This document provides an overview of guidelines for overhead line design, including both AC and DC line design. For AC line design, it discusses electrical characteristics such as resistance, inductance and capacitance and how to optimize them. It also covers mechanical considerations, thermal rating, planning requirements and objective indicators for determining the best design. For DC line design, it discusses electrical characteristics like resistance and power transfer, as well as corona power loss. The document provides information on a variety of factors to consider for optimizing overall overhead line design.
The document mentions the following with tentative quantities:
1. List of 17 nos. of main equipment
2. List of 15 nos. of miscellaneous equipment
3. List of 16 nos. of civil works required
4. List of 8 nos. of lattice type equipment
5. List of 11 nos. of foundations required
MV Switchgear provides centralized control and protection of medium-voltage power equipment and circuits in industrial, commercial, and utility installations involving generators, motors, feeder circuits, and transmission and distribution lines.
The document contains electrical parameters and power loss calculations for three different transmission line configurations transmitting 40 MW of power: a 33kV double circuit line, a 66kV line, and a 132kV line. It compares the current, conductor type, resistance, distance, power loss in Watts, and percentage power losses for each configuration using both 261 sqmm and 484 sqmm conductors over a 1 km distance. The percentage power losses are highest for the 33kV line at 0.375% and reduce progressively for the 66kV and 132kV lines.
Tan delta is the insulation power factor & is equal to the ratio of power dissipated in the insulation in watts to the product of effective voltage & current in volt ampere when tested under sinusoidal voltage.
Cables are often the last component considered during system design even if in many situations cables are the true system’s lifeline: if a cable fails, the entire system may stop. Cable reliability is therefore extremely important, then a cable system should be engineered to last the life of the system in the installation environment for the required application. Environments in which cable systems are being used are often challenging, as extreme temperatures, chemicals, abrasion, and extensive flexing. These variables have a direct impact on the materials used for cable insulation and jacketing as well as the construction of the cable. Using a systematic approach will help ensure that designer select the best cable for the required application in the installation environment. This lessons will provide students main guidelines for perform this approach.
Cable sizing to withstand short-circuit current - ExampleLeonardo ENERGY
This document provides an example calculation of short circuit current for a power cable network. It first outlines the main design criteria for rating cable withstand for short circuit stresses. It then describes four methods for calculating short circuit current - ohmic, infinite bus, per unit and MVA methods. The example focuses on using the MVA method, providing equations and steps for calculating the equivalent short circuit power at different points in the network and converting this to a symmetrical fault current value. Resistances and reactances of cable sections are also included.
This document discusses high voltage substation design, applications, and considerations. It provides an overview of substation basics, electrical configurations, physical design, protection and controls, and coordination of design and construction. The presentation covers typical substation voltage levels, configurations such as ring bus and breaker-and-a-half, factors to consider in the design process such as service conditions and studies required, and reliability comparisons of different configurations. Design guidelines for spacing and clearances are also presented.
Rapport du CIGRE : Innovative solutions for overhead lines supports version-i...RTE
This document discusses innovative solutions for overhead line supports that balance functionality and aesthetics. It summarizes work by CIGRE Working Group B2.08 on this topic. The document outlines the evolution of overhead line tower design from early functional structures to more recent designs that integrate towers into the landscape or transform them into works of art. Case studies are presented from Finland, Denmark, France, and Iceland showcasing unique designs for specific locations that blend engineering and design considerations.
The document mentions the following with tentative quantities:
1. List of 17 nos. of main equipment
2. List of 15 nos. of miscellaneous equipment
3. List of 16 nos. of civil works required
4. List of 8 nos. of lattice type equipment
5. List of 11 nos. of foundations required
MV Switchgear provides centralized control and protection of medium-voltage power equipment and circuits in industrial, commercial, and utility installations involving generators, motors, feeder circuits, and transmission and distribution lines.
The document contains electrical parameters and power loss calculations for three different transmission line configurations transmitting 40 MW of power: a 33kV double circuit line, a 66kV line, and a 132kV line. It compares the current, conductor type, resistance, distance, power loss in Watts, and percentage power losses for each configuration using both 261 sqmm and 484 sqmm conductors over a 1 km distance. The percentage power losses are highest for the 33kV line at 0.375% and reduce progressively for the 66kV and 132kV lines.
Tan delta is the insulation power factor & is equal to the ratio of power dissipated in the insulation in watts to the product of effective voltage & current in volt ampere when tested under sinusoidal voltage.
Cables are often the last component considered during system design even if in many situations cables are the true system’s lifeline: if a cable fails, the entire system may stop. Cable reliability is therefore extremely important, then a cable system should be engineered to last the life of the system in the installation environment for the required application. Environments in which cable systems are being used are often challenging, as extreme temperatures, chemicals, abrasion, and extensive flexing. These variables have a direct impact on the materials used for cable insulation and jacketing as well as the construction of the cable. Using a systematic approach will help ensure that designer select the best cable for the required application in the installation environment. This lessons will provide students main guidelines for perform this approach.
Cable sizing to withstand short-circuit current - ExampleLeonardo ENERGY
This document provides an example calculation of short circuit current for a power cable network. It first outlines the main design criteria for rating cable withstand for short circuit stresses. It then describes four methods for calculating short circuit current - ohmic, infinite bus, per unit and MVA methods. The example focuses on using the MVA method, providing equations and steps for calculating the equivalent short circuit power at different points in the network and converting this to a symmetrical fault current value. Resistances and reactances of cable sections are also included.
This document discusses high voltage substation design, applications, and considerations. It provides an overview of substation basics, electrical configurations, physical design, protection and controls, and coordination of design and construction. The presentation covers typical substation voltage levels, configurations such as ring bus and breaker-and-a-half, factors to consider in the design process such as service conditions and studies required, and reliability comparisons of different configurations. Design guidelines for spacing and clearances are also presented.
Rapport du CIGRE : Innovative solutions for overhead lines supports version-i...RTE
This document discusses innovative solutions for overhead line supports that balance functionality and aesthetics. It summarizes work by CIGRE Working Group B2.08 on this topic. The document outlines the evolution of overhead line tower design from early functional structures to more recent designs that integrate towers into the landscape or transform them into works of art. Case studies are presented from Finland, Denmark, France, and Iceland showcasing unique designs for specific locations that blend engineering and design considerations.
COVERS THE LAYOUT AVAILABLE FOR ADOPTION WITH AN EYE ON EASY MAINTENANCE .The layouts were evolved by the author and his associate for use by power boards
This document provides details on substation layout and busbar arrangements. Part A discusses substation layout, including a single line diagram and descriptions of common switchyard accessories like lightning arrestors, CVTs, isolators, circuit breakers, transformers, and other equipment. It also covers PLCC and SCADA systems. Part B covers various busbar arrangements like the single bus system, double bus system, one and a half breaker system, and ring main bus system. It discusses the advantages and disadvantages of each configuration. In summary, the document is a technical report that outlines and compares different substation and busbar designs.
This document summarizes a seminar presentation on transmission line maintenance techniques in India. It provides an overview of extra high voltage alternating current (EHVAC) transmission line maintenance in India, including methods such as predictive maintenance using thermography and insulator testing, as well as preventive maintenance techniques including cold line maintenance (with the line de-energized) and live line maintenance (with the line energized). It describes some of the specific maintenance works that can be done using live line techniques, and discusses the advantages of live line maintenance.
EHV (extra high voltage) AC transmission refers to equipment designed for voltages greater than 345 kV. Higher transmission voltages increase efficiency by reducing transmission losses and current, decrease infrastructure costs, and increase transmission capacity. However, they also present safety and interference risks. New technologies like FACTS (flexible AC transmission systems) help maximize the benefits of EHV transmission by enabling voltage control and power flow management. There is growing support for expanding national EHV transmission grids to facilitate large-scale renewable energy integration and inter-regional power sharing.
Uso de cables en alimentadores de MT, “llegadas complicadas”
Cálculo de “ampacidad” de cables en régimen permanente
- Cálculo de resistencias térmicas
- Corrientes inducidas por pantalla
Estudio detallado de corrientes inducidas
Corrientes y voltajes inducidos
Transposición de pantallas
Expresiones para transferencia de calor son correlaciones
Pérdidas en pantallas :Existen dos casos básicos
Pantalla aterrizada a un lado
Pantalla aterrizada a ambos lados
En caso de aterrizar ambos extremos, es posible disminuir las corrientes por pantallas:
Usando impedancias (pararrayos)
Buen orden de fases
Disposición (flat, triangular)
Entrecruzamiento de pantallas (cross bonded)
Análisis de corriente por pantallas : Uso de diferentes expresiones para las inductancias mutuas
Se considera el efecto de la resistividad del suelo
Permite un modelamiento más detallado, y una buena base para estudiar el comportamiento en fallas
Practical handbook-for-relay-protection-engineersSARAVANAN A
The ‘Hand Book’ covers the Code of Practice in Protection Circuitry including standard lead and device numbers, mode of connections at terminal strips, colour codes in multicore cables, Dos and Donts in execution. Also, principles of various protective relays and schemes including special protection schemes like differential,
restricted, directional and distance relays are explained with sketches. The norms of protection of generators, transformers, lines & Capacitor Banks are also given.
Underground cables consist of one or more insulated conductors surrounded by protective layers. They are used to transmit electric power underground, which ensures continuous power supply with less maintenance compared to overhead lines. Common types include low, high, and extra high tension cables. Cables have conducting cores insulated and surrounded by a metallic sheath, bedding, armouring and serving for protection. Screened and belted cables are used for 3-phase underground transmission up to 66kV, while pressure cables are used above 66kV.
This guide presents a methodology based on standard PN-IEC 60354 to check overloading capacity of transformers. Main changes versus standard PN-71/E-81000 are discussed and step by step examples are given. An essential advantage of the recommended methods of verification of overloading capacity of transformers is that the size and cooling modes of transformers are considered.
This document provides an overview of electrical substations, including their classification, components, and specifications. It discusses the different types of substations based on voltage levels, configuration, and application. It also describes the primary functions and components of outdoor switchyards, including incoming and outgoing lines, transformers, circuit breakers, and earthing systems. Clearance requirements and specifications for indoor electrical panels, busbars, grounding, and cabling are also outlined.
This document discusses transformer vector groups and the phase shift between primary and secondary currents. It begins by introducing transformer basics like magnetically coupled circuits and phase relationships between voltages. Diagrams show how polarity markings and connections determine the vector group. Specific examples analyze the Yd1 and Yd11 vector groups in detail, showing how primary and secondary phase currents are related for both positive and negative sequence components. Tables summarize the results, and shortcuts are provided for identifying the vector group from winding configurations.
Design of substation (with Transformer Design) SayanSarkar55
This ppt is made for the subject Machine Design. Here the basic types, equipment, designs of substation is described with the preocess and calculation of designing a transformer also.
This document provides information on the classification, dimensions, and erection of transmission line towers. It classifies towers based on the number of circuits and angle of deviation. It provides the dimensions of different types of towers for various voltages. It describes tower erection methods including the use of templates, probes, and cranes. It discusses tower accessories, insulators, conductor types, hardware, and stringing methods. Safety practices for tower erection and stringing are also outlined.
The key factors that determine tower configuration are:
1. The required insulator assembly length, conductor clearances, and ground wire placement.
2. The tower height is determined by the minimum ground clearance, maximum conductor sag, vertical conductor spacing, and clearance between the ground wire and top conductor.
3. Other factors influencing tower configuration include wind loads, temperature variations, conductor size and material, and span length. Proper configuration ensures safety clearances and allows the transmission line to reliably carry power loads with the required safety factors.
The document provides information on LV switchgear, including its components and essential features. It discusses switchgear equipment such as protection devices, circuit breakers, relays, fuses, switching devices, control and sensing devices. It describes the working of miniature circuit breakers, molded case circuit breakers, relays, current transformers, fuses, overload relays, space heaters, grounding systems, lighting systems, and contactors. The switchgear ensures complete reliability, discrimination, quick operation, provision for manual control and instruments.
Turnkey Solutions – the key to successful projects
----------------------------------------------------------------
EPC Solutions has all it takes to design, construct, and operate turnkey electrical substation solutions that efficiently support the reliable supply of electrical power on all voltage levels: decades of practical experience as a contractor and equipment manufacturer and a vast number of successfully completed projects all over the world, unparalleled expertise in all transmission processes, and proven excellence in project management. A distinguished tradition of innovation in power engineering, customized financing solutions, and outstanding quality standards in all production facilities worldwide round out the picture.
EPCS turnkey solutions for high-voltage substations incorporate the strong performance of one of the world’s leading engineering companies and one-stop supplier of power transmission products, solutions, and services. The scope of services comprises consulting, project management, system planning, engineering, commissioning, and comprehensive after-sales support. Centers of competence and branches all over the world create local value and ensure that EPCS experts are within close reach of every project.Customers worldwide benefit from numerous advantages of high-voltage substations from EPCS:
>One-stop approach comprising all technical, financial, and ecological aspects of the station’s entire life cycle
>Customized solutions based on proven EPCS technologies, even for the most challenging demands
>Freedom from coordination efforts and minimized financial and technical risk
This document discusses cable sizing calculations and techniques. It explains that proper cable sizing is important to ensure efficient, safe and economic transmission of electrical energy without interruptions or exceeding the cable's limits. The document outlines the common steps for cable sizing: 1) gathering data on the cable, load and installation conditions, 2) determining the minimum size based on current capacity, voltage drop, temperature rise and fault impedance, and 3) selecting the optimally sized cable. Several examples are provided to illustrate implementing the cable selection process. Risks of improper sizing like voltage drops, overheating and shorter lifespan are also summarized.
This document discusses transformer protection philosophy and methods. It describes various types of faults that can occur in transformers like ground faults, phase-to-phase faults, interturn faults, and core faults. It also discusses mechanical protections like Buchholz relay, sudden pressure relay, pressure relief valve, and temperature indicators. Electrical protections discussed include biased differential relay protection and harmonic restraint. The document provides details on how these protections work and their settings.
This document discusses the key considerations for designing large-scale solar PV systems. It covers selecting appropriate module, inverter and mounting technologies based on factors like efficiency, temperature coefficient, and warranty. Layout is important to minimize shading effects using optimal tilt angle, orientation and inter-row spacing. The electrical design section explains sizing PV arrays and strings, inverters, cables, switchgear, transformers and setting up the substation for metering and monitoring. The document emphasizes optimizing the overall system design to reduce losses and balance annual energy yield with economic returns.
Power cable selection, cable selection Methodology wessam alaslmi
Cable installation and Selection Methodology according to IEC code supported with an example of how to do so.
Explain what practical environment requires when establishing a new facility requires electricity.
explain the purpose of the selected cable.
explain when to use the cable carrier types.
explain how to carry out calculations of such thing.
COVERS THE LAYOUT AVAILABLE FOR ADOPTION WITH AN EYE ON EASY MAINTENANCE .The layouts were evolved by the author and his associate for use by power boards
This document provides details on substation layout and busbar arrangements. Part A discusses substation layout, including a single line diagram and descriptions of common switchyard accessories like lightning arrestors, CVTs, isolators, circuit breakers, transformers, and other equipment. It also covers PLCC and SCADA systems. Part B covers various busbar arrangements like the single bus system, double bus system, one and a half breaker system, and ring main bus system. It discusses the advantages and disadvantages of each configuration. In summary, the document is a technical report that outlines and compares different substation and busbar designs.
This document summarizes a seminar presentation on transmission line maintenance techniques in India. It provides an overview of extra high voltage alternating current (EHVAC) transmission line maintenance in India, including methods such as predictive maintenance using thermography and insulator testing, as well as preventive maintenance techniques including cold line maintenance (with the line de-energized) and live line maintenance (with the line energized). It describes some of the specific maintenance works that can be done using live line techniques, and discusses the advantages of live line maintenance.
EHV (extra high voltage) AC transmission refers to equipment designed for voltages greater than 345 kV. Higher transmission voltages increase efficiency by reducing transmission losses and current, decrease infrastructure costs, and increase transmission capacity. However, they also present safety and interference risks. New technologies like FACTS (flexible AC transmission systems) help maximize the benefits of EHV transmission by enabling voltage control and power flow management. There is growing support for expanding national EHV transmission grids to facilitate large-scale renewable energy integration and inter-regional power sharing.
Uso de cables en alimentadores de MT, “llegadas complicadas”
Cálculo de “ampacidad” de cables en régimen permanente
- Cálculo de resistencias térmicas
- Corrientes inducidas por pantalla
Estudio detallado de corrientes inducidas
Corrientes y voltajes inducidos
Transposición de pantallas
Expresiones para transferencia de calor son correlaciones
Pérdidas en pantallas :Existen dos casos básicos
Pantalla aterrizada a un lado
Pantalla aterrizada a ambos lados
En caso de aterrizar ambos extremos, es posible disminuir las corrientes por pantallas:
Usando impedancias (pararrayos)
Buen orden de fases
Disposición (flat, triangular)
Entrecruzamiento de pantallas (cross bonded)
Análisis de corriente por pantallas : Uso de diferentes expresiones para las inductancias mutuas
Se considera el efecto de la resistividad del suelo
Permite un modelamiento más detallado, y una buena base para estudiar el comportamiento en fallas
Practical handbook-for-relay-protection-engineersSARAVANAN A
The ‘Hand Book’ covers the Code of Practice in Protection Circuitry including standard lead and device numbers, mode of connections at terminal strips, colour codes in multicore cables, Dos and Donts in execution. Also, principles of various protective relays and schemes including special protection schemes like differential,
restricted, directional and distance relays are explained with sketches. The norms of protection of generators, transformers, lines & Capacitor Banks are also given.
Underground cables consist of one or more insulated conductors surrounded by protective layers. They are used to transmit electric power underground, which ensures continuous power supply with less maintenance compared to overhead lines. Common types include low, high, and extra high tension cables. Cables have conducting cores insulated and surrounded by a metallic sheath, bedding, armouring and serving for protection. Screened and belted cables are used for 3-phase underground transmission up to 66kV, while pressure cables are used above 66kV.
This guide presents a methodology based on standard PN-IEC 60354 to check overloading capacity of transformers. Main changes versus standard PN-71/E-81000 are discussed and step by step examples are given. An essential advantage of the recommended methods of verification of overloading capacity of transformers is that the size and cooling modes of transformers are considered.
This document provides an overview of electrical substations, including their classification, components, and specifications. It discusses the different types of substations based on voltage levels, configuration, and application. It also describes the primary functions and components of outdoor switchyards, including incoming and outgoing lines, transformers, circuit breakers, and earthing systems. Clearance requirements and specifications for indoor electrical panels, busbars, grounding, and cabling are also outlined.
This document discusses transformer vector groups and the phase shift between primary and secondary currents. It begins by introducing transformer basics like magnetically coupled circuits and phase relationships between voltages. Diagrams show how polarity markings and connections determine the vector group. Specific examples analyze the Yd1 and Yd11 vector groups in detail, showing how primary and secondary phase currents are related for both positive and negative sequence components. Tables summarize the results, and shortcuts are provided for identifying the vector group from winding configurations.
Design of substation (with Transformer Design) SayanSarkar55
This ppt is made for the subject Machine Design. Here the basic types, equipment, designs of substation is described with the preocess and calculation of designing a transformer also.
This document provides information on the classification, dimensions, and erection of transmission line towers. It classifies towers based on the number of circuits and angle of deviation. It provides the dimensions of different types of towers for various voltages. It describes tower erection methods including the use of templates, probes, and cranes. It discusses tower accessories, insulators, conductor types, hardware, and stringing methods. Safety practices for tower erection and stringing are also outlined.
The key factors that determine tower configuration are:
1. The required insulator assembly length, conductor clearances, and ground wire placement.
2. The tower height is determined by the minimum ground clearance, maximum conductor sag, vertical conductor spacing, and clearance between the ground wire and top conductor.
3. Other factors influencing tower configuration include wind loads, temperature variations, conductor size and material, and span length. Proper configuration ensures safety clearances and allows the transmission line to reliably carry power loads with the required safety factors.
The document provides information on LV switchgear, including its components and essential features. It discusses switchgear equipment such as protection devices, circuit breakers, relays, fuses, switching devices, control and sensing devices. It describes the working of miniature circuit breakers, molded case circuit breakers, relays, current transformers, fuses, overload relays, space heaters, grounding systems, lighting systems, and contactors. The switchgear ensures complete reliability, discrimination, quick operation, provision for manual control and instruments.
Turnkey Solutions – the key to successful projects
----------------------------------------------------------------
EPC Solutions has all it takes to design, construct, and operate turnkey electrical substation solutions that efficiently support the reliable supply of electrical power on all voltage levels: decades of practical experience as a contractor and equipment manufacturer and a vast number of successfully completed projects all over the world, unparalleled expertise in all transmission processes, and proven excellence in project management. A distinguished tradition of innovation in power engineering, customized financing solutions, and outstanding quality standards in all production facilities worldwide round out the picture.
EPCS turnkey solutions for high-voltage substations incorporate the strong performance of one of the world’s leading engineering companies and one-stop supplier of power transmission products, solutions, and services. The scope of services comprises consulting, project management, system planning, engineering, commissioning, and comprehensive after-sales support. Centers of competence and branches all over the world create local value and ensure that EPCS experts are within close reach of every project.Customers worldwide benefit from numerous advantages of high-voltage substations from EPCS:
>One-stop approach comprising all technical, financial, and ecological aspects of the station’s entire life cycle
>Customized solutions based on proven EPCS technologies, even for the most challenging demands
>Freedom from coordination efforts and minimized financial and technical risk
This document discusses cable sizing calculations and techniques. It explains that proper cable sizing is important to ensure efficient, safe and economic transmission of electrical energy without interruptions or exceeding the cable's limits. The document outlines the common steps for cable sizing: 1) gathering data on the cable, load and installation conditions, 2) determining the minimum size based on current capacity, voltage drop, temperature rise and fault impedance, and 3) selecting the optimally sized cable. Several examples are provided to illustrate implementing the cable selection process. Risks of improper sizing like voltage drops, overheating and shorter lifespan are also summarized.
This document discusses transformer protection philosophy and methods. It describes various types of faults that can occur in transformers like ground faults, phase-to-phase faults, interturn faults, and core faults. It also discusses mechanical protections like Buchholz relay, sudden pressure relay, pressure relief valve, and temperature indicators. Electrical protections discussed include biased differential relay protection and harmonic restraint. The document provides details on how these protections work and their settings.
This document discusses the key considerations for designing large-scale solar PV systems. It covers selecting appropriate module, inverter and mounting technologies based on factors like efficiency, temperature coefficient, and warranty. Layout is important to minimize shading effects using optimal tilt angle, orientation and inter-row spacing. The electrical design section explains sizing PV arrays and strings, inverters, cables, switchgear, transformers and setting up the substation for metering and monitoring. The document emphasizes optimizing the overall system design to reduce losses and balance annual energy yield with economic returns.
Power cable selection, cable selection Methodology wessam alaslmi
Cable installation and Selection Methodology according to IEC code supported with an example of how to do so.
Explain what practical environment requires when establishing a new facility requires electricity.
explain the purpose of the selected cable.
explain when to use the cable carrier types.
explain how to carry out calculations of such thing.
This document discusses transformer design and design parameters. It covers topics such as transformer ratings, core design, insulation coordination, voltages, impedance, forces, losses, temperature limits, and cooling. Standards from organizations like IEEE, ANSI, and NEMA are also referenced. Transformer design involves selecting appropriate ratings and parameters to meet requirements while considering factors like performance, reliability, insulation, cooling, and costs.
Concept of energy transmission & distribution ZunAib Ali
Downlaod is NOW Allowed (08/06/2016)
for more help: email me at zunaib_91@yahoo.com
Purpose of Electrical Transmission System
Main Parts of Power System
One-Line Diagram of Generating Station
Main Parts of Generating Station
Components of a Transmission Line
Getting the Most out of your Electrical Roommichaeljmack
This document discusses trends in electrical rooms and expectations for equipment. It aims to clarify terms and standards to increase awareness and address common questions about electrical rooms. Integrated switchboards and integrated motor control centers are presented as space-saving alternatives to conventional stick-built designs. Integrated solutions can reduce the electrical room footprint by consolidating components and eliminating unnecessary space. Device-level networking is also discussed as a way to further minimize space by replacing field wiring with communication networks.
Extra high voltage long ac transmission linesShivagee Raj
From economical point of view designing of transmission line system is very important in the electricity supply system. Extra High Voltage Transmission Lines are best suited for transmission of bulk power.
IRJET- Design and Fabrication of a Single-Phase 1KVA Transformer with Aut...IRJET Journal
1) The document describes the design and fabrication of a 1KVA, single-phase shell type transformer with an automatic cooling system. It discusses the core and winding designs based on specifications like voltage and power ratings.
2) A temperature sensor circuit with a thermistor is used to sense the temperature. When the temperature increases above a preset level, a DC fan is automatically switched on to cool the transformer. It is switched off once the temperature decreases.
3) The transformer is designed to output two voltages - 115V and 120V from an input of 230V, without any tapping. This is achieved through appropriate winding designs based on design calculations.
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
The document provides information on designing electrical systems for buildings and industry. It discusses:
- Design methodology including calculating panelboard ampere ratings from load data.
- Electrical wiring specifications and options for supply voltage in residential and commercial buildings.
- Examples of schematics for lighting circuits, socket outlets, and single and three-phase consumer wiring.
- Considerations for designing domestic and industrial electrical systems including load calculations and protection devices.
This document discusses cable monitoring solutions using distributed temperature sensing (DTS) technology to prevent cable failures and optimize power networks. It provides an overview of issues like overheating of buried cables, describes DTS principles and thermal modeling, presents a case study on monitoring a buried cable, discusses further applications like subsea cables and cable tunnels, emphasizes the importance of measurement speed, and introduces Sensornet's DTS product range for cable monitoring.
strain insulator must have considerable mechanical strength as well as the ne...Karthikkumar Shanmugam
When suspension string is used to sustain extraordinary tensile load of conductor it is referred
as string insulator. When there is a dead end or there is a sharp corner in transmission line, thline has to sustain a great tensile load of conductor or strain. A strain insulator must have
considerable mechanical strength as well as the necessary electrical insulating properties.
This document discusses several methods for measuring high DC voltages:
1. Series resistance micrometers measure voltage by passing a known small current through a high-value resistor and measuring the voltage drop, allowing measurement up to 500kV.
2. Resistance potential dividers use two high-value resistors to proportionally step down a high voltage to a measurable level.
3. Generating voltmeters induce a small current proportional to the measured voltage without a direct connection.
4. Sphere gaps measure peak voltages up to 2500kV by measuring the sparkover voltage between two conductive spheres. Atmospheric conditions and spacing accuracy affect measurements.
Presentation Design of Computer aided design of power transformerSMDDTech
The document summarizes the design of a 100 KVA power transformer. It includes the design calculations for the high voltage and low voltage windings, core, tank, and other components. Key specifications calculated include 11,000/433V voltage ratings, 3344 turns for the high voltage winding, 76 turns for the low voltage winding, and a core size of 115mm diameter. Performance metrics like 98.15% efficiency at full load, 3.94% voltage regulation, and total losses of 1561.617W are provided. Dimensions for the transformer tank and cooling system are also listed.
Chapter 4 mechanical design of transmission linesfiraoltemesgen1
This chapter discusses the mechanical design of transmission lines. It covers various topics such as types of conductors, line supports, spacing between conductors, and sag-tension calculations. The key conductors mentioned are copper, aluminum, and steel. Wooden poles, steel tubular poles, reinforced concrete poles, and steel towers are described as the main types of line supports. The document also discusses the effects of wind and ice loading on transmission lines. Sag-tension calculations are explained using catenary curve equations.
The document provides information on transformer design specifications and considerations. It discusses technical specifications for a 500KVA, 3 phase transformer including input/output voltages and power ratings. It also covers initial calculations, losses in transformers, core materials and construction, winding design, insulation, cooling methods, and connection configurations. The goal is to design a transformer that efficiently transfers power while meeting specifications for voltage, current, temperature rise and other factors.
wireless charging of an electrical vechicle 2hari prasad
This document presents a project on wireless power transfer for electric vehicle charging using resonance technique. It discusses the methodology, block diagram, simulation circuit, hardware progress, inverter circuit, transmitter and receiver coil specifications, and future prospects. The project aims to wirelessly charge electric vehicles using resonant inductive coupling between a transmitter coil connected to a high frequency inverter and a receiver coil connected to a rectifier and load. Simulation and hardware results showing voltage and current waveforms are presented.
This document provides details about the design, manufacturing, and testing processes for power transformers. It discusses:
1) The design process, which begins with designing the core and windings based on specifications. Calculations are checked using computer programs.
2) Short circuit strength considerations, including calculating radial and axial forces on windings from leakage flux, and ensuring windings can withstand these forces.
3) Manufacturing of cores from grain-oriented steel, and winding manufacturing steps like paper wrapping conductors and different winding types.
4) Testing includes short circuit testing to prove designs can withstand forces, and ABB has extensively tested transformers.
The document provides highlights and key insights from the DNV Energy Transition Outlook 2021 report. It finds that:
1) Global emissions are not decreasing fast enough to meet Paris Agreement goals, and warming is projected to reach 2.3°C by 2100 despite renewable growth.
2) Electrification is surging, with renewables like solar and wind outcompeting other sources by 2030 and providing over 80% of power by 2050, supported by technologies like storage.
3) Energy efficiency gains lead to flat global energy demand after the 2030s, with a 2.4% annual improvement in energy intensity outpacing economic growth.
Thermography test of electrical panels Thermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panelThermography test of electrical panel
What does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving meanWhat does peak shaving mean
Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide Power System Restoration Guide
Big data analytics Big data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analyticsBig data analytics
Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action SchemeSPS to RAS Special Protection Scheme Remedial Action Scheme
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...Power System Operation
SVC PLUS
Frequency Stabilizer
Frequency and voltage support for dynamic grid stability
SVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer FrequencySVC PLUS Frequency Stabilizer Frequency
What is load management What is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load managementWhat is load management
What does merit order mean What does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order meanWhat does merit order mean
Balancing services help maintain the frequency of the power grid by providing short-term energy or capacity reserves. They include balancing energy, which system operators use to maintain grid frequency, and balancing capacity, which providers agree to keep available. Different balancing services have varying activation speeds to respond to frequency deviations. Harmonization efforts in Europe are working to establish common balancing markets and platforms for cross-border exchange of reserves.
The Need for Enhanced Power System Modelling Techniques & Simulation Tools Power System Operation
The Need for Enhanced Power System Modelling Techniques & Simulation Tools The Need for Enhanced Power System Modelling Techniques The Need for Enhanced Power System Modelling Techniques & Simulation Tools The Need for Enhanced Power System Modelling Techniques & Simulation Tools & Simulation Tools
Power Quality Trends in the Transition to Carbon-Free Electrical Energy SystemPower System Operation
Power Quality
Trends in the Transition to
Carbon-Free Electrical Energy System Carbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy SystemCarbon-Free Electrical Energy System
A Power Purchase Agreement (PPA) is a long-term contract between an electricity generator and purchaser that defines the conditions for the sale of electricity. PPAs provide price stability and help finance renewable energy projects by guaranteeing revenue. There are physical PPAs, which deliver electricity directly, and virtual PPAs, which financially settle the contract without physical delivery. PPAs benefit both renewable developers by enabling project financing, and buyers seeking long-term electricity price certainty and renewable attributes.
Harmonic study and analysis Harmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysisHarmonic study and analysis
What is leakage current testing What is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testingWhat is leakage current testing
SCADA systems are used to monitor and control industrial processes that occur across geographically dispersed locations. They involve remote terminal units collecting field data and sending it back to a central control room via a communications system. This enables operators to view real-time data and remotely control processes from a central location for more efficient, reliable and safer operations. Common applications of SCADA systems include power generation and distribution, manufacturing, water and waste management, and buildings.
International Conference on NLP, Artificial Intelligence, Machine Learning an...gerogepatton
International Conference on NLP, Artificial Intelligence, Machine Learning and Applications (NLAIM 2024) offers a premier global platform for exchanging insights and findings in the theory, methodology, and applications of NLP, Artificial Intelligence, Machine Learning, and their applications. The conference seeks substantial contributions across all key domains of NLP, Artificial Intelligence, Machine Learning, and their practical applications, aiming to foster both theoretical advancements and real-world implementations. With a focus on facilitating collaboration between researchers and practitioners from academia and industry, the conference serves as a nexus for sharing the latest developments in the field.
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
Low power architecture of logic gates using adiabatic techniquesnooriasukmaningtyas
The growing significance of portable systems to limit power consumption in ultra-large-scale-integration chips of very high density, has recently led to rapid and inventive progresses in low-power design. The most effective technique is adiabatic logic circuit design in energy-efficient hardware. This paper presents two adiabatic approaches for the design of low power circuits, modified positive feedback adiabatic logic (modified PFAL) and the other is direct current diode based positive feedback adiabatic logic (DC-DB PFAL). Logic gates are the preliminary components in any digital circuit design. By improving the performance of basic gates, one can improvise the whole system performance. In this paper proposed circuit design of the low power architecture of OR/NOR, AND/NAND, and XOR/XNOR gates are presented using the said approaches and their results are analyzed for powerdissipation, delay, power-delay-product and rise time and compared with the other adiabatic techniques along with the conventional complementary metal oxide semiconductor (CMOS) designs reported in the literature. It has been found that the designs with DC-DB PFAL technique outperform with the percentage improvement of 65% for NOR gate and 7% for NAND gate and 34% for XNOR gate over the modified PFAL techniques at 10 MHz respectively.
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
Understanding Inductive Bias in Machine LearningSUTEJAS
This presentation explores the concept of inductive bias in machine learning. It explains how algorithms come with built-in assumptions and preferences that guide the learning process. You'll learn about the different types of inductive bias and how they can impact the performance and generalizability of machine learning models.
The presentation also covers the positive and negative aspects of inductive bias, along with strategies for mitigating potential drawbacks. We'll explore examples of how bias manifests in algorithms like neural networks and decision trees.
By understanding inductive bias, you can gain valuable insights into how machine learning models work and make informed decisions when building and deploying them.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
5. What is a power line?
• A device to transmit power over distances.
• Design of the line can be tailor made to meet planner’s requirements.
• Load flow depends on R, X and B values.
5
6. LINE MODEL
• Reduce R and L (resistance and inductance)
• Increase C (capacitance)
6
7. Maximise Power Transfer
• Zs is surge impedance
• SIL is the surge impedance loading
• Reduce L and increase C to maximise transfer
L is series
inductance
C is shunt
capacitance
7
VLL is phase to phase
voltage
8. Determination of R, X and B
8
• Resistance is a function of
− Conductor construction material and line length
o Lay ratio, ACSR,AAAC, number of layers, diameter of strands.
− Temperature
o The higher the temperature the higher the resistance
− Current and frequency
o Transformer effect
o Eddy currents.
10. Determination of L
10
• L is a function of Geometric mean radius (GMR) and Geometric mean Distance
(GMD)
• Larger bundle radius and closer phase spacing gives lower L
12. Summary
12
• SIL (L and C) can be varied by
− varying phase spacing closer is better
− Increasing bundle size larger is better
• Resistance can be improved by
− Varying lay ratios per layer (not practical)
− Different materials
− Homogeneous conductors
13. Corona limitations
13
• Corona can produce audible noise under certain weather conditions. This is very
difficult to mitigate. It is desirable to avoid corona inception.
− Smaller bundle radius will reduce corona up to a point.
− Wider phase spacing better
− More sub conductor bundles better.
15. Mechanical considerations
• Wind load is major consideration in tower design
− Less conductors in the bundle the better
− Less ultimate tensile strength (UTS) the better (Lighter strain towers). Higher
tension to increase height.
• Vibration is a function of tension
− Need to design to the recommended T/m ratio
− Small bundle sizes (twin triple), need more care in vibration damping design
• Galloping mitigation needs to be taken into account
− Includes phase configuration
− Pendulum dampers, interphase spacers
15
16. Tower top Geometry
• Tower top geometry design applies to conventional towers with metal surrounded
center phase (tower window) as well as three phases in the same window as is
the case with the cross rope suspension.
• The interaction between the phases as well as the shielding angle for the
conductors needs to be carefully designed to ensure optimal insulation co-
ordination providing the required level of reliability.
18. Thermal loading
• Load at which the safety or annealing criteria of the line is met
− Current at which the height above the ground is in line with regulation
− Height determined by voltage and flashover distance
• Heat Balance equation used.
18
19. Joule and magnetic heating
• Joule dependent on AC resistance and temperature
• Magnetic heating dependent on current and conductor layers.
19
21. Convective cooling
21
• Dependent on
− the conductor diameter (bigger is better)
− Wind speed
− Temperature difference (bigger is better)
− Roughness
22. Templating temperature
22
• Templating temperature is the conductor temperature at which the height above
ground is in accordance with regulation
Conductor
Templating
temperature deg C
Normal
Amps
Emergency
Amps
TERN 50 611 814
TERN 60 784 991
TERN 70 911 1138
TERN 80 1023 1257
ZEBRA 50 642 859
ZEBRA 60 818 1049
ZEBRA 70 963 1203
ZEBRA 80 1080 1325
23. SUMMARY
SIL Corona Mechanical
loading
Thermal
rating
Phase spacing
decrease
Good Bad Good Neutral
Large al
area/cond (less
conductors)
Bad Bad Good Bad
Diameter
Bundle
increase
Good Bad Bad Neutral
High steel
content
Neutral Neutral Bad Good
23
25. Planning requirements
25
• Planners need to specify the following
− Load transfer requirements
− Load profile daily, annual
− Impedance parameters, high and low
− Line Voltage for AC
− Length of line
− Location, start and end points
− Reliability requirements
29. INSULATOR SELECTION
• Location of conductor bundle determined to meet insulation co-ordination
requirements
• Insulator creepage, dry arching distance, basic insulation level (BIL) determined.
− Depends on pollution levels in the line route
• Insulator configuration depends on tower selection, I or V or other.
• Material depends on pollution, vandalism, maintenance.
• Hardware depends on material (corona rings for composite), live line
requirements
• For cross rope towers I string permits less pollution accretion especially from
birds.
30. LIGHTNING CONSIDERATIONS
• Shield angle determination depends on tower type.
− Negative shield angles generally give better performance.
• Tower footing resistance needs to be determined and reduced on the line
− “crows foot”, buried earthwire, bentonite mix
• Note towers with large footprints generally give lower tower footing resistances.
− Cross rope suspensions provide excellent results
• If tower footing resistance still high may consider line surge arresters installed on
certain towers.
• Shield or earth wires are now often OPGW.
− Care to be taken for fault current in the earth wire.
32. Indicator to determine best design
32
• Need to combine
− SIL
− Thermal rating
− Cost initial and life cycle
o (Taking into account corona, magnetic fields, mech loading etc)
33. FACTOR 1 Life Cycle Cost (k1)
33
• Covers determination of optimum aluminium area required. (Kelvin’s law)
• Cost of maintenance (estimate)
• Cost of losses – use system losses not line losses. (Due to power flow in
interconnected system)
34. FACTOR 2 THERMAL (k2)
34
• Cost is directly proportional to Thermal rating
− Higher rating higher initial cost
• A ratio is therefore needed
− Initial cost/MVA thermal (emergency or normal)
• The lower the ratio the better.
35. FACTOR 3 SIL (k3)
35
• The higher the SIL the higher the initial cost (normally)
• Ratio is therefore also required
− Initial cost/MVAsil
36. COMBINATION OF THE FACTORS
36
• Objective Matrix method
− Present practice is given 3/10
− 0 or 10 level is determined (normally trial and error) and a linear
interpolation used.
• ATI = w1k1+w2k2+w3k3
− wn are weighting factors
37. DETERMINING SCORE – NEG SLOPE
Ratio value
S
c
o
r
e
Ratio of current practice
Provides score of 3
3
10
(x1;y1)
(x2;y2)
Assume ratio
value that is ideal.
Score of ideal ratio is 10
Ratio of optionA
Score of
optionA
Y=mx+c
1. For the ratio (LCC, IC/MVA etc),
allocate a score of 3 for the
current practice. This gives point
x1;y1.
2. Assume an ideal ratio that will not
be exceeded. Allocate a score of
10 for this ratio value. This will
provide point x2; y2.
3. Calculate the straight line
equation using these two points.
4. Use the straight line equation to
determine the scores for the
different design options.
5. You now have dimensionless
scores which can be added.
CALCULATION OF SCORE FOR
SITUATIONS WHERE THE LOWER
THE RATIO THE BETTER THE
DESIGN
38. DETERMINING SCORE – POSITIVE SLOPE
Ratio value
S
c
o
r
e 3
10
x1;y1
x2;y2
y=mx+c
Ratio value of current practice
allocated score of 3
Ratio value of ideal design.
Allocated score of 10
Ratio value of optionA
Score of
optionA
1. Calculate the ratio of the current
design option. Allocate it a score of 3
2. Assume an ideal design value and
allocate it a score of 10
3. This provides two points. Calculate
the straight line (y=mx+c) graph
equation from points x1;y1 and x2;y2
4. Using the equation determine the
scores for the other design options.
5. This provides a dimensionless score
which can be added.
CALCULATION OF SCORES WHERE
THE HIGHER THE RATIO THE
BETTER THE DESIGN
41. EXAMPLE LINE
41
− Quad “Zebra” guyed Vee tower
− Triple “Bunting” conductor guyed Vee tower
− Quad “Bunting” cross rope suspension (CRS) tower phase spacing of 6,5m.
− Quad “Rail” conductor with a CRS tower with a 6,5m phase spacing.
− Triple “Bittern” conductor with a CRS tower with a 6,5m phase spacing.
− Quad “Boblink” conductor with a CRS tower with a 6,5m phase spacing.
− Triple “Bersfort” conductor with a CRS tower with a 8,2m phase spacing.
44. FINDINGS/BENEFITS
44
• Tower, foundation, hardware, electrical designers work together with planners
(iterative process)
• Indicator very sensitive and detects errors rapidly
• Line optimisation is possible looking at overall line design.
• Reliability is assumed constant for options
• Cost system is critical
• Most aspects of the line design are taken into account
45. CONCLUSIONS
45
• Line design options can be objectively determined
• ATI is a guide from which options can be finalised.
• Alignment with Planners requirements
48. Power Transfer
x
Pmax
V 2
vd%
100R L
where vd% is the voltage drop expressed as a % of V,
and the equation applies for both 10% and 15% volt drop. {1/sqrt(44) is an approximation of 15/100} and the format
removes the generality of the basic and simple equation.
V=Sending end voltage, pole to ground in kV
Rx=DC Resistance of the conductor in ohm/km
L=Distance in kilometres.
49. DC resistance
• DC resistance not dependent on current
• Dependent on conductor geometry and conductivity of material.
• Dependent on temperature.
50. Effect of conductor radius (TB388)
The higher the conductor diameter and the more sub-conductors in the bundle the more resistant the bundle is to
corona and therefore the designer is more able to raise the voltage to ground and hence increase the power capability
of the line.
51. Corona power loss
225 3 3.05
20log
25
15log n 10log HS dE
P 11 40log mas
Where P is the corona loss is dB above 1 W/m, Emax is the positive polarity maximum bundle gradient in kV/cm, d is the
sub-conductor diameter in cm, n is the number of sub-conductors in the bundle, H is the average conductor height in m
and S is the pole spacing in m.
52. INSULATOR CONSIDERATIONS
• Similar requirements to AC as far as tower window design.
• For glass insulators need germanium glass as normal glass will shatter
− Zinc collar also required
• Creepage larger than for AC
• Space charge considerations as well as uneven pollution on insulator to be
taken into account.
• Composite insulators can be used for AC and DC lighter weight often suit
long insulator installation.
• Porcelain disc are also successfully used.
53. Summary of options
Action Parameter Voltage drop Corona Mechanical loading Thermal rating
+ and - pole spacing
decrease
Neutral Bad Good Neutral
Large Al area/cond (less
conductors)
Good Bad Good Bad
Diameter bundle
increase
Neutral Bad Bad Neutral
High steel content Neutral Neutral Bad Good
56. Optimisation process
• Select voltage (TB388)
• Determine range of conductor, bundle diameter and number of sub-conductors as
well as height above ground and pole spacings that will meet corona limitations
and power flow.
• Determine range of tower, foundation and conductor configurations.
• Finalise by further analysis the most suitable tower, foundation, conductor bundle
option. Recheck with power flow requirements, converter cost and technology.
57. Objective indicator
th
IC
3
MVA
ATIDC w1LCC w2IC* Posscoronal w
ATIdc Appropriate Technology Index for DC lines
LCC is the life cycle cost expressed in terms of a score from 1 to 10 and IC is the initial cost.
Plosscorona is the power loss due tocorona.
IC is the initial cost.
MVAthermal is the thermal rating of the line and depends, as in the AC case, to the templating temperature of theline.
58. Line requirements
• DC voltage (V) 600;700;800 kV
• Number of sub-conductors per pole (N) 4; 5; 6
• Conductor type ACSR
• Line length 1750 km
• Transmitted Power 3000 MW (bipolar)
• Cost of the losses 60 U$/MWh; loss factor =0,5
• Life= 30 years; yearly interest rate= 10%
• Interest during construction 10%; maintenance 2% per year (of initial cost)
63. Purpose
• The purpose of the questionnaire was to compare the work done by WG09
in 1990 to the latest figures as many component costs may have changed.
• The questionnaire was in two parts, the first to compare component costs
of existing projects, the second to compare costs of an actual line with
given parameters.
• The response was generally poor with around 13 respondents compared
with over 100 in 1990.
69. Competitive line costs
• From the graphs, if the conductor cost as a percentage of total line cost is greater
than 10% the cost is likely to be relatively low. The range of percentages in the
examples received indicated that the conductor cost for relatively low cost per km
lines, should vary between 10 and 15%.
• In the previous survey it was found that the conductor cost was 32% of the
material cost which was 63%. This results in 20% of the total line cost. It could
be concluded that the cost/km of lines has increased from 1990 to 2014 in real
terms mainly due to cost of labour and environmental issues.
• A good target for a competitive cost per km line would be that the conductor cost
should be between 15 and 20% in 2014.
70. COMPARISON TO 1991
YEAR
MATERIAL
COSTS
CONSTRUCTION
COSTS
CONDUCTORS SHIELD WIRE INSULATORS TOWERS FOUNDATIONS
For all lines and voltages 1991 63.7 36.3 32.7 3.8 8.1 36.2 19.2
2013 42.4 57.6 31.8 2.7 7.6 46.3 11.6
For all lines up to 150kV 1991 64.3 35.7 31.6 4.1 8.8 36.0 19.5
2013 46.4 53.6 28.6 2.0 7.9 49.6 11.9
For all lines over300kV 1991 62.6 37.4 34.1 3.9 6.9 36.4 18.7
2013 46.8 53.2 35.7 3.0 7.2 42.7 11.4
All single circuit lines 1991 63.6 36.4 33.1 4.2 8.2 35.6 18.8
2013 42.8 57.2 33.4 2.8 6.9 43.7 13.3
All double circuit lines 1991 63.8 36.2 32.0 3.3 7.9 37.1 19.7
2013 31.0 69.0 24.7 2.3 10.6 58.1 4.3
Guyed structure lines 1991 59.6 40.4 32.8 3.2 8.3 36.0 19.8
2013 55.0 45.0 36.5 3.2 6.3 41.3 12.7
Lines with 1 conductor/phase 1991 64.4 35.6 32.2 4.2 8.5 36.3 18.8
2013 38.7 61.3 28.3 2.0 7.8 45.1 16.9
Lines with 2 conductors/phase 1991 64.6 35.4 32.3 4.0 8.1 36.2 19.4
2013 38.0 62.0 32.3 2.3 10.6 48.4 6.3
Lines with 3 conductors/phase 1991 60.8 39.2 35.1 3.7 7.0 40.3 13.8
2013 41.5 58.5 36.6 4.6 6.6 42.6 9.6
Lines with 4 conductors/phase 1991 61.4 38.6 33.4 2.7 7.6 33.4 22.9
2013 56.5 43.5 34.2 3.4 7.9 37.9 16.7
Conductor, shield wire etc % as a function of material costs.
72. Summary of Trends
• Material and construction costs – the trend appears to be that the material cost has reduced as a function of
total cost with the construction cost being the more prevalent cost. This appears to be the case over the entire
range of lines investigated.
• Conductors – in the 2013 cases the steel shield wire is included in the conductor cost. Even with this inclusion,
it appears the conductor cost is generally the same or lower percentage of the total cost as compared to 1991.
• Shield wire – this cost is related to the OPGW cost for 2013 and the steel wire cost for 1991. The sample for
double circuit and single circuit lines for 2013 is very small and therefore cannot be considered to be
representative. However it indicates a similar percentage to the 1991 costs even though the shield wire is more
complicated and expensive in real terms in 2013.
• Insulators – the percentage of total cost spent on insulators seem to be slightly lower than in 1991. This could
be due to the advent of composite insulators which have dropped in price considerably over the years as well as
glass being more competitive with merger of manufacturers.
• Towers – The percentage of the total cost spent on towers seem to be higher than in 1991. This cost includes
the erection cost which could indicate the higher cost of labour which is reflected in the construction cost
compared to material cost. As mentioned previously the environmental constraints on current lines could have
resulted in more angle or strain towers as well as more aesthetically pleasing towers such as the Wintrack
towers.
• Foundations – The percentage of the total cost spent on foundations seems to be lower than is 1991.
This may be due to the higher level of mechanisation and perhaps use of more pile foundations
but this is not confirmed.
73. GUIDE TO OVERALL
LINE DESIGN
EXAMPLES OF OPTIMISATION
GUIDE TO OVERHEAD OHL DESIGN TB 638
77. REFERENCES/
ACKNOWLEDGEMENTS
77
[Stephen 2004] Stephen R. “Use of indicators to optimise design of overhead transmission lines”. Paper330-1
Shanghai Symposium, Cigré 2003. (Held in Lubljana April 4-62004)
[Stephen 2011] Stephen R “Objective detetermination of Optimal power line designs” PhD thesis submitted in 2011
University of Cape Town.
[Muftic]. Muftic D, Bisnath S, Britten A, Cretchley DH, Pillay T,Vajeth R “The Planning design and constructionof
overhead power lines” Published by Crown publications 2005 ISBN 9780620330428
[Southwire] Overhead Conductor Manual First edition copyright1994.
Prof. C.T.Gaunt (UCT) acknowledged for comments andinput.
J. Lindquist AC/DC conversion TB583
Nolasco, Jardini, TB 388