SlideShare a Scribd company logo
QUANTITY SURVEYING AND
VALUATION
Lecture #2
Types of Estimates
(1) Preliminary or Approximate estimate
(2) Rough cost estimate based on plinth area
(3) Rough cost estimate based on cubic contents
(4) Detailed estimate
(5) Annual repair estimate
(6) Special repair estimate
(7) Revised estimate
(8) Supplementary estimate
1. Preliminary or Approximate estimate
It is prepared after preliminary investigation and preliminary
surveying
Detailed surveying, design, drawings etc. are not required
Rates are determined either from practical knowledge or
from records for similar works
For example: To calculate approximate estimate for a
Hospital, per bed cost is calculated from the recent
completed hospital and is multiplied with the number of
beds required.
2. Rough cost estimate based on plinth area
Plinth area of a building shall be determined first
Plinth area of a building means Length x Breadth
Estimate of a building is calculated by multiplying the
plinth area of the building with plinth area rate of the
locality for similar buildings.
Example
Total cost of a building is Rs. 2 lac and its plinth area is 50 m2
Plinth area rate =2,00,000/50 = Rs.4000/- per m2
For a new building plan with 100m2, Total cost =4000x100 =
Rs.4,000,00/-
3. Rough cost estimate based on cubic content
Plinth area of a building shall be determined first
The cubic contents of a building means plinth area x height
of the building.
Estimate of a building is calculated by multiplying the cubic
content of the building with cubic rate of the locality for
similar buildings.
4. Detailed Estimate
After getting Administrative approval on rough cost
estimate, detailed estimates are prepared
Quantities of various items are calculated individually
An abstract of cost -giving quantities of each item and rate
of every item according to the sanctioned schedule of rates
Detailed specifications & report should also be attached
with the estimate.
Technical sanction is given on detailed estimate
5. Annual repair estimate
To keep building and roads in perfect condition, annual
repairs should be carried
11/2% to 2% of the capital cost of the building
6. Special repair estimate
If the work cannot be carried out of the annual repair funds
due to certain reasons resulting in the genuine increase in
cost, then special repairs estimate is to be prepared.
Eg. Replastering walls, new doors etc.
7. Revised estimate
If the sanctioned estimate exceeds by 5% either due to the
rate being found insufficient or due to some other reasons, a
fresh estimate is prepared which is called a Revised Estimate
A comparative statement on the last page of the estimate is
attached giving there in the reasons of the increase of cost in
case of each item.
7. Supplementary estimate
A fresh detailed estimate in addition to the original
sanctioned estimate prepared due to some changes in
structural design.
THANK YOU

More Related Content

What's hot

Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
ArunRavi43
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Prasad Manerikar
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimator
AshwiniChaudhari13
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
Shahin MB
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
Kailash Chander
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
Sakshi Kirar
 
Rate analysis
Rate analysisRate analysis
Rate analysis
DhavalMithaiwala
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
Namrata Agnihotri
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
Ganesh Murugan
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ganesh Tatikonda
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
Vijay325
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
Ganesh Tatikonda
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
Simarpreet Singh
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
Arpit Sethia
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
AyushHajare
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
Aditya Mistry
 
rate analysis
rate analysisrate analysis
rate analysis
Ganesh Tatikonda
 
Canal alignment
Canal alignmentCanal alignment
Canal alignment
Naveenaa
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
Simarpreet Singh
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
Krishna Spoorthy Rachamalla
 

What's hot (20)

Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimator
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
rate analysis
rate analysisrate analysis
rate analysis
 
Canal alignment
Canal alignmentCanal alignment
Canal alignment
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 

Similar to 2# types of estimate

Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
AHMADAHMAD735251
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
Educational Learner
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
Nat Rice
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
anbukkarasi dhuraisamy
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
Muthanna Abbu
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
cricketreview
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
DhavalMithaiwala
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
Padmasinh Patil
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
NaumanIjaz12
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
Prasad Manerikar
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptx
rikeshbisen
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
JunaidMughal34
 
IV -I - EQS - .pptx
IV -I - EQS - .pptxIV -I - EQS - .pptx
IV -I - EQS - .pptx
GovindarajuluBadana
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
lckr117
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
Deepak37004
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx
RaniVishwakarma15
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
Ar Naveen Naveen
 
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
SURAJITDASBAURI
 

Similar to 2# types of estimate (20)

Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
Estimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptxEstimating and costing I Chapter 2.pptx
Estimating and costing I Chapter 2.pptx
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptx
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
IV -I - EQS - .pptx
IV -I - EQS - .pptxIV -I - EQS - .pptx
IV -I - EQS - .pptx
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
 

More from LIJI A

Estimation of one room building
Estimation of one room buildingEstimation of one room building
Estimation of one room building
LIJI A
 
Estimation of wall
Estimation of  wallEstimation of  wall
Estimation of wall
LIJI A
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
LIJI A
 
4#Rate analysis
4#Rate analysis4#Rate analysis
4#Rate analysis
LIJI A
 
3#specifications
3#specifications3#specifications
3#specifications
LIJI A
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
LIJI A
 

More from LIJI A (6)

Estimation of one room building
Estimation of one room buildingEstimation of one room building
Estimation of one room building
 
Estimation of wall
Estimation of  wallEstimation of  wall
Estimation of wall
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
 
4#Rate analysis
4#Rate analysis4#Rate analysis
4#Rate analysis
 
3#specifications
3#specifications3#specifications
3#specifications
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
 

Recently uploaded

Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 

Recently uploaded (20)

Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 

2# types of estimate

  • 2. Types of Estimates (1) Preliminary or Approximate estimate (2) Rough cost estimate based on plinth area (3) Rough cost estimate based on cubic contents (4) Detailed estimate (5) Annual repair estimate (6) Special repair estimate (7) Revised estimate (8) Supplementary estimate
  • 3. 1. Preliminary or Approximate estimate It is prepared after preliminary investigation and preliminary surveying Detailed surveying, design, drawings etc. are not required Rates are determined either from practical knowledge or from records for similar works For example: To calculate approximate estimate for a Hospital, per bed cost is calculated from the recent completed hospital and is multiplied with the number of beds required.
  • 4. 2. Rough cost estimate based on plinth area Plinth area of a building shall be determined first Plinth area of a building means Length x Breadth Estimate of a building is calculated by multiplying the plinth area of the building with plinth area rate of the locality for similar buildings. Example Total cost of a building is Rs. 2 lac and its plinth area is 50 m2 Plinth area rate =2,00,000/50 = Rs.4000/- per m2 For a new building plan with 100m2, Total cost =4000x100 = Rs.4,000,00/-
  • 5. 3. Rough cost estimate based on cubic content Plinth area of a building shall be determined first The cubic contents of a building means plinth area x height of the building. Estimate of a building is calculated by multiplying the cubic content of the building with cubic rate of the locality for similar buildings.
  • 6. 4. Detailed Estimate After getting Administrative approval on rough cost estimate, detailed estimates are prepared Quantities of various items are calculated individually An abstract of cost -giving quantities of each item and rate of every item according to the sanctioned schedule of rates Detailed specifications & report should also be attached with the estimate. Technical sanction is given on detailed estimate
  • 7. 5. Annual repair estimate To keep building and roads in perfect condition, annual repairs should be carried 11/2% to 2% of the capital cost of the building
  • 8. 6. Special repair estimate If the work cannot be carried out of the annual repair funds due to certain reasons resulting in the genuine increase in cost, then special repairs estimate is to be prepared. Eg. Replastering walls, new doors etc.
  • 9. 7. Revised estimate If the sanctioned estimate exceeds by 5% either due to the rate being found insufficient or due to some other reasons, a fresh estimate is prepared which is called a Revised Estimate A comparative statement on the last page of the estimate is attached giving there in the reasons of the increase of cost in case of each item.
  • 10. 7. Supplementary estimate A fresh detailed estimate in addition to the original sanctioned estimate prepared due to some changes in structural design.