A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS
MANAGEMENT IN KERALA CONSTRUCTION INDUSTRY
Yadhun M.K1 Shrinath Rao K2
1 M.Tech (Construction Management) Student,
Srinivas University Institute of Engineering and Technology. Mukka, Mangalore
2 Associate Professor, Dept of Civil Engineering,
Srinivas University Institute of Engineering and Technology. Mukka, Mangalore
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - This project thesis titled “A study on the
qualitative analysis of materials management in Kerala
construction industry” is an attempt made on studying and
assessing thematerialmanagementprinciplesandpracticesin
construction industry in Kerala. The objective ofthestudyisto
understand about the problems occurring in the organization
because of improper application of materials management
and to find the factors affecting material management in
construction projects. In the construction industry, material
management is critical for the successful and timely
completion of a project. When the planning, material
identification, and material management systems are
inadequate, the project's cost rises. Labor productivity will
suffer as a result of material shortages and insufficient
storage. A good material management system on a
construction site can help to avoid project delays and cost
variations. This results in better planning, higher labor
productivity, accurate schedules, and lower project costs.
Key Words: Materials Management, Construction, Civil
Engineering, Storage, Planning.
1. INTRODUCTION
Materials Management is the process of planning, executing,
and controlling field activities in construction, The goal of
material management is to ensure that construction
materials are available when needed. Material management
is concerned with the principles and practises that
effectively reduce the cost of materials used in a project.
Material management is the line of responsibilitythat begins
with supplier selection and ends when the material is
delivered to its destination.
Materials Management is concerned with the planning,
acquisition, storage, and provision of appropriate materials
of the appropriate quality and quantity at the appropriate
location and time in order to coordinate and schedule the
construction activity. Materials management is a single
manpower organisation concept that encompasses all
activities and line responsibilitythatbeginwiththeselection
and personnel primarily concerned with the flow of
materials into and within an organisation.
Materials Management is a critical component of project
management. Materials are a major expense in a
construction project, so lowering procurement costs
increases the chances of lowering overall project costs.Poor
material management can lead to increased construction
costs. Efficient material managementcanresultinsignificant
project cost savings. Budget overruns, delays, and claims
plague far too many construction projects. A well-executed
materials management programme can ensure the timely
delivery of materials and equipment to the job site, allowing
for better work face planning, increasedlabourproductivity,
better schedules, and lower project costs
1.1 Definition
Material management is defined as “The function
responsible for the coordination of planning, sourcing,
purchasing, moving, storing and controlling materials in an
optimum manner so as to provide a pre-decided service to
the customer at a minimum cost.”
The International Federation of Purchasing and Materials
Management accept the definition of materialsmanagement
as “Materials Management is a total concept having its
definite organization to plan and control all types of
materials, its supply, and its flow from raw stage to finished
stage so as to deliver the product to customer as per his
requirements in time”.
1.2 Different stages of material management are:
a) Planning and Scheduling
b) Monitoring and Controlling
c) Organization and Personnel
d) Procurement
e) Delivery
f) Storage and Storage Facilities
g) Usage
h) Surplus and Waste Control
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 16
a) Planning and Scheduling
The first and most important process in any project is
planning. Material planning, a critical function of material
management, is inextricably linked with project planning
and control setup. The entire material programme must be
planned in order to meet the project deadline. Indeed,
planning and schedulingare importantintermsofincreasing
productivity, profit, and ensuring that construction projects
are completed on time.
b) Monitoring and Controlling
All construction activities in material management are
monitored and controlled to ensure that the right materials
with the exact quality are available at the right time and
place suitable for the lowest cost construction process.Itisa
step in which facilities, personnel, resources, and capital are
monitored and controlled to have a significant impact on
construction project operations.
c) Organization and Personnel
The material management process is structured in such a
way that it allows for integrated planning and coordination
of material flow in order to maximise resource utilisation
and minimise costs. The organisation must be designed to
ensure that work is completed on time, with material
personnel located at an appropriate level of project
management and influencing decision-making.
d) Procurement
Floating enquiry indents conduct primary investigations to
develop sources for material procurement.Itisprocessedby
the material procurement responsible personnel in orderto
invite quotations with material samples where applicable.
e) Delivery
Delivery ensures the efficient use of workforce and
production or process in constructionprojectsbyorganising
the movement of vehicles, people, and materials. One of the
major factors influencing cost and time during the
construction stage is material routing.
f) Storage and Storage facilities
The provision of required space, protection, and control of
building materials and components held on site during the
construction process is referred to as material storage. A
good and systematic storage of materials allows for better
material management in construction.
g) Usage
Material usage is the facilitation that allows for their
movement and placement. The construction industry
employs a wide range of building materials for various
aspects of home construction. Architects work with
structural engineers to determine the load-bearing
capabilities of the materials they recommend.
h) Surplus and Waste control
Waste reduction can be accomplished through a zero-waste
attitude, proper design decisions, site management, and
proper standardisation of construction materials. Waste
management on construction projects can also help to
reduce waste. Every construction personnel involved in
minimising the overall waste generation at the project must
plan the project activities at each stage. The waste rate
estimation method can be used to improve material
handling, reduce waste, and increase productivity
1.3 Advantages of Material Management:
To manage interface problemsbetweenfunctions,a material
management function is established.Thebenefitsthatcanbe
expected from the use of material management are those
that arise when a systems approach is used to handle an
organization's day-to-day activities as interconnected parts
of the overall process.
These advantages include:
• Improved coordination of activities.
• Reduced sub-optimization
• Increased flexibility
• Balanced stocks and fewer obsolete stocks
• Lower purchase prices and better delivery
conditions
• Lower storage and transportation costs
2. OBJECTIVES
The objective of the paper is to study the different material
management procedures practiced currently in local
construction projects and also identify the factors affecting
material management in construction projects in the state of
Kerala. The primary goal of material management is to
reduce the cost of materials to the greatest extent possibleso
that the final products are more competitive and the
organization's profit increases. This study will generatea list
of root causes for ineffective material management that can
be used as a benchmark to control the existing and future
projects. Furthermore the most concerning issues like cost
overrun and delay in terms of projectdeliveryanditsrelation
with the current material management practice will reveal
the weakness in the current material management practices
to the stakeholders. Apart from this research being useful to
the field professionals, this study will be valuable for the
academicians too.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 17
The project focuses on the following objectives:
• To identify the problems faced in material
management.
• To identify the critical factors in various stages of
material management
• Recommendations to reduce the problems faced in
material management.
3. LITERATURE REVIEW
[1] Narimah Binti Kasim (2008): Thisresearchfocusesonthe
creation of a tool to help construction projects improve their
materials management concepts and practices. Integrating
materials management and resource modelling allows for
investigation. This development will be based upon
management recognition of the significance of materials
management, combined with extensive pressure upon the
costs and efficiency in the functions which make up the
materials management systems .The incorrect control of
materials during project execution is a critical element
negatively affecting project performance. The case studies
under discussion involve procedures used in construction
projects that have major issues with materials management.
[2] Anusha Rajendran K (2011): This study examines the
implementationofMaterialCodingandMaterialRequirement
Planning on a residential project. It also emphasises
enhancing the project site's material storage efficiency. The
study does not include non-consumable products, and the
work was completed in a short amount of time. The work's
output does not include a thorough examination of each and
every project item; rather, only a few significantelementsare
examined.
[3] Abhilin G B, and Vishak M S” (2017): Poor material
management is one of the leading causes of building project
delays. The material management plan aims to ensure that
the right quality and quantity of materials are identified,
purchased, transported, and handled on site in a timely and
cost-effective manner. Time, money, and quality are three
interrelated concerns in every building job. Control and
management are required. It is necessary to change the
material management process in order to make a profit.
Using information and communication technologies
technology, accurate material usage, stocking material, and
material location may all be found. It saves time and money
by reducing labour-intensive error
[4] Harsh Soni (2016) this study explored the current
practice of Material Management in construction industry
and analyzed using ABC, SDE, & EOQ inventory control
technique. The purpose is to find out the ways of managing
the inventory properly, so that there would be a little impact
on the profits. They conclude that ABC analysis provides
identifying those items that make the largest impact on a
company’s overall inventory cost performance. SDE analysis
in very useful in knowing present dayscarcityofmaterials,in
lead time and deciding upon purchase strategies. EOQ
maintains the sufficient material safety stock in period short
supply and reduced material wastage. Economic Order
Quantity total investment is reduced and no of order is more
in a year. So, Rate of Interest is increasing in actual site
ordered material.
A literature review is typically conducted to better
understand the topic, identify the problem, and provide
appropriate solutionssuggestedbyvariousresearchersinthe
project. Various researches in material management and
inventory management are studied to learn about the
problems encountered in the industry around the world. It
aids in discovering and comprehending the various possible
solutions that can be obtained from literature research.
4. METHODOLOGY
The research approach adopted in this project is
qualitative methodology. In this study the questionnairewas
prepared followed by literature review related to material
management. Information collected through the literature
review was used to generate questionnaire surveys. The
structured questionnaire is most likely the most widely used
data collection technique forsurveyresearch.Questionnaires
have been widely used in descriptive and analytical surveys
to gather facts, opinions, and points of view.
Methodology of the study is as follows.
1. Literature Survey
2. Literature review
3. Identify material management processes and root
causes in ineffective material management in other
countries to formulate the questions
4. Preparation of the questionnaire
5. Distribute the questionnaire
6. Data collection
7. Data analysis
8. Result and discussion.
4.1 Designing and collecting data through a
questionnaire survey:
Questionnaires have been widely used in descriptive and
analytical surveys to gather facts, opinions, and points of
view. It improves confidentiality, strengthens internal and
external validity,simplifiesanalysis,andsavesresources.Asa
source of primary data, a questionnaire survey was
conducted. The data gathered from the literature reviewwas
used to create questionnaire surveys. This is a set of
questions that have been developed to provide useful
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 18
answers to researchers. The survey wasdividedintosections
based on the research goals and objectives. Each section was
given a title that reflected its purpose and purpose, and
questions were used to cover the main areas of research
4.2 Questionnaire:
Table 1 - Questionnaire Survey
CATEGORY FACTORS
MATERIAL
PLANNING
1. Incorrect materials take off from
drawing and design documents
2. Vendor evaluation criteria is not
organized.
3. Supply chain challenge
4. Lack of communication
5. Nonstandardspecificationsofmaterials
6. Difference between plans and
specifications
7. Changes in material types and
specifications during construction leads
to delay
8. Late in selection of finishing materials
due to diversity in market and also from
many contractors and subcontractors.
9. Unexpected increase in demand of
materials
MATERIAL
PROCUREMENT
10. Receiving materials before they are
required
11. Not receiving materials at the time of
requirement
12. Selection of type of contract for
specific materials procurement
13. Shortage of materials in the market
(availability)
14. Over-ordering of materials (wastage
problems).
15. Over-payments for materials
(inadequate administration procedures)
16. Loss of benefits (lack of skilled
negotiating procedures).
17. Lack of knowledge on procurement of
materials
18. Late delivery
19. Incorrect delivery
20. Incomplete delivery
MATERIAL
STORAGE
21. Piling up of inventory items and
controlling of the same is most difficult
task at site.
22. Management of surplus materials
consumes a lot of space and incurs cost
23. Storage constraints
24. Problems with de-centralized
processing of materials toandfromthesite
to storage
25. Inadequate training practices given to
the store in charge
26. Difficulty in delivery of long lead time
materials
SITE FACTORS 27. Regulation consideration: the
permission from local authority to deal
with materials delivery into the
construction site
28. Project size challenge: Thescale/sizeof
the project and physical access problems
with traffic overflow andsurroundinglocal
roads near the construction site
29. Improper handling of materials: This is
related to poor handling of materials by
site labor.
30. No proper stock yard available for
storing of materials (steel and shuttering
material’s) leading to material wastage.
31. Site access problems: The single site
access point led to traffic congestion when
many vehicles come to the construction
site at the same time.
32. Small loading area: This leads to
constraints in the loading and unloadingof
materials
34. Change in design according to site
conditions leading for change in level
difference during excavation
35. Inaccessibility to the site area during
harsh weather conditions.
36. Work diversion of personnel’s. -
Concentration of the managementtowards
other blocks in the sameprojectsleadingto
work diversion.
37. Rework due to inevitable reasons
occurred
38. Material unavailability at site
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 19
4.2 Data Collection
The weight and authenticity of the research are heavily
reliant on the validity and dependability of the data
collected. Data are frequently thought of as 'the facts,' or
things that are known to be true. But data are social
products. The records produced are not reality in and of
themselves; rather, they are the result of researchers'
attempts to observe or measure traces or evidence of
phenomena occurring within complex systems. Dataforthis
study were gathered using primary data collectionmethods.
For this study the primary data was collected using
questionnaires by the help of ‘Google form’ as well as direct
communication with thee Stakeholders. The questionnaires
was transmitted to the targeted respondents and they were
expected to fill this form and to submit the same.
4.3 Rating scale
Each statement in these questions should be rated onascale
from strongly agree to strongly disagree, starting with the
rating system was given as follow;
Strongly agree – 5, Agree – 4, Satisfactory – 3, Disagree – 2
strongly disagree – 1.
5. RESULT AND ANALYSIS
Table -2: Result Analysis Chart
Question
No
No. Of companies
with 4 & 5 (agree)
No. Of companies who
have given 2 &1(disagree)
No. Of companies who
have given 3((satisfactory)
1 24 3 3
2 23 0 7
3 27 0 3
4 23 3 4
5 18 1 11
6 25 1 4
7 24 0 6
8 28 0 2
9 25 1 4
10 18 3 9
11 25 2 3
12 26 0 4
13 25 1 4
14 17 2 11
15 17 7 6
16 17 3 10
17 23 1 6
18 26 2 2
19 24 1 5
20 21 2 7
21 21 0 9
22 25 3 2
23 23 2 5
24 23 1 6
25 23 1 6
26 22 1 7
27 24 0 6
28 24 1 5
29 24 1 5
30 23 1 6
31 25 0 5
32 20 2 8
33 24 1 5
34 23 1 6
35 25 0 5
36 23 2 5
37 17 1 12
38 26 0 4
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 20
Chart -1: - Number of companies responded, 4&5
Chart -2 - Number of companies responded 3
Chart -3 - Number of companies responded 1&2
Chart -4 - Overall Result Analysis
6. CONCLUSIONS
The purpose of this study wastoidentifythefactorsaffecting
materials management in construction projects in the State
of Kerala and their effects and solution. The factors were
compiled into a questionnaire, and responseswereobtained
from stakeholders involved in residential projects in Kerala.
Based on the research in the Kerala construction industry, I
have discovered top 15 most common factors affecting
material management. Based on the response from the
stakeholders, after analysing based on the feedbacks of the
questionnaire survey, we can conclude that different factors
affecting at each stage of material management and are
treated in different form.
The following conclusions are:
1. Poorly defined roles and responsibilities were identified
as a major issue during the material planning stage of
material management.
2. Supply chain challenge also be considered at material
planning stage of material management
3. Poorcoordinationandcommunicationbetweencontractor
and material supplier was identified as the major issue
during the vendor analysis stage of material management.
4. Local issues causing material delaysandunavailabilityare
regarded as the major problem during the material
purchasing stage of material management.
5. The main issue in the storage and inventory stages of
material management is a lack of modern equipment and
methods for handling.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 21
6. Damage to material on site and a lack of onsite material
control were identified as major issues during the supply
and distribution stages of material management.
7. Project size challenge, Site access problems and Small
loading area are regarded as the problem at site factors
stages of material management.
7. RECOMMENDATION
Recommendations are made based on the conclusions and
issues discovered during my study. These suggestions are
intended to improve materials management and reduce
project complexity.
• Making changes in the plans or the materials used should
be avoided by the owners as much as possible
• Proper and clear contracts must be written to make the
missions and responsibilities of contractors, consultant,and
management team
• Do not utilize substandard materials in construction
• Avoid of buying more or less amount of materials thanthat
are needed for construction
• Experienced Construction Manager should be hired for
tasks like selecting appropriate construction methods or
materials, managing costs and time, observing the
construction process, and organising contracts.
• Hiring trained and skilled labourspeedsuptheprocessand
eliminates the possibility of defective work and repeated
works.
• To avoid communication issues, it is recommended that all
indents, requests, notes, and records be kept in writing.
• Material handling equipment such as conveyor belts,
trolleys, cranes, and so on should be used to reduce waste
caused by improper material handling.
• Every construction firm should use the EOQ technique
before placing any order to reduce project cost overruns
• To avoid manual errors in material management, software
such as MSP, PRIMAVERA, ERP, SAP, and others should be
used.
8. REFERENCES
[1]. N. Hamzah, M.A. Khoiry, I. Arshad,N.M.tawil,andA.I.Che
Ani (2011) “Causes of Construction Delay” “Theoretical
Frame work”, Procedia Engineering.
[2].. Mohamed M. Marzouk *, Tarek I. El-Rasas, “Analysing
delay causes in Egyptian construction projects”, Journal of
Advanced Research (2014) 5,49–55.
[3]. Megha Desai, Rajiv Bhatt P.G. Student, “Critical Causesof
Delay in Residential Construction Projects”, International
Journal of Emerging Technology and Advanced Engineering,
(ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume
3, Issue 3, March 2013).
[4]. Ajibade Ayodeji Aibinu and Agboola Odeyinka (2006)
“Construction Delays and their causative factors in Nigeria”,
Journal of Construction Engineering and Management,
Vol.132, No.8, Page No.667-677
[5]. Assaf SA, Al-Khalil M, Al-Hazmi M. “Causes of delays in
large building construction projects.” ASCE J Manage Eng.
1995; 11(2):45–50.
[6]. M.E. Abd EI-Razek, H.A. Bassioni, And A.M. Mobarak
(2008) “Causes of Delay in Building Construction Projectsin
Egypt” Journal of Construction Engineering and
Management, Vol.134, No.11, Page No. 831-841.
[7]. Pablo Gonzalez, Vicente Gonzalez, Keith Molenaar Ph.D.
M ASCE and Francisco Orozco Ph.D. (2013) “Analysis of
causes of delay and times performance in construction
projects”, Journal of Construction Engineering and
Management.
[8]. Thillai A. Rajan, Govind Gopinath and Monalisa Behera
(2013) “PPPs and Project Overruns: Evidence from Road
Projects in India” Journal of Construction Engineering and
Management.
[9]. Cecilia Gravina da Racha andSergioLuizKemmer(2013)
“Method of Implement Delayed product Differentiation in
Construction of High-Rise Apartment Building Projects”
Journal of Construction Engineering and Management.
[10]. Hemant Doloi, Anil Sawhney, K.C. Iyer, Sameer Rentala
“Analysing factors affecting delays in Indian construction
projects”, International Journal of Project Management 30
(2012) 479–4.
BIOGRAPHIES
Yadhun M. K. is pursuing M.Tech
Construction Management at
Srinivas University Institute of
Engineering & Technology, Mukka,
Mangaluru. After Bachelor Degree
in Civil Engineering, Yadhun has
worked as Civil Engineer at M. K.
Associates, Kannur (Kerala, India)
for 3 years.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 22
Shrinath Rao K is working as
Associate Professor in the Dept of
Civil Engg at Srinivas University
Institute of Engineering &
Technology,Mukka,Mangaluru.He
has 7 years of work experience at
Abroad and 14 years at India
including Teaching, Review & Re-
Design of Syllabus, Quality
Assurance in Higher Educational
Institutions and Construction
Industry.

More Related Content

Similar to A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRUCTION INDUSTRY

Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...
eSAT Journals
 
Factors Affecting Material Management on Construction Site
Factors Affecting Material Management on Construction SiteFactors Affecting Material Management on Construction Site
Factors Affecting Material Management on Construction Site
IRJET Journal
 
IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction ProjectsIRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET Journal
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
IRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
IRJET Journal
 
IRJET-Improving Effective Material Management by Identifying Common Factors i...
IRJET-Improving Effective Material Management by Identifying Common Factors i...IRJET-Improving Effective Material Management by Identifying Common Factors i...
IRJET-Improving Effective Material Management by Identifying Common Factors i...
IRJET Journal
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction Management
IRJET Journal
 
IRJET- Analysis of Material Requirement Planning for Construction Project : C...
IRJET- Analysis of Material Requirement Planning for Construction Project : C...IRJET- Analysis of Material Requirement Planning for Construction Project : C...
IRJET- Analysis of Material Requirement Planning for Construction Project : C...
IRJET Journal
 
Project Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewProject Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A Review
IRJET Journal
 
Management for Construction Materials and Control of Construction Waste in Co...
Management for Construction Materials and Control of Construction Waste in Co...Management for Construction Materials and Control of Construction Waste in Co...
Management for Construction Materials and Control of Construction Waste in Co...
IJERA Editor
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
IRJET Journal
 
IRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable ConstructionIRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable Construction
IRJET Journal
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET Journal
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project management
Sanjeev Deshmukh
 
Optimization in Supply Logistics Cost of Construction Projects of a Company
Optimization in Supply Logistics Cost of Construction Projects of a CompanyOptimization in Supply Logistics Cost of Construction Projects of a Company
Optimization in Supply Logistics Cost of Construction Projects of a Company
IRJET Journal
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
IRJET Journal
 
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
civej
 
Application of ABC Analysis for Material Management of a Residential Building
Application of ABC Analysis for Material Management of a Residential BuildingApplication of ABC Analysis for Material Management of a Residential Building
Application of ABC Analysis for Material Management of a Residential Building
IRJET Journal
 
B1304021217
B1304021217B1304021217
B1304021217
IOSR Journals
 

Similar to A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRUCTION INDUSTRY (20)

Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...
 
Factors Affecting Material Management on Construction Site
Factors Affecting Material Management on Construction SiteFactors Affecting Material Management on Construction Site
Factors Affecting Material Management on Construction Site
 
IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction ProjectsIRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction Projects
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
IRJET-Improving Effective Material Management by Identifying Common Factors i...
IRJET-Improving Effective Material Management by Identifying Common Factors i...IRJET-Improving Effective Material Management by Identifying Common Factors i...
IRJET-Improving Effective Material Management by Identifying Common Factors i...
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction Management
 
IRJET- Analysis of Material Requirement Planning for Construction Project : C...
IRJET- Analysis of Material Requirement Planning for Construction Project : C...IRJET- Analysis of Material Requirement Planning for Construction Project : C...
IRJET- Analysis of Material Requirement Planning for Construction Project : C...
 
Project Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A ReviewProject Planning: Advanced Techniques and Process Waste Removals – A Review
Project Planning: Advanced Techniques and Process Waste Removals – A Review
 
Management for Construction Materials and Control of Construction Waste in Co...
Management for Construction Materials and Control of Construction Waste in Co...Management for Construction Materials and Control of Construction Waste in Co...
Management for Construction Materials and Control of Construction Waste in Co...
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
 
IRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable ConstructionIRJET- Application of Decision Making Tool in Sustainable Construction
IRJET- Application of Decision Making Tool in Sustainable Construction
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project management
 
Optimization in Supply Logistics Cost of Construction Projects of a Company
Optimization in Supply Logistics Cost of Construction Projects of a CompanyOptimization in Supply Logistics Cost of Construction Projects of a Company
Optimization in Supply Logistics Cost of Construction Projects of a Company
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
 
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
 
Application of ABC Analysis for Material Management of a Residential Building
Application of ABC Analysis for Material Management of a Residential BuildingApplication of ABC Analysis for Material Management of a Residential Building
Application of ABC Analysis for Material Management of a Residential Building
 
B1304021217
B1304021217B1304021217
B1304021217
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
Gas agency management system project report.pdf
Gas agency management system project report.pdfGas agency management system project report.pdf
Gas agency management system project report.pdf
Kamal Acharya
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
AI for Legal Research with applications, tools
AI for Legal Research with applications, toolsAI for Legal Research with applications, tools
AI for Legal Research with applications, tools
mahaffeycheryld
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
aryanpankaj78
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
CVCSOfficial
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
MadhavJungKarki
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
ycwu0509
 
Generative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdfGenerative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdf
mahaffeycheryld
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 

Recently uploaded (20)

ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
Gas agency management system project report.pdf
Gas agency management system project report.pdfGas agency management system project report.pdf
Gas agency management system project report.pdf
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
AI for Legal Research with applications, tools
AI for Legal Research with applications, toolsAI for Legal Research with applications, tools
AI for Legal Research with applications, tools
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
 
Generative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdfGenerative AI Use cases applications solutions and implementation.pdf
Generative AI Use cases applications solutions and implementation.pdf
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 

A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRUCTION INDUSTRY

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 15 A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRUCTION INDUSTRY Yadhun M.K1 Shrinath Rao K2 1 M.Tech (Construction Management) Student, Srinivas University Institute of Engineering and Technology. Mukka, Mangalore 2 Associate Professor, Dept of Civil Engineering, Srinivas University Institute of Engineering and Technology. Mukka, Mangalore ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - This project thesis titled “A study on the qualitative analysis of materials management in Kerala construction industry” is an attempt made on studying and assessing thematerialmanagementprinciplesandpracticesin construction industry in Kerala. The objective ofthestudyisto understand about the problems occurring in the organization because of improper application of materials management and to find the factors affecting material management in construction projects. In the construction industry, material management is critical for the successful and timely completion of a project. When the planning, material identification, and material management systems are inadequate, the project's cost rises. Labor productivity will suffer as a result of material shortages and insufficient storage. A good material management system on a construction site can help to avoid project delays and cost variations. This results in better planning, higher labor productivity, accurate schedules, and lower project costs. Key Words: Materials Management, Construction, Civil Engineering, Storage, Planning. 1. INTRODUCTION Materials Management is the process of planning, executing, and controlling field activities in construction, The goal of material management is to ensure that construction materials are available when needed. Material management is concerned with the principles and practises that effectively reduce the cost of materials used in a project. Material management is the line of responsibilitythat begins with supplier selection and ends when the material is delivered to its destination. Materials Management is concerned with the planning, acquisition, storage, and provision of appropriate materials of the appropriate quality and quantity at the appropriate location and time in order to coordinate and schedule the construction activity. Materials management is a single manpower organisation concept that encompasses all activities and line responsibilitythatbeginwiththeselection and personnel primarily concerned with the flow of materials into and within an organisation. Materials Management is a critical component of project management. Materials are a major expense in a construction project, so lowering procurement costs increases the chances of lowering overall project costs.Poor material management can lead to increased construction costs. Efficient material managementcanresultinsignificant project cost savings. Budget overruns, delays, and claims plague far too many construction projects. A well-executed materials management programme can ensure the timely delivery of materials and equipment to the job site, allowing for better work face planning, increasedlabourproductivity, better schedules, and lower project costs 1.1 Definition Material management is defined as “The function responsible for the coordination of planning, sourcing, purchasing, moving, storing and controlling materials in an optimum manner so as to provide a pre-decided service to the customer at a minimum cost.” The International Federation of Purchasing and Materials Management accept the definition of materialsmanagement as “Materials Management is a total concept having its definite organization to plan and control all types of materials, its supply, and its flow from raw stage to finished stage so as to deliver the product to customer as per his requirements in time”. 1.2 Different stages of material management are: a) Planning and Scheduling b) Monitoring and Controlling c) Organization and Personnel d) Procurement e) Delivery f) Storage and Storage Facilities g) Usage h) Surplus and Waste Control
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 16 a) Planning and Scheduling The first and most important process in any project is planning. Material planning, a critical function of material management, is inextricably linked with project planning and control setup. The entire material programme must be planned in order to meet the project deadline. Indeed, planning and schedulingare importantintermsofincreasing productivity, profit, and ensuring that construction projects are completed on time. b) Monitoring and Controlling All construction activities in material management are monitored and controlled to ensure that the right materials with the exact quality are available at the right time and place suitable for the lowest cost construction process.Itisa step in which facilities, personnel, resources, and capital are monitored and controlled to have a significant impact on construction project operations. c) Organization and Personnel The material management process is structured in such a way that it allows for integrated planning and coordination of material flow in order to maximise resource utilisation and minimise costs. The organisation must be designed to ensure that work is completed on time, with material personnel located at an appropriate level of project management and influencing decision-making. d) Procurement Floating enquiry indents conduct primary investigations to develop sources for material procurement.Itisprocessedby the material procurement responsible personnel in orderto invite quotations with material samples where applicable. e) Delivery Delivery ensures the efficient use of workforce and production or process in constructionprojectsbyorganising the movement of vehicles, people, and materials. One of the major factors influencing cost and time during the construction stage is material routing. f) Storage and Storage facilities The provision of required space, protection, and control of building materials and components held on site during the construction process is referred to as material storage. A good and systematic storage of materials allows for better material management in construction. g) Usage Material usage is the facilitation that allows for their movement and placement. The construction industry employs a wide range of building materials for various aspects of home construction. Architects work with structural engineers to determine the load-bearing capabilities of the materials they recommend. h) Surplus and Waste control Waste reduction can be accomplished through a zero-waste attitude, proper design decisions, site management, and proper standardisation of construction materials. Waste management on construction projects can also help to reduce waste. Every construction personnel involved in minimising the overall waste generation at the project must plan the project activities at each stage. The waste rate estimation method can be used to improve material handling, reduce waste, and increase productivity 1.3 Advantages of Material Management: To manage interface problemsbetweenfunctions,a material management function is established.Thebenefitsthatcanbe expected from the use of material management are those that arise when a systems approach is used to handle an organization's day-to-day activities as interconnected parts of the overall process. These advantages include: • Improved coordination of activities. • Reduced sub-optimization • Increased flexibility • Balanced stocks and fewer obsolete stocks • Lower purchase prices and better delivery conditions • Lower storage and transportation costs 2. OBJECTIVES The objective of the paper is to study the different material management procedures practiced currently in local construction projects and also identify the factors affecting material management in construction projects in the state of Kerala. The primary goal of material management is to reduce the cost of materials to the greatest extent possibleso that the final products are more competitive and the organization's profit increases. This study will generatea list of root causes for ineffective material management that can be used as a benchmark to control the existing and future projects. Furthermore the most concerning issues like cost overrun and delay in terms of projectdeliveryanditsrelation with the current material management practice will reveal the weakness in the current material management practices to the stakeholders. Apart from this research being useful to the field professionals, this study will be valuable for the academicians too.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 17 The project focuses on the following objectives: • To identify the problems faced in material management. • To identify the critical factors in various stages of material management • Recommendations to reduce the problems faced in material management. 3. LITERATURE REVIEW [1] Narimah Binti Kasim (2008): Thisresearchfocusesonthe creation of a tool to help construction projects improve their materials management concepts and practices. Integrating materials management and resource modelling allows for investigation. This development will be based upon management recognition of the significance of materials management, combined with extensive pressure upon the costs and efficiency in the functions which make up the materials management systems .The incorrect control of materials during project execution is a critical element negatively affecting project performance. The case studies under discussion involve procedures used in construction projects that have major issues with materials management. [2] Anusha Rajendran K (2011): This study examines the implementationofMaterialCodingandMaterialRequirement Planning on a residential project. It also emphasises enhancing the project site's material storage efficiency. The study does not include non-consumable products, and the work was completed in a short amount of time. The work's output does not include a thorough examination of each and every project item; rather, only a few significantelementsare examined. [3] Abhilin G B, and Vishak M S” (2017): Poor material management is one of the leading causes of building project delays. The material management plan aims to ensure that the right quality and quantity of materials are identified, purchased, transported, and handled on site in a timely and cost-effective manner. Time, money, and quality are three interrelated concerns in every building job. Control and management are required. It is necessary to change the material management process in order to make a profit. Using information and communication technologies technology, accurate material usage, stocking material, and material location may all be found. It saves time and money by reducing labour-intensive error [4] Harsh Soni (2016) this study explored the current practice of Material Management in construction industry and analyzed using ABC, SDE, & EOQ inventory control technique. The purpose is to find out the ways of managing the inventory properly, so that there would be a little impact on the profits. They conclude that ABC analysis provides identifying those items that make the largest impact on a company’s overall inventory cost performance. SDE analysis in very useful in knowing present dayscarcityofmaterials,in lead time and deciding upon purchase strategies. EOQ maintains the sufficient material safety stock in period short supply and reduced material wastage. Economic Order Quantity total investment is reduced and no of order is more in a year. So, Rate of Interest is increasing in actual site ordered material. A literature review is typically conducted to better understand the topic, identify the problem, and provide appropriate solutionssuggestedbyvariousresearchersinthe project. Various researches in material management and inventory management are studied to learn about the problems encountered in the industry around the world. It aids in discovering and comprehending the various possible solutions that can be obtained from literature research. 4. METHODOLOGY The research approach adopted in this project is qualitative methodology. In this study the questionnairewas prepared followed by literature review related to material management. Information collected through the literature review was used to generate questionnaire surveys. The structured questionnaire is most likely the most widely used data collection technique forsurveyresearch.Questionnaires have been widely used in descriptive and analytical surveys to gather facts, opinions, and points of view. Methodology of the study is as follows. 1. Literature Survey 2. Literature review 3. Identify material management processes and root causes in ineffective material management in other countries to formulate the questions 4. Preparation of the questionnaire 5. Distribute the questionnaire 6. Data collection 7. Data analysis 8. Result and discussion. 4.1 Designing and collecting data through a questionnaire survey: Questionnaires have been widely used in descriptive and analytical surveys to gather facts, opinions, and points of view. It improves confidentiality, strengthens internal and external validity,simplifiesanalysis,andsavesresources.Asa source of primary data, a questionnaire survey was conducted. The data gathered from the literature reviewwas used to create questionnaire surveys. This is a set of questions that have been developed to provide useful
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 18 answers to researchers. The survey wasdividedintosections based on the research goals and objectives. Each section was given a title that reflected its purpose and purpose, and questions were used to cover the main areas of research 4.2 Questionnaire: Table 1 - Questionnaire Survey CATEGORY FACTORS MATERIAL PLANNING 1. Incorrect materials take off from drawing and design documents 2. Vendor evaluation criteria is not organized. 3. Supply chain challenge 4. Lack of communication 5. Nonstandardspecificationsofmaterials 6. Difference between plans and specifications 7. Changes in material types and specifications during construction leads to delay 8. Late in selection of finishing materials due to diversity in market and also from many contractors and subcontractors. 9. Unexpected increase in demand of materials MATERIAL PROCUREMENT 10. Receiving materials before they are required 11. Not receiving materials at the time of requirement 12. Selection of type of contract for specific materials procurement 13. Shortage of materials in the market (availability) 14. Over-ordering of materials (wastage problems). 15. Over-payments for materials (inadequate administration procedures) 16. Loss of benefits (lack of skilled negotiating procedures). 17. Lack of knowledge on procurement of materials 18. Late delivery 19. Incorrect delivery 20. Incomplete delivery MATERIAL STORAGE 21. Piling up of inventory items and controlling of the same is most difficult task at site. 22. Management of surplus materials consumes a lot of space and incurs cost 23. Storage constraints 24. Problems with de-centralized processing of materials toandfromthesite to storage 25. Inadequate training practices given to the store in charge 26. Difficulty in delivery of long lead time materials SITE FACTORS 27. Regulation consideration: the permission from local authority to deal with materials delivery into the construction site 28. Project size challenge: Thescale/sizeof the project and physical access problems with traffic overflow andsurroundinglocal roads near the construction site 29. Improper handling of materials: This is related to poor handling of materials by site labor. 30. No proper stock yard available for storing of materials (steel and shuttering material’s) leading to material wastage. 31. Site access problems: The single site access point led to traffic congestion when many vehicles come to the construction site at the same time. 32. Small loading area: This leads to constraints in the loading and unloadingof materials 34. Change in design according to site conditions leading for change in level difference during excavation 35. Inaccessibility to the site area during harsh weather conditions. 36. Work diversion of personnel’s. - Concentration of the managementtowards other blocks in the sameprojectsleadingto work diversion. 37. Rework due to inevitable reasons occurred 38. Material unavailability at site
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 19 4.2 Data Collection The weight and authenticity of the research are heavily reliant on the validity and dependability of the data collected. Data are frequently thought of as 'the facts,' or things that are known to be true. But data are social products. The records produced are not reality in and of themselves; rather, they are the result of researchers' attempts to observe or measure traces or evidence of phenomena occurring within complex systems. Dataforthis study were gathered using primary data collectionmethods. For this study the primary data was collected using questionnaires by the help of ‘Google form’ as well as direct communication with thee Stakeholders. The questionnaires was transmitted to the targeted respondents and they were expected to fill this form and to submit the same. 4.3 Rating scale Each statement in these questions should be rated onascale from strongly agree to strongly disagree, starting with the rating system was given as follow; Strongly agree – 5, Agree – 4, Satisfactory – 3, Disagree – 2 strongly disagree – 1. 5. RESULT AND ANALYSIS Table -2: Result Analysis Chart Question No No. Of companies with 4 & 5 (agree) No. Of companies who have given 2 &1(disagree) No. Of companies who have given 3((satisfactory) 1 24 3 3 2 23 0 7 3 27 0 3 4 23 3 4 5 18 1 11 6 25 1 4 7 24 0 6 8 28 0 2 9 25 1 4 10 18 3 9 11 25 2 3 12 26 0 4 13 25 1 4 14 17 2 11 15 17 7 6 16 17 3 10 17 23 1 6 18 26 2 2 19 24 1 5 20 21 2 7 21 21 0 9 22 25 3 2 23 23 2 5 24 23 1 6 25 23 1 6 26 22 1 7 27 24 0 6 28 24 1 5 29 24 1 5 30 23 1 6 31 25 0 5 32 20 2 8 33 24 1 5 34 23 1 6 35 25 0 5 36 23 2 5 37 17 1 12 38 26 0 4
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 20 Chart -1: - Number of companies responded, 4&5 Chart -2 - Number of companies responded 3 Chart -3 - Number of companies responded 1&2 Chart -4 - Overall Result Analysis 6. CONCLUSIONS The purpose of this study wastoidentifythefactorsaffecting materials management in construction projects in the State of Kerala and their effects and solution. The factors were compiled into a questionnaire, and responseswereobtained from stakeholders involved in residential projects in Kerala. Based on the research in the Kerala construction industry, I have discovered top 15 most common factors affecting material management. Based on the response from the stakeholders, after analysing based on the feedbacks of the questionnaire survey, we can conclude that different factors affecting at each stage of material management and are treated in different form. The following conclusions are: 1. Poorly defined roles and responsibilities were identified as a major issue during the material planning stage of material management. 2. Supply chain challenge also be considered at material planning stage of material management 3. Poorcoordinationandcommunicationbetweencontractor and material supplier was identified as the major issue during the vendor analysis stage of material management. 4. Local issues causing material delaysandunavailabilityare regarded as the major problem during the material purchasing stage of material management. 5. The main issue in the storage and inventory stages of material management is a lack of modern equipment and methods for handling.
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 21 6. Damage to material on site and a lack of onsite material control were identified as major issues during the supply and distribution stages of material management. 7. Project size challenge, Site access problems and Small loading area are regarded as the problem at site factors stages of material management. 7. RECOMMENDATION Recommendations are made based on the conclusions and issues discovered during my study. These suggestions are intended to improve materials management and reduce project complexity. • Making changes in the plans or the materials used should be avoided by the owners as much as possible • Proper and clear contracts must be written to make the missions and responsibilities of contractors, consultant,and management team • Do not utilize substandard materials in construction • Avoid of buying more or less amount of materials thanthat are needed for construction • Experienced Construction Manager should be hired for tasks like selecting appropriate construction methods or materials, managing costs and time, observing the construction process, and organising contracts. • Hiring trained and skilled labourspeedsuptheprocessand eliminates the possibility of defective work and repeated works. • To avoid communication issues, it is recommended that all indents, requests, notes, and records be kept in writing. • Material handling equipment such as conveyor belts, trolleys, cranes, and so on should be used to reduce waste caused by improper material handling. • Every construction firm should use the EOQ technique before placing any order to reduce project cost overruns • To avoid manual errors in material management, software such as MSP, PRIMAVERA, ERP, SAP, and others should be used. 8. REFERENCES [1]. N. Hamzah, M.A. Khoiry, I. Arshad,N.M.tawil,andA.I.Che Ani (2011) “Causes of Construction Delay” “Theoretical Frame work”, Procedia Engineering. [2].. Mohamed M. Marzouk *, Tarek I. El-Rasas, “Analysing delay causes in Egyptian construction projects”, Journal of Advanced Research (2014) 5,49–55. [3]. Megha Desai, Rajiv Bhatt P.G. Student, “Critical Causesof Delay in Residential Construction Projects”, International Journal of Emerging Technology and Advanced Engineering, (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 3, Issue 3, March 2013). [4]. Ajibade Ayodeji Aibinu and Agboola Odeyinka (2006) “Construction Delays and their causative factors in Nigeria”, Journal of Construction Engineering and Management, Vol.132, No.8, Page No.667-677 [5]. Assaf SA, Al-Khalil M, Al-Hazmi M. “Causes of delays in large building construction projects.” ASCE J Manage Eng. 1995; 11(2):45–50. [6]. M.E. Abd EI-Razek, H.A. Bassioni, And A.M. Mobarak (2008) “Causes of Delay in Building Construction Projectsin Egypt” Journal of Construction Engineering and Management, Vol.134, No.11, Page No. 831-841. [7]. Pablo Gonzalez, Vicente Gonzalez, Keith Molenaar Ph.D. M ASCE and Francisco Orozco Ph.D. (2013) “Analysis of causes of delay and times performance in construction projects”, Journal of Construction Engineering and Management. [8]. Thillai A. Rajan, Govind Gopinath and Monalisa Behera (2013) “PPPs and Project Overruns: Evidence from Road Projects in India” Journal of Construction Engineering and Management. [9]. Cecilia Gravina da Racha andSergioLuizKemmer(2013) “Method of Implement Delayed product Differentiation in Construction of High-Rise Apartment Building Projects” Journal of Construction Engineering and Management. [10]. Hemant Doloi, Anil Sawhney, K.C. Iyer, Sameer Rentala “Analysing factors affecting delays in Indian construction projects”, International Journal of Project Management 30 (2012) 479–4. BIOGRAPHIES Yadhun M. K. is pursuing M.Tech Construction Management at Srinivas University Institute of Engineering & Technology, Mukka, Mangaluru. After Bachelor Degree in Civil Engineering, Yadhun has worked as Civil Engineer at M. K. Associates, Kannur (Kerala, India) for 3 years.
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 22 Shrinath Rao K is working as Associate Professor in the Dept of Civil Engg at Srinivas University Institute of Engineering & Technology,Mukka,Mangaluru.He has 7 years of work experience at Abroad and 14 years at India including Teaching, Review & Re- Design of Syllabus, Quality Assurance in Higher Educational Institutions and Construction Industry.