SlideShare a Scribd company logo
Gas Insulated Switchgear?
Gas-Insulated
High-Voltage
Switchgear
(GIS)
What is
It is very much required to establish an electrical substation at
load center. Since, establishing a substation at load center is
quite economical and profitable in many aspects. As it reduces
length of feeders and due to short length feeders, the quality of
voltage regulation improves.
But the main obstruction of establishing a substation at load
center is space. Generally main load center of any place is
situated at very congested place where, sufficient land for
establishing conventional electrical substation is very hardly
available.
This problem can be solved by using Gas Insulated Switchgear
Technology. In this Type of Switchgear, all the necessary
components of switchgear can be assembled in very limited space.
GIS is a kind of Metal enclosed Switchgear.
That means, all the equipments of the Electrical Switchgear are
enclosed by gas tight metal enclosure and SF6 Gas is used as
insulation between live parts of the equipments and earthed metal
enclosure. This type of switchgear, means, and gas insulated
switchgear is available from 12 KV systems to 800 KV system.
For establishing electrical substation in very limited place this type
of SF6 insulated electrical switchgear plays the major role.
Gas insulated components of substation are generally,
Electrical bus bars:
 Electrical Isolators or Disconnectors.
 Circuit Breakers.
 Current Transformers.
 Voltage Transformers.
 Earth Switches.
 Surge Arrestors or Lightning Arresters.
The substation, assembled by gas insulated switchgear, is popularly
known as gas insulated metal enclosed substation (GIMES). GIMES
technology is not very recent invention, it is successfully running
for over thirty years.
In gas insulated medium voltage switchgear, vacuum technology is
used as interrupting purpose and SF6 gas is used as insulation
material. Although for both interruption and insulation, SF6 gas is
used in many medium voltage GIS system. But for such equipments
rated SF6 gas pressures are different for interruption and insulation.
SF6 gas pressure for insulating purpose is generally kept below 2.5
bar whereas SF6 gas pressure for interrupting purpose is ranged
from 5 bar to 7 bar.
As vacuum technology is not available for high voltage, so for GIS or
gas insulated switchgear system above 72.5 KV, only SF6 is used
both for interruption medium and insulation.
There are different types of gas insulated metal enclosed
switchgears available depending upon their constructional feature.
Isolated Phase GIS
In this configuration, each phase of the bay is assembled
separately. That is, for each phase, one pole of circuit breaker, a
single pole of electrical isolator, one phase assembly of current
transformer are assembled together. This type of GIS requires
larger bay width as compared to other gas insulated switchgear
system.
Integrated 3 Phase GIS
In this configuration all three phase of circuit breaker, 3 phases of
disconnectors and three phase current transformer are encapsulated in
an individual metal enclosure. The arrangement forms a three phase
module for the element. The size of this type of module is one third of
the isolated phase GIS.
Hybrid GIS System
It is a suitable combination of isolated phase and three phase common
elements. Here three phase common bus bar system simplifies the
connection from the bus bar. The isolated phase equipment prevents
phase to phase faults. This is an optimum design considering, both facts
in mind, i.e. space requirement and maintenance facility.
Compact GIS
In this GIS or gas insulated switchgear system than one functional
element are encapsulate in a single metal enclosure. For example, in
some design, a three phase circuit breaker, current transformer, earth
switches, even other feeder elements are covered together in a single
metal capsule.
Highly Integrated System
This design was introduced in the year of 2000, where, total substation
equipments are encapsulated together in single enclosure housing.
This single unit gas insulated substation has gained user appreciation as
it is a complete solution for an outdoor substation, in a single unit. As
such, only equipment (HIS) is substitute of a total outdoor switch yard.
◼ Introduction to GIS
◼ Advantages Of SF6-Insulated Installations
◼ Switchgear Characteristic
◼ Surge Arresters
◼ Disconnectors
◼ Earthing Switches
◼ Circuit Breakers
◼ Instrument Transformers for GIS Substations
◼ Tests for GIS
Introduction
◼ At normal atmospheric conditions, the insulation distances
determine the main sizes of the classic distribution substation.
◼ For a long time, the development in substation construction
concentrated simply in combining existing devices to obtain the
arrangement more adequate for exploitation and supply security.
◼ On the other hand, the increasing needs to convey electric energy,
at higher voltages, towards the regions with grand population
density and the industrial centres, causes great difficulties due to
the size of the involved installations.
◼ Official prescriptions and the town-planning requirements
complicate the construction.
Introduction
 Due to the troubles caused by pollution in insulators, the tendency is to build
indoors installations.
◼ However, the cost increasing in construction leads to reduce, as much as
possible, the dimensions of the installation.
◼ Hence, to solve this problem, smaller installations are needed, which
should also comply the following requirements:
◼ They shall be insensible to climatic influences.
◼ They can be raised outdoors, inside a building or underground.
◼ They require reduced maintenance.
◼ They are silent.
◼ They should not generate radioelectric disturbances.
◼ They shall not imply danger for the nearby populated zones.
Introduction
As a solution for this problem, metal-enclosed installations with
SF6 insulation are used.
Introduction
 In this system, the parts of the main current circuit (such as the circuit breaker, the
disconnector, the buses, etc.) are mechanically integrated in a set that can be called
coupling group.
◼ The compact manufacturing and the highly developed wiring technique allow the free
determination of the site, and ensure the independence regarding climatic conditions.
◼ Some possible applications of this very high voltage metal-enclosed stations:
◼ Main distribution stations inside cities.
◼ Main distribution stations for important customers.
◼ Main distribution stations in zones with pollution, salt, or risk of explosion.
 Maindistribution stations with special characteristics(underground
stations, shelters of reinforced concrete, etc.).
◼Classic installation expansion, in case of reduced space.
◼Mobile transformation stations.
Introduction
 The gas-insulated substations utilize the same switchgear of conventional substations,
but with design and characteristics slightly different.
◼ The whole station is integrated inside a grounded aluminium enclosure filled with
SF6, which ensures the insulation to ground.
◼ Diagram of a 220 kV gas-insulated substation.
Introduction
 Fig. presents some basic layouts of the assorted types of gas- insulated
substations, which will vary according to the requirements of each
installation
◼ Introduction to GIS
◼ Advantages Of SF6 - Insulated Installations
◼ Switchgear Characteristic
◼ Surge Arresters
◼ Disconnectors
◼ Earthing Switches
◼ Circuit Breakers
◼ Instrument Transformers for GIS Substations
◼ Tests
Advantages of SF6-Insulated Installations
 Reduced required space
◼ Outlook compatible with surroundings without altering architectural or
natural beauty.
◼ Reduced erection and assembly times.
◼ The installations are dielectrically and totally tested in-site (unlike
conventional substations).
◼ Reduced maintenance and consequently, lower costs.
◼ From 30 kV to 500 kV they might result cheaper than conventional units.
◼ Up to 170 kV, tripolar design is used (three phases in the same casing).
For upper voltages, each phase is separately insulated, enclosed and
compartmentalized.
◼ Introduction to GIS
◼ Advantages Of SF6 - Insulated Installations
◼ Switchgear Characteristic
◼ Surge Arresters
◼ Disconnectors
◼ Earthing Switches
◼ Circuit Breakers
◼ Instrument Transformers for GIS Substations
◼ Tests
Surge Arresters
 When the connection with the network is performed through an overhead
line, the surge arrester is located at the entrance of the gas-insulated
substation.
◼ The surge arrester can be conventional or SF6-insulated.
◼ In this last case, if distances in the substation are higher than the
protection distance of the surge arrester, it is convenient to install,
besides, a surge arrester inside the metal-enclosed substation.
 When the substation is connected to the network through a
high voltage cable, it is advisable to integrate the surge arrester
inside the substation casing.
◼ This advice becomes mandatory if the conductor is longer
than 50 m, or if the substation occupies a very extended surface.
◼ The surge arresters are also encapsulated and their discharge
voltage is lower than in conventional arresters, due to the lack of
pollution and to the direct coupling to the breaking device (not
necessarily connected to the line).
Surge Arresters
Surge Arresters Metallic Casing
 The cylindrical metallic casing is comprised of concentric sheets of
aluminium, welded as a tube.
◼ The clamps are also aluminium pieces.
◼ The rated values of filling pressure (Pats) for the SF6 are 420 540 kPa
at 20 º C.
◼ Ifthe surge arrester needs accessories,such as gas valves, densimeter
ormanometer, discharge counter or breaking disks (pressure lever), they will
be mounted in its top.
◼ As mentioned before, up to 170 kV the three phases are located in the
same casing. For upper voltages, each phase is mounted in individual
compartments.
Surge Arresters Metal-Oxide Disks
 The surge arresters insulated in SF6,
alike conventional arresters, are
constituted by columns with several piled
up metal-oxide disks of variable
resistance.
◼ These columns are concentrically
mounted in the metallic casing.
Surge Arresters Metal-Oxide Disks
 The flat contact surfaces are manufactured with a
conductive
metallic layer and the cylindrical hermetic sides are elaborated
with a layerof passivated crystal (neutral metal that prevents
corrosion).
◼This design allows that the disks can be in direct contact with
the SF6, which increases the capability of heat evacuation
during, for example, repetitive strong discharges.
◼ To avoid the excessive size of surge arresters for voltages
upper than 170 kV, the disks are piled up in three columns,
forming a triangle, electrically connected in series.
◼ Each column consists of fibreglass axles and springs that
compress the disks.
Surge Arresters Metal-Oxide Disks
 A device that evenly distributes the voltage among all disks is located
in the top of the columns.
◼Fig.compares arresters with and without such device.
◼ Introduction to GIS
◼ Advantages Of SF6 - Insulated Installations
◼ Switchgear Characteristic
◼ Surge Arresters
◼ Disconnectors
◼ Earthing Switches
◼ Circuit Breakers
◼ Instrument Transformers for GIS Substations
◼ Tests
Disconnectors
 Slide-in disconnectors are used in gas-insulated
substations, capable to break the capacitive currents that
take place during the coupling manoeuvres in the
installation, and to break commutation currents caused by
changes in the buses configuration.
◼ To optimise the operation of the disconnectors in different
points of the distribution station, the active parts are
encased separately, reducing to minimum the number of
flanged joints.
Disconnectors
 The disconnector consist of the main contact (6) and the casing of the
sliding contact (9), in which interior is located the coupling of the sliding
contact (12).
◼ The conductor is connected to both contacts by sheet contacts.
◼ The sliding contact (12)
is tripolar-operated by the
drive (10), which comprises
lever, pitman and insulating
rotary bar (8) with motorised
drive.
Disconnectors
 Each disconnector can include one or two earthing switches (4).
◼ The receiving earthing contacts (5) are mounted in the casings of the
main and sliding contacts (6, 9).
◼ The gas compartment of the disconnector, usually jointed to other parts of
the installation, is enclosed in the casing (3) and surveyed by means of
densimeters (7).
◼ The discharging plate
(1) protects the casing against
excessive overpressure, and the
absorber (2) keeps the gas dry.
Disconnectors
 Each disconnector has a spyhole to observe the position of the contacts
and allows checking their condition.
◼ The disconnectors shall be opened solely for inspection works.
◼ For maintenance or expansion of the installation, the disconnectors can
be mechanically interlocked in the desired ended position, and locked by
means of a padlock or any other
locking device.
◼ The interlocking with circuit
breakers, other disconnectors or earthing
switches is electric.
1. Casing
2. Insulator
3. Fixed contact
4. Mobile contact
5. Mobile contact casing
6. Fixed contact
7. Insulating rotary bar
8. Drive
9. Earthing switch (optional)
1. Fixed contact 2. Fixed contact casing
3. Mobile contact 4. Insulating rotary bar
5. Support of the contact 6. Drive
7. Insulator 8. Casing
Disconnectors
◼ Introduction to GIS
◼ Advantages Of SF6 - Insulated Installations
◼ Switchgear Characteristic
◼ Surge Arresters
◼ Disconnectors
◼ Earthing Switches
◼ Circuit Breakers
◼ Instrument Transformers for GIS Substations
◼ Tests
Earthing Switches
• ◼ The maintenance earthing switches endure short-circuit currents in the closed position.
• ◼ They comprise the casing of the mechanism with sliding contact incorporated and contact
bar by lever and pitman.
• ◼ The switching is either unipolar by hand or
• tripolar by motor.
◼ The earthing switches can be adapted to diverse
components, and according to the layout and the
buyer specifications, can be mounted in any point of
the installation, as maintenance earthing switches or
as fast- closing earthing switches.
◼ Locking bolts provided with padlocks or similar
devices ensure the locking in the desired
position.
Earthing Switches
 The fast-closing earthing switches are used to ground parts of the
installation under supply normal conditions.
◼Their tripolar switching mechanism is capable to make short-circuit
currents.
◼ During the closing manoeuvre, the closing spring (10) is tightened by the
linkage (6) and the manoeuvring lever (5), through a motorised drive.
Earthing Switches
 Once tightened the spring, the trigger (11) releases the manoeuvring
lever (9), and the manoeuvring bar (2) closes rapidly by means of the
coupling bar (8), the axle and the pitman.
◼ The receiving contact (1) is a standardised piece of these devices, as
well as in the maintenance earthing switches in the corresponding
device.
◼ Introduction to GIS
◼ Advantages Of SF6 - Insulated Installations
◼ Switchgear Characteristic
◼ Surge Arresters
◼ Disconnectors
◼ Earthing Switches
◼ Circuit Breakers
◼ Instrument Transformers for GIS Substations
◼ Tests
Circuit Breakers
 Likewise in conventional installations, the automatic circuit breakers
ensure the break of short-circuit currents.
◼ The gas in the breaking chamber is injected by means of a piston
mechanically coupled to the mobile contact, which compress the gas at a
pressure two or three times higher than the supply pressure, in order to
generate the blowing, enlargement and cooling of the arc, and its
extinction at the zero crossing of the current wave.
◼ They can be arranged horizontally or vertically to minimize the size of
the substation.
◼ The number of chambers depends on the rated voltage and the
breaking capacity of the circuit breaker.
◼ The drive can be mechanical or hydromechanical.
Circuit Breakers
 Fig.shows a circuit breaker in horizontalposition for 245
kV, with mechanical drive.
◼ In the pole enclosure (2), the truncated-cone insulator (1) supports the
main fixed contact (5), which is jointed to the expansion casing (3).
◼ The other truncated-cone insulator (1) carries, in its vertical axis, a
clamp contact (8) that links the breaking device to the fixed part of the
installation.
Circuit Breakers
 This allows, with inspection and revision purposes, to unplug and extract
the active part fixed to the lid by means of two cylindrical insulators (9).
◼ The energy required to generate the extinction flux in the blowing cylinder
(7) and nozzle (6) is conveyed by the gear (14) and the insulating pitman of
traction (11).
◼ The densimeter (4) surveys the gas compartment of the pole, protected
against excessive overpressure by a discharging plate (12).
Circuit Breakers
 The following figure shows a
circuit breaker in vertical position
for
245 kV with
hydromechanical drive.
1. Hydromechanical drive,
2. SF6, 3. Breaking chamber
4. Casing, 5. Input feeder connection,
6. Output feeder connection
Circuit Breakers ; Hydromechanical Drive
Highpressure
Low pressure
Circuit Breakers; Breaking Chamber
◼ Introduction to GIS
◼ Advantages Of SF6 - Insulated Installations
◼ Switchgear Characteristic
◼ Surge Arresters
◼ Disconnectors
◼ Earthing Switches
◼ Circuit Breakers
◼ Instrument Transformers for GIS Substations
◼ Tests
Instrument Transformers for GIS
 The measurement and protection transformers for SF6-insulated
substations are different from conventional transformers in their especial
constructive characteristics.
◼Fig. shows the shape and location of voltage and current transformers in an
SF6-insulated substation.
Current Transformers
 The one-phase current transformers are bushing type, with ring-
shaped core and toroidal secondary winding.
◼ The cores are externally stick on the metallic enclosure, outside
the SF6 container, separated from the high voltage region by a
cylindrical shield.
1. Insulator
2. Terminal box
3. Support of co 4.
Current Transformers
 The secondary winding is located above the core and connected to the terminal
box. The commutation of the transformation ratio is possible through the
secondary winding.
◼ The stresses caused by the inner overpressure of the gas and for the current
circulating through the casing are conveyed by the traction bars.
◼ The maximum number of cores that can be placed inside the casing depends on
the transformation ratio and on the characteristics of the cores.
1. Insulator
2. Terminal box
3. Support of co 4.
Voltage Transformers
 The voltage transformer is one-
phase (phase-to-ground connection)
and can be inductive or capacitive.
◼ In the Inductive voltage
transformer, the
Active parts are enclosed in a
casing of melted aluminium.
◼ The stratified core supports the
primary and secondary windings.
1. Terminal box
2. Primary winding
3. Secondary winding
4. Core
5. High voltage terminal
Voltage Transformers
 The insulation among the layers
of the primary winding is
elaborated with plastic sheets, and the
insulation between the primary
winding covered by a shielding
electrode, and the external casing is
SF6.
◼ The voltage transformer is
accommodated in an independent gas
compartment, separated form the others
by a conical fastening insulator.
Voltage Transformers
 The high voltage connection is performed
through an interconnection bolt.
◼ The opposite extreme of the primary
winding, connected to ground, as well as
the extremes of the secondary windings,
are carried in a gastight fashion out of the
transformer casing, and jointed to the
terminals for the external connections of
the connection box.
Voltage Transformers
 In the capacitive voltage transformer, the core and the windings
are replaced by a capacitive divider, created between the
metallic casing and the conductor.
◼ The capacitive divider is coupled to an operational amplifier
that provides the signalling to the protection and measurement
devices.
◼ Introduction to GIS
◼ Advantages Of SF6 - Insulated Installations
◼ Switchgear Characteristic
◼ Surge Arresters
◼ Disconnectors
◼ Earthing Switches
◼ Circuit Breakers
◼ Instrument Transformers for GIS Substations
◼ Tests
Tests
 The type tests performed in the gas-insulated switchgear
(disconnectors, circuit breakers, surge arresters and protection and
measurement transformers) follow the same standards and guidelines
than conventional switchgear.
◼ However, additional tests shall be carried out, based on the standard
IEC 62271-203 “Gas-insulated metal-enclosed switchgear for rated
voltages above 52 kV”, such as
◼ the gas tightness test and
◼ the test of internal failure arc.
◼ Besides, every manufacturer has its own testing protocol no
prescribed in the standards
Gas Tightness Test
 This test is performed to verify that the metal-enclosed substation complies
with the permitted value of gas losses, which shall be lower than 1%.
◼ The test is divided in several steps:
◼ Individually, the porosity of the aluminium casing is verified, filling it
with helium.
◼ With the substation totally assembled, the air is extracted until a pressure
inferior to 100 Pa is reached. Then, the possible pressure rises are
observed.
◼ Finally, the substation is filled with SF6, in the nominal conditions of the
installation, and tests are performed in order to verify the pressure
specifications of every gasket and welding.
Test of Internal Failure ARC
 The test consist in verifying that the metal-enclosed installation complies
the demands of endurance to arc, even in the unlikely cases of a failure
with the highest short-circuit current possible.
◼ Under these conditions, the following requirements shall be satisfied:
◼ No metal-enclosed part shall explode.
◼ The damages shall be exclusively restricted to the gas compartment.
◼ The arc should not puncture the shielding during the first step of
protection.

More Related Content

What's hot

Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
Ajay Kuriakose
 
GIS 400kv substation
GIS  400kv substationGIS  400kv substation
GIS 400kv substation
Anbarasu Balakrishnan
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated Substation
Soumya Raj Poddar
 
Gas insulated substation 2
Gas insulated substation 2Gas insulated substation 2
Gas insulated substation 2
naga pooja
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATION
sujitmandalsk
 
Powerpoint presentation on SF6 circuit breaker
Powerpoint presentation on SF6 circuit breakerPowerpoint presentation on SF6 circuit breaker
Powerpoint presentation on SF6 circuit breaker
PoojaGupta663
 
SF6 Circuit breaker by Khalid, NIT Warangal 2014 Batch
SF6 Circuit breaker by Khalid, NIT Warangal 2014 BatchSF6 Circuit breaker by Khalid, NIT Warangal 2014 Batch
SF6 Circuit breaker by Khalid, NIT Warangal 2014 Batch
Khalid Khan
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
MOHDFAIZAN75
 
GIS(GAS INSULATED SUBSTATION)
GIS(GAS  INSULATED  SUBSTATION) GIS(GAS  INSULATED  SUBSTATION)
GIS(GAS INSULATED SUBSTATION)
suneel kumar Aggela
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxJeffrey Dorsey
 
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
Power System Operation
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
Fazlur Rahman
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
Dhananjay Jha
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
Modal Holong Education
 
Sub stations-air insulated substations
Sub stations-air insulated substationsSub stations-air insulated substations
Sub stations-air insulated substations
bhanu lucky
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
Power cable - Voltage drop
Power cable - Voltage dropPower cable - Voltage drop
Power cable - Voltage drop
Leonardo ENERGY
 

What's hot (20)

Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
GIS 400kv substation
GIS  400kv substationGIS  400kv substation
GIS 400kv substation
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated Substation
 
Gas insulated substation 2
Gas insulated substation 2Gas insulated substation 2
Gas insulated substation 2
 
Ppt
PptPpt
Ppt
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATION
 
GIS-NESCL-6
GIS-NESCL-6GIS-NESCL-6
GIS-NESCL-6
 
Powerpoint presentation on SF6 circuit breaker
Powerpoint presentation on SF6 circuit breakerPowerpoint presentation on SF6 circuit breaker
Powerpoint presentation on SF6 circuit breaker
 
SF6 Circuit breaker by Khalid, NIT Warangal 2014 Batch
SF6 Circuit breaker by Khalid, NIT Warangal 2014 BatchSF6 Circuit breaker by Khalid, NIT Warangal 2014 Batch
SF6 Circuit breaker by Khalid, NIT Warangal 2014 Batch
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
GIS(GAS INSULATED SUBSTATION)
GIS(GAS  INSULATED  SUBSTATION) GIS(GAS  INSULATED  SUBSTATION)
GIS(GAS INSULATED SUBSTATION)
 
HVDC vs HVAC ppt
HVDC vs HVAC pptHVDC vs HVAC ppt
HVDC vs HVAC ppt
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docx
 
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
Sub stations-air insulated substations
Sub stations-air insulated substationsSub stations-air insulated substations
Sub stations-air insulated substations
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Power cable - Voltage drop
Power cable - Voltage dropPower cable - Voltage drop
Power cable - Voltage drop
 

Similar to Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)

Gas Insulated Switch Gear ABB Presentation
Gas Insulated Switch Gear ABB PresentationGas Insulated Switch Gear ABB Presentation
Gas Insulated Switch Gear ABB Presentation
SANGARKAREEM
 
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
ashwini kumar
 
substation 101
substation 101substation 101
substation 101danica11
 
Substation_fundamental.pptx
Substation_fundamental.pptxSubstation_fundamental.pptx
Substation_fundamental.pptx
Satish Pydimarla
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1
Ronal Parmar
 
Gagan
GaganGagan
Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstation
raja sukumar
 
GSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURGSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURHARISH KUMAR
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
borapring
 
Internship ppt(santhosh).pptx
Internship ppt(santhosh).pptxInternship ppt(santhosh).pptx
Internship ppt(santhosh).pptx
Basavarajbanakar6
 
Busduct___Busbar.pptx
Busduct___Busbar.pptxBusduct___Busbar.pptx
Busduct___Busbar.pptx
pramod719257
 
Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?
Torben Haagh
 
Gi e
Gi eGi e
Gi e
hoa hong2
 
Govind S N.pptx
Govind S N.pptxGovind S N.pptx
Govind S N.pptx
GovindNemane1
 
GIS PRESENTATION.pdf
GIS PRESENTATION.pdfGIS PRESENTATION.pdf
GIS PRESENTATION.pdf
AyazAhmadKhan3
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
Ang Sovann
 
Substation
Substation Substation
Substation
SanjayMk11
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
f95346
 

Similar to Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS) (20)

Gas Insulated Switch Gear ABB Presentation
Gas Insulated Switch Gear ABB PresentationGas Insulated Switch Gear ABB Presentation
Gas Insulated Switch Gear ABB Presentation
 
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
 
substation 101
substation 101substation 101
substation 101
 
Substation_fundamental.pptx
Substation_fundamental.pptxSubstation_fundamental.pptx
Substation_fundamental.pptx
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1
 
Deepak kumar
Deepak kumarDeepak kumar
Deepak kumar
 
Gagan
GaganGagan
Gagan
 
Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstation
 
GSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURGSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPUR
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
 
Internship ppt(santhosh).pptx
Internship ppt(santhosh).pptxInternship ppt(santhosh).pptx
Internship ppt(santhosh).pptx
 
Busduct___Busbar.pptx
Busduct___Busbar.pptxBusduct___Busbar.pptx
Busduct___Busbar.pptx
 
Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?
 
RPS-SF6LBS-PKE
RPS-SF6LBS-PKERPS-SF6LBS-PKE
RPS-SF6LBS-PKE
 
Gi e
Gi eGi e
Gi e
 
Govind S N.pptx
Govind S N.pptxGovind S N.pptx
Govind S N.pptx
 
GIS PRESENTATION.pdf
GIS PRESENTATION.pdfGIS PRESENTATION.pdf
GIS PRESENTATION.pdf
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
 
Substation
Substation Substation
Substation
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
 

More from Power System Operation

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
Power System Operation
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
Power System Operation
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
Power System Operation
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
Power System Operation
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
Power System Operation
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
Power System Operation
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
Power System Operation
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
Power System Operation
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
Power System Operation
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
Power System Operation
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
Power System Operation
 
What is load management
What is load managementWhat is load management
What is load management
Power System Operation
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
Power System Operation
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
Power System Operation
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
Power System Operation
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power System Operation
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
Power System Operation
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
Power System Operation
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
Power System Operation
 
SCADA System ? Supervisory Control & Data Acquisition
SCADA System ? Supervisory Control & Data AcquisitionSCADA System ? Supervisory Control & Data Acquisition
SCADA System ? Supervisory Control & Data Acquisition
Power System Operation
 

More from Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 
SCADA System ? Supervisory Control & Data Acquisition
SCADA System ? Supervisory Control & Data AcquisitionSCADA System ? Supervisory Control & Data Acquisition
SCADA System ? Supervisory Control & Data Acquisition
 

Recently uploaded

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 

Recently uploaded (20)

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 

Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)

  • 2. It is very much required to establish an electrical substation at load center. Since, establishing a substation at load center is quite economical and profitable in many aspects. As it reduces length of feeders and due to short length feeders, the quality of voltage regulation improves. But the main obstruction of establishing a substation at load center is space. Generally main load center of any place is situated at very congested place where, sufficient land for establishing conventional electrical substation is very hardly available.
  • 3. This problem can be solved by using Gas Insulated Switchgear Technology. In this Type of Switchgear, all the necessary components of switchgear can be assembled in very limited space. GIS is a kind of Metal enclosed Switchgear. That means, all the equipments of the Electrical Switchgear are enclosed by gas tight metal enclosure and SF6 Gas is used as insulation between live parts of the equipments and earthed metal enclosure. This type of switchgear, means, and gas insulated switchgear is available from 12 KV systems to 800 KV system. For establishing electrical substation in very limited place this type of SF6 insulated electrical switchgear plays the major role.
  • 4. Gas insulated components of substation are generally, Electrical bus bars:  Electrical Isolators or Disconnectors.  Circuit Breakers.  Current Transformers.  Voltage Transformers.  Earth Switches.  Surge Arrestors or Lightning Arresters.
  • 5. The substation, assembled by gas insulated switchgear, is popularly known as gas insulated metal enclosed substation (GIMES). GIMES technology is not very recent invention, it is successfully running for over thirty years. In gas insulated medium voltage switchgear, vacuum technology is used as interrupting purpose and SF6 gas is used as insulation material. Although for both interruption and insulation, SF6 gas is used in many medium voltage GIS system. But for such equipments rated SF6 gas pressures are different for interruption and insulation. SF6 gas pressure for insulating purpose is generally kept below 2.5 bar whereas SF6 gas pressure for interrupting purpose is ranged from 5 bar to 7 bar.
  • 6. As vacuum technology is not available for high voltage, so for GIS or gas insulated switchgear system above 72.5 KV, only SF6 is used both for interruption medium and insulation. There are different types of gas insulated metal enclosed switchgears available depending upon their constructional feature. Isolated Phase GIS In this configuration, each phase of the bay is assembled separately. That is, for each phase, one pole of circuit breaker, a single pole of electrical isolator, one phase assembly of current transformer are assembled together. This type of GIS requires larger bay width as compared to other gas insulated switchgear system.
  • 7. Integrated 3 Phase GIS In this configuration all three phase of circuit breaker, 3 phases of disconnectors and three phase current transformer are encapsulated in an individual metal enclosure. The arrangement forms a three phase module for the element. The size of this type of module is one third of the isolated phase GIS. Hybrid GIS System It is a suitable combination of isolated phase and three phase common elements. Here three phase common bus bar system simplifies the connection from the bus bar. The isolated phase equipment prevents phase to phase faults. This is an optimum design considering, both facts in mind, i.e. space requirement and maintenance facility.
  • 8. Compact GIS In this GIS or gas insulated switchgear system than one functional element are encapsulate in a single metal enclosure. For example, in some design, a three phase circuit breaker, current transformer, earth switches, even other feeder elements are covered together in a single metal capsule. Highly Integrated System This design was introduced in the year of 2000, where, total substation equipments are encapsulated together in single enclosure housing. This single unit gas insulated substation has gained user appreciation as it is a complete solution for an outdoor substation, in a single unit. As such, only equipment (HIS) is substitute of a total outdoor switch yard.
  • 9. ◼ Introduction to GIS ◼ Advantages Of SF6-Insulated Installations ◼ Switchgear Characteristic ◼ Surge Arresters ◼ Disconnectors ◼ Earthing Switches ◼ Circuit Breakers ◼ Instrument Transformers for GIS Substations ◼ Tests for GIS
  • 10. Introduction ◼ At normal atmospheric conditions, the insulation distances determine the main sizes of the classic distribution substation. ◼ For a long time, the development in substation construction concentrated simply in combining existing devices to obtain the arrangement more adequate for exploitation and supply security. ◼ On the other hand, the increasing needs to convey electric energy, at higher voltages, towards the regions with grand population density and the industrial centres, causes great difficulties due to the size of the involved installations. ◼ Official prescriptions and the town-planning requirements complicate the construction.
  • 11. Introduction  Due to the troubles caused by pollution in insulators, the tendency is to build indoors installations. ◼ However, the cost increasing in construction leads to reduce, as much as possible, the dimensions of the installation. ◼ Hence, to solve this problem, smaller installations are needed, which should also comply the following requirements: ◼ They shall be insensible to climatic influences. ◼ They can be raised outdoors, inside a building or underground. ◼ They require reduced maintenance. ◼ They are silent. ◼ They should not generate radioelectric disturbances. ◼ They shall not imply danger for the nearby populated zones.
  • 12. Introduction As a solution for this problem, metal-enclosed installations with SF6 insulation are used.
  • 13. Introduction  In this system, the parts of the main current circuit (such as the circuit breaker, the disconnector, the buses, etc.) are mechanically integrated in a set that can be called coupling group. ◼ The compact manufacturing and the highly developed wiring technique allow the free determination of the site, and ensure the independence regarding climatic conditions. ◼ Some possible applications of this very high voltage metal-enclosed stations: ◼ Main distribution stations inside cities. ◼ Main distribution stations for important customers. ◼ Main distribution stations in zones with pollution, salt, or risk of explosion.  Maindistribution stations with special characteristics(underground stations, shelters of reinforced concrete, etc.). ◼Classic installation expansion, in case of reduced space. ◼Mobile transformation stations.
  • 14. Introduction  The gas-insulated substations utilize the same switchgear of conventional substations, but with design and characteristics slightly different. ◼ The whole station is integrated inside a grounded aluminium enclosure filled with SF6, which ensures the insulation to ground. ◼ Diagram of a 220 kV gas-insulated substation.
  • 15. Introduction  Fig. presents some basic layouts of the assorted types of gas- insulated substations, which will vary according to the requirements of each installation
  • 16. ◼ Introduction to GIS ◼ Advantages Of SF6 - Insulated Installations ◼ Switchgear Characteristic ◼ Surge Arresters ◼ Disconnectors ◼ Earthing Switches ◼ Circuit Breakers ◼ Instrument Transformers for GIS Substations ◼ Tests
  • 17. Advantages of SF6-Insulated Installations  Reduced required space ◼ Outlook compatible with surroundings without altering architectural or natural beauty. ◼ Reduced erection and assembly times. ◼ The installations are dielectrically and totally tested in-site (unlike conventional substations). ◼ Reduced maintenance and consequently, lower costs. ◼ From 30 kV to 500 kV they might result cheaper than conventional units. ◼ Up to 170 kV, tripolar design is used (three phases in the same casing). For upper voltages, each phase is separately insulated, enclosed and compartmentalized.
  • 18. ◼ Introduction to GIS ◼ Advantages Of SF6 - Insulated Installations ◼ Switchgear Characteristic ◼ Surge Arresters ◼ Disconnectors ◼ Earthing Switches ◼ Circuit Breakers ◼ Instrument Transformers for GIS Substations ◼ Tests
  • 19. Surge Arresters  When the connection with the network is performed through an overhead line, the surge arrester is located at the entrance of the gas-insulated substation. ◼ The surge arrester can be conventional or SF6-insulated. ◼ In this last case, if distances in the substation are higher than the protection distance of the surge arrester, it is convenient to install, besides, a surge arrester inside the metal-enclosed substation.
  • 20.  When the substation is connected to the network through a high voltage cable, it is advisable to integrate the surge arrester inside the substation casing. ◼ This advice becomes mandatory if the conductor is longer than 50 m, or if the substation occupies a very extended surface. ◼ The surge arresters are also encapsulated and their discharge voltage is lower than in conventional arresters, due to the lack of pollution and to the direct coupling to the breaking device (not necessarily connected to the line). Surge Arresters
  • 21. Surge Arresters Metallic Casing  The cylindrical metallic casing is comprised of concentric sheets of aluminium, welded as a tube. ◼ The clamps are also aluminium pieces. ◼ The rated values of filling pressure (Pats) for the SF6 are 420 540 kPa at 20 º C. ◼ Ifthe surge arrester needs accessories,such as gas valves, densimeter ormanometer, discharge counter or breaking disks (pressure lever), they will be mounted in its top. ◼ As mentioned before, up to 170 kV the three phases are located in the same casing. For upper voltages, each phase is mounted in individual compartments.
  • 22. Surge Arresters Metal-Oxide Disks  The surge arresters insulated in SF6, alike conventional arresters, are constituted by columns with several piled up metal-oxide disks of variable resistance. ◼ These columns are concentrically mounted in the metallic casing.
  • 23. Surge Arresters Metal-Oxide Disks  The flat contact surfaces are manufactured with a conductive metallic layer and the cylindrical hermetic sides are elaborated with a layerof passivated crystal (neutral metal that prevents corrosion). ◼This design allows that the disks can be in direct contact with the SF6, which increases the capability of heat evacuation during, for example, repetitive strong discharges. ◼ To avoid the excessive size of surge arresters for voltages upper than 170 kV, the disks are piled up in three columns, forming a triangle, electrically connected in series. ◼ Each column consists of fibreglass axles and springs that compress the disks.
  • 24. Surge Arresters Metal-Oxide Disks  A device that evenly distributes the voltage among all disks is located in the top of the columns. ◼Fig.compares arresters with and without such device.
  • 25. ◼ Introduction to GIS ◼ Advantages Of SF6 - Insulated Installations ◼ Switchgear Characteristic ◼ Surge Arresters ◼ Disconnectors ◼ Earthing Switches ◼ Circuit Breakers ◼ Instrument Transformers for GIS Substations ◼ Tests
  • 26. Disconnectors  Slide-in disconnectors are used in gas-insulated substations, capable to break the capacitive currents that take place during the coupling manoeuvres in the installation, and to break commutation currents caused by changes in the buses configuration. ◼ To optimise the operation of the disconnectors in different points of the distribution station, the active parts are encased separately, reducing to minimum the number of flanged joints.
  • 27. Disconnectors  The disconnector consist of the main contact (6) and the casing of the sliding contact (9), in which interior is located the coupling of the sliding contact (12). ◼ The conductor is connected to both contacts by sheet contacts. ◼ The sliding contact (12) is tripolar-operated by the drive (10), which comprises lever, pitman and insulating rotary bar (8) with motorised drive.
  • 28. Disconnectors  Each disconnector can include one or two earthing switches (4). ◼ The receiving earthing contacts (5) are mounted in the casings of the main and sliding contacts (6, 9). ◼ The gas compartment of the disconnector, usually jointed to other parts of the installation, is enclosed in the casing (3) and surveyed by means of densimeters (7). ◼ The discharging plate (1) protects the casing against excessive overpressure, and the absorber (2) keeps the gas dry.
  • 29. Disconnectors  Each disconnector has a spyhole to observe the position of the contacts and allows checking their condition. ◼ The disconnectors shall be opened solely for inspection works. ◼ For maintenance or expansion of the installation, the disconnectors can be mechanically interlocked in the desired ended position, and locked by means of a padlock or any other locking device. ◼ The interlocking with circuit breakers, other disconnectors or earthing switches is electric.
  • 30. 1. Casing 2. Insulator 3. Fixed contact 4. Mobile contact 5. Mobile contact casing 6. Fixed contact 7. Insulating rotary bar 8. Drive 9. Earthing switch (optional) 1. Fixed contact 2. Fixed contact casing 3. Mobile contact 4. Insulating rotary bar 5. Support of the contact 6. Drive 7. Insulator 8. Casing Disconnectors
  • 31. ◼ Introduction to GIS ◼ Advantages Of SF6 - Insulated Installations ◼ Switchgear Characteristic ◼ Surge Arresters ◼ Disconnectors ◼ Earthing Switches ◼ Circuit Breakers ◼ Instrument Transformers for GIS Substations ◼ Tests
  • 32. Earthing Switches • ◼ The maintenance earthing switches endure short-circuit currents in the closed position. • ◼ They comprise the casing of the mechanism with sliding contact incorporated and contact bar by lever and pitman. • ◼ The switching is either unipolar by hand or • tripolar by motor. ◼ The earthing switches can be adapted to diverse components, and according to the layout and the buyer specifications, can be mounted in any point of the installation, as maintenance earthing switches or as fast- closing earthing switches. ◼ Locking bolts provided with padlocks or similar devices ensure the locking in the desired position.
  • 33. Earthing Switches  The fast-closing earthing switches are used to ground parts of the installation under supply normal conditions. ◼Their tripolar switching mechanism is capable to make short-circuit currents. ◼ During the closing manoeuvre, the closing spring (10) is tightened by the linkage (6) and the manoeuvring lever (5), through a motorised drive.
  • 34. Earthing Switches  Once tightened the spring, the trigger (11) releases the manoeuvring lever (9), and the manoeuvring bar (2) closes rapidly by means of the coupling bar (8), the axle and the pitman. ◼ The receiving contact (1) is a standardised piece of these devices, as well as in the maintenance earthing switches in the corresponding device.
  • 35. ◼ Introduction to GIS ◼ Advantages Of SF6 - Insulated Installations ◼ Switchgear Characteristic ◼ Surge Arresters ◼ Disconnectors ◼ Earthing Switches ◼ Circuit Breakers ◼ Instrument Transformers for GIS Substations ◼ Tests
  • 36. Circuit Breakers  Likewise in conventional installations, the automatic circuit breakers ensure the break of short-circuit currents. ◼ The gas in the breaking chamber is injected by means of a piston mechanically coupled to the mobile contact, which compress the gas at a pressure two or three times higher than the supply pressure, in order to generate the blowing, enlargement and cooling of the arc, and its extinction at the zero crossing of the current wave. ◼ They can be arranged horizontally or vertically to minimize the size of the substation. ◼ The number of chambers depends on the rated voltage and the breaking capacity of the circuit breaker. ◼ The drive can be mechanical or hydromechanical.
  • 37. Circuit Breakers  Fig.shows a circuit breaker in horizontalposition for 245 kV, with mechanical drive. ◼ In the pole enclosure (2), the truncated-cone insulator (1) supports the main fixed contact (5), which is jointed to the expansion casing (3). ◼ The other truncated-cone insulator (1) carries, in its vertical axis, a clamp contact (8) that links the breaking device to the fixed part of the installation.
  • 38. Circuit Breakers  This allows, with inspection and revision purposes, to unplug and extract the active part fixed to the lid by means of two cylindrical insulators (9). ◼ The energy required to generate the extinction flux in the blowing cylinder (7) and nozzle (6) is conveyed by the gear (14) and the insulating pitman of traction (11). ◼ The densimeter (4) surveys the gas compartment of the pole, protected against excessive overpressure by a discharging plate (12).
  • 39. Circuit Breakers  The following figure shows a circuit breaker in vertical position for 245 kV with hydromechanical drive. 1. Hydromechanical drive, 2. SF6, 3. Breaking chamber 4. Casing, 5. Input feeder connection, 6. Output feeder connection
  • 40. Circuit Breakers ; Hydromechanical Drive Highpressure Low pressure Circuit Breakers; Breaking Chamber
  • 41. ◼ Introduction to GIS ◼ Advantages Of SF6 - Insulated Installations ◼ Switchgear Characteristic ◼ Surge Arresters ◼ Disconnectors ◼ Earthing Switches ◼ Circuit Breakers ◼ Instrument Transformers for GIS Substations ◼ Tests
  • 42. Instrument Transformers for GIS  The measurement and protection transformers for SF6-insulated substations are different from conventional transformers in their especial constructive characteristics. ◼Fig. shows the shape and location of voltage and current transformers in an SF6-insulated substation.
  • 43. Current Transformers  The one-phase current transformers are bushing type, with ring- shaped core and toroidal secondary winding. ◼ The cores are externally stick on the metallic enclosure, outside the SF6 container, separated from the high voltage region by a cylindrical shield. 1. Insulator 2. Terminal box 3. Support of co 4.
  • 44. Current Transformers  The secondary winding is located above the core and connected to the terminal box. The commutation of the transformation ratio is possible through the secondary winding. ◼ The stresses caused by the inner overpressure of the gas and for the current circulating through the casing are conveyed by the traction bars. ◼ The maximum number of cores that can be placed inside the casing depends on the transformation ratio and on the characteristics of the cores. 1. Insulator 2. Terminal box 3. Support of co 4.
  • 45. Voltage Transformers  The voltage transformer is one- phase (phase-to-ground connection) and can be inductive or capacitive. ◼ In the Inductive voltage transformer, the Active parts are enclosed in a casing of melted aluminium. ◼ The stratified core supports the primary and secondary windings. 1. Terminal box 2. Primary winding 3. Secondary winding 4. Core 5. High voltage terminal
  • 46. Voltage Transformers  The insulation among the layers of the primary winding is elaborated with plastic sheets, and the insulation between the primary winding covered by a shielding electrode, and the external casing is SF6. ◼ The voltage transformer is accommodated in an independent gas compartment, separated form the others by a conical fastening insulator.
  • 47. Voltage Transformers  The high voltage connection is performed through an interconnection bolt. ◼ The opposite extreme of the primary winding, connected to ground, as well as the extremes of the secondary windings, are carried in a gastight fashion out of the transformer casing, and jointed to the terminals for the external connections of the connection box.
  • 48. Voltage Transformers  In the capacitive voltage transformer, the core and the windings are replaced by a capacitive divider, created between the metallic casing and the conductor. ◼ The capacitive divider is coupled to an operational amplifier that provides the signalling to the protection and measurement devices.
  • 49. ◼ Introduction to GIS ◼ Advantages Of SF6 - Insulated Installations ◼ Switchgear Characteristic ◼ Surge Arresters ◼ Disconnectors ◼ Earthing Switches ◼ Circuit Breakers ◼ Instrument Transformers for GIS Substations ◼ Tests
  • 50. Tests  The type tests performed in the gas-insulated switchgear (disconnectors, circuit breakers, surge arresters and protection and measurement transformers) follow the same standards and guidelines than conventional switchgear. ◼ However, additional tests shall be carried out, based on the standard IEC 62271-203 “Gas-insulated metal-enclosed switchgear for rated voltages above 52 kV”, such as ◼ the gas tightness test and ◼ the test of internal failure arc. ◼ Besides, every manufacturer has its own testing protocol no prescribed in the standards
  • 51. Gas Tightness Test  This test is performed to verify that the metal-enclosed substation complies with the permitted value of gas losses, which shall be lower than 1%. ◼ The test is divided in several steps: ◼ Individually, the porosity of the aluminium casing is verified, filling it with helium. ◼ With the substation totally assembled, the air is extracted until a pressure inferior to 100 Pa is reached. Then, the possible pressure rises are observed. ◼ Finally, the substation is filled with SF6, in the nominal conditions of the installation, and tests are performed in order to verify the pressure specifications of every gasket and welding.
  • 52. Test of Internal Failure ARC  The test consist in verifying that the metal-enclosed installation complies the demands of endurance to arc, even in the unlikely cases of a failure with the highest short-circuit current possible. ◼ Under these conditions, the following requirements shall be satisfied: ◼ No metal-enclosed part shall explode. ◼ The damages shall be exclusively restricted to the gas compartment. ◼ The arc should not puncture the shielding during the first step of protection.