SlideShare a Scribd company logo
Knowing how our project is performing means knowing how our Cost,
Schedule, and Technical Performance is performing according to Plan.
Performance measurement is one of 5 Immutable Principles of Project Success
5 Process Areas of any Successful Project
                                  
           Identify Capabilities   Elicit Technical &
        needed to achieve the      Operational Requirements
      project objectives or the
      particular end state for a   needed for the system
              specific scenario.   capabilities to be fulfilled.

                      Apply Continuous Risk
                       Management to each
                Performance Based Management
                          process area
         Execute Performance       Establish Performance
        Measurement Baseline       Measurement Baseline time–
       activities while assuring   phased network of work
      technical performance is     activities describing the
                            met    work to be performed

                                  
All Successful Projects Are Based On
5 Immutable Principles † …
                                                                          1. What Does DONE Look
                                                                             Like?
                                                                          2. What is the path to
                                                                             DONE?
                                                                          3. Do We Have Enough
                                                                             Time, Resources, And
                                                                             Money To Get To DONE?
                                                                          4. What Impediments Will
                                                                             We Encounter Along The
                                                                             Way To DONE?
                                                                          5. How Do We Know We
                                                                             Are Making Progress
5 Immutable Principles of Project Management, Glen B. Alleman, Carnegie
Mellon Silicon Valley, January 31st and February 1st, 2011                   Toward DONE?             3/22
We Need To Address All Aspects of Project
                  Success†
                         By their very nature, Programs are risky.
     The
                         Successful program management is risk management.
  Situation
                         Program management must be about avoiding surprises.
                         Traditional program management assumes technical and
    The
                          program processes drive outcomes.
  Problem
                         Focusing on process alone has failed in the past.
                         Program management is about avoiding surprises.
 The Need
                         Measures of physical percent complete are mandatory.
                         Organizations execute projects.
    The
                         Adapting the organization culture to the project paradigm
   Context
                          increases the probability of success.
                         Look to the final and intermediate outcomes as measures
    The
                          of increasing the probability of success.
   Solution
                         Earned Value Management reveals surprises.
† Project Management Case Study, Pierre Bonnal, CNAM IIM MBA Program, June 2004
                                                                                      4/22
   We need a plan to make progress against,
    without a planned measure of progress we’re
    passing time and spending money.
   We need to know what are the units of
    measure toward this plan
   Agile uses working software, which is fine.
   But money is universal unit of measure.
   Measuring progress by earning value of the
    product is a really good measure.
Earned Value is not business Value, that is different measure
 If the performance of our
  project is like cycling, then
  we plan to ride at a planned
  pace – say 20 mph.
 If our group maintains the
  target pace of 20 mph they
  can look at their watches to
  determine if we’re on pace
  to complete our 40 mile ride
  in 2 hours.
 30 minutes into the ride we’re still all riding as a group. Nice
  sustainable pace, we’ll make the 40 miles in our planned
  time – no problems so far.
   But some of us are starting to get
    tired. We’re falling to the back of
    pace line.
   Instead of our planned 20 mph,
    we’ve dropped to 19 mph, still
    moving along pretty well, but a gap
    is starting to open up.
   As time passes this gap is opening more – we’re falling off the
    back of pace line – and we’re gonna get dropped if we don’t do
    something soon.
   We’re Underperforming to our Plan
     For the invested effort (ACWP) we’re under delivering value (BCWP)
      against our planned value (BCWS).
  If we keep riding at our 19 mph pace,
   the gap will continue to open and
   we’ll soon be all alone.
 Our planned performance (BCWS) has
   fallen off the actual pace (BCWP) and
   we need to do something about it,
   and we need to do it fast.
 If we can get back on pace (BCWP) – go back to our planned 20
  mph – this will be good, but the gap that opened up will
  remain (SPI < 1.0).
 We’ll still have the gape between us and the peloton.
 Our riding group is now far ahead.
 We’re not falling further behind, but we’re still behind.
 We’ll need to pick up the pace (SPI > 1.0).
   In order to close the gap,
    riding at our planned 20
    mph pace is not enough.
   We have to ride faster –
    say a 22 mph to close the
    gap to rejoin the peloton.
   Let’s assume we have the strength, skills, stamina, and
    mental fortitude needed to pick up the pace and ride a 22 mph
    pace to try to regain contact with the group.
   Exactly how to do this will require some thought:
       Simply peddle faster – steady increase in effort.
       Sprint to close the gap on an uphill section.
       Ride faster down hill.
       Find someone to pull us to the Peloton in a draft.
 In order to close the gap,
  we need to find the
  needed actions that put
  us back on pace – 20 mph.
 But no matter how we
  need to ride faster – at
  22mph.
 Two things are actually needed:
     Close the gap – ride at 22 mph to regain contact.
     Once reconnected with the group, keep on planned pace –
      maintain 20 mph.
   Easy in concept – hard in the execution.
Lots of concurrent activities
The planned pace is BCWS for the group and for individual “packages of work”
The actual pace is BCWP for the group and for the individual “packages of work”
The work effort needed to ride at the planed pace is ACWP.
The effort need to close the gap for the group and the individual TCPI.
   Budgeted Cost for Work Scheduled (BCWS)
     The planned cost in hours and / or dollars.
   Budget Cost of Work Performed (BCWP)
     The planned value of the work delivered.
     When BCWS = BCWP we’re staying with the Peloton.
     This is the “Earned Value” over the period of
      performance.
   Actual Cost of Work Performed (ACWP)
     The cost in dollars or hours to “earn” the Earned Value
      (BCWP).
BCWS
   BCWP
   ACWP
     The same work component is in all three Earned
                   Value variables
† CPM–300: Principles of Earned Value Implementation, Lesson E: Developing the Performance
  Measurement Baseline, Dennis W. White, IPMC 2002 Fall Conference, Professional Education Program.
Time
              Now
We’ve spent
                                                 Planned Cost
more than
 planned                                         Actual Costs

                                        Measuring budget
                                        performance is useful for the
COST




                         Spending Gap   financial staff.
$                                       But program managers need
                                        insight into the delivery of
                                        technical value.
                                        So measuring cost variance is
                                        not that useful without know
                                        technical progress.
               TIME

              Time Now
Time
            Now
                                                Planned Costs
       We’ve made less
        progress than                           Actual Costs
           planned                              Earned Value

                                        It’s the Earned Value
COST




                                        measurement we’re after.
$                                       We need to earn our budgeted
                         Progress Gap   cost.
                                        The EV represents the
                                        delivered value to the
                                        customer, not just the
                                        consumption of resources.
              TIME
                                        But the technical performance
                                        is still missing
            Time Now
EAC: Estimate at Complete

                                                                  TAB: Total Allocated Budget
              Management Reserve
                                                                  BAC: Budget at Complete
                                     PMB
                                                                      The Performance
                                                                    Measurement Baseline
           Schedule Variance                                       (PMB) represents of the
                                            Cost
                                                                    program “on baseline”
$            ACWP
                                          Variance




    BCWS

                            BCWP


                     time          Time              Completion
                                   Now                 Date
TPM
                                                        Upper Limit
                                    Planned Profile
                                                                          Current Estimate

                                      Planned Value
Mean To Between Failure




                                                                             Threshold


                                        Variance          Lower Limit



                                     Achieved to Date


                                                                        Milestones

                           Time = Program Maturity
   When a gap opens in cost or schedule, it
    needs to be closed.
   Knowing the CPI and SPI is necessary but not
    sufficient.
   We need to know how much better we must
    perform to close the gap:
     Have much faster do we need to ride to get back
      to the Peloton?
     How much more efficient do we need to be for
      each dollar spent to get back on schedule?
   The To Complete Performance Index (TCPI)
    index states how much better we need to
    perform to close the gap:
           BAC  BCWP
    TCPI 
           EAC  ACWP

   The TCPI is an indicator of how our
    performance needs to improve to close the
    gap between the planned performance and
    the actual performance.
   If the TCPI is > 1.0 something has to change
    to stay on schedule and budget:
     Reduce scope – do less work (BCWP) for the same
      effort.
     Reduce rework – reduce breakage
     Increase efficiency – do more work (BCWP) with
      the same (ACWP).
   When a gap opens …
     Getting back on the original
      plan (pace) is necessary but
      not sufficient.
     We have to perform better
      (faster than plan) in order to
      close any gaps that opened
      while we were falling
      behind.
   Knowing the level to which we need to perform to
    close the gap is the To Complete Performance
    Index (TCPI) …
     Being able to perform at this level requires we
      understand what went wrong and how to fix it.
Performance Based Management
 Puts You On the Road to Success …




What does done look like?

How do we get there?

Are there enough resources?

What are impediments to progress?

How do we measure progress?

More Related Content

What's hot

Control systems
Control systemsControl systems
Control systems
Glen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
Glen Alleman
 
Lifecycle
LifecycleLifecycle
Lifecycle
Glen Alleman
 
Critical Success Factors for ERP
Critical Success Factors for ERPCritical Success Factors for ERP
Critical Success Factors for ERP
Glen Alleman
 
Ev+agile=success (final v2)
Ev+agile=success (final v2)Ev+agile=success (final v2)
Ev+agile=success (final v2)Glen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
Glen Alleman
 
Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)
Glen Alleman
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
Glen Alleman
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
Glen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
Glen Alleman
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
Glen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
Glen Alleman
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)
Glen Alleman
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management Guidance
Glen Alleman
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable Principles
Glen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
Glen Alleman
 
Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut Shell
Glen Alleman
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
Glen Alleman
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principles
Glen Alleman
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
Glen Alleman
 

What's hot (20)

Control systems
Control systemsControl systems
Control systems
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Lifecycle
LifecycleLifecycle
Lifecycle
 
Critical Success Factors for ERP
Critical Success Factors for ERPCritical Success Factors for ERP
Critical Success Factors for ERP
 
Ev+agile=success (final v2)
Ev+agile=success (final v2)Ev+agile=success (final v2)
Ev+agile=success (final v2)
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 
Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)Immutable principles of project management (utah pmi)(v1)(no exercise)
Immutable principles of project management (utah pmi)(v1)(no exercise)
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management Guidance
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable Principles
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut Shell
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
Five immutable principles
Five immutable principlesFive immutable principles
Five immutable principles
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 

Similar to The simple problem of schedule performance indices

The Synergistic Nature of PI Objectives
The Synergistic Nature of PI ObjectivesThe Synergistic Nature of PI Objectives
The Synergistic Nature of PI Objectives
Charlene Cuenca
 
Five immutable principles of project success
Five immutable principles of project successFive immutable principles of project success
Five immutable principles of project success
Glen Alleman
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
Glen Alleman
 
Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentation
Glen Alleman
 
Lessons from the Cornish Software Mines
Lessons from the Cornish Software MinesLessons from the Cornish Software Mines
Lessons from the Cornish Software Mines
allan kelly
 
Del
DelDel
IIIT Guest Talk 0512
IIIT Guest Talk 0512IIIT Guest Talk 0512
IIIT Guest Talk 0512
Vasantha Gullapalli
 
Commissioning for Profit, Performance and Windsurfing Bomex 2016
Commissioning for Profit, Performance and Windsurfing Bomex 2016  Commissioning for Profit, Performance and Windsurfing Bomex 2016
Commissioning for Profit, Performance and Windsurfing Bomex 2016
Murray Guy
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
Glen Alleman
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Cha3 F&B Fun
Cha3 F&B FunCha3 F&B Fun
Cha3 F&B Fun
Dean Louie
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayneNASAPMC
 
5 immutable principles webinar
5 immutable principles webinar5 immutable principles webinar
5 immutable principles webinar
Glen Alleman
 
Lean Administration And Fast Closing
Lean Administration And Fast ClosingLean Administration And Fast Closing
Lean Administration And Fast Closingggiacoma
 
Agile Improvement Method - Andrew Griffits (Lamri)
Agile Improvement Method - Andrew Griffits (Lamri)Agile Improvement Method - Andrew Griffits (Lamri)
Agile Improvement Method - Andrew Griffits (Lamri)Paula Gomes
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
Glen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
Glen Alleman
 
Earned value
Earned valueEarned value
Earned value
Dr Ezzat Mansour
 
You don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmYou don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pm
Glen Alleman
 

Similar to The simple problem of schedule performance indices (20)

The Synergistic Nature of PI Objectives
The Synergistic Nature of PI ObjectivesThe Synergistic Nature of PI Objectives
The Synergistic Nature of PI Objectives
 
Five immutable principles of project success
Five immutable principles of project successFive immutable principles of project success
Five immutable principles of project success
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentation
 
Lessons from the Cornish Software Mines
Lessons from the Cornish Software MinesLessons from the Cornish Software Mines
Lessons from the Cornish Software Mines
 
Del
DelDel
Del
 
IIIT Guest Talk 0512
IIIT Guest Talk 0512IIIT Guest Talk 0512
IIIT Guest Talk 0512
 
Commissioning for Profit, Performance and Windsurfing Bomex 2016
Commissioning for Profit, Performance and Windsurfing Bomex 2016  Commissioning for Profit, Performance and Windsurfing Bomex 2016
Commissioning for Profit, Performance and Windsurfing Bomex 2016
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Cha3 F&B Fun
Cha3 F&B FunCha3 F&B Fun
Cha3 F&B Fun
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayne
 
5 immutable principles webinar
5 immutable principles webinar5 immutable principles webinar
5 immutable principles webinar
 
Lean Administration And Fast Closing
Lean Administration And Fast ClosingLean Administration And Fast Closing
Lean Administration And Fast Closing
 
Agile Improvement Method - Andrew Griffits (Lamri)
Agile Improvement Method - Andrew Griffits (Lamri)Agile Improvement Method - Andrew Griffits (Lamri)
Agile Improvement Method - Andrew Griffits (Lamri)
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Earned value
Earned valueEarned value
Earned value
 
You don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmYou don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pm
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
Glen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
Glen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
Glen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
Glen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
Glen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
Glen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
Glen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
Glen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
Glen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
Glen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
Glen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
Glen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
Glen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
Glen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
Glen Alleman
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
Glen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 

Recently uploaded

Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 

Recently uploaded (20)

Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 

The simple problem of schedule performance indices

  • 1. Knowing how our project is performing means knowing how our Cost, Schedule, and Technical Performance is performing according to Plan. Performance measurement is one of 5 Immutable Principles of Project Success
  • 2. 5 Process Areas of any Successful Project   Identify Capabilities Elicit Technical & needed to achieve the Operational Requirements project objectives or the particular end state for a needed for the system specific scenario. capabilities to be fulfilled. Apply Continuous Risk Management to each  Performance Based Management process area Execute Performance Establish Performance Measurement Baseline Measurement Baseline time– activities while assuring phased network of work technical performance is activities describing the met work to be performed  
  • 3. All Successful Projects Are Based On 5 Immutable Principles † … 1. What Does DONE Look Like? 2. What is the path to DONE? 3. Do We Have Enough Time, Resources, And Money To Get To DONE? 4. What Impediments Will We Encounter Along The Way To DONE? 5. How Do We Know We Are Making Progress 5 Immutable Principles of Project Management, Glen B. Alleman, Carnegie Mellon Silicon Valley, January 31st and February 1st, 2011 Toward DONE? 3/22
  • 4. We Need To Address All Aspects of Project Success†  By their very nature, Programs are risky. The  Successful program management is risk management. Situation  Program management must be about avoiding surprises.  Traditional program management assumes technical and The program processes drive outcomes. Problem  Focusing on process alone has failed in the past.  Program management is about avoiding surprises. The Need  Measures of physical percent complete are mandatory.  Organizations execute projects. The  Adapting the organization culture to the project paradigm Context increases the probability of success.  Look to the final and intermediate outcomes as measures The of increasing the probability of success. Solution  Earned Value Management reveals surprises. † Project Management Case Study, Pierre Bonnal, CNAM IIM MBA Program, June 2004 4/22
  • 5. We need a plan to make progress against, without a planned measure of progress we’re passing time and spending money.  We need to know what are the units of measure toward this plan  Agile uses working software, which is fine.  But money is universal unit of measure.  Measuring progress by earning value of the product is a really good measure. Earned Value is not business Value, that is different measure
  • 6.  If the performance of our project is like cycling, then we plan to ride at a planned pace – say 20 mph.  If our group maintains the target pace of 20 mph they can look at their watches to determine if we’re on pace to complete our 40 mile ride in 2 hours.  30 minutes into the ride we’re still all riding as a group. Nice sustainable pace, we’ll make the 40 miles in our planned time – no problems so far.
  • 7. But some of us are starting to get tired. We’re falling to the back of pace line.  Instead of our planned 20 mph, we’ve dropped to 19 mph, still moving along pretty well, but a gap is starting to open up.  As time passes this gap is opening more – we’re falling off the back of pace line – and we’re gonna get dropped if we don’t do something soon.  We’re Underperforming to our Plan  For the invested effort (ACWP) we’re under delivering value (BCWP) against our planned value (BCWS).
  • 8.  If we keep riding at our 19 mph pace, the gap will continue to open and we’ll soon be all alone.  Our planned performance (BCWS) has fallen off the actual pace (BCWP) and we need to do something about it, and we need to do it fast.  If we can get back on pace (BCWP) – go back to our planned 20 mph – this will be good, but the gap that opened up will remain (SPI < 1.0).  We’ll still have the gape between us and the peloton.  Our riding group is now far ahead.  We’re not falling further behind, but we’re still behind.  We’ll need to pick up the pace (SPI > 1.0).
  • 9. In order to close the gap, riding at our planned 20 mph pace is not enough.  We have to ride faster – say a 22 mph to close the gap to rejoin the peloton.  Let’s assume we have the strength, skills, stamina, and mental fortitude needed to pick up the pace and ride a 22 mph pace to try to regain contact with the group.  Exactly how to do this will require some thought:  Simply peddle faster – steady increase in effort.  Sprint to close the gap on an uphill section.  Ride faster down hill.  Find someone to pull us to the Peloton in a draft.
  • 10.  In order to close the gap, we need to find the needed actions that put us back on pace – 20 mph.  But no matter how we need to ride faster – at 22mph.  Two things are actually needed:  Close the gap – ride at 22 mph to regain contact.  Once reconnected with the group, keep on planned pace – maintain 20 mph.  Easy in concept – hard in the execution.
  • 11. Lots of concurrent activities The planned pace is BCWS for the group and for individual “packages of work” The actual pace is BCWP for the group and for the individual “packages of work” The work effort needed to ride at the planed pace is ACWP. The effort need to close the gap for the group and the individual TCPI.
  • 12. Budgeted Cost for Work Scheduled (BCWS)  The planned cost in hours and / or dollars.  Budget Cost of Work Performed (BCWP)  The planned value of the work delivered.  When BCWS = BCWP we’re staying with the Peloton.  This is the “Earned Value” over the period of performance.  Actual Cost of Work Performed (ACWP)  The cost in dollars or hours to “earn” the Earned Value (BCWP).
  • 13. BCWS BCWP ACWP The same work component is in all three Earned Value variables † CPM–300: Principles of Earned Value Implementation, Lesson E: Developing the Performance Measurement Baseline, Dennis W. White, IPMC 2002 Fall Conference, Professional Education Program.
  • 14. Time Now We’ve spent Planned Cost more than planned Actual Costs Measuring budget performance is useful for the COST Spending Gap financial staff. $ But program managers need insight into the delivery of technical value. So measuring cost variance is not that useful without know technical progress. TIME Time Now
  • 15. Time Now Planned Costs We’ve made less progress than Actual Costs planned Earned Value It’s the Earned Value COST measurement we’re after. $ We need to earn our budgeted Progress Gap cost. The EV represents the delivered value to the customer, not just the consumption of resources. TIME But the technical performance is still missing Time Now
  • 16. EAC: Estimate at Complete TAB: Total Allocated Budget Management Reserve BAC: Budget at Complete PMB The Performance Measurement Baseline Schedule Variance (PMB) represents of the Cost program “on baseline” $ ACWP Variance BCWS BCWP time Time Completion Now Date
  • 17. TPM Upper Limit Planned Profile Current Estimate Planned Value Mean To Between Failure Threshold Variance Lower Limit Achieved to Date Milestones Time = Program Maturity
  • 18. When a gap opens in cost or schedule, it needs to be closed.  Knowing the CPI and SPI is necessary but not sufficient.  We need to know how much better we must perform to close the gap:  Have much faster do we need to ride to get back to the Peloton?  How much more efficient do we need to be for each dollar spent to get back on schedule?
  • 19. The To Complete Performance Index (TCPI) index states how much better we need to perform to close the gap: BAC  BCWP TCPI  EAC  ACWP  The TCPI is an indicator of how our performance needs to improve to close the gap between the planned performance and the actual performance.
  • 20. If the TCPI is > 1.0 something has to change to stay on schedule and budget:  Reduce scope – do less work (BCWP) for the same effort.  Reduce rework – reduce breakage  Increase efficiency – do more work (BCWP) with the same (ACWP).
  • 21. When a gap opens …  Getting back on the original plan (pace) is necessary but not sufficient.  We have to perform better (faster than plan) in order to close any gaps that opened while we were falling behind.  Knowing the level to which we need to perform to close the gap is the To Complete Performance Index (TCPI) …  Being able to perform at this level requires we understand what went wrong and how to fix it.
  • 22. Performance Based Management Puts You On the Road to Success … What does done look like? How do we get there? Are there enough resources? What are impediments to progress? How do we measure progress?