This document discusses various methods for estimating construction costs, including:
1. Detailed estimates that include all quantities and costs.
2. Approximate estimates that use comparative costs from similar past projects.
3. Quantity surveys that calculate material quantities.
4. It provides examples of estimating costs per unit like cost per pupil for a school.
Estimating is a complex process involving collection of available and pertinent information relating to the scope of a project, expected resource consumption, and future changes in resource costs. This process is required in all stages of the project life-cycle.
I will describe those things in the documents--
Types of Cost Estimates Used in Construction
Following are the different types of cost estimates used in construction,
Preliminary Cost Estimate
Plinth Area Cost Estimate
Cube Rate Cost Estimate
Approximate Quantity Method Cost Estimate
Detailed Cost Estimate
Revised Cost Estimate
Supplementary Cost Estimate
Annual Repair Cost Estimate
ESTIMATION AND COSTING
1. Introduction
2. Measurement of materials and works
3. Types of estimates
4. Detailed and abstract estimate of buildings
5. Specification and analysis of rates
6. Earthwork calculations
7. Detailed estimates
Estimating is a complex process involving collection of available and pertinent information relating to the scope of a project, expected resource consumption, and future changes in resource costs. This process is required in all stages of the project life-cycle.
I will describe those things in the documents--
Types of Cost Estimates Used in Construction
Following are the different types of cost estimates used in construction,
Preliminary Cost Estimate
Plinth Area Cost Estimate
Cube Rate Cost Estimate
Approximate Quantity Method Cost Estimate
Detailed Cost Estimate
Revised Cost Estimate
Supplementary Cost Estimate
Annual Repair Cost Estimate
ESTIMATION AND COSTING
1. Introduction
2. Measurement of materials and works
3. Types of estimates
4. Detailed and abstract estimate of buildings
5. Specification and analysis of rates
6. Earthwork calculations
7. Detailed estimates
Brief description is given about different types of estimates of buildings in civil engineering with basic technical terminology used in civil engineering field
This presentation covers introduction to Estimating and costing and its importance. Also, types of estimation, different terms and provisions used in estimating, are explained in it. Format of measurement sheet and abstract sheet and the rate analysis has been covered in this presentation. It can be helpful to study basics of estimating and costing.
This above data is related with Sheet Metal fabricated product line.I have elaborated basic difference between Estimation & Costing with strategy for getting best pricing & calculations involved in Actual Spending.
Brief description is given about different types of estimates of buildings in civil engineering with basic technical terminology used in civil engineering field
This presentation covers introduction to Estimating and costing and its importance. Also, types of estimation, different terms and provisions used in estimating, are explained in it. Format of measurement sheet and abstract sheet and the rate analysis has been covered in this presentation. It can be helpful to study basics of estimating and costing.
This above data is related with Sheet Metal fabricated product line.I have elaborated basic difference between Estimation & Costing with strategy for getting best pricing & calculations involved in Actual Spending.
For civil engineer quantity surveying and estimation costing is very important for any project.
In this presentation we study about the Important terms used in estimation and costing, contingencies, work charge establishment, tools and plants, etc. types of estimates and their functions.
With rapid development of india’s national economy and improvement of living standards, energy issues have turned into serious social problems, restricting further development in the country. Large public buildings in india consume a great quantity of energy, and the indian government has rolled out a number of programs to retrofit them. Many retrofit technologies are readily available in india. However, there is uncertainty about technology effectiveness and which technologies work better in which climate zone. Only spotty analyses and summaries of real projects are available in literature. This report compares and analyzes these technologies in detail and provides some guidance in selecting economically effective approaches to retrofitting large public buildings. The first section sorts out some common building energysaving technologies and describes each technology with real projects. This section offers related background information for calculations later in the report.the second section summarizes energy consumption in office buildings and retail stores based on a literature survey for three major locations in india. The data includes itemized energy consumption, as well as energy use at whole-building levels. Later, building energy consumption simulation software – equest is used to simulate typical public buildings we constructed out of the literature survey. We calibrated the models, adjusted the usage schedules, and built a series of prototype models for all three geographical locations. The last section evaluates the effectiveness of each retrofit technology. Equest simulated the energy consumption with and without retrofit technologies in order to determine savings. We then added a cost analysis and calculated the typical payback period for each technology. Finally, we summarized these findings in tables so that readers can easily compare and understand how much savings and the payback period they can expect before starting a retrofit project.
Similar to Lec.2 binifits of estamations...Types of Estimation (20)
Lec.5 earthworks for various engineering projectsMuthanna Abbu
Earthworks in construction of roads, canals, railway tracks and hydraulic structures represent substantial part of the whole work. Therefore, it is very important to estimate the quantities of earthworks as accurate as possible, despite of the complicated process of calculation caused by variation in ground level.
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysisMuthanna Abbu
Analysis of rates for various types of construction works provides very useful information for effective planning, control, organization and management.
Lec.2 statically determinate structures & statically indeterminate struct...Muthanna Abbu
The student will learn the determination of internal forces in different structures and the
kind of forces distribution due to external & internal effects .He will also learn about the
structures deformation due to these effects .
Lec.1 introduction to the theory of structures. types of structures, loads,Muthanna Abbu
The student will learn the determination of internal forces in different structures and the
kind of forces distribution due to external & internal effects .He will also learn about the
structures deformation due to these effects .
The student will learn the determination of internal forces in different structures and the kind of forces distribution due to external & internal effects .He will also learn about the structures deformation due to these effects .
The student will learn the manner of design & connecting the different parts in the steel structures . He also learn the transition nature of forces and stresses in steel members .
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Lec.2 binifits of estamations...Types of Estimation
1. Northern Technical University
Engineering Technical College of Mosul
Building & Construction
Technology Engineering Dept.
Estimation, Specifications and
Contracts
SECOND CLASS
Lecturer:
Dr. Muthanna Adil Najm ABBU
2017-2018
2. Estimation, Specifications
& Contracts Factors Lecture .2
1
Dr. Muthanna Adil Najm Northern Technical University
PROCEDURE OF ESTIMATING OR METHOD OF ESTIMATING.
Estimating involves the following operations
1. Preparing detailed Estimate.
2. Calculating the rate of each unit of work
3. Preparing abstract of estimate
DATA REQUIRED TO PREPARE AN ESTIMATE
1. Drawings i.e.plans, elevations, sections etc.
2. Specifications.
3. Rates.
DRAWINGS
If the drawings are not clear and without complete dimensions the preparation
of estimation become very difficult. So, It is very essential before preparing
an estimate.
SPECIFICATIONS
a) General Specifications:
This gives the nature, quality, class and work and materials in general terms to
be used in various parts of wok. It helps no form a general idea of building.
b) Detailed Specifications:
These gives the detailed description of the various items of work laying down
the Quantities and qualities of materials, their proportions, the method of
preparation workmanship and execution of work.
RATES:
For preparing the estimate the unit rates of each item of work are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labour, skilled or unskilled of masons, carpenters, Mazdoor,
etc.,
3. Estimation, Specifications
& Contracts Factors Lecture .2
2
Dr. Muthanna Adil Najm Northern Technical University
LUMPSUM:
While preparing an estimate, it is not possible to workout in detail in case of
petty items. Items other than civil engineering such items are called
lumpsum items or simply L.S.Items. The following are some of L.S. Items
in the estimate.
1. Water supply and sanitary arrangements.
2. Electrical installations like meter, motor, etc.,
3. Architectural features.
4. Contingencies and unforeseen items.
Ingeneral, certain percentage on the cost of estimation is alloted for the above
L.S.Items.
Even if subestimates prepared or at the end of execution of work, the actual
cost should not exceed the L.S.amounts provided in the main estimate.
Factors affecting cost estimation:
There are three further factors that have a significant influence on how an
estimator
goes about preparing a construction estimate:
1. The type of project to be built
2. The delivery system used to move from the developer’s project idea to
a finished structure
3. The nature of the contract(s) used in the delivery system
4. Estimation, Specifications
& Contracts Factors Lecture .2
3
Dr. Muthanna Adil Najm Northern Technical University
Types of estimation:
A. Detailed Estimate
The most accurate and most reliable type of estimate. It consists of the quantities
and the cost of everything required in the project. This includes:-
(1) report, (2) technical specifications, (3) detailed drawings, (4) design data and
calculations, (5) basis of the rated prices adopted in estimation.
B. Approximate (Rough/Order of magnitude/Preliminary) Estimate
This method is based on comparative Cost of Structure. It is readily adaptable to
virtually every type of structure, including bridges, stadiums, schools, hospitals, and
offices. Very little information is required about the planned structure except that
the following general characteristics should be known:
1. Use — school, office, hospital, and so on
5. Estimation, Specifications
& Contracts Factors Lecture .2
4
Dr. Muthanna Adil Najm Northern Technical University
2. Kind of construction — wood, steel, concrete, and so on
3. Quality of construction — cheap, moderate, top grade
4. Locality — labor and material supply market area
5. Time of construction — year
By identifying a similar completed structure with nearly the same characteristics,
an order-of-magnitude estimate can be determined by proportioning cost according
to the appropriate unit for the structure.
There are several techniques to prepare the approximate estimate:-
(1) Service Unit or cost per unit Method
These units might be as follows:
• Schools — pupils
• Stadium — seats
• Hospital — beds
• Warehouses — cubic feet
(2) Unit-Area or Floor-Area Or plinth area
In this technique the cost of unit area of an already constructed building is
adapted as the basis to estimate the cost of a new similar building.
In the case of multi-storey buildings either one of the methods below may be
used:
I- consider the cost of the construction unit of area equal to all floors.
II- taking into account the different construction cost of some floors in
comparison to others.
(3) Unit - Volume or Cubic Rate Method
This is more accurate than its predecessor as it takes into account the third
dimension (i.e., height of floors).
(4) Approximate Quantities
6. Estimation, Specifications
& Contracts Factors Lecture .2
5
Dr. Muthanna Adil Najm Northern Technical University
In this method approximate quantities of each item of the work are calculated
and priced then the approximate cost of the project is calculated.
Using approximate techniques of estimation one must consider the following
points: -
(1). Specification level & finishing requirements.
(2). Time & duration of construction and inflation effect.
(3). Site & location of the project.
(4). General & special requirements of project.
(5). The structural nature of the building.
(6). Shape & height of building compared to the prototype.
C- Quantity Survey or Quantity Estimate
This involves the calculation of the quantities of materials required to complete
the work in question.
D- Revised Estimate
This type of estimate is prepared during construction when the difference
between reality and prepared estimation exceeds 5% regardless the reason behind
this difference (except major structural changes).
E- Supplementary Estimate
Used for the additional works that may seem necessary during the construction
phase.
F- Complete Estimate
It is the cost estimation of each item of works related to the job. It includes:
1 - the cost of land or property including:
• the cost of purchasing the land or its monetary value.
7. Estimation, Specifications
& Contracts Factors Lecture .2
6
Dr. Muthanna Adil Najm Northern Technical University
• fees of surveyor and the delimitation of the property.
• the cost of testing and transfer of ownership of the property.
• real estate tax and making the required improvements, if any.
2 - necessary expenses for legal actions between the owner and the contractor.
3 - the basic amount of main contract ( materials, labor .... etc).
4 - Emergency and unexpected conditions: to be calculated as a percentage of
the work (≈ 5%) and added to the cost of the extra works and supervision.
5 - Engineering fees including:
• Preparation of plans, designs and estimation.
• supervising.
6 - water and electricity fees during the construction phase.
7 - others, if any.
G- Annual Maintenance or Repair Estimate
This type of estimate is pertinent to the repair works and maintenance works that
are necessary to keep the project usable.
Practical examples on approximate estimation:
Example 1: Assume that the current cost for a 120-pupil school constructed of wood
frame for a city is $1,800,000. We are asked to develop an order-of-magnitude
estimate for a 90-pupil school.
Solution:
The first step is to separate the per-pupil cost.
$1,800,000/ 120 = $15,000 pupil
Apply the unit cost to the new school.
$15,000 pupil x 90 pupils = $1,350,000
8. Estimation, Specifications
& Contracts Factors Lecture .2
7
Dr. Muthanna Adil Najm Northern Technical University
Example 2: The total cost of construction of a hospital with capacity of (50) beds
is150 million dinars.
Cost per bed (patient) = 150 ÷ 50 = 3 million dinars
We can use this number to estimate the cost of similar hospital but with 20 beds, as
follows:
20 x 3 = 60 million dinars.
Example 3: a 24x15 m building consisting of 6 floors including the basement,
ground and terrace. Calculate the cost of 1 m2
using both above-mentioned methods,
if the total cost of the building is (648) million dinars.
solution:
(1) first method:
Total construction area = 6x (24x15) = 2160 m2
Cost of 1 m2
= 648000000 ÷ 2160 = 300,000 ID
(2) second method: suppose the cost basement floor = 60% of the cost of any of the
other floors
The cost of terrace = 40% of the cost of any of the other floors (except for the
basement).
The equivalent area of the basement = 24x15x60% = 216 m2
The equivalent area of the terrace = 24x15x40% = 144 m2
Area of rest floors = 4x (24x15) = 1440 m2
Total area of construction =1800 m2
the cost of 1 m2
of construction for the (typical) floors
= 648000000 ÷ 1800 = 360000 dinars
The cost of 1 m2
of basement = 360000x60% = 216000 dinars
Finally, the cost of 1 m2
of the surface = 360000x40% = 144000 dinars
9. Estimation, Specifications
& Contracts Factors Lecture .2
8
Dr. Muthanna Adil Najm Northern Technical University
Example 4: A 60x40m building consists of basement (2.8 m high), three other
floors (each 3m high). The total cost of building 2250 million I. D.
Calculate the cost of unit volume of the building assuming: -
a- identical cost of 1m3
for all floors.
b- costs of basement & ground floor are 60% and 120% of the other floors
respectively.
Solution: a-
Vbasement = 40x60x2.8 = 6720 m3
Vothers = 40x60x3x3 = 21600 m3
__________
Total =28320 m3
Cost of 1 m3
= 2250000000 / 28320 = 79450 I. D.
b- equivalent Vbas . = 40x60x208x0.6 = 4032 m3
equivalent VG. F. = 40x60x3x1.2 = 8640 m3
V others = 40x60x3x2 = 14400 m3
__________
Total = 27072 m3
cost of 1m3
of typical floor = 2250000000 / 28320 = 83112 ID
cost of 1 m3
of basement = 83112x0.6 = 49867.2 I.D.
cost of 1 m3
ground floor = 83112x1.2 = 99734.4 I.D.