual spendings & pricingCosting_Actual spendings & pricing
Costing_Actual spendings & pricing
 
2# types of estimate
2# types of estimate2# types of estimate
2# types of estimate
 
4.1 conceptual estimates
4.1 conceptual estimates4.1 conceptual estimates
4.1 conceptual estimates
 
Ppv ppt
Ppv pptPpv ppt
Ppv ppt
 
Factors affeccting cost estimates of a project
Factors affeccting cost estimates of a projectFactors affeccting cost estimates of a project
Factors affeccting cost estimates of a project
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 

Similar to Lec.2 binifits of estamations...Types of Estimation

Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
AHMADAHMAD735251
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
SOUMITRAMUDI
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
BALAMURUGANR53
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
TauheedKhan45
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
Padmasinh Patil
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
NSHYAMANANDASINGH
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
DhavalMithaiwala
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
lckr117
 
CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdf
hitusp
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
Sakshi Kirar
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
cricketreview
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
Nat Rice
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
NaumanIjaz12
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Prasad Manerikar
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
Deepak37004
 
Estimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresEstimating & costing of civil engineering structures
Estimating & costing of civil engineering structures
Ayan Sengupta
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
Himani762003
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
Green Building Awareness HVAC
Green Building Awareness HVAC Green Building Awareness HVAC
Green Building Awareness HVAC
AKSHAY SHARMA
 

Similar to Lec.2 binifits of estamations...Types of Estimation (20)

Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation_and_Costing.ppt
Estimation_and_Costing.pptEstimation_and_Costing.ppt
Estimation_and_Costing.ppt
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdf
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
 
Estimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresEstimating & costing of civil engineering structures
Estimating & costing of civil engineering structures
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Green Building Awareness HVAC
Green Building Awareness HVAC Green Building Awareness HVAC
Green Building Awareness HVAC
 

More from Muthanna Abbu

Lec.5 earthworks for various engineering projects
Lec.5  earthworks for various engineering projectsLec.5  earthworks for various engineering projects
Lec.5 earthworks for various engineering projects
Muthanna Abbu
 
Lec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footingsLec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footings
Muthanna Abbu
 
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3  General rules in quantitative survey. Quantity measuring. Rate analysisLec.3  General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Muthanna Abbu
 
Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...
Muthanna Abbu
 
Lec.1 introduction to the theory of structures. types of structures, loads,
Lec.1   introduction to the theory of structures. types of structures, loads,Lec.1   introduction to the theory of structures. types of structures, loads,
Lec.1 introduction to the theory of structures. types of structures, loads,
Muthanna Abbu
 
Lec.9 strength design method doubly reinforced beams
Lec.9   strength design method doubly reinforced beamsLec.9   strength design method doubly reinforced beams
Lec.9 strength design method doubly reinforced beams
Muthanna Abbu
 
Lec.8 strength design method t beams
Lec.8   strength design method t beamsLec.8   strength design method t beams
Lec.8 strength design method t beams
Muthanna Abbu
 
Lec.7 strength design method rectangular sections 3
Lec.7   strength design method rectangular sections  3Lec.7   strength design method rectangular sections  3
Lec.7 strength design method rectangular sections 3
Muthanna Abbu
 
Lec.6 strength design method rectangular sections 2
Lec.6   strength design method rectangular sections  2Lec.6   strength design method rectangular sections  2
Lec.6 strength design method rectangular sections 2
Muthanna Abbu
 
Lec.5 strength design method rectangular sections 1
Lec.5   strength design method rectangular sections  1Lec.5   strength design method rectangular sections  1
Lec.5 strength design method rectangular sections 1
Muthanna Abbu
 
Lec.4 working stress 2
Lec.4   working stress 2Lec.4   working stress 2
Lec.4 working stress 2
Muthanna Abbu
 
Lec.3 working stress 1
Lec.3   working stress 1Lec.3   working stress 1
Lec.3 working stress 1
Muthanna Abbu
 
Lec.2 materials
Lec.2   materialsLec.2   materials
Lec.2 materials
Muthanna Abbu
 
Lec.1 introduction
Lec.1   introductionLec.1   introduction
Lec.1 introduction
Muthanna Abbu
 
Theory of Structures Syllabus
Theory of Structures SyllabusTheory of Structures Syllabus
Theory of Structures Syllabus
Muthanna Abbu
 
Analysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) SyllabusAnalysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) Syllabus
Muthanna Abbu
 
Analysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) SyllabusAnalysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) Syllabus
Muthanna Abbu
 
Design of Steel Structures Syllabus
Design of Steel Structures SyllabusDesign of Steel Structures Syllabus
Design of Steel Structures Syllabus
Muthanna Abbu
 
Computer Applications 2 Syllabus
Computer Applications 2 SyllabusComputer Applications 2 Syllabus
Computer Applications 2 Syllabus
Muthanna Abbu
 
هندسة المطارات والسكك 4
هندسة المطارات والسكك 4هندسة المطارات والسكك 4
هندسة المطارات والسكك 4
Muthanna Abbu
 

More from Muthanna Abbu (20)

Lec.5 earthworks for various engineering projects
Lec.5  earthworks for various engineering projectsLec.5  earthworks for various engineering projects
Lec.5 earthworks for various engineering projects
 
Lec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footingsLec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footings
 
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3  General rules in quantitative survey. Quantity measuring. Rate analysisLec.3  General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
 
Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...
 
Lec.1 introduction to the theory of structures. types of structures, loads,
Lec.1   introduction to the theory of structures. types of structures, loads,Lec.1   introduction to the theory of structures. types of structures, loads,
Lec.1 introduction to the theory of structures. types of structures, loads,
 
Lec.9 strength design method doubly reinforced beams
Lec.9   strength design method doubly reinforced beamsLec.9   strength design method doubly reinforced beams
Lec.9 strength design method doubly reinforced beams
 
Lec.8 strength design method t beams
Lec.8   strength design method t beamsLec.8   strength design method t beams
Lec.8 strength design method t beams
 
Lec.7 strength design method rectangular sections 3
Lec.7   strength design method rectangular sections  3Lec.7   strength design method rectangular sections  3
Lec.7 strength design method rectangular sections 3
 
Lec.6 strength design method rectangular sections 2
Lec.6   strength design method rectangular sections  2Lec.6   strength design method rectangular sections  2
Lec.6 strength design method rectangular sections 2
 
Lec.5 strength design method rectangular sections 1
Lec.5   strength design method rectangular sections  1Lec.5   strength design method rectangular sections  1
Lec.5 strength design method rectangular sections 1
 
Lec.4 working stress 2
Lec.4   working stress 2Lec.4   working stress 2
Lec.4 working stress 2
 
Lec.3 working stress 1
Lec.3   working stress 1Lec.3   working stress 1
Lec.3 working stress 1
 
Lec.2 materials
Lec.2   materialsLec.2   materials
Lec.2 materials
 
Lec.1 introduction
Lec.1   introductionLec.1   introduction
Lec.1 introduction
 
Theory of Structures Syllabus
Theory of Structures SyllabusTheory of Structures Syllabus
Theory of Structures Syllabus
 
Analysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) SyllabusAnalysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) Syllabus
 
Analysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) SyllabusAnalysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) Syllabus
 
Design of Steel Structures Syllabus
Design of Steel Structures SyllabusDesign of Steel Structures Syllabus
Design of Steel Structures Syllabus
 
Computer Applications 2 Syllabus
Computer Applications 2 SyllabusComputer Applications 2 Syllabus
Computer Applications 2 Syllabus
 
هندسة المطارات والسكك 4
هندسة المطارات والسكك 4هندسة المطارات والسكك 4
هندسة المطارات والسكك 4
 

Recently uploaded

RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 

Lec.2 binifits of estamations...Types of Estimation

  • 1. Northern Technical University Engineering Technical College of Mosul Building & Construction Technology Engineering Dept. Estimation, Specifications and Contracts SECOND CLASS Lecturer: Dr. Muthanna Adil Najm ABBU 2017-2018
  • 2. Estimation, Specifications & Contracts Factors Lecture .2 1 Dr. Muthanna Adil Najm Northern Technical University PROCEDURE OF ESTIMATING OR METHOD OF ESTIMATING. Estimating involves the following operations 1. Preparing detailed Estimate. 2. Calculating the rate of each unit of work 3. Preparing abstract of estimate DATA REQUIRED TO PREPARE AN ESTIMATE 1. Drawings i.e.plans, elevations, sections etc. 2. Specifications. 3. Rates. DRAWINGS If the drawings are not clear and without complete dimensions the preparation of estimation become very difficult. So, It is very essential before preparing an estimate. SPECIFICATIONS a) General Specifications: This gives the nature, quality, class and work and materials in general terms to be used in various parts of wok. It helps no form a general idea of building. b) Detailed Specifications: These gives the detailed description of the various items of work laying down the Quantities and qualities of materials, their proportions, the method of preparation workmanship and execution of work. RATES: For preparing the estimate the unit rates of each item of work are required. 1. For arriving at the unit rates of each item. 2. The rates of various materials to be used in the construction. 3. The cost of transport materials. 4. The wages of labour, skilled or unskilled of masons, carpenters, Mazdoor, etc.,
  • 3. Estimation, Specifications & Contracts Factors Lecture .2 2 Dr. Muthanna Adil Najm Northern Technical University LUMPSUM: While preparing an estimate, it is not possible to workout in detail in case of petty items. Items other than civil engineering such items are called lumpsum items or simply L.S.Items. The following are some of L.S. Items in the estimate. 1. Water supply and sanitary arrangements. 2. Electrical installations like meter, motor, etc., 3. Architectural features. 4. Contingencies and unforeseen items. Ingeneral, certain percentage on the cost of estimation is alloted for the above L.S.Items. Even if subestimates prepared or at the end of execution of work, the actual cost should not exceed the L.S.amounts provided in the main estimate. Factors affecting cost estimation: There are three further factors that have a significant influence on how an estimator goes about preparing a construction estimate: 1. The type of project to be built 2. The delivery system used to move from the developer’s project idea to a finished structure 3. The nature of the contract(s) used in the delivery system
  • 4. Estimation, Specifications & Contracts Factors Lecture .2 3 Dr. Muthanna Adil Najm Northern Technical University Types of estimation: A. Detailed Estimate The most accurate and most reliable type of estimate. It consists of the quantities and the cost of everything required in the project. This includes:- (1) report, (2) technical specifications, (3) detailed drawings, (4) design data and calculations, (5) basis of the rated prices adopted in estimation. B. Approximate (Rough/Order of magnitude/Preliminary) Estimate This method is based on comparative Cost of Structure. It is readily adaptable to virtually every type of structure, including bridges, stadiums, schools, hospitals, and offices. Very little information is required about the planned structure except that the following general characteristics should be known: 1. Use — school, office, hospital, and so on
  • 5. Estimation, Specifications & Contracts Factors Lecture .2 4 Dr. Muthanna Adil Najm Northern Technical University 2. Kind of construction — wood, steel, concrete, and so on 3. Quality of construction — cheap, moderate, top grade 4. Locality — labor and material supply market area 5. Time of construction — year By identifying a similar completed structure with nearly the same characteristics, an order-of-magnitude estimate can be determined by proportioning cost according to the appropriate unit for the structure. There are several techniques to prepare the approximate estimate:- (1) Service Unit or cost per unit Method These units might be as follows: • Schools — pupils • Stadium — seats • Hospital — beds • Warehouses — cubic feet (2) Unit-Area or Floor-Area Or plinth area In this technique the cost of unit area of an already constructed building is adapted as the basis to estimate the cost of a new similar building. In the case of multi-storey buildings either one of the methods below may be used: I- consider the cost of the construction unit of area equal to all floors. II- taking into account the different construction cost of some floors in comparison to others. (3) Unit - Volume or Cubic Rate Method This is more accurate than its predecessor as it takes into account the third dimension (i.e., height of floors). (4) Approximate Quantities
  • 6. Estimation, Specifications & Contracts Factors Lecture .2 5 Dr. Muthanna Adil Najm Northern Technical University In this method approximate quantities of each item of the work are calculated and priced then the approximate cost of the project is calculated. Using approximate techniques of estimation one must consider the following points: - (1). Specification level & finishing requirements. (2). Time & duration of construction and inflation effect. (3). Site & location of the project. (4). General & special requirements of project. (5). The structural nature of the building. (6). Shape & height of building compared to the prototype. C- Quantity Survey or Quantity Estimate This involves the calculation of the quantities of materials required to complete the work in question. D- Revised Estimate This type of estimate is prepared during construction when the difference between reality and prepared estimation exceeds 5% regardless the reason behind this difference (except major structural changes). E- Supplementary Estimate Used for the additional works that may seem necessary during the construction phase. F- Complete Estimate It is the cost estimation of each item of works related to the job. It includes: 1 - the cost of land or property including: • the cost of purchasing the land or its monetary value.
  • 7. Estimation, Specifications & Contracts Factors Lecture .2 6 Dr. Muthanna Adil Najm Northern Technical University • fees of surveyor and the delimitation of the property. • the cost of testing and transfer of ownership of the property. • real estate tax and making the required improvements, if any. 2 - necessary expenses for legal actions between the owner and the contractor. 3 - the basic amount of main contract ( materials, labor .... etc). 4 - Emergency and unexpected conditions: to be calculated as a percentage of the work (≈ 5%) and added to the cost of the extra works and supervision. 5 - Engineering fees including: • Preparation of plans, designs and estimation. • supervising. 6 - water and electricity fees during the construction phase. 7 - others, if any. G- Annual Maintenance or Repair Estimate This type of estimate is pertinent to the repair works and maintenance works that are necessary to keep the project usable. Practical examples on approximate estimation: Example 1: Assume that the current cost for a 120-pupil school constructed of wood frame for a city is $1,800,000. We are asked to develop an order-of-magnitude estimate for a 90-pupil school. Solution: The first step is to separate the per-pupil cost. $1,800,000/ 120 = $15,000 pupil Apply the unit cost to the new school. $15,000 pupil x 90 pupils = $1,350,000
  • 8. Estimation, Specifications & Contracts Factors Lecture .2 7 Dr. Muthanna Adil Najm Northern Technical University Example 2: The total cost of construction of a hospital with capacity of (50) beds is150 million dinars. Cost per bed (patient) = 150 ÷ 50 = 3 million dinars We can use this number to estimate the cost of similar hospital but with 20 beds, as follows: 20 x 3 = 60 million dinars. Example 3: a 24x15 m building consisting of 6 floors including the basement, ground and terrace. Calculate the cost of 1 m2 using both above-mentioned methods, if the total cost of the building is (648) million dinars. solution: (1) first method: Total construction area = 6x (24x15) = 2160 m2 Cost of 1 m2 = 648000000 ÷ 2160 = 300,000 ID (2) second method: suppose the cost basement floor = 60% of the cost of any of the other floors The cost of terrace = 40% of the cost of any of the other floors (except for the basement). The equivalent area of the basement = 24x15x60% = 216 m2 The equivalent area of the terrace = 24x15x40% = 144 m2 Area of rest floors = 4x (24x15) = 1440 m2 Total area of construction =1800 m2 the cost of 1 m2 of construction for the (typical) floors = 648000000 ÷ 1800 = 360000 dinars The cost of 1 m2 of basement = 360000x60% = 216000 dinars Finally, the cost of 1 m2 of the surface = 360000x40% = 144000 dinars
  • 9. Estimation, Specifications & Contracts Factors Lecture .2 8 Dr. Muthanna Adil Najm Northern Technical University Example 4: A 60x40m building consists of basement (2.8 m high), three other floors (each 3m high). The total cost of building 2250 million I. D. Calculate the cost of unit volume of the building assuming: - a- identical cost of 1m3 for all floors. b- costs of basement & ground floor are 60% and 120% of the other floors respectively. Solution: a- Vbasement = 40x60x2.8 = 6720 m3 Vothers = 40x60x3x3 = 21600 m3 __________ Total =28320 m3  Cost of 1 m3 = 2250000000 / 28320 = 79450 I. D. b- equivalent Vbas . = 40x60x208x0.6 = 4032 m3 equivalent VG. F. = 40x60x3x1.2 = 8640 m3 V others = 40x60x3x2 = 14400 m3 __________ Total = 27072 m3  cost of 1m3 of typical floor = 2250000000 / 28320 = 83112 ID cost of 1 m3 of basement = 83112x0.6 = 49867.2 I.D. cost of 1 m3 ground floor = 83112x1.2 = 99734.4 I.D.