SlideShare a Scribd company logo
Building Economy ARE 431
Dr. Mohammad A. Hassanain 1
1
Conceptual Estimate - Approach
Conceptual estimate, also called rough order of magnitude
(ROM) estimates, are typically developed by establishing a
cost per usable unit from past projects and multiplying this
cost times the number of units being proposed.
Example of these costs might be:
Cost per bed for a hospital.
Cost per apartment.
Cost per student for a school.
Cost per mile for a highway.
If the costs are developed on a national average basis,
they must be adjusted using the appropriate cost index.
2
Conceptual Estimate - Approach
Cost taken from past projects must also be adjusted to the
future.
If the proposed project will be smaller or larger than normal,
the cost can also be adjusted for size.
An appropriate contingency should be applied to allow for
scope adjustments as well as economic or market
conditions.
Conceptual estimates can be done quickly, in 10-15
minutes, and provide an accuracy in the plus or minus 20%
range.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 2
3
Conceptual Estimate - Data
The accuracy of a conceptual estimate is dependent on the
quality of the data that the estimator has available.
The best scenario would be to look into the company data
and find the exact project size, quality, and location, then
adjust for inflation and market conditions, and the estimate is
done.
Unfortunately, most projects vary enough that it is difficult to
compare one with another.
Companies that specialize in certain areas of work often do
have reasonably good data on that type of project, but
companies that do a lot of different kinds of work must rely
on published data.
Example: figure 5-1.
4
Conceptual Estimate - Data
These data are based on an average of over 11, 500
projects as reported to Means from contractors, designers,
and owners.
These costs are all adjusted to the current year and
averaged.
To adjust for quality, the unit costs are divided into three
columns, ¼, median, and ¾. This allows the estimator to
adjust for quality quickly.
The median cost value represents the cost of average quality
projects.
The ¾ cost value represents the cost of higher quality
projects.
The ¼ cost value represent the cost of lower quality projects.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 3
5
Conceptual Estimate - Data
After selecting the appropriate project type and quality value,
the next step is to multiply the cost times the appropriate
number of units.
Let us take the example of a 50-unit motel; assume a high
quality (3/4) price, 1995 data:
Total cost = Number of units x unit cost
Total cost = 50 units x 40,700 per unit
Total cost = $2,035,000
This total cost reflects the cost of building a typical, high
quality motel in a national average location.
It includes the overhead and profit and, assuming this
project is of normal size, should represent the average of the
bids received in that year under normal market conditions.
6
Conceptual Estimate - Adjustments
There are a number of adjustments that may have to be
made. These include adjusting for:
Size
As the project increases or decreases from what the data is
showing as average, the cost per unit increases or
decreases.
In general, larger projects can be built more efficiently than
smaller projects because materials can be bought in larger
quantities and productivity generally increases as workers
“learn” the job.
Referring to figure 5-2, the typical high quality (3/4) motel
unit would be 620 square feet. Therefore:
Motel’s size = 620 sq. ft. x 50 unit = 31,000 sq. ft.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 4
7
Conceptual Estimate - Adjustments
Figure 5-3 Project size modifier table.
In the project size modifier table (figure 5-3), the typical motel
equals 27,000 sq. ft. Therefore the cost multiplier for the size
adjustment can be calculated as follows:
Size factor = Proposed building area/Typical building area
Size factor = 31,000/27,000 = 1.148
Using a size factor of 1.148 (round off to 1.1), read from the
graph on figure 5-3 a cost multiplier of 0.99.
Therefore for the motel project, the price adjusted to size is:
Size adjusted cost = Base cost x Cost multiplier
Size adjusted cost = $2,035,000 x 0.99 = $2,014, 650
8
Conceptual Estimate - Adjustments
This price reflects the cost of a high quality motel, adjusted
to a slightly lower unit price since the motel is slightly larger
than normal.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 5
9
Conceptual Estimate - Adjustments
Another adjustment that may have to be made is for
location.
Adjustments can be made for location by comparing the
price of common building materials and labor from one city
to another.
Figure 5-4 shows example tables for a few of the over 200
cities throughout the US and Canada for which Means has
complied the cost of construction.
Indices have been established for material, installation and
total cost, broken down by building system.
This allows the estimator to analyze specific project
elements, such as a subcontractor package, as well as look
at material purchasing costs and the cost of labor relative
to a particular location.
10
Conceptual Estimate - Adjustments
In this table the national average city would have a total
index equal to 100.
A material index of 111.2, indicates that the cost of material
is 11.2% above the national average.
Many projects are built in areas without a readily available
city cost index.
In that situation the estimator must analyze the project and
create the proper adjustment.
Companies that do a lot of work in the same location usually
develop their own location index.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 6
11
Conceptual Estimate - Adjustments
To adjust the model to three cities: New York, Columbia,
Spokane, a ratio could be set us as follows:
Estimated cost/100 = Adjusted cost for city/City index
New York City:
2,014,650/100 = Adjusted New York Cost/133.8
New York Cost = $2,695,601
Columbia:
2,014,650/100 = Adjusted Columbia Cost/77.9
Columbia Cost = $1,569,412
Spokane:
2,014,650 = Adjusted Spokane Cost/99.9
Spokane Cost = $2,012,635
12
Conceptual Estimate - Adjustments
This example illustrates the importance of location to the
cost of construction.
As can be seen, the cost of constructing the motel in New
York is more than $1 million over the estimated cost in
Columbia.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 7
13
Conceptual Estimate - Adjustments
The last adjustment that will be made for this estimate is for
time.
Time
This estimate was prepared using 1995 data (early 1995).
A project set to begin in early 1997 would have to be
adjusted for expected increases in labor and material.
Indices for past projects can be adjusted to the present by
comparing actual past project costs to the index of the year
as compared to the index today.
14
Conceptual Estimate - Adjustments
Assuming a 1980 project cost of $2 million, calculation of the
same project cost in 1995 would be figured as follows:
Past project cost = Current project cost
Index past year Index 1995
2,000,000/59.5 = Current project cost/100
Current project cost = $3,361,344
The difficulty often faced in conducting estimates is that
indices are not available for future years, so past and current
trends must be looked at and projected to the future.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 8
15
Conceptual Estimate - Adjustments
Another source of cost index information is Engineering
News Record (ENR) which publishes on a weekly basis cost
indices dating back to 1913 (the year which has been set as
the base year).
Each week the magazine looks at different materials,
industries, regions and make comparisons as well as
projections.
Indices are published for:
Construction cost.
Building cost.
Common labor.
Skilled labor.
Materials.
ENR indices can be used just as the Means indices to adjust
a project for time.
16
Conceptual Estimate - Adjustments
To construct a roadway in August 1994 that cost $5 million
in August 1981, the adjustment would be figured as follows:
From figure 5-5:
Construction Cost Index (ENR) Aug. 1981 = 3,575.
Construction Cost Index (ENR) Aug. 1994 = 5,433.
$5,000,000/3,575 = Construction cost 1994/5,433
Construction cost 1994 = $7,598, 601
Building Economy ARE 431
Dr. Mohammad A. Hassanain 9
17
Conceptual Estimate - Presentation
In presenting any estimate, it is important to consider the
purpose of the estimate as well as understand what is
included and not included in the price.
It is also important to understand all of the included
assumptions and the accuracy of the data.
Conceptual estimates are the first costs that are presented
to the owner. Although they are normally accomplished with
little information, they tend to be the number most
remembered.
It is important to identify information that has to be adjusted
for.
In the motel example, the cost of land, demolition if required
and design fees have not been included in the price and
would have to be added.

More Related Content

What's hot

Hydraulic jump
Hydraulic jumpHydraulic jump
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ganesh Tatikonda
 
Future Worth method
Future Worth methodFuture Worth method
Future Worth method
Suhail Ahmed
 
Valuation
ValuationValuation
Valuation
srinivas2036
 
Mass haul diagram
Mass haul diagramMass haul diagram
Mass haul diagram
Professional Engineer
 
Phases of soil investigation
Phases of soil investigationPhases of soil investigation
Phases of soil investigation
MachenLink
 
Introduction and types of soil mechanics
Introduction and types of soil mechanicsIntroduction and types of soil mechanics
Introduction and types of soil mechanics
Safiullah Khan
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
Gaurang Kakadiya
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
Essam Lotffy, PMP®, CCP®
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
Priodeep Chowdhury
 
Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)
Shanmugasundaram N
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
Kailash Chander
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
Nikhil Kumar
 
Boussinesq'S theory
Boussinesq'S theoryBoussinesq'S theory
Boussinesq'S theory
SANJEEV Wazir
 
Docks and their classification
Docks and their classificationDocks and their classification
Docks and their classification
Latif Hyder Wadho
 
ROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYINGROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYING
manashkedia098
 
Valuation
ValuationValuation
Valuation
kajol panchal
 
Engineering costs and cost estimating
Engineering costs and cost estimatingEngineering costs and cost estimating
Engineering costs and cost estimating
anwar khan
 
Valuation(1)
Valuation(1)Valuation(1)
Valuation(1)
jagadish108
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
briankirui9
 

What's hot (20)

Hydraulic jump
Hydraulic jumpHydraulic jump
Hydraulic jump
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Future Worth method
Future Worth methodFuture Worth method
Future Worth method
 
Valuation
ValuationValuation
Valuation
 
Mass haul diagram
Mass haul diagramMass haul diagram
Mass haul diagram
 
Phases of soil investigation
Phases of soil investigationPhases of soil investigation
Phases of soil investigation
 
Introduction and types of soil mechanics
Introduction and types of soil mechanicsIntroduction and types of soil mechanics
Introduction and types of soil mechanics
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
 
Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Boussinesq'S theory
Boussinesq'S theoryBoussinesq'S theory
Boussinesq'S theory
 
Docks and their classification
Docks and their classificationDocks and their classification
Docks and their classification
 
ROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYINGROAD NETWORKING AND SURVEYING
ROAD NETWORKING AND SURVEYING
 
Valuation
ValuationValuation
Valuation
 
Engineering costs and cost estimating
Engineering costs and cost estimatingEngineering costs and cost estimating
Engineering costs and cost estimating
 
Valuation(1)
Valuation(1)Valuation(1)
Valuation(1)
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 

Similar to 4.1 conceptual estimates

4.2 square foot estimating
4.2 square foot estimating4.2 square foot estimating
4.2 square foot estimating
Ali Juma Albahrani
 
3 estimate considerations
3 estimate considerations3 estimate considerations
3 estimate considerations
Ali Juma Albahrani
 
4.3 assemblies estimating
4.3 assemblies estimating4.3 assemblies estimating
4.3 assemblies estimating
Ali Juma Albahrani
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
Muthanna Abbu
 
Engineering economics ECO-202
Engineering economics ECO-202Engineering economics ECO-202
Engineering economics ECO-202
Saqib Imran
 
Engineering economics eco202
Engineering economics eco202Engineering economics eco202
Engineering economics eco202
Saqib Imran
 
cost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdfcost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdf
ArnabChakraborty499766
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
SudipBalLama
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303
MARK547399
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
hlksd
 
5.3 estimate setup
5.3 estimate setup5.3 estimate setup
5.3 estimate setup
Ali Juma Albahrani
 
Project cost management
Project cost management Project cost management
Project cost management
PALLA NARASIMHUDU
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptx
rikeshbisen
 
3 Reasons to Get Energy Simulation for your Building as the Best Investment
3 Reasons to Get Energy Simulation for your Building as the Best Investment3 Reasons to Get Energy Simulation for your Building as the Best Investment
3 Reasons to Get Energy Simulation for your Building as the Best Investment
Krishna Outsourcing
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Moustafa Ismail Abu Dief
 
Cost Indices for Industrial Application
Cost Indices for Industrial ApplicationCost Indices for Industrial Application
Cost Indices for Industrial Application
K. Shahzad Baig
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
IOSR Journals
 
Part 11) You are providing a revie.docx
Part 11) You are providing a revie.docxPart 11) You are providing a revie.docx
Part 11) You are providing a revie.docx
karlhennesey
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
Educational Learner
 

Similar to 4.1 conceptual estimates (20)

4.2 square foot estimating
4.2 square foot estimating4.2 square foot estimating
4.2 square foot estimating
 
3 estimate considerations
3 estimate considerations3 estimate considerations
3 estimate considerations
 
4.3 assemblies estimating
4.3 assemblies estimating4.3 assemblies estimating
4.3 assemblies estimating
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
Engineering economics ECO-202
Engineering economics ECO-202Engineering economics ECO-202
Engineering economics ECO-202
 
Engineering economics eco202
Engineering economics eco202Engineering economics eco202
Engineering economics eco202
 
cost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdfcost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdf
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303Project selection and estimating technique spencer o’briencpmgt303
Project selection and estimating technique spencer o’briencpmgt303
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
 
5.3 estimate setup
5.3 estimate setup5.3 estimate setup
5.3 estimate setup
 
Project cost management
Project cost management Project cost management
Project cost management
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptx
 
3 Reasons to Get Energy Simulation for your Building as the Best Investment
3 Reasons to Get Energy Simulation for your Building as the Best Investment3 Reasons to Get Energy Simulation for your Building as the Best Investment
3 Reasons to Get Energy Simulation for your Building as the Best Investment
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
 
Cost Indices for Industrial Application
Cost Indices for Industrial ApplicationCost Indices for Industrial Application
Cost Indices for Industrial Application
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
 
Part 11) You are providing a revie.docx
Part 11) You are providing a revie.docxPart 11) You are providing a revie.docx
Part 11) You are providing a revie.docx
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 

More from Ali Juma Albahrani

10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletion
Ali Juma Albahrani
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio method
Ali Juma Albahrani
 
8.the rate of return method
8.the rate of return method8.the rate of return method
8.the rate of return method
Ali Juma Albahrani
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method
Ali Juma Albahrani
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth method
Ali Juma Albahrani
 
7.0 life cycle costing
7.0 life cycle costing7.0 life cycle costing
7.0 life cycle costing
Ali Juma Albahrani
 
6.4 multiple factors
6.4 multiple factors6.4 multiple factors
6.4 multiple factors
Ali Juma Albahrani
 
6.3 use of interest tables
6.3 use of interest tables6.3 use of interest tables
6.3 use of interest tables
Ali Juma Albahrani
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagrams
Ali Juma Albahrani
 
6.1 simple versus compound interest
6.1 simple versus compound interest6.1 simple versus compound interest
6.1 simple versus compound interest
Ali Juma Albahrani
 
5.2 unit pricing
5.2 unit pricing5.2 unit pricing
5.2 unit pricing
Ali Juma Albahrani
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
Ali Juma Albahrani
 
5.0 detailed estimating
5.0 detailed estimating5.0 detailed estimating
5.0 detailed estimating
Ali Juma Albahrani
 
4.0 pre-construction estimates
4.0 pre-construction estimates4.0 pre-construction estimates
4.0 pre-construction estimates
Ali Juma Albahrani
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
Ali Juma Albahrani
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
Ali Juma Albahrani
 

More from Ali Juma Albahrani (16)

10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletion
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio method
 
8.the rate of return method
8.the rate of return method8.the rate of return method
8.the rate of return method
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth method
 
7.0 life cycle costing
7.0 life cycle costing7.0 life cycle costing
7.0 life cycle costing
 
6.4 multiple factors
6.4 multiple factors6.4 multiple factors
6.4 multiple factors
 
6.3 use of interest tables
6.3 use of interest tables6.3 use of interest tables
6.3 use of interest tables
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagrams
 
6.1 simple versus compound interest
6.1 simple versus compound interest6.1 simple versus compound interest
6.1 simple versus compound interest
 
5.2 unit pricing
5.2 unit pricing5.2 unit pricing
5.2 unit pricing
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
5.0 detailed estimating
5.0 detailed estimating5.0 detailed estimating
5.0 detailed estimating
 
4.0 pre-construction estimates
4.0 pre-construction estimates4.0 pre-construction estimates
4.0 pre-construction estimates
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
 

Recently uploaded

CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 

Recently uploaded (20)

CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 

4.1 conceptual estimates

  • 1. Building Economy ARE 431 Dr. Mohammad A. Hassanain 1 1 Conceptual Estimate - Approach Conceptual estimate, also called rough order of magnitude (ROM) estimates, are typically developed by establishing a cost per usable unit from past projects and multiplying this cost times the number of units being proposed. Example of these costs might be: Cost per bed for a hospital. Cost per apartment. Cost per student for a school. Cost per mile for a highway. If the costs are developed on a national average basis, they must be adjusted using the appropriate cost index. 2 Conceptual Estimate - Approach Cost taken from past projects must also be adjusted to the future. If the proposed project will be smaller or larger than normal, the cost can also be adjusted for size. An appropriate contingency should be applied to allow for scope adjustments as well as economic or market conditions. Conceptual estimates can be done quickly, in 10-15 minutes, and provide an accuracy in the plus or minus 20% range.
  • 2. Building Economy ARE 431 Dr. Mohammad A. Hassanain 2 3 Conceptual Estimate - Data The accuracy of a conceptual estimate is dependent on the quality of the data that the estimator has available. The best scenario would be to look into the company data and find the exact project size, quality, and location, then adjust for inflation and market conditions, and the estimate is done. Unfortunately, most projects vary enough that it is difficult to compare one with another. Companies that specialize in certain areas of work often do have reasonably good data on that type of project, but companies that do a lot of different kinds of work must rely on published data. Example: figure 5-1. 4 Conceptual Estimate - Data These data are based on an average of over 11, 500 projects as reported to Means from contractors, designers, and owners. These costs are all adjusted to the current year and averaged. To adjust for quality, the unit costs are divided into three columns, ¼, median, and ¾. This allows the estimator to adjust for quality quickly. The median cost value represents the cost of average quality projects. The ¾ cost value represents the cost of higher quality projects. The ¼ cost value represent the cost of lower quality projects.
  • 3. Building Economy ARE 431 Dr. Mohammad A. Hassanain 3 5 Conceptual Estimate - Data After selecting the appropriate project type and quality value, the next step is to multiply the cost times the appropriate number of units. Let us take the example of a 50-unit motel; assume a high quality (3/4) price, 1995 data: Total cost = Number of units x unit cost Total cost = 50 units x 40,700 per unit Total cost = $2,035,000 This total cost reflects the cost of building a typical, high quality motel in a national average location. It includes the overhead and profit and, assuming this project is of normal size, should represent the average of the bids received in that year under normal market conditions. 6 Conceptual Estimate - Adjustments There are a number of adjustments that may have to be made. These include adjusting for: Size As the project increases or decreases from what the data is showing as average, the cost per unit increases or decreases. In general, larger projects can be built more efficiently than smaller projects because materials can be bought in larger quantities and productivity generally increases as workers “learn” the job. Referring to figure 5-2, the typical high quality (3/4) motel unit would be 620 square feet. Therefore: Motel’s size = 620 sq. ft. x 50 unit = 31,000 sq. ft.
  • 4. Building Economy ARE 431 Dr. Mohammad A. Hassanain 4 7 Conceptual Estimate - Adjustments Figure 5-3 Project size modifier table. In the project size modifier table (figure 5-3), the typical motel equals 27,000 sq. ft. Therefore the cost multiplier for the size adjustment can be calculated as follows: Size factor = Proposed building area/Typical building area Size factor = 31,000/27,000 = 1.148 Using a size factor of 1.148 (round off to 1.1), read from the graph on figure 5-3 a cost multiplier of 0.99. Therefore for the motel project, the price adjusted to size is: Size adjusted cost = Base cost x Cost multiplier Size adjusted cost = $2,035,000 x 0.99 = $2,014, 650 8 Conceptual Estimate - Adjustments This price reflects the cost of a high quality motel, adjusted to a slightly lower unit price since the motel is slightly larger than normal.
  • 5. Building Economy ARE 431 Dr. Mohammad A. Hassanain 5 9 Conceptual Estimate - Adjustments Another adjustment that may have to be made is for location. Adjustments can be made for location by comparing the price of common building materials and labor from one city to another. Figure 5-4 shows example tables for a few of the over 200 cities throughout the US and Canada for which Means has complied the cost of construction. Indices have been established for material, installation and total cost, broken down by building system. This allows the estimator to analyze specific project elements, such as a subcontractor package, as well as look at material purchasing costs and the cost of labor relative to a particular location. 10 Conceptual Estimate - Adjustments In this table the national average city would have a total index equal to 100. A material index of 111.2, indicates that the cost of material is 11.2% above the national average. Many projects are built in areas without a readily available city cost index. In that situation the estimator must analyze the project and create the proper adjustment. Companies that do a lot of work in the same location usually develop their own location index.
  • 6. Building Economy ARE 431 Dr. Mohammad A. Hassanain 6 11 Conceptual Estimate - Adjustments To adjust the model to three cities: New York, Columbia, Spokane, a ratio could be set us as follows: Estimated cost/100 = Adjusted cost for city/City index New York City: 2,014,650/100 = Adjusted New York Cost/133.8 New York Cost = $2,695,601 Columbia: 2,014,650/100 = Adjusted Columbia Cost/77.9 Columbia Cost = $1,569,412 Spokane: 2,014,650 = Adjusted Spokane Cost/99.9 Spokane Cost = $2,012,635 12 Conceptual Estimate - Adjustments This example illustrates the importance of location to the cost of construction. As can be seen, the cost of constructing the motel in New York is more than $1 million over the estimated cost in Columbia.
  • 7. Building Economy ARE 431 Dr. Mohammad A. Hassanain 7 13 Conceptual Estimate - Adjustments The last adjustment that will be made for this estimate is for time. Time This estimate was prepared using 1995 data (early 1995). A project set to begin in early 1997 would have to be adjusted for expected increases in labor and material. Indices for past projects can be adjusted to the present by comparing actual past project costs to the index of the year as compared to the index today. 14 Conceptual Estimate - Adjustments Assuming a 1980 project cost of $2 million, calculation of the same project cost in 1995 would be figured as follows: Past project cost = Current project cost Index past year Index 1995 2,000,000/59.5 = Current project cost/100 Current project cost = $3,361,344 The difficulty often faced in conducting estimates is that indices are not available for future years, so past and current trends must be looked at and projected to the future.
  • 8. Building Economy ARE 431 Dr. Mohammad A. Hassanain 8 15 Conceptual Estimate - Adjustments Another source of cost index information is Engineering News Record (ENR) which publishes on a weekly basis cost indices dating back to 1913 (the year which has been set as the base year). Each week the magazine looks at different materials, industries, regions and make comparisons as well as projections. Indices are published for: Construction cost. Building cost. Common labor. Skilled labor. Materials. ENR indices can be used just as the Means indices to adjust a project for time. 16 Conceptual Estimate - Adjustments To construct a roadway in August 1994 that cost $5 million in August 1981, the adjustment would be figured as follows: From figure 5-5: Construction Cost Index (ENR) Aug. 1981 = 3,575. Construction Cost Index (ENR) Aug. 1994 = 5,433. $5,000,000/3,575 = Construction cost 1994/5,433 Construction cost 1994 = $7,598, 601
  • 9. Building Economy ARE 431 Dr. Mohammad A. Hassanain 9 17 Conceptual Estimate - Presentation In presenting any estimate, it is important to consider the purpose of the estimate as well as understand what is included and not included in the price. It is also important to understand all of the included assumptions and the accuracy of the data. Conceptual estimates are the first costs that are presented to the owner. Although they are normally accomplished with little information, they tend to be the number most remembered. It is important to identify information that has to be adjusted for. In the motel example, the cost of land, demolition if required and design fees have not been included in the price and would have to be added.