SlideShare a Scribd company logo
1 of 130
LECTION OF FOUNDATION
MADE BY : MISS.DHARA DATTANI
(ME TRANSPORTATAION)
LECTURER AT ATMIYA INSTITUTE OF TECHNOLOGY AND
SCIENCE FOR DIPLOMA STUDIES,RAJKOT.GUJRAT,INDIA.
PART-1
1
PART 1: TYPES OF FOUNDATION
2
What s Foundation ?
• Every building consists of two basic components :
1. The Super-structure
2. The Sub-structure
• The substructure or foundation is that part of the structure which is usually
below the ground level and in direct contact with the soil , through which the
load of superstructure is transmitted to the soil.
• The basic function of a foundation is to transmit the dead loads, superimposed
loads and wind loads from a building (superstructure) to the soil in such a way
that:
a. Settlements are uniform and within permissible limit. &
b. The soil does not fail. 3
Functions of Foundations :
1. Reduction of load intensity.
Foundations distribute the load of the superstructure to a larger area so the total
intensity of load doesn't exceed the safe bearing capacity of soil.
2. Even distribution of load.
Foundations distribute the non uniform load of the super structure evenly to the
subsoil.
3. Provision of level surface.
Foundations provide a levelled and hard surface over which a super-structure can
be built.
4. Lateral stability.
It anchors the super-structure to the ground thus imparting stability to the building.
5. Safety against undermining.
It provides safety against undermining or scouring due to burrowing animals &
flood water.
6. Protection against soil movements.
Special measures prevent or minimise the distress (cracks) in superstructure, due
to expansion or contraction of sub-soil.
4
ESSENTIAL REQUIREMENTS FOR A GOOD
FOUNDATION
 The foundation shall be constructed to sustain load and transmit these to
subsoil in such a way that pressure on it will not cause settlement which
would impair the stability of the building.
 Foundation should be rigid so that the differential settlements are
minimised.
 Specially for the case when superimposed loads are not evenly distributed.
 Foundations should be taken sufficiently deep to guard the building against
damage or distress caused by swelling or shrinkage of sub-soil.
 Foundations should be so located that its performance may not be affected
due to any unexpected future influence.
5
• Types of Foundation
Shallow Foundation Deep Foundation
(A) Shallow Foundation: According to Terzaghi, a foundation is shallow if its
depth is equal to or less than its width. (D<B)
(B) Normally shallow foundation used upto 5m depth.also called open
foundation
• Types of Shallow Foundation:
 Spread footing
 Combined footing
 Strap Footing
 Mat Foundation or Raft Foundation
 Grillage Foundation
6
• Spread Footing/ Isolated column:-Spread footings are those which
spread the super-imposed load of wall or column over larger area.
Spread footing support either column or wall.
• It may be following kinds
• Stepped footing for column: This type of footing provided for heavily
loaded column which required greater spread with steps. The base is
generally made of concrete. Used in wall/column
• Sloped footing for column: In this type of footing concrete base does
not have uniform thickness but is made sloped. Generally used when
sbc is low and hard strata is not found.
• Wall footing without step: It consist of concrete base without any steps
including masonry wall.
• Stepped footing for wall: It consist of masonry wall have stepped
footing with concrete base .
7
8
• Grillage Foundation
• It is special type of isolated footing generally provided for heavily loaded
steel column and used in those location where bearing capacity of soil is
poor.
• The depth of such foundation is limited to 1 to 1.5 m.
• This type of arrangement avoids deep excavation and provide necessary area
at the base to reduce the intensity of pressure.
9
10
Combined Footing:
• A spread footing which supports two or more columns is termed as combined
footing.
• When two column are so close to each other that tier individual footing would
over lap.
• The combined footing may be of following kinds.
• Rectangular combined footing: The combined footings will be provide in
rectangular in shape if columns carry equal loads. The design of rectangular
combined footing should be done in such way that centre of gravity of column
coincide with centroid of footing area.
• Trapezoidal combined footing: If columns carry unequal loads the footing is of
trapezoidal shape are provided.
• Combined column-wall footing: It may be required to provide a combined
footing for column and wall. Such combined footing are shown in fig.
11
12
13
Strap Footing:
• It is a Independent footing of two columns are connected by a beam, it
is called a strap footing.
• The strap connects the two footings such that they behaves as one
unit.
• The strap does not remain in contact with soil and does not transfer
any pressure to the soil.
• A strap footing is more economical than a combined footing.
• Also used when the distance between two column is large.
14
15
Raft foundation:
 A raft Foundation is a combined footing that covers the entire
area beneath a structure and support all the wall and column.
 When the allowable soil pressure is low.
 When the structure loads are heavy
 When there is a large variation in the loads on individual
columns.
 When foundation of soil is non homogeneous and there are
chances of differential settlements.
16
17
Deep foundation
• Deep foundation are those in which the depth of foundation is very
large in comparison to its width.(D>B).
Deep foundation may be of following types
• Pile foundation
• Pier foundation
• Caissons or Well foundation
18
• Pile Foundation
• Pile Foundation is that type of foundation in which the
loads are taken to a low level by means of vertical
members which may be timber, concrete or steel.
• Pile foundation may be adopted when no firm bearing
strata is available and the loading is uneven.
• Piles may be of following types
• End bearing piles
• Friction Pile
• Compaction pile
Prepared By : Mr. Mayank M. Parekh 19
• End bearing piles: This types of piles are used to
transfer load through water or soft soil to a
suitable bearing stratum.
• Friction Pile: Friction piles are used to transfer
loads to a depth of friction load carrying material
by means of skin friction along the length of piles.
• Compaction pile: Compaction piles are used to
compact loose granular soils, thus increasing their
bearing capacity.
20
21
• Pier foundation:
• A Pier foundation consist of cylindrical
column of large diameter to support and
transfer large superimposed load to the firm
strata below.
• Generally, pier foundation is shallow in depth
than the pile foundation.
22
23
• Well Foundation:
• Well Foundation or Caisson are box like
structures which are sunk from the surface of
either land or water to the desired depth.
• They are much larger than the pier foundation
or drilled caissons.
• Caisson foundations are used for major
foundation works like
• Bridge piers
• Docks
• Large water front structure such as pump
house.
24
25
26
Coffer dams:
• A cofferdam is a
temporary structure
which is built in a river,
lake etc. to remove water
from an area and make it
possible to carry on the
construction work under
reasonably dry
conditions.
• Cofferdams are usually
required for project such
as dams and construction
of piers and abutment.
Requirement of a cofferdam :-
• The cofferdam should be reasonably watertight.
• It should be generally constructed at site of work.
• The design and layout of a cofferdam should be such that the
total cost of construction, maintenance and pumping is
minimum.
• It should be stable against bursting, overturning and sliding,
under the floods and waves.
• The water to be excluded by a coffer dam may be either
ground water of water lying above ground level, it may be
deep or shallow and still or running.
• The materials used in construction of a cofferdam are earth,
timber, steel and concrete.
Necessity of cofferdam :-
 The coffer dams are required in the following situation:
• When it is required to construct a structure in the river bad.
• When structure is to be constructed on a sea shore.
• When it is required to construct a structure one a bank of the
lake or inside the lake.
• When deep excavation are carried out in a course grained soil.
• When excavation is carried out below ground water table.
• During deep excavation, when sides of the trenches are likely
to collapse.
Use of cofferdam
• To facilitate pile driving operation
• To place grillage and raft foundation
• To construct foundations for piers and abutments of
bridge, dams, locks, etc.;
• To enclose a space for the removal of sunken vessels
• To provide a working platform for the foundation of
building when water is met with; and
• To provide space for carrying out the foundation work
without disturbing or damaging the adjoining structure
such as buildings, pipelines, sewers, etc.
Types of cofferdam :-
• Earthen cofferdam
• Rock-filled cofferdams
• Sand bags cofferdam
• Single wall cofferdams
• Double wall cofferdams
• Cellular cofferdam
Earthen cofferdam :-
• This is the simplest form of cofferdam. It essentially consist
of an earthen embankment built around the area to be
enclosed.
• Suitable for low, 1.2 to 1.5 m and moderate head of water.
• The top of embankment should be 1m above the water
level.
Rock-filled cofferdams :-
• Suitable for turbulent flow and up to 3m depth of water.
• Stone or rubble is used for the embankment.
• It construction is adopted only the stone is easily available
in the nearby areas.
Sand bags cofferdam :-
• The method of
using laminated
sand bags to build
cofferdam are
easy to construct,
cost-efficient and
economic friendly
Single wall cofferdams
• This type of
cofferdam is used in
places where the
area to be enclosed
is very small and the
depth of water is
more, say 4.5 to 6 m.
• It can be used for up
to 25m depth of
water.
Double wall cofferdams :-
 Two-parallel rows of steel
sheet piles driven into the
ground
 Tied together with anchors
and wales, then filled with
soil
 There are two types of this
type of cofferdams:
1. ohio river type wood
sheeting cofferdam
2. Wood or steel sheeting
cofferdam with wales and
tie rods
Cellular cofferdams :-
• Circular cells are connected by
diaphragms
• Deep excavations
• Used when the construction
area is very large
• Also used when internal
bracing is impractical
• There are two types of this
type of cofferdams:
1. Circular
2. Diaphragm
• Foundations on Black Cotton Soil
• Black cotton soils and other expansive soils have typical characteristics of
shrinkage and swelling due to moisture movement through them.
• When moisture enter between the soil particles under some hydrostatic pressure,
the particles separate out, resulting in increase in the volume.
• This increase in volume is commonly known as swelling. If this swelling is
checked or restricted high swelling pressure, acting in the upward direction, will
be induced.
• This would result in several cracks in the walls and may some times damage the
structural such as lintels, beams, slabs etc.
• During summer season, moisture moves out of the soil and consequently, the soil
shrinks.
• Shrinkage cracks are formed on the ground surface. These shrinkage cracks
some times also known as tension cracks, may be 10 to 15 cm wide on the
ground surface.
• Black cotton soils and other expansive soils are dangerous due to their shrinkage
and swelling characteristics.
• In addition, these soils have very poor bearing capacity, ranging from 5 t/m2 to
10 t/m2.
38
• For designing footings on these soils, the following points should be kept in mind:
• 1. The safe bearing capacity should be properly determined, taking into account the
effect of sustained loading. The bearing capacity of these soils may be limited to 5 to
10 t/m2.
2. The foundation should be taken at least 50 cm lower than the depth of moisture
movement.
3. Where this soil occurs only in top layer, and where the thickness of this layer does
not exceed 1 to 1.5 m, the entire layer of black cotton soil should be removed, and
the foundation should be laid on non-shrinkable non- expansive soil.
5. Where the soil is highly expansive, it is very essential to have minimum contact
between the soil and the footing. This can be best achieved by transmitting the loads
through deep piles.
6. Where the bearing capacity of soil is poor, or soil is very soft, the bed of the
foundation trench should be made firm or hard by ramming mooram.
39
Types of foundation in black cotton soils.
Foundation in black cotton soils may be of the following types:
1. Strip foundation. For medium loads, strip foundation may
be provided, along with special design features.
2. Pier foundation Piers are dug at regular interval and filled
with cement concrete. The piers may rest on good bearing
strata.
3. Under-reamed pile foundation. An under-reamed pile is a
pile of shallow depth (1 to 6 m) having one bulb at its lower
end.
40
• Under-reamed Pile Foundation
• Under-reamed piles are bored cast-in-situ concrete piles
having bulk shaped enlargement near base.
• These piles are commonly recommended for providing safe
and economical foundations in expansive soils such as black
cotton soil having poor bearing capacity.
• In these type of foundation the structure is anchored to the
ground at a depth where ground movement due to changes in
moisture content negligible.
• A pile having one bulk is known as single under-reamed pile.
It is seen that the load bearing capacity of the pile can be
increased by increasing the number of bulk at the base.
• In such a case the pile is named as multi-under-reamed pile.
The increase in the bearing capacity of the pile can also be
achieved by increasing the diameter and the length of the pile.
41
• The method of construction of under-reamed pile is very simple.
The holes for casting piles in the ground may be bored by using
hand augers.
• After boring is carried out at the required depth, the base of the
bore hole is enlarged in the form of a bulb near its base by use of a
tool, known under-reamer.
• After the pile holes are ready for concreting, reinforcement cage are
lowered in the holes and concrete is poured.
• The piles should be cast at least 200 to 400 mm above the cut-off
level. Later on, when the concrete is hardened, the extra length of
each pile is broken and the pile top is brought to the desired level.
• Thus, besides relative saving in direct cost (when compared with
conventional isolated footings) it is possible to have overall saving
in time of completion of a work by adopting under-reamed piles.
42
Prepared By : Mr. Mayank M. Parekh 43
Part 2: SUBSOIL EXPLORATION…
44
Definition
•The process of determining the layers of
natural soil deposits that will underlie a
proposed structure and their physical
properties is generally referred to as site
investigation.
• The field and laboratory studies carried out
for obtaining the necessary information about
the sub soil characteristics including the
position of ground water table are termed as
soil exploration
45
METHODS OF EXPLORATION
1. Preliminary exploration
Local topography, excavations, cuttings, drainage
pattern and other natural features like streams,
flood marks etc.
Geophysical methods
2. Detailed investigation
Nature, sequence and thickness of layers. Borings and
detailed sampling, in-situ test.
OBJECTIVES OF SITE INVESTIGATION
1. Site selection.
2. Foundation and earthworks design.
3. Temporary works design.
4. The effects of the proposed project on its
environment.
5. Investigation of existing construction.
6. The design of remedial works.
7. Safety checks.
EXPLORATION PROGRAM
The purpose of the exploration program is to
determine, within practical limits, the
stratification and engineering properties of the
soils underlying the site.
The principal properties of interest will be the
strength, deformation, and hydraulic
characteristics. The program should be planned
so that the maximum amount of information can
be obtained at minimum cost.
48
The general objective of an exploration program is to identify all
of the significant features of the geologic environment that
may impact on the proposed construction.
Specific objectives are to:
1. Define the lateral distribution and thickness of soil and rock
strata within the zone of influence of the proposed
construction.
2. Define groundwater conditions considering seasonal changes
and the effects of construction or development extraction.
3. Identify geologic hazards, such as unstable slopes, faults,
ground subsidence and collapse, floodplains, regional
seismicity, and lahars.
4. Procure samples of geologic materials for the
identification, classification, and measurement of
engineering properties.
5. Perform in situ testing to measure the engineering
properties of the geologic materials
The purpose of a soil investigation program
1. Selection of the type and the depth of foundation suitable for a
given structure.
2. Evaluation of the load-bearing capacity of the foundation.
3. Estimation of the probable settlement of a structure.
4. Determination of potential foundation problems (for example,
expansive soil, collapsible soil, landfill, and so on).
5. Establishment of ground water table.
6. Prediction of lateral earth pressure for structures like retaining
walls, sheet pile bulkheads, and braced cuts.
7. Establishment of construction methods for changing subsoil
conditions.
51
If only they had proper site investigation…
52
…Tower of Pisa will not be leaning today!
Depth of Boring
1. Determine the net increase of stress, under a foundation
with depth as shown in the Figure.
2. Estimate the variation of the vertical effective stress, ', with
depth.
3. Determine the depth, D = D1, at which the stress increase 
is equal to (1/10) q (q = estimated net stress on the
foundation).
4. Determine the depth, D = D2, at which /' = 0.05.
5. Unless bedrock is encountered, the smaller of the two depths,
D1 and D2, just determined is the approximate minimum depth
of boring required. Table shows the minimum depths of
borings for buildings based on the preceding rule.
53
Depth of Boring
54
Determination of the minimum depth of boring
Building
width
Number of Storeys
1 2 4 8 16
Boring Depth
30.5 3.4 6.1 10.1 16.2 24.1
61 3.7 6.7 12.5 20.7 32.9
122 3.7 7 13.7 24.7 41.5
Depth of Boring
When deep excavations are anticipated, the depth
of boring should be at, least 1.5 times the depth
of excavation. Sometimes subsoil conditions are
such that the foundation load may have to be
transmitted to the bedrock. The minimum depth
of core boring into the bedrock is about 3m. If the
bedrock is irregular or weathered, the core
borings may have to be extended to greater
depths.
56
Spacing Boring
There are no hard and fast rules for the
spacing of the boreholes. The following
table gives some general guidelines for
borehole spacing. These spacing can be
increased or decreased, depending on the
subsoil condition. If various soil strata are
more or less uniform and predictable, the
number of boreholes can be reduced.
59
SOIL BORING
The earliest method of obtaining a test hole was to
excavate a test pit using a pick and shovel.
Because of economics, the current procedure is to
use power-excavation equipment such as a
backhoe to excavate the pit and then to use hand
tools to remove a block sample or shape the site
for in situ testing. This is the best method at
present for obtaining quality undisturbed samples
or samples for testing at other than vertical
orientation.
61
SOIL BORING
62
Boring tools
64
Auger boring
Diamond drill bit
1. Holding verically and pressing it down while the
auger is rotated
2. Fills annular space
3. Upto depth of 6m in soft soils with or with out
casing
4. Samples are highly disturbed
5. For shallow foundaion, highways .etc
SHELL and AUGER method is widely used in india.
1. Water is forced under
pressure through a
hollow drill which may
be rotated or moved up
and down inside casing
2. Lower end has
chopping bit
Only boring can be done
and sample of no use
/ Wash boring
1. Breaking up the formation by repeated blows of
heavy bit or chisel inside casing pipe
2. Limited water forming slurry of pulverized material
and removed using bailer
3. Cables in place of drill rods
1. Cutting action of rotating
bit –kept in contact with
the bottom of hole
2. (Bentonite) Drilling mud is
used
3. Core-barrel with diamond
bits for rock cores
Boring tools
74
c) Sub-surface sounding
• The sounding method consists of measuring the resistance of the soil with the
depth by the means of penetrometer under static and dynamic loading.
• The penetrometer may consist of sampling spoon or cone or any other shaped
tool.
• The resistance to penetration is correlated with some engineering properties of
soil such as density index, consistency, bearing capacity etc.
• Thus in this method by using sounding , the resistance of soil is measured
which is useful for general exploration of erratic soil profiles , for finding depth
to bed rock or stratum.
• We can have an approximate induction of strength and other properties of soil.
• The two commonly used tests are standard penetration test and the cone
penetration test.
75
76
d) Geo Physical Methods
• Geo physical methods are used when the depth of exploration is very large, and
also when the speed of investigation is of primary importance.
• Geo physical investigations involve the detection of significant differences in
the physical properties of geological formations.
• The most commonly used methods of geophysical investigation are :
1. Seismic Refraction Method :
• The seismic refraction method is based on the property of seismic waves to
refract (or be bent) when they travel from one medium to another of different
density or elasticity.
• In this method, shock waves are created into the soil at their ground level or a
certain depth below it.
• The radiating shockwaves are picked up by the vibration detector (Geophone or
seismometer) where the time of travel of shock waves get recorded.
77
• Direct waves or primary waves travel directly from shock point along the ground
surface to be picked up by geophone.
• Refracted waves travel through the soil and also get refracted at the interface of two soil
strata. The refracted waves are also picked up by the geophone.
• If the underlying level is denser the refracted waves travel much faster and at longer
distances, the shock waves reach faster than the direct waves.
• Hence by distance-time graphs and analytical methods, the depth of various strata can
be evaluated by using the time of travel of primary and refracted waves.
• Seismic refraction method is fast & reliable in establishing the profile of different
strata.
• Different material such as gravel, clay hardpan or rock have characteristic properties
and hence can be identified by distance-time graphs.
• But for exact recognition and exploration, boring or sounding methods should be
supplemented along. 78
79
80
2. Electrical resistivity method
• The electrical resistivity method is based on the measurement and recording of changes
in the mean resistivity of various soils.
• Each soil has its own resistivity depending upon its composition , compaction, water
content etc.
• In this method , four metal spikes serve as electrodes which are drive into the ground
along a straight line at equal distance.
• A direct voltage is imposed between the outer two electrodes, and potential drop is
measured between the inner electrodes.
• The mean resistivity Ω (ohm-cm) is calculated by : Ω = 2 Π D E / I
D = Distance between electrodes. (cm)
E = Potential drop between inner electrodes. ( volts)
I = Current between outer electrodes. (ampere)
• The depth of exploration is roughly proportional to the electrode spacing .
• So to study greater depths, the electrode spacing is increased gradually and made
roughly equal to depth of exploration required. This method is know as resistivity
sounding.
81
82
Preparation of Boring Logs
1. Name and address of the drilling company
2. Driller’s name
3. Job description and number
4. Number, type, and location of boring
5. Date of boring
6. Subsurface stratification, which can he obtained by visual observation of
the soil brought out by auger, split-spoon sampler, and thin-walled
Shelby tube sampler
7. Elevation of water table and date observed, use of casing and mud losses,
and so on
8. Standard penetration resistance and the depth of SPT
9. Number, type, and depth of soil sample collected
10. In case of rock coring, type of core barrel used and, for each run, the
actual length of coring, length of core recovery, and RQD
83
85
SOIL SAMPLING
1. Two types of soil samples can be obtained during sampling
disturbed and undisturbed.
2. Reasonably good estimates of properties for cohesive soils
can be made by laboratory tests on undisturbed samples
which can be obtained with moderate difficulty.
3. It is nearly impossible to obtain a truly undisturbed sample of
soil; so in general usage the term "undisturbed" means a
sample where some precautions have been taken to
minimize disturbance or remolding effects.
4. In this context, the quality of an "undisturbed" sample varies
widely between soil laboratories.
86
Disturbed vs Undisturbed
• Disturbed samples are those where the natural soil
structure gets modified or destroyed during the
sampling operation.
• Natural moisture content and proportion of mineral
constituents are preserved
• “Representative samples”-useful in identification and
are partially deformed. The engineering properties
are changed, but the original fabric and structure
vary from unchanged to distorted, and are still
apparent. Such distortion occurs with split-barrel
samples.
• “Non-representative samples”- Alteration in original soil
structure,soils from other layers gets mixed up or the
mineral constituents gets altered
Extent of sample disturbance
• Cutting edge
• Inside wall friction
• Non-return valve
1) Inside clearance Ci=((D3-D1)/D1)x100
2) Outside clearance Co= ((D2-D4/D4)x100
3) Area ratio Ar= ((D2
2-D1
2)/D1
2)x100
• Inside clearance
1. Reduce friction between the soil sample and the
sampler when the soil enters, by allowing for elastic
expansion. If too large, there will be too much lateral
expansion
2. Should be between 1 to 3 percent
• Outside clearance
Reduce friction while sampler is being driven and when it is
being withdrawn after sample is collected
1. Not greater than inside clearance
2. Lies between 0 and 2 percent
• Area ratio
1. Kept as low as possible
2. Not greater than 20 percent for stiff formations and 10
percent for soft sensitive clays
Index of sample disturbance
Recovery ratio ,Lr=
𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑠𝑎𝑚𝑝𝑙𝑒
𝑃𝑒𝑛𝑒𝑡𝑟𝑎𝑡𝑖𝑜𝑛 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡ℎ𝑒 𝑠𝑎𝑚𝑝𝑙𝑒𝑟
• Lr=1
• Lr<1
• Lr>1
Disturbed vs Undisturbed
• Undisturbed samples-Original soil structure is
preserved and the material properties have not
undergone any alteration or modification.
• Undisturbed samples may display slight deformations
around their perimeter, but for the most part, the
engineering properties are unchanged. Such results
are obtained with tube or block samples.
• However an undisturbed sample may be considered
as one of in which the material has been subjected
to such a small disturbance that it is still suitable for
all lab test like shear strength and consolidation
Disturbed vs Undisturbed
(%)100
..
....
2
22



DI
DIDO
AR
92
Good quality samples necessary.
AR<10%
sampling tube
soil
area ratio
Thicker the wall, greater the disturbance.
Disturbed vs Undisturbed
93
SPLIT SPOON SAMPLER
• Split-Barrel Sampler (Split Spoon) (ASTM D1586-99)
Purpose
• Split-barrel samplers are used to obtain representative
samples suitable for field examination of soil texture and
fabric and for laboratory tests, including measurements
of grain size distribution, specific gravity, and plasticity
index, which require retaining the entire sample in a
large jar.
Sampler Description
• Split-barrel samplers are available with and without
liners; A common O.D. is 51mm and I.D 35mm. with ¼ in.
wall thickness (1½ in. sample). Larger diameters are used
for sampling gravelly soils. Lengths are either 18 or 24 in.
• A ball check valve prevents drill pipe fluid from pushing
the sample out during retrieval. To prevent sample
spillage during retrieval, flap valves can be installed in the
shoe for loose sands, or a leaf-spring core retainer
(basket) can be installed for very soft clays and fine
cohesion-less soils. Upon retrieval, the barrel between
the head and the shoe is split open, the sample is
examined and described, removed, and stored.
• In some sampler types, brass liners are used for
procuring drive samples of strong cohesive soils for
laboratory direct-shear testing.
Sampling Procedure
• The sampler is installed on the hole bottom, then driven
into the soil with a hammer falling on the drill rods. The
number of blows required for a given weight and drop
height, and a given penetration, are recorded to provide
a measure of soil compactness or consistency as in
Standard Penetration Test.
Thin-Wall Tube Samplers
Purpose
• Thin-wall tube samplers are used to obtain UD of soft to
stiff cohesive soils for laboratory testing of strength,
compressibility, and permeability.
Tube Materials
• Cold-drawn, seamless steel tubing (trade name “Shelby
tube”) is used for most soil materials; brass tubes are
used for organic soils where corrosion resistance is
required. Lacquer coating can provide corrosion
protection and reduce internal frictional resistance and
sample disturbance. and sample disturbance.
• Tube diameters and lengths range from 2 to 6 in. in diameter,
24 to 30 in. in length. 2 in. diameter samples have a large
ratio of perimeter disturbance to area and are considered too
small for reliable laboratory engineering-property testing.
• The tube should be provided with a cutting edge drawn in to
provide inside clearance (or 0.5 to 3% less than the tube
I.D.), which permits the sample to expand slightly upon
entering the tube, thereby relieving sample friction along the
walls and reducing disturbance.
• Tubes 4 to 6 in. in diameter reduce disturbance but require
more costly borings.
• Outside dia- 40 to 125mm
• Tickness 1.25 mm to 3.15mm
• Length- 5 to 10 times dia for sandy soil and 10 to 15 times dai
for clay
Operations
• Thin-wall tubes are normally pressed into the soil by
hydraulically applied force. After pressing, the sample is
left to rest in the ground for 2 to 3 min to permit slight
expansion and an increase in wall friction to aid in
retrieval. The rods and sampler are rotated clockwise
about two revolutions to free the sampler by shearing
the soil at the sampler bottom.
• The sample is withdrawn slowly from the hole with an
even pull and no jerking. In soft soils and loose granular
soils, the sampler bottom is capped just before it
emerges from the casing fluid to prevent the soil from
falling from the tube.
Shellby Tube Sampling
• A thin-wall tube is fitted to a head assembly that is attached
to drill rod. An “O ring” provides a seal between the head
and the tube, and a ball check valve prevents water in the
rods from flushing the sample out during retrieval.
Application is most satisfactory in firm to hard cohesive soils.
• Care is required that the sampler is not pressed to a
distance greater than its length.
• Soft soils are difficult to sample and retain because they
have insufficient strength to push the column of fluid in the
tube past the ball check valve. In stiff to hard cohesive soils,
samples are often taken by driving heavy-gage tubes.
ROCK SAMPLING - Definition
105
Rock Quality Designation
106
RQD
Rock Quality Designation (RQD) is defined as the percentage of rock cores that have
length equal or greater than 10 cm over the total drill length.
FIELD STRENGTH TESTS
The following are the major field tests for
determining the soil strength:
1. Vane shear test (VST).
2. Standard Penetration Test (SPT).
3. Cone Penetration Test (CPT).
4. The Plate Load Test (PLT).
107
Standard Penetration Test (SPT)
108
Standard Penetration Test (SPT)
109
Standard penetration test IS 2131-
1963
• Useful in determining the relative density and the angle
of shearing resistance of cohesion-less soils
• Also can find the compressive strength of cohesive soils
• Test is conducted in BH using split spoon sampler
• Drop hammer of weight 63.5 kg falling from a height of
75cm
• First 15 cm seating drive
• Number of blows required for next 30 cm penetration
was noted-SPT number
• Test is discontinued if the number of blows exceed 50
Standard Penetration Test (SPT)
Corrections are normally applied to the SPT blow
count to account for differences in:
• energy imparted during the test (60%
hammer efficiency)
• the stress level at the test depth
The following equation is used to compensate for
the testing factors (Skempton, 1986):
111
Standard Penetration Test (SPT)
112
SPT Correlations in Granular Soils
113
(N)60 Dr (%) consistency
0-4 0-15 very loose
4-10 15-35 loose
10-30 35-65 medium
30-50 65-85 dense
>50 85-100 very dense
•  = 28+0.15RD (degrees)
• it can vary 2
114
SPT Correlations in Clays
115
N60 cu (kPa) consistency visual identification
0-2 0 - 12 very soft Thumb can penetrate > 25 mm
2-4 12-25 soft Thumb can penetrate 25 mm
4-8 25-50 medium Thumb penetrates with moderate
effort
8-15 50-100 stiff Thumb will indent 8 mm
15-30 100-200 very stiff Can indent with thumb nail; not
thumb
>30 >200 hard Cannot indent even with thumb
nail
Use with caution; unreliable.
Cone penetration test
• Cone test was developed by Dutch government. Hence known as
Dutch cone test
• “IS: 4968 (Part-III)-1976—Method for subsurface sounding for
soils—Part III Static cone penetration test”.
• Static method or dynamic method
• STATIC METHOD
1. Cone is pushed downward by applying thrust at a steady rate of
10mm/sec through a depth of 35mm each time-Cone resistance
2. Cone is withdrawn and the sleeve is pushed on to the cone and
both are pushed together.-Combined resistance
3. Sleeve resistance-Combined resistance-Cone resistance
• Results of SCPT is compared with SPT
• Gravels- qc= 800N to 1000N
• Sands-qc= 500N to 600 N
• Silty sands qc= 300 N to 400 N
• Silts and Clayey silts qc- 200N
N is the SPT number
Cone Penetration Test (CPT)
119
Apex angle 60o
Diameter 35.7 mm
Cone Penetration Test (CPT)
120
Electrical Cone
Cone Penetrometer (CPT)
CPT Truck
Crawler Type CPT Truck
Typical CPT
Data
Cone Penetration Test (CPT)
127
Cone Penetration Test (CPT)
128
Type of clay Cone factor
Normally consolidated 11 – 19
Over consolidated
At shallow depth 15 to 20
At large depth 12 to 18
THANK YOU
130

More Related Content

What's hot (20)

Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Deep foundation
Deep foundationDeep foundation
Deep foundation
 
Shallow foundations
Shallow foundationsShallow foundations
Shallow foundations
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
DIFFERENT TYPE OF SHALLOW FOUNDATION
DIFFERENT TYPE OF SHALLOW FOUNDATIONDIFFERENT TYPE OF SHALLOW FOUNDATION
DIFFERENT TYPE OF SHALLOW FOUNDATION
 
Foundation
FoundationFoundation
Foundation
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Earth pressure
Earth pressureEarth pressure
Earth pressure
 
Well foundation
Well foundationWell foundation
Well foundation
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Foundation
FoundationFoundation
Foundation
 
Standard Penetration Test
Standard Penetration TestStandard Penetration Test
Standard Penetration Test
 
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
1. SELECTION OF FOUNDATION AND SUBSOIL EXPLORATION/INVESTIGATION (FE) 2180609...
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Bearing capacity of Soil
Bearing capacity of SoilBearing capacity of Soil
Bearing capacity of Soil
 
1)methods of exploration
1)methods of exploration1)methods of exploration
1)methods of exploration
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 

Similar to TYPES OF FOUNDATION AND COFFERDAM

Similar to TYPES OF FOUNDATION AND COFFERDAM (20)

Foundations
FoundationsFoundations
Foundations
 
Foundation
FoundationFoundation
Foundation
 
4. Types-of Foundations.pdf
4. Types-of Foundations.pdf4. Types-of Foundations.pdf
4. Types-of Foundations.pdf
 
Foundations grp 1
Foundations grp 1Foundations grp 1
Foundations grp 1
 
Building foundation
Building foundationBuilding foundation
Building foundation
 
Foundations
FoundationsFoundations
Foundations
 
Foundation
FoundationFoundation
Foundation
 
2-basics-of-foundation.ppt
2-basics-of-foundation.ppt2-basics-of-foundation.ppt
2-basics-of-foundation.ppt
 
foundationtypes-161207082056.pdf
foundationtypes-161207082056.pdffoundationtypes-161207082056.pdf
foundationtypes-161207082056.pdf
 
Foundation
FoundationFoundation
Foundation
 
CHAPTER-2.1 FOUNDATIONS.ppt
CHAPTER-2.1 FOUNDATIONS.pptCHAPTER-2.1 FOUNDATIONS.ppt
CHAPTER-2.1 FOUNDATIONS.ppt
 
Types of deep foundation
Types of deep foundationTypes of deep foundation
Types of deep foundation
 
special foundation techniques
 special foundation techniques special foundation techniques
special foundation techniques
 
Pile Foundation - Rohan Dasgupta.pdf
Pile Foundation - Rohan Dasgupta.pdfPile Foundation - Rohan Dasgupta.pdf
Pile Foundation - Rohan Dasgupta.pdf
 
Unit 3
Unit 3Unit 3
Unit 3
 
Study on foundation in Construction
Study on foundation in ConstructionStudy on foundation in Construction
Study on foundation in Construction
 
substructures ppt.ppt
substructures ppt.pptsubstructures ppt.ppt
substructures ppt.ppt
 
Presentation tos
Presentation tosPresentation tos
Presentation tos
 
Foundation_(Anshumi Tanna BCT-II).pptx
Foundation_(Anshumi Tanna BCT-II).pptxFoundation_(Anshumi Tanna BCT-II).pptx
Foundation_(Anshumi Tanna BCT-II).pptx
 
LECT 6 UPDATE.pdf
LECT  6 UPDATE.pdfLECT  6 UPDATE.pdf
LECT 6 UPDATE.pdf
 

More from dhara dattani

Global positioning system
Global positioning systemGlobal positioning system
Global positioning systemdhara dattani
 
Sources and de mand and water supply
Sources and de mand and water supplySources and de mand and water supply
Sources and de mand and water supplydhara dattani
 
Sewage treatment Disposal
Sewage treatment DisposalSewage treatment Disposal
Sewage treatment Disposaldhara dattani
 
Recycling of waste water
Recycling of waste waterRecycling of waste water
Recycling of waste waterdhara dattani
 
Quality &amp; quantity of water
Quality &amp; quantity of waterQuality &amp; quantity of water
Quality &amp; quantity of waterdhara dattani
 
Maintenance of sewer
Maintenance of sewerMaintenance of sewer
Maintenance of sewerdhara dattani
 
WATER AND WASTE WATER ENGINEERING- DIPLOMA GTU
WATER AND WASTE WATER ENGINEERING- DIPLOMA GTUWATER AND WASTE WATER ENGINEERING- DIPLOMA GTU
WATER AND WASTE WATER ENGINEERING- DIPLOMA GTUdhara dattani
 
Maintenance of water supply
Maintenance of water supplyMaintenance of water supply
Maintenance of water supplydhara dattani
 
Valves & Fittings WS&SE DIPLOMA ENGINEERING
Valves &  Fittings WS&SE DIPLOMA ENGINEERINGValves &  Fittings WS&SE DIPLOMA ENGINEERING
Valves & Fittings WS&SE DIPLOMA ENGINEERINGdhara dattani
 
Chapter 3 station,yards,points and crossing,signalling and interlocking
Chapter 3 station,yards,points and crossing,signalling and interlockingChapter 3 station,yards,points and crossing,signalling and interlocking
Chapter 3 station,yards,points and crossing,signalling and interlockingdhara dattani
 
Chapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainanceChapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainancedhara dattani
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent waydhara dattani
 
Subsoil exploiration
Subsoil exploirationSubsoil exploiration
Subsoil exploirationdhara dattani
 

More from dhara dattani (20)

Women's day 2021
Women's day 2021Women's day 2021
Women's day 2021
 
Global positioning system
Global positioning systemGlobal positioning system
Global positioning system
 
Plane table survey
Plane table surveyPlane table survey
Plane table survey
 
Sources and de mand and water supply
Sources and de mand and water supplySources and de mand and water supply
Sources and de mand and water supply
 
Sewage treatment Disposal
Sewage treatment DisposalSewage treatment Disposal
Sewage treatment Disposal
 
Sanitation systems
Sanitation systems Sanitation systems
Sanitation systems
 
Recycling of waste water
Recycling of waste waterRecycling of waste water
Recycling of waste water
 
Quality &amp; quantity of water
Quality &amp; quantity of waterQuality &amp; quantity of water
Quality &amp; quantity of water
 
Maintenance of sewer
Maintenance of sewerMaintenance of sewer
Maintenance of sewer
 
Drains and sewer
Drains and sewerDrains and sewer
Drains and sewer
 
WATER AND WASTE WATER ENGINEERING- DIPLOMA GTU
WATER AND WASTE WATER ENGINEERING- DIPLOMA GTUWATER AND WASTE WATER ENGINEERING- DIPLOMA GTU
WATER AND WASTE WATER ENGINEERING- DIPLOMA GTU
 
Maintenance of water supply
Maintenance of water supplyMaintenance of water supply
Maintenance of water supply
 
Treatment of water
Treatment of waterTreatment of water
Treatment of water
 
Valves & Fittings WS&SE DIPLOMA ENGINEERING
Valves &  Fittings WS&SE DIPLOMA ENGINEERINGValves &  Fittings WS&SE DIPLOMA ENGINEERING
Valves & Fittings WS&SE DIPLOMA ENGINEERING
 
Chapter 3 station,yards,points and crossing,signalling and interlocking
Chapter 3 station,yards,points and crossing,signalling and interlockingChapter 3 station,yards,points and crossing,signalling and interlocking
Chapter 3 station,yards,points and crossing,signalling and interlocking
 
Chapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainanceChapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainance
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent way
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
SHALLOW FOUNDATION
SHALLOW FOUNDATIONSHALLOW FOUNDATION
SHALLOW FOUNDATION
 
Subsoil exploiration
Subsoil exploirationSubsoil exploiration
Subsoil exploiration
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 

TYPES OF FOUNDATION AND COFFERDAM

  • 1. LECTION OF FOUNDATION MADE BY : MISS.DHARA DATTANI (ME TRANSPORTATAION) LECTURER AT ATMIYA INSTITUTE OF TECHNOLOGY AND SCIENCE FOR DIPLOMA STUDIES,RAJKOT.GUJRAT,INDIA. PART-1 1
  • 2. PART 1: TYPES OF FOUNDATION 2
  • 3. What s Foundation ? • Every building consists of two basic components : 1. The Super-structure 2. The Sub-structure • The substructure or foundation is that part of the structure which is usually below the ground level and in direct contact with the soil , through which the load of superstructure is transmitted to the soil. • The basic function of a foundation is to transmit the dead loads, superimposed loads and wind loads from a building (superstructure) to the soil in such a way that: a. Settlements are uniform and within permissible limit. & b. The soil does not fail. 3
  • 4. Functions of Foundations : 1. Reduction of load intensity. Foundations distribute the load of the superstructure to a larger area so the total intensity of load doesn't exceed the safe bearing capacity of soil. 2. Even distribution of load. Foundations distribute the non uniform load of the super structure evenly to the subsoil. 3. Provision of level surface. Foundations provide a levelled and hard surface over which a super-structure can be built. 4. Lateral stability. It anchors the super-structure to the ground thus imparting stability to the building. 5. Safety against undermining. It provides safety against undermining or scouring due to burrowing animals & flood water. 6. Protection against soil movements. Special measures prevent or minimise the distress (cracks) in superstructure, due to expansion or contraction of sub-soil. 4
  • 5. ESSENTIAL REQUIREMENTS FOR A GOOD FOUNDATION  The foundation shall be constructed to sustain load and transmit these to subsoil in such a way that pressure on it will not cause settlement which would impair the stability of the building.  Foundation should be rigid so that the differential settlements are minimised.  Specially for the case when superimposed loads are not evenly distributed.  Foundations should be taken sufficiently deep to guard the building against damage or distress caused by swelling or shrinkage of sub-soil.  Foundations should be so located that its performance may not be affected due to any unexpected future influence. 5
  • 6. • Types of Foundation Shallow Foundation Deep Foundation (A) Shallow Foundation: According to Terzaghi, a foundation is shallow if its depth is equal to or less than its width. (D<B) (B) Normally shallow foundation used upto 5m depth.also called open foundation • Types of Shallow Foundation:  Spread footing  Combined footing  Strap Footing  Mat Foundation or Raft Foundation  Grillage Foundation 6
  • 7. • Spread Footing/ Isolated column:-Spread footings are those which spread the super-imposed load of wall or column over larger area. Spread footing support either column or wall. • It may be following kinds • Stepped footing for column: This type of footing provided for heavily loaded column which required greater spread with steps. The base is generally made of concrete. Used in wall/column • Sloped footing for column: In this type of footing concrete base does not have uniform thickness but is made sloped. Generally used when sbc is low and hard strata is not found. • Wall footing without step: It consist of concrete base without any steps including masonry wall. • Stepped footing for wall: It consist of masonry wall have stepped footing with concrete base . 7
  • 8. 8
  • 9. • Grillage Foundation • It is special type of isolated footing generally provided for heavily loaded steel column and used in those location where bearing capacity of soil is poor. • The depth of such foundation is limited to 1 to 1.5 m. • This type of arrangement avoids deep excavation and provide necessary area at the base to reduce the intensity of pressure. 9
  • 10. 10
  • 11. Combined Footing: • A spread footing which supports two or more columns is termed as combined footing. • When two column are so close to each other that tier individual footing would over lap. • The combined footing may be of following kinds. • Rectangular combined footing: The combined footings will be provide in rectangular in shape if columns carry equal loads. The design of rectangular combined footing should be done in such way that centre of gravity of column coincide with centroid of footing area. • Trapezoidal combined footing: If columns carry unequal loads the footing is of trapezoidal shape are provided. • Combined column-wall footing: It may be required to provide a combined footing for column and wall. Such combined footing are shown in fig. 11
  • 12. 12
  • 13. 13
  • 14. Strap Footing: • It is a Independent footing of two columns are connected by a beam, it is called a strap footing. • The strap connects the two footings such that they behaves as one unit. • The strap does not remain in contact with soil and does not transfer any pressure to the soil. • A strap footing is more economical than a combined footing. • Also used when the distance between two column is large. 14
  • 15. 15
  • 16. Raft foundation:  A raft Foundation is a combined footing that covers the entire area beneath a structure and support all the wall and column.  When the allowable soil pressure is low.  When the structure loads are heavy  When there is a large variation in the loads on individual columns.  When foundation of soil is non homogeneous and there are chances of differential settlements. 16
  • 17. 17
  • 18. Deep foundation • Deep foundation are those in which the depth of foundation is very large in comparison to its width.(D>B). Deep foundation may be of following types • Pile foundation • Pier foundation • Caissons or Well foundation 18
  • 19. • Pile Foundation • Pile Foundation is that type of foundation in which the loads are taken to a low level by means of vertical members which may be timber, concrete or steel. • Pile foundation may be adopted when no firm bearing strata is available and the loading is uneven. • Piles may be of following types • End bearing piles • Friction Pile • Compaction pile Prepared By : Mr. Mayank M. Parekh 19
  • 20. • End bearing piles: This types of piles are used to transfer load through water or soft soil to a suitable bearing stratum. • Friction Pile: Friction piles are used to transfer loads to a depth of friction load carrying material by means of skin friction along the length of piles. • Compaction pile: Compaction piles are used to compact loose granular soils, thus increasing their bearing capacity. 20
  • 21. 21
  • 22. • Pier foundation: • A Pier foundation consist of cylindrical column of large diameter to support and transfer large superimposed load to the firm strata below. • Generally, pier foundation is shallow in depth than the pile foundation. 22
  • 23. 23
  • 24. • Well Foundation: • Well Foundation or Caisson are box like structures which are sunk from the surface of either land or water to the desired depth. • They are much larger than the pier foundation or drilled caissons. • Caisson foundations are used for major foundation works like • Bridge piers • Docks • Large water front structure such as pump house. 24
  • 25. 25
  • 26. 26
  • 27. Coffer dams: • A cofferdam is a temporary structure which is built in a river, lake etc. to remove water from an area and make it possible to carry on the construction work under reasonably dry conditions. • Cofferdams are usually required for project such as dams and construction of piers and abutment.
  • 28. Requirement of a cofferdam :- • The cofferdam should be reasonably watertight. • It should be generally constructed at site of work. • The design and layout of a cofferdam should be such that the total cost of construction, maintenance and pumping is minimum. • It should be stable against bursting, overturning and sliding, under the floods and waves. • The water to be excluded by a coffer dam may be either ground water of water lying above ground level, it may be deep or shallow and still or running. • The materials used in construction of a cofferdam are earth, timber, steel and concrete.
  • 29. Necessity of cofferdam :-  The coffer dams are required in the following situation: • When it is required to construct a structure in the river bad. • When structure is to be constructed on a sea shore. • When it is required to construct a structure one a bank of the lake or inside the lake. • When deep excavation are carried out in a course grained soil. • When excavation is carried out below ground water table. • During deep excavation, when sides of the trenches are likely to collapse.
  • 30. Use of cofferdam • To facilitate pile driving operation • To place grillage and raft foundation • To construct foundations for piers and abutments of bridge, dams, locks, etc.; • To enclose a space for the removal of sunken vessels • To provide a working platform for the foundation of building when water is met with; and • To provide space for carrying out the foundation work without disturbing or damaging the adjoining structure such as buildings, pipelines, sewers, etc.
  • 31. Types of cofferdam :- • Earthen cofferdam • Rock-filled cofferdams • Sand bags cofferdam • Single wall cofferdams • Double wall cofferdams • Cellular cofferdam
  • 32. Earthen cofferdam :- • This is the simplest form of cofferdam. It essentially consist of an earthen embankment built around the area to be enclosed. • Suitable for low, 1.2 to 1.5 m and moderate head of water. • The top of embankment should be 1m above the water level.
  • 33. Rock-filled cofferdams :- • Suitable for turbulent flow and up to 3m depth of water. • Stone or rubble is used for the embankment. • It construction is adopted only the stone is easily available in the nearby areas.
  • 34. Sand bags cofferdam :- • The method of using laminated sand bags to build cofferdam are easy to construct, cost-efficient and economic friendly
  • 35. Single wall cofferdams • This type of cofferdam is used in places where the area to be enclosed is very small and the depth of water is more, say 4.5 to 6 m. • It can be used for up to 25m depth of water.
  • 36. Double wall cofferdams :-  Two-parallel rows of steel sheet piles driven into the ground  Tied together with anchors and wales, then filled with soil  There are two types of this type of cofferdams: 1. ohio river type wood sheeting cofferdam 2. Wood or steel sheeting cofferdam with wales and tie rods
  • 37. Cellular cofferdams :- • Circular cells are connected by diaphragms • Deep excavations • Used when the construction area is very large • Also used when internal bracing is impractical • There are two types of this type of cofferdams: 1. Circular 2. Diaphragm
  • 38. • Foundations on Black Cotton Soil • Black cotton soils and other expansive soils have typical characteristics of shrinkage and swelling due to moisture movement through them. • When moisture enter between the soil particles under some hydrostatic pressure, the particles separate out, resulting in increase in the volume. • This increase in volume is commonly known as swelling. If this swelling is checked or restricted high swelling pressure, acting in the upward direction, will be induced. • This would result in several cracks in the walls and may some times damage the structural such as lintels, beams, slabs etc. • During summer season, moisture moves out of the soil and consequently, the soil shrinks. • Shrinkage cracks are formed on the ground surface. These shrinkage cracks some times also known as tension cracks, may be 10 to 15 cm wide on the ground surface. • Black cotton soils and other expansive soils are dangerous due to their shrinkage and swelling characteristics. • In addition, these soils have very poor bearing capacity, ranging from 5 t/m2 to 10 t/m2. 38
  • 39. • For designing footings on these soils, the following points should be kept in mind: • 1. The safe bearing capacity should be properly determined, taking into account the effect of sustained loading. The bearing capacity of these soils may be limited to 5 to 10 t/m2. 2. The foundation should be taken at least 50 cm lower than the depth of moisture movement. 3. Where this soil occurs only in top layer, and where the thickness of this layer does not exceed 1 to 1.5 m, the entire layer of black cotton soil should be removed, and the foundation should be laid on non-shrinkable non- expansive soil. 5. Where the soil is highly expansive, it is very essential to have minimum contact between the soil and the footing. This can be best achieved by transmitting the loads through deep piles. 6. Where the bearing capacity of soil is poor, or soil is very soft, the bed of the foundation trench should be made firm or hard by ramming mooram. 39
  • 40. Types of foundation in black cotton soils. Foundation in black cotton soils may be of the following types: 1. Strip foundation. For medium loads, strip foundation may be provided, along with special design features. 2. Pier foundation Piers are dug at regular interval and filled with cement concrete. The piers may rest on good bearing strata. 3. Under-reamed pile foundation. An under-reamed pile is a pile of shallow depth (1 to 6 m) having one bulb at its lower end. 40
  • 41. • Under-reamed Pile Foundation • Under-reamed piles are bored cast-in-situ concrete piles having bulk shaped enlargement near base. • These piles are commonly recommended for providing safe and economical foundations in expansive soils such as black cotton soil having poor bearing capacity. • In these type of foundation the structure is anchored to the ground at a depth where ground movement due to changes in moisture content negligible. • A pile having one bulk is known as single under-reamed pile. It is seen that the load bearing capacity of the pile can be increased by increasing the number of bulk at the base. • In such a case the pile is named as multi-under-reamed pile. The increase in the bearing capacity of the pile can also be achieved by increasing the diameter and the length of the pile. 41
  • 42. • The method of construction of under-reamed pile is very simple. The holes for casting piles in the ground may be bored by using hand augers. • After boring is carried out at the required depth, the base of the bore hole is enlarged in the form of a bulb near its base by use of a tool, known under-reamer. • After the pile holes are ready for concreting, reinforcement cage are lowered in the holes and concrete is poured. • The piles should be cast at least 200 to 400 mm above the cut-off level. Later on, when the concrete is hardened, the extra length of each pile is broken and the pile top is brought to the desired level. • Thus, besides relative saving in direct cost (when compared with conventional isolated footings) it is possible to have overall saving in time of completion of a work by adopting under-reamed piles. 42
  • 43. Prepared By : Mr. Mayank M. Parekh 43
  • 44. Part 2: SUBSOIL EXPLORATION… 44
  • 45. Definition •The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally referred to as site investigation. • The field and laboratory studies carried out for obtaining the necessary information about the sub soil characteristics including the position of ground water table are termed as soil exploration 45
  • 46. METHODS OF EXPLORATION 1. Preliminary exploration Local topography, excavations, cuttings, drainage pattern and other natural features like streams, flood marks etc. Geophysical methods 2. Detailed investigation Nature, sequence and thickness of layers. Borings and detailed sampling, in-situ test.
  • 47. OBJECTIVES OF SITE INVESTIGATION 1. Site selection. 2. Foundation and earthworks design. 3. Temporary works design. 4. The effects of the proposed project on its environment. 5. Investigation of existing construction. 6. The design of remedial works. 7. Safety checks.
  • 48. EXPLORATION PROGRAM The purpose of the exploration program is to determine, within practical limits, the stratification and engineering properties of the soils underlying the site. The principal properties of interest will be the strength, deformation, and hydraulic characteristics. The program should be planned so that the maximum amount of information can be obtained at minimum cost. 48
  • 49. The general objective of an exploration program is to identify all of the significant features of the geologic environment that may impact on the proposed construction. Specific objectives are to: 1. Define the lateral distribution and thickness of soil and rock strata within the zone of influence of the proposed construction. 2. Define groundwater conditions considering seasonal changes and the effects of construction or development extraction. 3. Identify geologic hazards, such as unstable slopes, faults, ground subsidence and collapse, floodplains, regional seismicity, and lahars.
  • 50. 4. Procure samples of geologic materials for the identification, classification, and measurement of engineering properties. 5. Perform in situ testing to measure the engineering properties of the geologic materials
  • 51. The purpose of a soil investigation program 1. Selection of the type and the depth of foundation suitable for a given structure. 2. Evaluation of the load-bearing capacity of the foundation. 3. Estimation of the probable settlement of a structure. 4. Determination of potential foundation problems (for example, expansive soil, collapsible soil, landfill, and so on). 5. Establishment of ground water table. 6. Prediction of lateral earth pressure for structures like retaining walls, sheet pile bulkheads, and braced cuts. 7. Establishment of construction methods for changing subsoil conditions. 51
  • 52. If only they had proper site investigation… 52 …Tower of Pisa will not be leaning today!
  • 53. Depth of Boring 1. Determine the net increase of stress, under a foundation with depth as shown in the Figure. 2. Estimate the variation of the vertical effective stress, ', with depth. 3. Determine the depth, D = D1, at which the stress increase  is equal to (1/10) q (q = estimated net stress on the foundation). 4. Determine the depth, D = D2, at which /' = 0.05. 5. Unless bedrock is encountered, the smaller of the two depths, D1 and D2, just determined is the approximate minimum depth of boring required. Table shows the minimum depths of borings for buildings based on the preceding rule. 53
  • 54. Depth of Boring 54 Determination of the minimum depth of boring
  • 55. Building width Number of Storeys 1 2 4 8 16 Boring Depth 30.5 3.4 6.1 10.1 16.2 24.1 61 3.7 6.7 12.5 20.7 32.9 122 3.7 7 13.7 24.7 41.5
  • 56. Depth of Boring When deep excavations are anticipated, the depth of boring should be at, least 1.5 times the depth of excavation. Sometimes subsoil conditions are such that the foundation load may have to be transmitted to the bedrock. The minimum depth of core boring into the bedrock is about 3m. If the bedrock is irregular or weathered, the core borings may have to be extended to greater depths. 56
  • 57.
  • 58.
  • 59. Spacing Boring There are no hard and fast rules for the spacing of the boreholes. The following table gives some general guidelines for borehole spacing. These spacing can be increased or decreased, depending on the subsoil condition. If various soil strata are more or less uniform and predictable, the number of boreholes can be reduced. 59
  • 60.
  • 61. SOIL BORING The earliest method of obtaining a test hole was to excavate a test pit using a pick and shovel. Because of economics, the current procedure is to use power-excavation equipment such as a backhoe to excavate the pit and then to use hand tools to remove a block sample or shape the site for in situ testing. This is the best method at present for obtaining quality undisturbed samples or samples for testing at other than vertical orientation. 61
  • 63.
  • 66. 1. Holding verically and pressing it down while the auger is rotated 2. Fills annular space 3. Upto depth of 6m in soft soils with or with out casing 4. Samples are highly disturbed 5. For shallow foundaion, highways .etc SHELL and AUGER method is widely used in india.
  • 67. 1. Water is forced under pressure through a hollow drill which may be rotated or moved up and down inside casing 2. Lower end has chopping bit Only boring can be done and sample of no use / Wash boring
  • 68. 1. Breaking up the formation by repeated blows of heavy bit or chisel inside casing pipe 2. Limited water forming slurry of pulverized material and removed using bailer 3. Cables in place of drill rods
  • 69. 1. Cutting action of rotating bit –kept in contact with the bottom of hole 2. (Bentonite) Drilling mud is used 3. Core-barrel with diamond bits for rock cores
  • 70.
  • 71.
  • 72.
  • 73.
  • 75. c) Sub-surface sounding • The sounding method consists of measuring the resistance of the soil with the depth by the means of penetrometer under static and dynamic loading. • The penetrometer may consist of sampling spoon or cone or any other shaped tool. • The resistance to penetration is correlated with some engineering properties of soil such as density index, consistency, bearing capacity etc. • Thus in this method by using sounding , the resistance of soil is measured which is useful for general exploration of erratic soil profiles , for finding depth to bed rock or stratum. • We can have an approximate induction of strength and other properties of soil. • The two commonly used tests are standard penetration test and the cone penetration test. 75
  • 76. 76
  • 77. d) Geo Physical Methods • Geo physical methods are used when the depth of exploration is very large, and also when the speed of investigation is of primary importance. • Geo physical investigations involve the detection of significant differences in the physical properties of geological formations. • The most commonly used methods of geophysical investigation are : 1. Seismic Refraction Method : • The seismic refraction method is based on the property of seismic waves to refract (or be bent) when they travel from one medium to another of different density or elasticity. • In this method, shock waves are created into the soil at their ground level or a certain depth below it. • The radiating shockwaves are picked up by the vibration detector (Geophone or seismometer) where the time of travel of shock waves get recorded. 77
  • 78. • Direct waves or primary waves travel directly from shock point along the ground surface to be picked up by geophone. • Refracted waves travel through the soil and also get refracted at the interface of two soil strata. The refracted waves are also picked up by the geophone. • If the underlying level is denser the refracted waves travel much faster and at longer distances, the shock waves reach faster than the direct waves. • Hence by distance-time graphs and analytical methods, the depth of various strata can be evaluated by using the time of travel of primary and refracted waves. • Seismic refraction method is fast & reliable in establishing the profile of different strata. • Different material such as gravel, clay hardpan or rock have characteristic properties and hence can be identified by distance-time graphs. • But for exact recognition and exploration, boring or sounding methods should be supplemented along. 78
  • 79. 79
  • 80. 80
  • 81. 2. Electrical resistivity method • The electrical resistivity method is based on the measurement and recording of changes in the mean resistivity of various soils. • Each soil has its own resistivity depending upon its composition , compaction, water content etc. • In this method , four metal spikes serve as electrodes which are drive into the ground along a straight line at equal distance. • A direct voltage is imposed between the outer two electrodes, and potential drop is measured between the inner electrodes. • The mean resistivity Ω (ohm-cm) is calculated by : Ω = 2 Π D E / I D = Distance between electrodes. (cm) E = Potential drop between inner electrodes. ( volts) I = Current between outer electrodes. (ampere) • The depth of exploration is roughly proportional to the electrode spacing . • So to study greater depths, the electrode spacing is increased gradually and made roughly equal to depth of exploration required. This method is know as resistivity sounding. 81
  • 82. 82
  • 83. Preparation of Boring Logs 1. Name and address of the drilling company 2. Driller’s name 3. Job description and number 4. Number, type, and location of boring 5. Date of boring 6. Subsurface stratification, which can he obtained by visual observation of the soil brought out by auger, split-spoon sampler, and thin-walled Shelby tube sampler 7. Elevation of water table and date observed, use of casing and mud losses, and so on 8. Standard penetration resistance and the depth of SPT 9. Number, type, and depth of soil sample collected 10. In case of rock coring, type of core barrel used and, for each run, the actual length of coring, length of core recovery, and RQD 83
  • 84.
  • 85. 85
  • 86. SOIL SAMPLING 1. Two types of soil samples can be obtained during sampling disturbed and undisturbed. 2. Reasonably good estimates of properties for cohesive soils can be made by laboratory tests on undisturbed samples which can be obtained with moderate difficulty. 3. It is nearly impossible to obtain a truly undisturbed sample of soil; so in general usage the term "undisturbed" means a sample where some precautions have been taken to minimize disturbance or remolding effects. 4. In this context, the quality of an "undisturbed" sample varies widely between soil laboratories. 86
  • 87. Disturbed vs Undisturbed • Disturbed samples are those where the natural soil structure gets modified or destroyed during the sampling operation. • Natural moisture content and proportion of mineral constituents are preserved • “Representative samples”-useful in identification and are partially deformed. The engineering properties are changed, but the original fabric and structure vary from unchanged to distorted, and are still apparent. Such distortion occurs with split-barrel samples.
  • 88. • “Non-representative samples”- Alteration in original soil structure,soils from other layers gets mixed up or the mineral constituents gets altered Extent of sample disturbance • Cutting edge • Inside wall friction • Non-return valve 1) Inside clearance Ci=((D3-D1)/D1)x100 2) Outside clearance Co= ((D2-D4/D4)x100 3) Area ratio Ar= ((D2 2-D1 2)/D1 2)x100
  • 89. • Inside clearance 1. Reduce friction between the soil sample and the sampler when the soil enters, by allowing for elastic expansion. If too large, there will be too much lateral expansion 2. Should be between 1 to 3 percent • Outside clearance Reduce friction while sampler is being driven and when it is being withdrawn after sample is collected 1. Not greater than inside clearance 2. Lies between 0 and 2 percent
  • 90. • Area ratio 1. Kept as low as possible 2. Not greater than 20 percent for stiff formations and 10 percent for soft sensitive clays Index of sample disturbance Recovery ratio ,Lr= 𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑒𝑑 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑠𝑎𝑚𝑝𝑙𝑒 𝑃𝑒𝑛𝑒𝑡𝑟𝑎𝑡𝑖𝑜𝑛 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑡ℎ𝑒 𝑠𝑎𝑚𝑝𝑙𝑒𝑟 • Lr=1 • Lr<1 • Lr>1
  • 91. Disturbed vs Undisturbed • Undisturbed samples-Original soil structure is preserved and the material properties have not undergone any alteration or modification. • Undisturbed samples may display slight deformations around their perimeter, but for the most part, the engineering properties are unchanged. Such results are obtained with tube or block samples. • However an undisturbed sample may be considered as one of in which the material has been subjected to such a small disturbance that it is still suitable for all lab test like shear strength and consolidation
  • 92. Disturbed vs Undisturbed (%)100 .. .... 2 22    DI DIDO AR 92 Good quality samples necessary. AR<10% sampling tube soil area ratio Thicker the wall, greater the disturbance.
  • 94. SPLIT SPOON SAMPLER • Split-Barrel Sampler (Split Spoon) (ASTM D1586-99) Purpose • Split-barrel samplers are used to obtain representative samples suitable for field examination of soil texture and fabric and for laboratory tests, including measurements of grain size distribution, specific gravity, and plasticity index, which require retaining the entire sample in a large jar.
  • 95.
  • 96.
  • 97. Sampler Description • Split-barrel samplers are available with and without liners; A common O.D. is 51mm and I.D 35mm. with ¼ in. wall thickness (1½ in. sample). Larger diameters are used for sampling gravelly soils. Lengths are either 18 or 24 in. • A ball check valve prevents drill pipe fluid from pushing the sample out during retrieval. To prevent sample spillage during retrieval, flap valves can be installed in the shoe for loose sands, or a leaf-spring core retainer (basket) can be installed for very soft clays and fine cohesion-less soils. Upon retrieval, the barrel between the head and the shoe is split open, the sample is examined and described, removed, and stored.
  • 98. • In some sampler types, brass liners are used for procuring drive samples of strong cohesive soils for laboratory direct-shear testing. Sampling Procedure • The sampler is installed on the hole bottom, then driven into the soil with a hammer falling on the drill rods. The number of blows required for a given weight and drop height, and a given penetration, are recorded to provide a measure of soil compactness or consistency as in Standard Penetration Test.
  • 99. Thin-Wall Tube Samplers Purpose • Thin-wall tube samplers are used to obtain UD of soft to stiff cohesive soils for laboratory testing of strength, compressibility, and permeability. Tube Materials • Cold-drawn, seamless steel tubing (trade name “Shelby tube”) is used for most soil materials; brass tubes are used for organic soils where corrosion resistance is required. Lacquer coating can provide corrosion protection and reduce internal frictional resistance and sample disturbance. and sample disturbance.
  • 100.
  • 101. • Tube diameters and lengths range from 2 to 6 in. in diameter, 24 to 30 in. in length. 2 in. diameter samples have a large ratio of perimeter disturbance to area and are considered too small for reliable laboratory engineering-property testing. • The tube should be provided with a cutting edge drawn in to provide inside clearance (or 0.5 to 3% less than the tube I.D.), which permits the sample to expand slightly upon entering the tube, thereby relieving sample friction along the walls and reducing disturbance. • Tubes 4 to 6 in. in diameter reduce disturbance but require more costly borings. • Outside dia- 40 to 125mm • Tickness 1.25 mm to 3.15mm • Length- 5 to 10 times dia for sandy soil and 10 to 15 times dai for clay
  • 102. Operations • Thin-wall tubes are normally pressed into the soil by hydraulically applied force. After pressing, the sample is left to rest in the ground for 2 to 3 min to permit slight expansion and an increase in wall friction to aid in retrieval. The rods and sampler are rotated clockwise about two revolutions to free the sampler by shearing the soil at the sampler bottom. • The sample is withdrawn slowly from the hole with an even pull and no jerking. In soft soils and loose granular soils, the sampler bottom is capped just before it emerges from the casing fluid to prevent the soil from falling from the tube.
  • 103. Shellby Tube Sampling • A thin-wall tube is fitted to a head assembly that is attached to drill rod. An “O ring” provides a seal between the head and the tube, and a ball check valve prevents water in the rods from flushing the sample out during retrieval. Application is most satisfactory in firm to hard cohesive soils. • Care is required that the sampler is not pressed to a distance greater than its length. • Soft soils are difficult to sample and retain because they have insufficient strength to push the column of fluid in the tube past the ball check valve. In stiff to hard cohesive soils, samples are often taken by driving heavy-gage tubes.
  • 104.
  • 105. ROCK SAMPLING - Definition 105
  • 106. Rock Quality Designation 106 RQD Rock Quality Designation (RQD) is defined as the percentage of rock cores that have length equal or greater than 10 cm over the total drill length.
  • 107. FIELD STRENGTH TESTS The following are the major field tests for determining the soil strength: 1. Vane shear test (VST). 2. Standard Penetration Test (SPT). 3. Cone Penetration Test (CPT). 4. The Plate Load Test (PLT). 107
  • 110. Standard penetration test IS 2131- 1963 • Useful in determining the relative density and the angle of shearing resistance of cohesion-less soils • Also can find the compressive strength of cohesive soils • Test is conducted in BH using split spoon sampler • Drop hammer of weight 63.5 kg falling from a height of 75cm • First 15 cm seating drive • Number of blows required for next 30 cm penetration was noted-SPT number • Test is discontinued if the number of blows exceed 50
  • 111. Standard Penetration Test (SPT) Corrections are normally applied to the SPT blow count to account for differences in: • energy imparted during the test (60% hammer efficiency) • the stress level at the test depth The following equation is used to compensate for the testing factors (Skempton, 1986): 111
  • 113. SPT Correlations in Granular Soils 113 (N)60 Dr (%) consistency 0-4 0-15 very loose 4-10 15-35 loose 10-30 35-65 medium 30-50 65-85 dense >50 85-100 very dense
  • 114. •  = 28+0.15RD (degrees) • it can vary 2 114
  • 115. SPT Correlations in Clays 115 N60 cu (kPa) consistency visual identification 0-2 0 - 12 very soft Thumb can penetrate > 25 mm 2-4 12-25 soft Thumb can penetrate 25 mm 4-8 25-50 medium Thumb penetrates with moderate effort 8-15 50-100 stiff Thumb will indent 8 mm 15-30 100-200 very stiff Can indent with thumb nail; not thumb >30 >200 hard Cannot indent even with thumb nail Use with caution; unreliable.
  • 116.
  • 117. Cone penetration test • Cone test was developed by Dutch government. Hence known as Dutch cone test • “IS: 4968 (Part-III)-1976—Method for subsurface sounding for soils—Part III Static cone penetration test”. • Static method or dynamic method • STATIC METHOD 1. Cone is pushed downward by applying thrust at a steady rate of 10mm/sec through a depth of 35mm each time-Cone resistance 2. Cone is withdrawn and the sleeve is pushed on to the cone and both are pushed together.-Combined resistance 3. Sleeve resistance-Combined resistance-Cone resistance
  • 118. • Results of SCPT is compared with SPT • Gravels- qc= 800N to 1000N • Sands-qc= 500N to 600 N • Silty sands qc= 300 N to 400 N • Silts and Clayey silts qc- 200N N is the SPT number
  • 119. Cone Penetration Test (CPT) 119 Apex angle 60o Diameter 35.7 mm
  • 120. Cone Penetration Test (CPT) 120
  • 123.
  • 127. Cone Penetration Test (CPT) 127
  • 128. Cone Penetration Test (CPT) 128
  • 129. Type of clay Cone factor Normally consolidated 11 – 19 Over consolidated At shallow depth 15 to 20 At large depth 12 to 18