This document discusses integrating risk management with earned value management. It provides several key steps:
1. Physically connect risk management tasks to the integrated master schedule and work breakdown structure to ensure risks are planned and tracked.
2. Start by identifying risks and owners, then analyze probability and impact to determine mitigation owners and plans.
3. Track risk status using the same processes as earned value, such as percent complete. Analyze impacts and make control decisions based on integrated data.
The goal is to ensure risks are planned like any other task and progress is measured alongside cost and schedule performance to aid management decisions. Monte Carlo analysis can also model schedule risk using probability distributions.