Pile foundation
Prepared by:
Thaiyam Sameer K.
Assistant Professor
Darshan Institute of Engineering & Technology
Rajkot.
Pile foundation
• Introduction
• Use of piles
• Selection of type of pile
• Types of piles
• Pile cap and pile shoes
• Pile driving equipment and method
• Micro piling
• Pulling of piles
• Causes of failure of pile
Types of foundation
• Shallow foundation
• Deep foundation
• Pile foundation
• Cofferdam foundation
• Caissons foundation
What is pile ?
• A pile is a slender structural member made of concrete, steel, wood
or composite material.
• A pile is either driven into the soil or formed in-site by excavating a
hole and filling it with concrete.
Pile foundation
• Pile foundation is that type of deep foundation in which the loads are
taken to a low level by means of vertical members which may be
 Timber
 Concrete
 steel
Uses of Piles
• The load of the super-structure is heavy and its distribution is uneven.
• The top soil has poor bearing capacity.
• The subsoil water is high so that pumping of water from the open
trenches for the shallow foundation is difficult and uneconomical.
• Large fluctuation in subsoil water level.
• The structure is situated on sea shore or river bed, where there is
danger of scouring action of water.
• Canal or deep drainage line exist near the foundation.
• For foundation of transmission towers and off-shore platforms which
are subjected to uplift forces.
Scouring
Off shore platform
Transmission Tower
Factor Affecting Selection Of Type Of Piles
• Nature and type of structure
• Location
• Material, equipment and fund availability
• Type of soil and its properties
• Ground water table
• Durability of pile
• Length and number of pile
• Case study of adjacent building
• Facility for pile driving
• Erosion of soil near structure
Classification of Piles
• Based on function
• Based on materials
• Based on method of installation
Based on function
• End bearing Pile
• Friction Pile
• Compaction Pile
• Tension Pile
• Anchor Pile
• Fender Pile
• Better Pile
• sheet Pile
End bearing Pile
• Penetrate through the soft soil
• Bottom or tips rest on hard
strata
• Work as column
• For this pile Qu=Qp
where, Qu=ultimate load
Qp= Pile load
Friction Pile
• Loose soil extend to a greater depth
• Pile are driven at depth when friction
resistance developed equal to load
• In that case Qu=Qs (Qs= skin friction)
• Total friction resistance can be increased
• Increasing length and diameter
• Making Pile surface rough
• Placing closely or grouping of pile
Compaction Pile
• Pile do not carry any load
• For increase the bearing
capacity of soil
Tension pile
• When structure subjected
to uplift due to hydrostatic
pressure or over turning
moment
• Also known as uplift pile
Anchor piles
• These provided anchorage
against the horizontal pull
from sheet pulling or any
other pulling.
Fender pile
• These are used to protect
water front structures
against impact from ships
or other floating objects.
Better Pile
• They are used for resist
large horizontal forces or
inclined forces.
Sheet Pile
• They are used as bulk
heads or as impervious
cutoff to reduce seepage
and uplift under hydraulic
structures.
• Sheet pile is classified as,
1. Concrete sheet piles
2. Steel sheet pile
3. Timber sheet pile
Classification Based on Pile Material
• Concrete pile
• Steel piles
• Timber piles
• Composite pile
• Sand pile
Concrete Piles
• Pre cast piles
• Cast-in-situ
• Pre stressed
Pre Cast Concrete Pile
• It is those which are manufactured in factory or at a place away from
the construction site and then driven into ground at the place
required.
• It requires heavy pile driving machinery.
• It may be square, octagonal or circular in cross section.
• Size of pile vary from 30 cm to 50 cm in cross section and up to 20 m
or more length.
• Grade of concrete should be M20.
Cast In Situ
• A bore is dug into the ground by inserting a casing.
• Bore is filled with cement concrete after placing
reinforcement
• The casing be kept in position or it may be withdraw.
• The piles with casing are known as cased cast in situ
concrete pile.
• The piles without casing are known as uncased cast in situ
concrete pile.
Cased
• Raymond piles
• Mac Arthur piles
• BSP base driven piles
• Swage piles
• Button bottom piles
Raymond Pile
• It used primarily as a friction pile.
• It is provided with uniform taper of 1 in 30
shorter pile.
• The length of piles vary from 6 to 12 m.
• Top diameter= 40 to 60 cm.
• Bottom diameter = 20 to 30 cm
• Collapsible mandrel is driven into ground.
• When the pile is driven to the desired
depth mandrel is collapsed and withdraw.
• The shell is gradually filled with concrete
up to the top.
Mac Arthur pile
• Mac Arthur is pile of uniform diameter
using the corrugated steel shell which
remain in place as in Raymond piles.
• A heavy steel casing with a core is
driven into the ground.
• When the desired depth is reached,
the core is withdrawn and a
corrugated steel shell is placed in the
casing.
• Concrete is placed in the shell by
gradually compacting and withdrawing
the steel casing.
BSP base driven piles
• This pile consist of a helically welded
shell of steel plate.
• A concrete plug is provided at the
bottom of the shell.
• Driving is done by allowing hammer to
fall on the concrete plug.
• The casing is driven to the desired depth
and then it is filled with concrete.
Swage piles
• It is used with advantage of driving in very
hard or it is designed to leave water tight
shell for some time filling of the concrete.
• steel shell is placed on a precast concrete
plug
• Pipe is driven over plug until the core
reached the plug, then pipe is swage out by
tapper of plug which form water tight joint.
• Pipe is driven up to specified depth by help
of driven force of core.
• Core is removed and pipe is filled with
concrete.
Button Bottom piles
• It is used where increase of end bearing
area is required.
• Pile use concrete plug shape of button
which enlarge hole in soil during driving.
• It used for length up to 23 m and load up
to 50 tones.
• 12 mm thick steel pipe set on concrete
button which have diameter of 25 mm.
• Pipe and button driven to specified depth.
• The casing is removed and concrete is
placed with reinforcement.
Uncased
• Simplex
• Franki
• Vibro
• Pedestal
• Pressure
Simplex Piles
• Simplex piles can be driven through
soft or hard soil.
• Steel tube fitted with a cast iron
shoe is driven into ground up to
desired depth.
• If Reinforcement is necessary it put
in tube then concrete is poured in
pile.
• Tube is withdrawn slowly without
concrete being tamped.
Franki Piles
• It is used at placed where high load is
transfer.(ex .marine structure)
• Plug of dry concrete is formed on
ground by heavy removable pipe shell.
• By help of Diesel operated hammer of
20 to 30 KN weight plug is driven at
desired depth.
• Diameter of pile is 50 to 60 cm ,while
at enlargement is about 90 cm.
• Capacity of pile is 60 tones to 90 tones.
Vibro Piles
• This type of pile is best suited for places where
the ground is soft and offers little frictional
resistance to the flow of concrete.
• Pile are formed by driving a steel tube and shoe,
filling with concrete and withdraw steel tube.
• Diameter of pile 35 to 50 cm for load of 60 to 70
tones. Length of pile is 25 m and above.
• Steel tube fitted with cast iron shoe by 2-2.5
tone hammer by 40 blow per minute, with stroke
about 1.4 m
• When shoe and tube reached the desired level
tube is filled with concrete and tube is
withdrawn at 80 blow per minute by hammer.
• Steel tube is withdrawn leaving the shoe in place
and pile is formed with corrugation along its
height.
Pedestal Pile
• It is used where thin bearing stratum is
reached with reasonable depth.
• Pedestal pile gives the effect of spread
footing on thin bearing stratum.
• Core and casing are driven together
into the ground till reached the desired
level.
• Core is taken out and a charge of
concrete is placed in the tube.
• The core is again placed in the casing
to rest on the top of poured concrete.
• Pressure is applied on the concrete
though the core, and as the same time
the casing is withdrawn.
Pressure Pile
• These piles are especially suitable for
congested site where heavy vibration and
noise are not permissible.
• Boring is done up to required depth to tube.
• After withdrawn boring tool reinforcement is
placed if required.
• A layer of concrete is laid and pressure cap is
provided at the top of tube.
• Compressed air is admitted through pipe
which cause rise the tube.
• Tube is lifted same time of concreting is doing
by means of compressed air.
• Care should be taken that some portion of
concrete remain at bottom when tube is
lifting for receiving new layer.
Steel Piles
• Commonly used steel piles are;
 H-piles
 Box piles
 Tube piles
H-piles
• These pile are usually of wide
flange section.
• They are suitable for trestle type
structure in which pile extend
above ground level and act as
column.
• They have small cross section
area, there for they can be easily
driven In soil.
• It used as long pile with high
bearing capacity.
Box Piles
• They are rectangular or
octagonal in form filled with
concrete.
• These pile are used when not
possible to drive H-piles into
hard strata.
Tube Piles
• Tubes or piles of steel are driven
into the ground.
• Concrete is filled inside the tube
piles.
• Because of circular cross section
tube piles are easy to handle
and easy to drive in.
Timber Piles
• These pile are prepared from trunks
of trees.
• They may be circular or square .
• Diameter of pile are 30 to 50 cm and
length not exceeding 20 times its top
width.
• At bottom, a cast-iron shoe is
provided and at the top a steel plate
is fixed.
• For group pile each pile is brought at
same level and concrete plate is
provided to have common platform.
Composite Piles
• This is a type of construction in
which piles of two different
material are driven one over the
other.
• They act together to perform the
function of a single pile.
• In this pile advantage is taken of
durability of concrete piles and the
cheapest of timber pile.
• Timber pile is terminated just at
the level of ground water table.
Sand Piles
• These pile are formed by making hole in
ground and fill with the sand and well
rammed.
• The sand to be used should be moist at
time of placing.
• Bore hole diameter usually 30 cm. length
of sand pile is kept about 12 times its
diameter.
• The top of sand pile is filled with
concrete.
• Sand pile are placed at 2 to 3 m spacing.
• Load test should be carried out
determining the bearing capacity of sand
pile.
• Properly compacted sand pile can carry
load up to 100 tone/m2 or more.
Classification Based on Method of Installation
• Driven pile
• Driven and cast-in-situ pile
• Bore and cast-in-situ piles
• Screw piles
• Jacked pile
Driven pile
• These pile are driven into
ground by applying blow with a
heavy hammer.
• Timber, steel and precast
concrete pile are installed by
driving.
Driven and cast-in-situ
pile
• These pile are formed by driving
a casing with a closed bottom
end into the soil .
• The casing is later filled with
concrete.
• The casing may or may not be
withdrawn.
Bore And Cast-in-Situ
Piles
• These pile are formed by
excavating a hole into the
ground and then filling it with
concrete.
Screw Piles
Jacked pile
• These piles are jacked into the
ground by applying a downward
force by a hydraulic jack.
Under Reamed Piles
• These piles are developed by
C.B.R.I for serving foundation for
black cotton soils, filled up ground
and other type of soil having poor
bearing capacity.
Under reamed piles
• An under reamed pile is bored cast-in-situ
concrete pile having one or more bulbs or under
reamed in its lower level.
• The bulb or under reamed are formed by under
reaming tool.
• Diameter of pile is 20 to 50 cm and bulb diameter
is 2-3 times of diameter of pile.
• Length of pile is 3 to 8 m and spacing between
piles are 2 to 4 m.
• Load carrying capacity can increase by making
more bulb at the base.
• The vertical spacing between two bulb is varies
from 1.25 to 1.5 times diameter of bulb.
• For black cotton soil the bulb is increase bearing
capacity and also provide anchorage against
uplift.
Construction of Under Reamed Piles
• The equipment required for the construction of pile are,
1. Spiral auger - for boring
2. Under reamer - for making bulb
3. Boring guide -to keep the hole vertical
Boring Using
Spiral Auger
Making Bulb Using
Under Reamer
Placing of Concrete
Placing of
Reinforcement
Pile Accessories
• Pile cap
• Pile shoe
Pile Cap
• To protect the top of pile from blow
of hammer on top, pile cap is
provided.
• Pile carry load from structure and
distribute it to various pile.
• Generally, Pile cap is made of steel.
Thickness and size of cap is depend
on shape and size of pile hammer.
• Pile should penetrate into the cap
at least 10 cm length.
• For group pile a common R.C.C. is
provided for all the pile.
Pile shoe
• There for pile shoe is fitted at
bottom end of pile to protect the
pile and to facilitate easy pile
driving.
• Pile shoe are made of cast iron,
steel or wrought iron.
• Various types of shoe are;
Square pile shoe
Wedged shaped pile shoe
Round pile shoe
Steel trap pile shoe for timber pile
Socket type pile shoe for timber pile
 closed end shoe for pipe piles
Pile driving Equipment
• The operation of inserting pile into ground is known as pile driving.
• Pile are driven into the ground by means of hammer.
• The equipment used for lifting hammer and allow to fall on head of
pile is known as Pile driver.
• Various method for pile driving are;
• Hammer driving
• Vibratory pile driver
• Watter jetting and hammering
• Partial angering method
Factor for selection of pile driving method
• Type of soil at site
• Costs of pile driving equipment
• Availability of fluid pressure
• Material of pile
• Length of pile
• Ground water level
• etc……
Hammer driving
• Equipment required for hammer driving
 Pile frame or pile driving rig
 Pile hammer
 Leads
 Winches
 Miscellaneous equipment
Pile Frame Or Pile Driving Rig
• Pile drive with crawler mounted
crane rig commonly used for pile
driving.
• The hammer is guided between
two parallel steel channel known
as leads.
Leads
• Leads are also called leaders.
• It is used to guide hammer and
pile for alignment.
• In case of drop hammer fixed
lead are used.
• Lead can be movable and can be
adjusted as per the requirement.
• Movable leads are more
convenient as they can adjusted
as required.
Winches
• Winches are used for lift hammer and
pile.
• It should be light with single drum
provision or heavy with double drums.
• Winches may be fitted with reverse
gear system.
• Winches are driven with diesel or
petrol engines or electrical power in
case of drop hammer and pneumatic
hammers.
Pile hammer
• Types of hammer used for driving
the pile are;
• Drop hammer
• Single acting hammer
• Double acting hammer
• Diesel hammer
• Vibratory hammer
1. Drop hammer
• The drop hammer is the oldest type of
hammer used pile driving.
• A drop hammer is rise by a winch and
allowed to drop the top of the pile
under gravity from a certain height.
• During the driving operation a cap is
fixed to the pile and cushion is
generally provided between the pile
and the cap.
• Another cushion known as hammer
cushion is placed on the pile cap on
which the hammer causes the impact.
2.Single acting hammer
• In this hammer the ram is raised
by air or steam under pressure to
the required height.
• It is then allowed to fall under
gravity on the top of the pile cap.
• The weight of hammer is about
1000 kg to 10,000 kg.
3. Double acting hammer
• In double acting hammer raise by using air or
steam pressure and drop the hammer.
• When hammer has been raised to the
required height steam or air pressure is
applied to other side of piston and the
hammer is pushed downward under pressure.
• The weight of the hammer may be about 1000
kg to 2500 kg.
• It can be apply 90 to 240 blow per minute.
• It is used for driving light to moderate weight
piles in soils of average resistance against
driving.
Vibratory hammer
Pulling Of Pile
• To replace the damaged piles during the driving operation.
• To reuse the existing piles when the structure above the pile is
demolished.
• To prepare the data of strata trough which piles are to be driven by
carrying out pulling tests.
• To remove the pile which are driven temporarily as in case of a
cofferdam.
Method For Pulling Of Pile
• The method for pulling of piles will depend on the type of pile,
equipment availability.
• Various method are;
 Use of double acting steam hammer
 Use of pile extractors
 Use of tongs
 Use of vibrator
 Use of electricity
Pile Extractor
Vibration Pulling
Failure of Pile
Causes Of Failure Of Pile
• Most common causes of failure of piles;
• Absence of statistical data of nature of soil strata
• Load coming on pile is high than design load.
• Bad workmanship
• Attack by insets on wood
• Breakage due to over driving (timber pile)
• Buckling of pile
• Damage due to absence of protective cover
• Improper type of pile, method of driving, classification of soil
• Insufficient reinforcement in case of R.C.C
• Misinterpretation of result from pile load test.
• Wrong formula use for determining load bearing capacity.
Causes of Failure of R.C.C. piles
• Improperly designed concrete mix.
• Use of wrong type of cement
• Insufficient concrete cover to the reinforcement
• Early removal of concrete form.
• Use of aggregate that react with the type of cement.
Micro pilling
• A Micro pile is a small
diameter, typically less than
300mm.
• A drilled and grouted non-
displacement pile which is
heavily reinforced and carries
most of its loading on the high
capacity steel reinforcement.
• Reinforcement and cement
grout are the major
component of micro pile.
• It also known as mini pile.
Construction of micro pile
• Following step are carried out for construction of micro pile.
 Drilling and/or installation of temporary casing
 Remove inner drilling bit rod.
 Placing reinforcement and grouting by tremie.
 Remove temporary casing, inject further grout under pressure.
 Complete pile (casing may be left in place of compressible stratum)
Application of micro pile
• For structure support
• New foundation
• Under pinning of existing
foundation
• Seismic retrofitting of existing
structure
• Scour protection
• Excavation support in confined
area
• For situ reinforcement
• Slop stabilization
• Earth retention
• Ground strengthening and
protection
• Settlement reduction
Advantages of micro pile
• It used to underpin the existing structure where need of minimum
vibration
• It can be easily laid where low head room is constraint.
• It can be installed at any angle.
• It offers practical and cost effective solution to costly alternative pile
system.
• Not require large access road or drilling platforms
Pile driving formula
• Load carrying capacity of pile can be determine following method;
1. Dynamic formula
2. Static formula
Dynamic formula
• Dynamic pile formula are useful in estimating pile capacity.
• The dynamic formula are based on assumption that the kinetic energy delivered by hammer
during driving operation is equal to the work done in penetrating the pile.
Kinematic energy delivered=work done in penetration
Whηh = R x s + energy loss
W=weight of hammer (KN)
h= height of fall of hammer
ηh = Efficiency of hammer
 R= pile resistance taken equal to Qu
S=penetration of pile per blow
Various Dynamic formula
• Engineering News Record (ENR) formula
• Hiley’s formula
• Danish formula
Engineering News Record formula
• As per the Engineering News formula the allowable load of driven pile
is given by
Qa=
Wh
F(s+c)
Qa= Allowable load in kg
W = Weight of hammer
h = Height of fall in mm
s = Final settlement per blow known as set
c = Empirical constant ( drop hammer= 25 mm, single acting hammer=2.5 mm)
F = Factor of safety (Usually taken as 6)
Hiley’s formula
• Hiley’s gave the formula which take into various energy loss.
Qu =
Whηh
(S + C/2)
Qu=ultimate load on pile
W=weight of hammer
h= Height of fall of hammer
C=elastic compression
ηh =efficiency of hammer
(drop hammer=100%,single acting hammer= 75-85 %,double acting =85%)
S= Avg. settlement per blow
Danish formula
• Qu =
Whηh
(S + S0/2)
S0=Elastic compression of pile
S0={2ηh (WhL)
(S + S0/2)
}1/2
L= Length of pile
A= Area of cross section of pile
E=Modulus of elasticity of pile material Allowable
Static Formula
• In static formula ultimate bearing capacity of pile is considered to the
sum of end bearing pile and resistance of skin friction.
Qu=Qp +Qs
=qp.Ap +fs.As
Where,
Qp=end bearing resistance
qp= unit end bearing resistance
Ap =area at the base
Qs= skin friction resistance
fs= unit skin friction
As= surface area
Pile foundations

Pile foundations

  • 1.
    Pile foundation Prepared by: ThaiyamSameer K. Assistant Professor Darshan Institute of Engineering & Technology Rajkot.
  • 2.
    Pile foundation • Introduction •Use of piles • Selection of type of pile • Types of piles • Pile cap and pile shoes • Pile driving equipment and method • Micro piling • Pulling of piles • Causes of failure of pile
  • 4.
    Types of foundation •Shallow foundation • Deep foundation • Pile foundation • Cofferdam foundation • Caissons foundation
  • 5.
    What is pile? • A pile is a slender structural member made of concrete, steel, wood or composite material. • A pile is either driven into the soil or formed in-site by excavating a hole and filling it with concrete.
  • 6.
    Pile foundation • Pilefoundation is that type of deep foundation in which the loads are taken to a low level by means of vertical members which may be  Timber  Concrete  steel
  • 7.
    Uses of Piles •The load of the super-structure is heavy and its distribution is uneven. • The top soil has poor bearing capacity. • The subsoil water is high so that pumping of water from the open trenches for the shallow foundation is difficult and uneconomical. • Large fluctuation in subsoil water level. • The structure is situated on sea shore or river bed, where there is danger of scouring action of water. • Canal or deep drainage line exist near the foundation. • For foundation of transmission towers and off-shore platforms which are subjected to uplift forces.
  • 8.
  • 9.
    Factor Affecting SelectionOf Type Of Piles • Nature and type of structure • Location • Material, equipment and fund availability • Type of soil and its properties • Ground water table • Durability of pile • Length and number of pile • Case study of adjacent building • Facility for pile driving • Erosion of soil near structure
  • 10.
    Classification of Piles •Based on function • Based on materials • Based on method of installation
  • 11.
    Based on function •End bearing Pile • Friction Pile • Compaction Pile • Tension Pile • Anchor Pile • Fender Pile • Better Pile • sheet Pile
  • 12.
    End bearing Pile •Penetrate through the soft soil • Bottom or tips rest on hard strata • Work as column • For this pile Qu=Qp where, Qu=ultimate load Qp= Pile load
  • 13.
    Friction Pile • Loosesoil extend to a greater depth • Pile are driven at depth when friction resistance developed equal to load • In that case Qu=Qs (Qs= skin friction) • Total friction resistance can be increased • Increasing length and diameter • Making Pile surface rough • Placing closely or grouping of pile
  • 14.
    Compaction Pile • Piledo not carry any load • For increase the bearing capacity of soil
  • 15.
    Tension pile • Whenstructure subjected to uplift due to hydrostatic pressure or over turning moment • Also known as uplift pile
  • 16.
    Anchor piles • Theseprovided anchorage against the horizontal pull from sheet pulling or any other pulling.
  • 17.
    Fender pile • Theseare used to protect water front structures against impact from ships or other floating objects.
  • 18.
    Better Pile • Theyare used for resist large horizontal forces or inclined forces.
  • 19.
    Sheet Pile • Theyare used as bulk heads or as impervious cutoff to reduce seepage and uplift under hydraulic structures. • Sheet pile is classified as, 1. Concrete sheet piles 2. Steel sheet pile 3. Timber sheet pile
  • 20.
    Classification Based onPile Material • Concrete pile • Steel piles • Timber piles • Composite pile • Sand pile
  • 21.
    Concrete Piles • Precast piles • Cast-in-situ • Pre stressed
  • 22.
    Pre Cast ConcretePile • It is those which are manufactured in factory or at a place away from the construction site and then driven into ground at the place required. • It requires heavy pile driving machinery. • It may be square, octagonal or circular in cross section. • Size of pile vary from 30 cm to 50 cm in cross section and up to 20 m or more length. • Grade of concrete should be M20.
  • 23.
    Cast In Situ •A bore is dug into the ground by inserting a casing. • Bore is filled with cement concrete after placing reinforcement • The casing be kept in position or it may be withdraw. • The piles with casing are known as cased cast in situ concrete pile. • The piles without casing are known as uncased cast in situ concrete pile.
  • 24.
    Cased • Raymond piles •Mac Arthur piles • BSP base driven piles • Swage piles • Button bottom piles
  • 25.
    Raymond Pile • Itused primarily as a friction pile. • It is provided with uniform taper of 1 in 30 shorter pile. • The length of piles vary from 6 to 12 m. • Top diameter= 40 to 60 cm. • Bottom diameter = 20 to 30 cm • Collapsible mandrel is driven into ground. • When the pile is driven to the desired depth mandrel is collapsed and withdraw. • The shell is gradually filled with concrete up to the top.
  • 26.
    Mac Arthur pile •Mac Arthur is pile of uniform diameter using the corrugated steel shell which remain in place as in Raymond piles. • A heavy steel casing with a core is driven into the ground. • When the desired depth is reached, the core is withdrawn and a corrugated steel shell is placed in the casing. • Concrete is placed in the shell by gradually compacting and withdrawing the steel casing.
  • 27.
    BSP base drivenpiles • This pile consist of a helically welded shell of steel plate. • A concrete plug is provided at the bottom of the shell. • Driving is done by allowing hammer to fall on the concrete plug. • The casing is driven to the desired depth and then it is filled with concrete.
  • 28.
    Swage piles • Itis used with advantage of driving in very hard or it is designed to leave water tight shell for some time filling of the concrete. • steel shell is placed on a precast concrete plug • Pipe is driven over plug until the core reached the plug, then pipe is swage out by tapper of plug which form water tight joint. • Pipe is driven up to specified depth by help of driven force of core. • Core is removed and pipe is filled with concrete.
  • 29.
    Button Bottom piles •It is used where increase of end bearing area is required. • Pile use concrete plug shape of button which enlarge hole in soil during driving. • It used for length up to 23 m and load up to 50 tones. • 12 mm thick steel pipe set on concrete button which have diameter of 25 mm. • Pipe and button driven to specified depth. • The casing is removed and concrete is placed with reinforcement.
  • 30.
    Uncased • Simplex • Franki •Vibro • Pedestal • Pressure
  • 31.
    Simplex Piles • Simplexpiles can be driven through soft or hard soil. • Steel tube fitted with a cast iron shoe is driven into ground up to desired depth. • If Reinforcement is necessary it put in tube then concrete is poured in pile. • Tube is withdrawn slowly without concrete being tamped.
  • 32.
    Franki Piles • Itis used at placed where high load is transfer.(ex .marine structure) • Plug of dry concrete is formed on ground by heavy removable pipe shell. • By help of Diesel operated hammer of 20 to 30 KN weight plug is driven at desired depth. • Diameter of pile is 50 to 60 cm ,while at enlargement is about 90 cm. • Capacity of pile is 60 tones to 90 tones.
  • 33.
    Vibro Piles • Thistype of pile is best suited for places where the ground is soft and offers little frictional resistance to the flow of concrete. • Pile are formed by driving a steel tube and shoe, filling with concrete and withdraw steel tube. • Diameter of pile 35 to 50 cm for load of 60 to 70 tones. Length of pile is 25 m and above. • Steel tube fitted with cast iron shoe by 2-2.5 tone hammer by 40 blow per minute, with stroke about 1.4 m • When shoe and tube reached the desired level tube is filled with concrete and tube is withdrawn at 80 blow per minute by hammer. • Steel tube is withdrawn leaving the shoe in place and pile is formed with corrugation along its height.
  • 34.
    Pedestal Pile • Itis used where thin bearing stratum is reached with reasonable depth. • Pedestal pile gives the effect of spread footing on thin bearing stratum. • Core and casing are driven together into the ground till reached the desired level. • Core is taken out and a charge of concrete is placed in the tube. • The core is again placed in the casing to rest on the top of poured concrete. • Pressure is applied on the concrete though the core, and as the same time the casing is withdrawn.
  • 35.
    Pressure Pile • Thesepiles are especially suitable for congested site where heavy vibration and noise are not permissible. • Boring is done up to required depth to tube. • After withdrawn boring tool reinforcement is placed if required. • A layer of concrete is laid and pressure cap is provided at the top of tube. • Compressed air is admitted through pipe which cause rise the tube. • Tube is lifted same time of concreting is doing by means of compressed air. • Care should be taken that some portion of concrete remain at bottom when tube is lifting for receiving new layer.
  • 36.
    Steel Piles • Commonlyused steel piles are;  H-piles  Box piles  Tube piles
  • 37.
    H-piles • These pileare usually of wide flange section. • They are suitable for trestle type structure in which pile extend above ground level and act as column. • They have small cross section area, there for they can be easily driven In soil. • It used as long pile with high bearing capacity.
  • 38.
    Box Piles • Theyare rectangular or octagonal in form filled with concrete. • These pile are used when not possible to drive H-piles into hard strata.
  • 39.
    Tube Piles • Tubesor piles of steel are driven into the ground. • Concrete is filled inside the tube piles. • Because of circular cross section tube piles are easy to handle and easy to drive in.
  • 40.
    Timber Piles • Thesepile are prepared from trunks of trees. • They may be circular or square . • Diameter of pile are 30 to 50 cm and length not exceeding 20 times its top width. • At bottom, a cast-iron shoe is provided and at the top a steel plate is fixed. • For group pile each pile is brought at same level and concrete plate is provided to have common platform.
  • 41.
    Composite Piles • Thisis a type of construction in which piles of two different material are driven one over the other. • They act together to perform the function of a single pile. • In this pile advantage is taken of durability of concrete piles and the cheapest of timber pile. • Timber pile is terminated just at the level of ground water table.
  • 42.
    Sand Piles • Thesepile are formed by making hole in ground and fill with the sand and well rammed. • The sand to be used should be moist at time of placing. • Bore hole diameter usually 30 cm. length of sand pile is kept about 12 times its diameter. • The top of sand pile is filled with concrete. • Sand pile are placed at 2 to 3 m spacing. • Load test should be carried out determining the bearing capacity of sand pile. • Properly compacted sand pile can carry load up to 100 tone/m2 or more.
  • 43.
    Classification Based onMethod of Installation • Driven pile • Driven and cast-in-situ pile • Bore and cast-in-situ piles • Screw piles • Jacked pile
  • 44.
    Driven pile • Thesepile are driven into ground by applying blow with a heavy hammer. • Timber, steel and precast concrete pile are installed by driving.
  • 45.
    Driven and cast-in-situ pile •These pile are formed by driving a casing with a closed bottom end into the soil . • The casing is later filled with concrete. • The casing may or may not be withdrawn.
  • 46.
    Bore And Cast-in-Situ Piles •These pile are formed by excavating a hole into the ground and then filling it with concrete.
  • 47.
  • 48.
    Jacked pile • Thesepiles are jacked into the ground by applying a downward force by a hydraulic jack.
  • 49.
    Under Reamed Piles •These piles are developed by C.B.R.I for serving foundation for black cotton soils, filled up ground and other type of soil having poor bearing capacity.
  • 50.
    Under reamed piles •An under reamed pile is bored cast-in-situ concrete pile having one or more bulbs or under reamed in its lower level. • The bulb or under reamed are formed by under reaming tool. • Diameter of pile is 20 to 50 cm and bulb diameter is 2-3 times of diameter of pile. • Length of pile is 3 to 8 m and spacing between piles are 2 to 4 m. • Load carrying capacity can increase by making more bulb at the base. • The vertical spacing between two bulb is varies from 1.25 to 1.5 times diameter of bulb. • For black cotton soil the bulb is increase bearing capacity and also provide anchorage against uplift.
  • 51.
    Construction of UnderReamed Piles • The equipment required for the construction of pile are, 1. Spiral auger - for boring 2. Under reamer - for making bulb 3. Boring guide -to keep the hole vertical
  • 52.
    Boring Using Spiral Auger MakingBulb Using Under Reamer
  • 53.
  • 54.
    Pile Accessories • Pilecap • Pile shoe
  • 55.
    Pile Cap • Toprotect the top of pile from blow of hammer on top, pile cap is provided. • Pile carry load from structure and distribute it to various pile. • Generally, Pile cap is made of steel. Thickness and size of cap is depend on shape and size of pile hammer. • Pile should penetrate into the cap at least 10 cm length. • For group pile a common R.C.C. is provided for all the pile.
  • 56.
    Pile shoe • Therefor pile shoe is fitted at bottom end of pile to protect the pile and to facilitate easy pile driving. • Pile shoe are made of cast iron, steel or wrought iron. • Various types of shoe are; Square pile shoe Wedged shaped pile shoe Round pile shoe Steel trap pile shoe for timber pile Socket type pile shoe for timber pile  closed end shoe for pipe piles
  • 57.
    Pile driving Equipment •The operation of inserting pile into ground is known as pile driving. • Pile are driven into the ground by means of hammer. • The equipment used for lifting hammer and allow to fall on head of pile is known as Pile driver. • Various method for pile driving are; • Hammer driving • Vibratory pile driver • Watter jetting and hammering • Partial angering method
  • 58.
    Factor for selectionof pile driving method • Type of soil at site • Costs of pile driving equipment • Availability of fluid pressure • Material of pile • Length of pile • Ground water level • etc……
  • 59.
    Hammer driving • Equipmentrequired for hammer driving  Pile frame or pile driving rig  Pile hammer  Leads  Winches  Miscellaneous equipment
  • 60.
    Pile Frame OrPile Driving Rig • Pile drive with crawler mounted crane rig commonly used for pile driving. • The hammer is guided between two parallel steel channel known as leads.
  • 61.
    Leads • Leads arealso called leaders. • It is used to guide hammer and pile for alignment. • In case of drop hammer fixed lead are used. • Lead can be movable and can be adjusted as per the requirement. • Movable leads are more convenient as they can adjusted as required.
  • 62.
    Winches • Winches areused for lift hammer and pile. • It should be light with single drum provision or heavy with double drums. • Winches may be fitted with reverse gear system. • Winches are driven with diesel or petrol engines or electrical power in case of drop hammer and pneumatic hammers.
  • 63.
    Pile hammer • Typesof hammer used for driving the pile are; • Drop hammer • Single acting hammer • Double acting hammer • Diesel hammer • Vibratory hammer
  • 64.
    1. Drop hammer •The drop hammer is the oldest type of hammer used pile driving. • A drop hammer is rise by a winch and allowed to drop the top of the pile under gravity from a certain height. • During the driving operation a cap is fixed to the pile and cushion is generally provided between the pile and the cap. • Another cushion known as hammer cushion is placed on the pile cap on which the hammer causes the impact.
  • 65.
    2.Single acting hammer •In this hammer the ram is raised by air or steam under pressure to the required height. • It is then allowed to fall under gravity on the top of the pile cap. • The weight of hammer is about 1000 kg to 10,000 kg.
  • 66.
    3. Double actinghammer • In double acting hammer raise by using air or steam pressure and drop the hammer. • When hammer has been raised to the required height steam or air pressure is applied to other side of piston and the hammer is pushed downward under pressure. • The weight of the hammer may be about 1000 kg to 2500 kg. • It can be apply 90 to 240 blow per minute. • It is used for driving light to moderate weight piles in soils of average resistance against driving.
  • 67.
  • 68.
    Pulling Of Pile •To replace the damaged piles during the driving operation. • To reuse the existing piles when the structure above the pile is demolished. • To prepare the data of strata trough which piles are to be driven by carrying out pulling tests. • To remove the pile which are driven temporarily as in case of a cofferdam.
  • 69.
    Method For PullingOf Pile • The method for pulling of piles will depend on the type of pile, equipment availability. • Various method are;  Use of double acting steam hammer  Use of pile extractors  Use of tongs  Use of vibrator  Use of electricity
  • 70.
  • 71.
  • 72.
  • 73.
    Causes Of FailureOf Pile • Most common causes of failure of piles; • Absence of statistical data of nature of soil strata • Load coming on pile is high than design load. • Bad workmanship • Attack by insets on wood • Breakage due to over driving (timber pile) • Buckling of pile • Damage due to absence of protective cover • Improper type of pile, method of driving, classification of soil • Insufficient reinforcement in case of R.C.C • Misinterpretation of result from pile load test. • Wrong formula use for determining load bearing capacity.
  • 74.
    Causes of Failureof R.C.C. piles • Improperly designed concrete mix. • Use of wrong type of cement • Insufficient concrete cover to the reinforcement • Early removal of concrete form. • Use of aggregate that react with the type of cement.
  • 75.
    Micro pilling • AMicro pile is a small diameter, typically less than 300mm. • A drilled and grouted non- displacement pile which is heavily reinforced and carries most of its loading on the high capacity steel reinforcement. • Reinforcement and cement grout are the major component of micro pile. • It also known as mini pile.
  • 76.
    Construction of micropile • Following step are carried out for construction of micro pile.  Drilling and/or installation of temporary casing  Remove inner drilling bit rod.  Placing reinforcement and grouting by tremie.  Remove temporary casing, inject further grout under pressure.  Complete pile (casing may be left in place of compressible stratum)
  • 78.
    Application of micropile • For structure support • New foundation • Under pinning of existing foundation • Seismic retrofitting of existing structure • Scour protection • Excavation support in confined area • For situ reinforcement • Slop stabilization • Earth retention • Ground strengthening and protection • Settlement reduction
  • 80.
    Advantages of micropile • It used to underpin the existing structure where need of minimum vibration • It can be easily laid where low head room is constraint. • It can be installed at any angle. • It offers practical and cost effective solution to costly alternative pile system. • Not require large access road or drilling platforms
  • 81.
    Pile driving formula •Load carrying capacity of pile can be determine following method; 1. Dynamic formula 2. Static formula
  • 82.
    Dynamic formula • Dynamicpile formula are useful in estimating pile capacity. • The dynamic formula are based on assumption that the kinetic energy delivered by hammer during driving operation is equal to the work done in penetrating the pile. Kinematic energy delivered=work done in penetration Whηh = R x s + energy loss W=weight of hammer (KN) h= height of fall of hammer ηh = Efficiency of hammer  R= pile resistance taken equal to Qu S=penetration of pile per blow
  • 83.
    Various Dynamic formula •Engineering News Record (ENR) formula • Hiley’s formula • Danish formula
  • 84.
    Engineering News Recordformula • As per the Engineering News formula the allowable load of driven pile is given by Qa= Wh F(s+c) Qa= Allowable load in kg W = Weight of hammer h = Height of fall in mm s = Final settlement per blow known as set c = Empirical constant ( drop hammer= 25 mm, single acting hammer=2.5 mm) F = Factor of safety (Usually taken as 6)
  • 85.
    Hiley’s formula • Hiley’sgave the formula which take into various energy loss. Qu = Whηh (S + C/2) Qu=ultimate load on pile W=weight of hammer h= Height of fall of hammer C=elastic compression ηh =efficiency of hammer (drop hammer=100%,single acting hammer= 75-85 %,double acting =85%) S= Avg. settlement per blow
  • 86.
    Danish formula • Qu= Whηh (S + S0/2) S0=Elastic compression of pile S0={2ηh (WhL) (S + S0/2) }1/2 L= Length of pile A= Area of cross section of pile E=Modulus of elasticity of pile material Allowable
  • 87.
    Static Formula • Instatic formula ultimate bearing capacity of pile is considered to the sum of end bearing pile and resistance of skin friction. Qu=Qp +Qs =qp.Ap +fs.As Where, Qp=end bearing resistance qp= unit end bearing resistance Ap =area at the base Qs= skin friction resistance fs= unit skin friction As= surface area